Factual and Procedural Background

The petitioners are Sundar Garden Welfare Association, formed by residents of Sundar Garden Colony, and its Secretary (Petitioner No. 2) authorised by a resolution dated 28-11-2004 to file and prosecute this writ petition. The association's members had purchased various specified plots (listed in the writ petition) by registered sale deeds and developed a residential colony with houses occupied by members.

The revenue authorities had declared the land to be abadi (residential) by an order dated 19-3-2001 following a Tehsildar report dated 2-1-2001. The State Government later issued a Gazette notification dated 16-4-2003 under Section 4 of the Land Acquisition Act (also invoking Section 17(1) to treat the land as urgently required) and a subsequent Gazette notification dated 30-6-2003 under Section 6 directing acquisition for planned industrial development and related steps under the Act.

On learning of the acquisition, the association filed objections and a representation dated 12-5-2004 seeking exclusion of the plots declared abadi. When no action followed and demolition/dispossession appeared imminent, the association filed this writ petition seeking quashing of the Section 4 and Section 6 notifications and a mandamus restraining demolition and dispossession. The petition obtained interim relief (interlocutory order dated 20-12-2004). The State and the requiring body filed counter affidavits; respondent No. 4 raised preliminary objections to maintainability based on the association's status and court-fee issues.

Legal Issues Presented

  1. Whether a single writ petition filed on behalf of the association (registered or unregistered) by an authorised secretary is maintainable on behalf of multiple members who purchased distinct plots.
  2. Whether the Gazette notifications issued under Section 4 (dated 16-4-2003) and under Section 6 (dated 30-6-2003) of the Land Acquisition Act are valid, particularly where the land had been declared abadi earlier and mandatory publication and notice requirements under Section 4 were allegedly not complied with.
  3. Whether the State could invoke Section 17 (urgency) to dispense with the inquiry and hearing of objections under Section 5-A of the Act, thereby depriving the petitioners of the opportunity to be heard and of protections under Article 300-A of the Constitution.
  4. Whether the requiring body (U.P. State Industrial Development Corporation) could legitimately acquire or subsequently use the acquired land for purposes other than planned industrial development (including for residential development) when the land had been declared abadi and was subject to local development plans.

Arguments of the Parties

Petitioners' Arguments

  • The land in question had been declared abadi on 19-3-2001 and was being used for residential purposes; therefore it could not be lawfully acquired under the Land Acquisition Act (petitioners relied on Ved Prakash (2003) 9 SCC 542).
  • The Section 4 notification (16-4-2003) was procedurally defective: it was published in a newspaper not proven to have wide circulation, no local language publication or original language notice was made, and required publication in two local newspapers and other formalities were not followed.
  • The State improperly invoked Section 17 (urgency) to make Section 5-A (inquiry/hearing of objections) inapplicable; this deprived petitioners of their right to be heard and affected their rights under Article 300-A of the Constitution.
  • The Section 4 notification was vague in disclosing the public purpose/scheme; change of user (from residential/abadi to industrial) vitiated acquisition; reliance also placed on other precedents argued to support these contentions.

Respondents' Arguments

  • Respondents Nos. 1–3 (State) stated the land had been acquired under the relevant Act; owners had been paid; the affected persons had not challenged the 30-6-2003 notification and the agreement had ended; petitioners were not shown as owners in revenue records and thus the petition should be dismissed.
  • The State asserted that publications had appeared in newspapers ("Dainik Jagran" on 23-5-2003 and "Dainik Pralayahkar" on 25-5-2003) and a beat of drum had been made to notify the public.
  • It was contended the petitioners' names did not appear in revenue records and there was doubt whether they had true proprietary title; it was asserted the acquiring body had entered agreements and paid compensation in accordance with the Act.
  • Respondent No. 4 (requiring body / UPSIDC) filed that a proposal was prepared and sent to the Collector for acquisition and contended the land was vacant and used for agricultural purposes.
  • Separately, respondent No. 4 (through counsel V.K. Singh) raised a preliminary objection to maintainability: no documents were annexed to establish the association's authority (bye-laws or the cited resolution were not filed); a single court-fee payment cannot create a juridical relationship among individual members; each member has a separate cause of action and therefore a single writ petition is impermissible (reliance placed on Umesh Chand Vinod Kumar Full Bench decision).

Table of Precedents Cited

Precedent Rule or Principle Cited For (as stated in the opinion) Application by the Court in this Opinion
Ved Prakash v. Ministry of Industries, (2003) 9 SCC 542 Authority relied on by petitioners for the proposition that abadi land could not be acquired. The petitioners relied on this decision to contend that land already declared abadi in 2001 was not liable to be acquired; the Court cited it in support of its conclusion that abadi status pre-dated acquisition and weighs against the notifications.
Om Prakash v. State of U.P, (1998) 6 SCC 1 Authority cited for the proposition that land declared abadi is not liable to be acquired. The Court relied on this decision (along with Ved Prakash) to assert that the land, having been declared abadi in 2001, was not liable to be put under acquisition proceedings.
Umesh Chand Vinod Kumar v. Krishi Utpadan Mandi Samiti, AIR 1984 Allahabad 46 (Full Bench) Full Bench guidance on when an association or multiple persons may maintain a single writ petition and on court-fee consequences for joiners. The Court applied the Full Bench's principles to hold the association's single writ petition maintainable but directed that individual court-fees be paid by the disclosed members to cure any misjoinder/technical defects.
Mal Singh (1968 A.L.J. 210) (Full Bench decision cited) Principle that where rights arise from the same act and common questions of law exist, petitioners jointly interested may approach the Court in a single writ petition. Followed to support that the association members, affected by the same acquisition action, could join in a single petition.
Mota Singh's case, (1980 Supp) SCC 600 : AIR 1981 SC 484 Principle that where a single writ petition is not validly maintainable, each petitioner may have to pay separate court-fees; mentioned in Full Bench guidance. Cited (via the Full Bench quotation) to justify curing any misjoinder by requiring separate court-fees from each member.
(1991) 4 SCC 224 : AIR 1992 SC 1827 The opinion states that in para 12 of this decision it was held that acquisition proceedings cannot be reopened and land would be available to the owners (as cited by petitioners). Petitioners relied on this authority to argue against reopening/acquision or to support their contention on change of user and its legal consequences; the Court recorded the reliance.
Registrar, Co-operative Societies v. Maharshi Dayanand Co-operative Housing Society, (1998) 6 SCC 536 Cited by petitioners (context: relevance to acquisition/change of user arguments). The Court recorded that petitioners relied on this decision as part of their submissions concerning acquisition proceedings and related rights.
Union of India v. Krishna Lal Arneja, (2004) 8 SCC 453 Cited in relation to the scope of permissible uses once land is acquired for industrial development (that connected public/commercial/residential accommodation may be permissible). The Court cited this decision (along with others) in discussing the permissible post-acquisition uses and distinguishing simple housing development from industrial development schemes.
Union of India v. Mukesh Hans, (2004) 8 SCC 14 Cited concerning permissible uses after acquisition and related principles. Relied upon in the Court's consideration of whether the requiring body could use acquired land for residential housing as distinct from industrial development-related accommodation.
Kashama Sahkari Avas Samiti Ltd. v. State of U.P, 2006 (3) UPLBEC 2484 : 2006 (6) ALJ 363 Cited in the context of post-acquisition use and related authority. Referenced by the Court when considering the nature of permissible development once land is acquired for industrial purposes.

Court's Reasoning and Analysis

The Court's reasoning proceeded in two principal stages: (A) preliminary/maintainability issues and (B) merits regarding the validity of acquisition notifications.

A. Maintainability and Preliminary Objections

  1. The Court considered the objection that an association (registered or unregistered) had not produced bye-laws or the resolution and that a single court-fee was insufficient because each member had a separate cause of action. The respondent relied on a Full Bench decision (Umesh Chand).
  2. After examining the record, the Court held that a single writ petition by an association asserting rights arising from the same act of acquisition and common questions of law is maintainable. The Court referred to Full Bench authorities (Mal Singh and Umesh Chand) establishing that joint interest and common cause permit a single petition.
  3. However, the Court required a procedural cure for the "technical defect" of misjoinder: the 291 members disclosed in the supplementary affidavit must pay separate court-fees for each member; only upon payment would certified copies be made available. This direction implements the principle (as drawn from the cited Full Bench and Mota Singh principles) that court-fee defects may be cured by payment rather than outright dismissal.

B. Merits — Validity of Acquisition Notifications

  1. Fact-finding: The Court noted the land had been declared abadi on 19-3-2001 (per revenue authorities) and that plotting and residential occupation pre-dated the initiation of acquisition proceedings (Section 4 notification dated 16-4-2003).
  2. Procedural compliance: The Court found non-compliance with mandatory publication requirements under Section 4 — the notification had not been shown to have been published in two local newspapers of wide circulation, local language publication and other procedural steps (notice, conspicuous posting, Munadi) were not established.
  3. Urgency under Section 17: The State invoked Section 17 to dispense with Section 5-A inquiry and hearing. The Court analysed that invocation of urgency to both dispossess and to deprive petitioners of their statutory right to be heard is improper where the factual basis for urgency is not satisfactorily shown. The burden lies on the State to demonstrate reasons for disregarding the Section 5-A process.
  4. Change of user and public purpose: The petitioners argued, and the Court accepted, that the acquisition notifications failed to disclose cogent material and correct facts (notably the abadi status and residential nature) and that the public purpose and scheme were not sufficiently specified in the Section 4 notification. The Court observed that once land is taken for industrial development it may include accommodation connected with industry, but it cannot be used as a substitute for housing development schemes properly within the domain of development authorities.
  5. Application of precedents: The Court relied on earlier decisions (including Ved Prakash and Om Prakash) for the principle that land declared abadi before acquisition proceedings is not liable to acquisition. Other cited authorities were used to evaluate permissible uses after acquisition and the consequences of procedural non-compliance or mis-specification of purpose.
  6. Conclusion on merits: For these reasons — prior abadi status, non-compliance with Section 4 publication requirements, lack of cogent material supporting the Governor's satisfaction under Section 17, and insufficiency in specifying public purpose — the Court concluded the notifications were unsustainable and the satisfaction was void ab initio as to the specified plots.

Holding and Implications

Holding: The writ petition is allowed in the manner indicated by the Court. Specifically, the Court QUASHED:

  • The Notification No. 203/77-4-203-116-Bha/99 dated 16-4-2003 under Section 4 of the Land Acquisition Act as it relates to plot Nos. 496, 497, 544, 501, 500, 578, 502, 504, 505, 498, 536, 538, 539 and 541 of village Harampur, Pargana Loni, Tehsil and District Ghaziabad (Annexure-8 to the writ petition).
  • The Gazette Notification dated 30-6-2003 under Section 6 of the Land Acquisition Act, 1894, insofar as it relates to the same specified plots.

The Court ordered that the writ petition be allowed to the extent indicated and recorded "Petition allowed." No order as to costs was made.

Direct Consequences and Broader Implications

  • Direct effect: The immediate legal consequence is that the two impugned notifications (16-4-2003 and 30-6-2003) are quashed with respect to the specifically listed plots. The petitioners obtain relief from the acquisition and from imminent dispossession/demolition to that extent.
  • Remedial procedural direction: The Court remedied the preliminary technical defect concerning joinder by directing separate court-fee payments by the disclosed members (291) to cure misjoinder; only then would certified copies be supplied.
  • On broader precedent: The opinion applies and follows earlier authorities on (a) the inapplicability of acquisition to pre-declared abadi land and (b) procedural requirements under Section 4/Section 17. The opinion does not announce a new legal principle beyond applying established case law to the facts of this matter; its practical effect is to invalidate the specific notifications on factual and procedural grounds in this case.

Note: This summary is strictly confined to the matters, facts, arguments, citations and conclusions contained in the provided opinion. No information beyond the text of the opinion has been added or inferred.

Show all summary ...

V.C Misra, J.:— The present writ petition has been filed by the petitioners-Sundar Garden Welfare Association formed by the residents of the society. The petitioner No, 2 is the Secretary of the society who has been authorized by the residents of the colony to prefer the present writ petition vide resolution dated 28-11-2004 of the association and authorized the petitioner No. 2 to sign and contest the petition on their behalf challenging the notification issued under Sections 4 and 6 of the Land Acquisition Act (hereinafter referred to as the Act) in respect with the plots purchased and owned by the petitioners mentioned in para 5 of the writ petition and seeking a writ order or direction in the nature of certiorari for quashing the said gazettea notification along with a writ of mandamus commanding the respondents not to dispossess the petitioners by demolition of the houses situate on the aforesaid plots have been acquired by the State Government.

2. The facts of the case of the petitioners in brief are that the petitioners-association purchased the aforesaid bhumidhar land free from all encumbrances bearing plot Nos. 496, 497, 544, 501, 500, 578, 502, 504, 505, 498, 536, 538, 539 and 541 distributed amongst its members through registered sale deeds. After purchasing the aforesaid plots a colony was developed by the petitioners in the name of Sundar Garden Colony and after developing the said land the houses were constructed thereupon by the members of the society. The said houses are being occupied by the members of the society. The State Government acquired a large area of land under the Act. The members of the petitioners society had filed case No. 2 of 2001 before the Assistant Collector under Section 143 of U.P.Z.A & L.R Act for being declared as abadi land. Since the petitioners, as per the report of the Tehsildar, were registered as bhumidhar with transferable rights over the said land on 2-1-2001, the Tehsildar, Ghaziabad recommended for declaration of the said land as abadi and the same was being used as tenure holders for residential purposes and was not being used for Agriculture, Horticulture and Animal Husbandry. The Sub Divisional Magistrate, Loni, Ghaziabad vide its order dated 19-3-2001 declared the said land as abadi. On coming to know of some acquisition proceedings to be initiated by the respondents-State Government in respect with the said land, they filed their objections before the State Government and a survey was made by he concerned authorities of the State Government. As per survey report there exists several residential houses of the members of the society on the aforesaid plots. However, the State Government vide gazette notification dated 16-4-2003 acquired the aforesaid land which was published in an unknown newspaper, namely, “Dainik Pralayankar”. A gazette notification dated 16-4-2003 under Section 17(1) of the Act was issued by the State Government to the effect that the provisions of Section 17(1) of the Act are applicable to the said land inasmuch as the same was urgently required for the Planned Industrial Development in District Ghaziabad and it was necessary to ward off the delay likely to be caused by an inquiry and hearing of objections from the owners of the land under Section 5-A of the Act with further directions under Section 16(4) of the Act making the provisions of Section 5-A of the Act inapplicable. Thus, the due procedure as provided under Section 4 of the Act was not followed as the notifiction was not published in two local newspapers having vide circulation neither local publication was made in original language nor the notice was pasted on conspicuous place, even Munadi was not made. This notification was followed by a gazette notifiction dated 30-6-2003 under Section 6 of the Act being satisfied that the land mentioned in the schedule was needed for the purpose of industrial Development of Ghaziabad through Uttar Pradesh State Industrial Development Corporation, Kanpur (hereinafter referred to as the Corporation) and directed the Collector, Ghaziabad to take out the order of acquisition for the said land under Section 7 of the Act and that there being urgency to take possession of the land under Section 9(1) of the Act and to pass an award under Section 11 of the Act.

3. The members of the society on gaining knowledge of such acquisition filed a representation dated 12-5-2004 before the State Government that the aforesaid plots of the petitioners are abadi land declared vide order dated 19-3-2001 by the revenue authorities over which their houses are standing and the same may be excluded from the acquisition. Since no action was taken by the State Government on the representation and the authorities were in hot haste to demolish the construction standing upon the land, in question, the petitioners filed the present writ petition and prayed for an interlocutory order restraining the respondents from dispossessing and demolishing the constructions made upon the said land and obtained an interim order dated 20-12-2004.

4. The main ground raised in this petition is that the land in question was recorded as abadi land in the revenue records and was being used as such and was not being used as agricultural land and thus could not be acquired, as per the decision given by the Hon'ble Apex Court in the case of Ved Prakash v. Ministry of Industries, Lucknow, reported in (2003) 9 SCC 542 : (2003 All LJ 1256). Learned counsel for the petitioners has submitted that the notification issued udner Sections 4 and 6 of the Act were null and void as mandatory requirements regarding gazette and publication etc. prescribed under the Act had not been followed and complied with. More so, there was no necessity of applying the provisions of urgency under Section 17(4) of the Act dispensing with the provisions of Section 5-A of the Act preventing the petitioners from being heard of their objections and holding of an inquiry.

5. In the counter affidavit filed on behalf of the State-respondents Nos. 1, 2 & 3 it has been stated that the plots of land in question have been acquired under the provisions of U.P.Z.A & L.R Act and the owners of the aforesaid land have obtained money and the affected persons have not challenged the Government Notification dated 30-6-2003 thereafter the agreement has come to an end which has not been challenged, and that the petitioners have not been shown as the owners of the land and as such the writ petition is liable to be dismissed with costs. It has also been submitted that the State Government published a news item in two daily newspapers, viz. “Dainik Jagran” on 23-5-2003 and “Dainik Pralayahkar” on 25-5-2003 and a beat of drum was also made and therefore, after expiry of the agreement the petitioners did not continue as owner of the Sundar Garden and since their names do no find place in the revenue record, it seems doubtful that the petitioners have purchased the land for construction of the colony. It is also stated that the General Manager of the Corporation made a proposal for requirement of land for the development of industrial area. On 3-6-1997 about 83.9 acres of land was acquired but considering the gravity of the grievance of the villagers 12 bighas and odd land was left for the interests of the villagers and according to the Nigam propsal for amended acquisition was made. It has also been stated that in the order dated 19-3-2001 passed by Sub Divisional Magistrate with reference to the report of the Tehsildar dated 2-2-2001 wherein it has been mentioned over the vacant land in which plotting had been done for abadi, roads are being constructed between the plots 4 and 5 and consequently, acquiring body entered into some agreement with the land holders which was done in accordance with Section 11(2) of the Act and after the decision the land owners have been paid their compensation. It has been further stated that the petitioners (Sundar Garden Welfare Association) had entered into an agreement with the land owners' through power of attorney and the sale deeds were executed after the expiry of the period of agreement and as such the petitioners are left with no right, title or interest over the land and as the land in question is registered in the names of land holders in the revenue records therefore, after settlement with the acquiring body the compensation has been paid to them.

6. It has been contended that the counter and supplementary counter affidavits have been filed on behalf of respondent No. 4-the requiring body. In para 5 of the counter affidavit filed on behalf of respondent No. 4 it has been stated that a proposal was prepared to acquire the land in question and the same was sent to the Collector, Ghaziabad. It has also been contended that the land was being used for agricultural purposes only and was totally vacant.

7. Sri V.K Singh learned Senior Advocate appearing for the respondent No. 4 has raised a preliminary objection regarding maintainability of the writ petition on two counts; Firstly, no document is annexed for establishing the averments made in the para graphs 3 and 4 of the writ petition by the association or person for enforcement of rights of the members, neither the rules nor the regulation of the society are available to authorise the association to take legal proceedings on behalf of the members for giving binding effect on them of any order passed or to be passed by the Court in the proceeding even when the association is unregistered. Secondly, payment of single Court fee on behalf of the association in such a situation cannot give in jurial relationship between the members of the association. More so, each of the member of the petitioners' association has a separate cause of action having purchased land under separte sale deed hence, single writ petition cannot be held to be maintainable. He has placed reliance upon a Full Bench decision of this Court in the case of Umesh Chand Vinod Kumar v. Krishi Utpadan Mandi Samiti, Bharthana reported in AIR 1984 Allahabad 46, Paras-17, 18, 20, 34, 35 & 45. Learned counsel for the respondents has further submitted that the interlocutory order passed by this Court on 12-1-2005 for giving particulars of the members has not been complied with. Therefore, the petitioners are not entitled to be heard in the present writ petition as the petitioners did not disclose the identity of the petitioners and the number of his members and the description of the land/plots and the constructions made thereupon. The bye laws of association has not been filed neither the resolution referred to in para 2 of the writ petition has been filed.

8. Having heard extensively the learned counsel for the parties and perusal of the record including Full Bench decision of Umesh Chand (supra) in respect with the preliminary objections, we are of the view that the writ petition is very much maintainable on both the counts. Petitioner Nos. 1 and 2 have described in para 3 the details of the plots held by the members of the petitioners' association. No doubt, in para 17 a mention has been made to the effect that there are about 150 members in the petitioners' association but in the supplementary affidavit dated 16-12-2007 the figure of Members has been shown as 291 who had purchased the land in question through registered sale deeds, much before the initiation of land acquisition proceedings, and at that time the land was recorded as abadi. So far as the joinder or misjoinder of petitioners is concerned, the petitioners have a right to approach this Court in a single writ petition through the association as the right seeking relief against respondents arises from the same act of acquisition of land under the Land Acquisition Act and common questions of law arise and the petitioners are jointly interested in the same cause of action which has been settled by the Full Bench decision of our Court in Mal Singh's case reported in 1968 A.L.J 210, paras 24 and 28 followed by another Full Bench decision of this Court reported in AIR 1984 Allahabad page 46, paras 24 and 25. In paras 36, 37 and 38 in the case of Umesh Chand (supra) whcih reads as under:—

“36. Where a single writ petition by an association or by more than one person is maintainable as mentioned as above, only one set of court-fees would be payable. The levy of court-fee will not depend on the number of persons-who have joined in the writ petition. But, where a single writ petition is not validly maintainable, but nonetheless several persons joint in it, then the principle laid down in Mota Singh's case (1980 Supp SCC 600 : AIR 1981 SC 484) will apply; namely, each petitioner will have to pay court-fee separately as if he had filed a separate writ petition. In such cases the writ petition may not, in the discretion of the Court, be dismissed outright. The defect of misjoinder of petitioners can be cured by requiring each petitioner to pay separate court-fees.

37. Our answer to the third question is that whether a single writ petition by an association or by more than one person is maintainable, then a single set of court-fees would be payable. Else, each petitioner is liable to pay separate court-fees.

38. Our answer to fourth question is that the technical defect of misjoinder of petitioners can, in the discretion of the Court, be cured by each petitioner paying separate court-fees.”

9. In the instant case, we are of the view that although the single writ petition on behalf of the association whether registered or unregistered can be held to be maintainable but in the present circumstances particularly in view of the interim order, separate Court fees are directed to be paid to cure the defects, if any. The 291 members of the association disclosed in Annexure-2 of the supplementary affidavit dated 16th December, 2007 are directed to pay the Court fees separately for each of them to cure the technical defect of misjoinder of petitioners which the petitioners shall file the Court fees before the Registry and only under such circumstances the certified copy would be made available to the petitioners. The preliminary objections raised by the respondent No. 4 is accordingly disposed off.

10. On coming to the merits of the case the learned counsel for the petitioners have submitted that the change of nature and purpose of the user vitiated the entire proceedings under the Land Acquisition Act. The objections under Section 5-A of the Act have not been disposed off by the State Government-the acquiring body on the ground of urgency and Section 17 of the Act cannot be invoked in the present circumstances since Section 5-A is depriving the legal rights of the petitioners under Article 300-A of the Constitution. The land was surveyed for the purpose of acquisition under the scheme of Planned Industrial Development as far back as in 1997 but the notification was issued under Section 4 of the Act only on 16-4-2003 in respect with the opinion of the State Government for acquiring the land followed by Section 6 of the Act. Both of them have independent scope but while proceedings under Section 17 of the Act depriving the petitioners of their legal rights to file objections and be heard followed by an inquiry while going through satisfaction of the urgency, two matters arise; first is urgency to dispossess and the second is urgency to deprive. Once there is no ground of urgency apparently found to be present then the burden lies on the State to show as to why the objections under Section 5-A of the Act are to be ignored. Secondly, there is non-compliance of the consideration under Section 6 of the Act while declaring that the land is required for public purpose. The public purpose has to be specified which in the present case was for Planned Industrial Development required by respondent No. 1 the U.P State Industrial Development Corporation. It has been urged that the abadi land being situated in Ghaziabad which is hub of the residential area and under the master plan the land is put for residential purposes only and not for industrial purpose. Thus, there being a change in user all these facts could be seen and looked into by the State Government at the time when the petitioners' objections under Section 5-A of the Act would have been considered. The industrial development was the only public purpose for which the land was acquired and not the present scheme and no details had been furnished as is required under Section 4 notification. The impugned notification under Section 4 is thus assailed on the ground of vagueness in disclosing the scheme. Reliance has been placed on (1991) 4 SCC 224 : (AIR 1992 SC 1827). In para 12 of the said decision it has been held that acquisition proceedings cannot be allowed to be reopened and land would be available to the owners. Reliance is placed on (1998) 6 SCC 536 (Registrar, Co-operative Societies v. Maharshi Dayanand Co-operative Housing Society).

11. From the record it is found that the land is no more required for industrial purpose and has been made subject to Ghaziabad Development Authority and placed with the master plan of 2021 of Ghaziabad Development Authority which has already taken necessary steps for proceeding accordingly, as per minutes dated 20-6-2005, a translated copy in English of the said minutes has been placed by the learned counsel for the petitioners before the Court, which is kept on record. A reference has been made to the booklet of Ghaziabad Master Plan 2020. Reliance has been placed on the decision in the cases of (2004) 8 SCC 453 : (AIR 2004 SC 3582) (Union of India v. Krishna Lal Arneja), (2004) 8 SCC 14 : (AIR 2004 SC 4307) (Union of India v. Mukesh Hans) and 2006 (3) UPLBEC 2484 : (2006 (6) ALJ 363) (Kashama Sahkari Avas Samiti Ltd. v. State of U.P).

12. We are of the view that once the land was acquired and taken over by the requiring body for the purposes of industrial development, then it can be public or commercial and residential accommodation connected with the said industrial development but it cannot enter into simple housing development scheme performing the job of the development authorities and Nagar Nigams etc., which are authorized under the U.P Urban Planning and Development Act, 1973 and other similar Acts.

13. We find that the notification dated 16-4-2003 under Section 4 read with Section 17 of the Act is unsustainable on the grounds of non consideration of correct facts, therefore, the opinion of the Governor is not based upon cogent material and therefore, non consideration of relevant facts such as abadi land, as per report of the revenue authorities etc., non compliance of due procedures, as envisaged under Section 4 of the Act, i.e non publication of notification into two local newspapers having vide circulations in area. The contesting respondents alleged to have published in Dainik Pralayankar and Dainik Bhavi which have not been proved to be widely circulated and known in the area to make people aware of acquisition proceedings. In such circumstances, the notification dated 30-6-2003 under Section 6 read with Section 17 is wrong, bad, unsustainable and illegal and since the objections have not been considered, at all, the satisfaction of the Governor is void ab initio as the relevant factor regarding use of the land is as abadi and not for the agricultural use nor it was vacant land.

14. We further find that the UPSIDC is a company registered under the provisions of the Companies Act and the same is established for planned industrial development as per Memorandum of Association, under which the UPSIDC is not empowered to develop an abadi for residential purpose, specially when the land, in question had already been declared abadi land subject to the provisions of Ghaziabad Development Authority.

15. The land acquired was abadi in 2001 under Section 143 of the U.P.Z.A and L.R Act where as the initiation of the acquisition proceedings took place in April 2003, as such this fact is undisputed that the land in question was abadi land much before the initiation of the acquisition proceedings for which no further enquiry is needed, as the same is already on record and in view of the same, the land in question was not liable to be put under acquisition proceedings, as held in (1998) 6 SCC 1 : (1998 All LJ 1824) (Om Prakash v. State of U.P) and (2003) 9 SCC 542 : (2003 All LJ 1256) (Ved Prakash v. Ministry of Industry).

16. Under the aforesaid facts and circumstances of the case, the Notification No. 203/77-4-203-116-Bha/99 Lucknow dated 16-4-2003 under Section 4 of the Land Acquisition Act (Annexure-8 to the writ petition) as far as it relates to plot Nos. 496, 497, 544, 501, 500, 578, 502, 504, 505, 498, 536, 538, 539 and 541 of village Harampur, Pargana Loni, Tehsil and District Ghaziabad and the Gazette Notification dated 30-6-2003 under Section 6 of the Land Acquisition Act, 1894 are hereby quashed.

17. With the above observations, the writ petition is allowed to the extent indicated above. No order is passed as to costs.

18. Petition allowed.