Govinda Pillai Sankara Pillai v. Krishna Pillai Kesava Pillai And Others

Kerala High Court
Apr 1, 1952
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The decree permitted the plaintiffs to recover possession of plots 5 and 7 on payment of mortgage money and value of improvements. In C.M.P. 5413 of 1122 the 2nd plaintiff, the legal representatives of the deceased 1st plaintiff and their assignees asserted that rights in block No. 5 were assigned to petitioners Nos. 5 and 6 by a sale deed dated 21-5-1121 and sought delivery of specified areas in blocks No. 7 and No. 5 to various petitioners on payment. Govinda Pillai Sankara Pillai (a tarwad member) and Ouseph Ouseph resisted execution, claiming tarwad rights or their own sale deed entitling them to execute. The 49th defendant, in possession of 9 acres in block No. 5, resisted on similar grounds and additionally pleaded limitation and claimed entitlement to proportionate mortgage money (mortgage of 1092) and value of improvements. The learned Judge allowed the petitioners in C.M.P. 5413 to execute the decree; appeals A.S. 251 of 1124 (49th defendant), A.S. 231 of 1124 (Govinda Pillai) and A.S. 250/1124 (Ouseph) followed.

Legal Issues Presented

  1. Whether the execution application filed after the death of the 1st plaintiff is a continuation of the prior execution petition (and thus not barred by the 12 years' rule) or must be treated as a fresh substantive execution application not continuable by substitution.
  2. Whether the petitioners in C.M.P. 5413 have the right to execute the decree, in light of claims that rights under the decree belong to the tarwad or arise only as a power that ceased on death.
  3. Whether the 49th defendant is entitled, prior to surrendering possession, to proportionate mortgage money and the value of improvements, and the manner of ascertaining those amounts.

Arguments of the Parties

Petitioners in C.M.P. 5413

  • Asserted assignment of decree-rights in block No. 5 to petitioners Nos. 5 and 6 by sale deed dated 21-5-1121.
  • Prayed for delivery of specified areas in blocks No. 7 and No. 5 on payment of mortgage money and value of improvements.

Govinda Pillai Sankara Pillai (resisting party)

  • Contended decree-rights belong to the tarwad and the assignment is invalid.
  • Prayed to be permitted to execute the decree himself.

Ouseph Ouseph (resisting party)

  • Relied on a sale deed from tarwad members in his favour and prayed to be permitted to execute the decree and obtain delivery for block No. 5.

49th Defendant

  • Questioned petitioners' rights to execute on same grounds as other resistors (tarwad/assignment).
  • Pleaded execution barred by limitation (12 years) as alternative ground.
  • Claimed entitlement to proportionate mortgage money (mortgage of 1092) and value of improvements; sought payment before delivery.

Respondents' Advocate

  • Did not dispute 49th defendant's right to value of improvements but contended an existing commission report (from trial) should be adopted as basis for valuation.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Palaniappa Chettiar v. Valliammai Achi, AIR 1927 Mad 184 Held: On the death of a decree-holder who is in course of executing his decree, his legal representative cannot be substituted in the execution petition to continue it. Relied on by appellants to argue substitution was not permissible; the court noted the decision but did not follow it in view of later Full Bench authority.
Venkatachalam Chetti v. Ramaswami Servai, AIR 1932 Mad 73 Full Bench concluded that by reason of section 146 and Order 21, rule 16, the legal representative of a decree-holder who dies during the pendency of an execution petition can be substituted and continue it. The court agreed with this Full Bench view, treated C.M.P. 5413 as a continuation of the prior execution petition and held execution not barred by the 12 years' rule.
Perraju v. S. Bapireddi, AIR 1927 Mad 284 Earlier authority on substitution in execution proceedings (expressly dissented from by the Full Bench in AIR 1932 Mad 73). Not followed; the court accepted the Full Bench dissension and did not treat Perraju as controlling.
Judgment in A.S. 439 of 1103 (review) Recognised that the defendant (then 17th, present 49th) is entitled to proportionate mortgage amount and value of improvements before surrendering the area in his possession; left the exact amount to the execution court. The court relied on this review judgment to hold the 49th defendant entitled to proportionate mortgage money and value of improvements to be ascertained and paid before delivery; directed execution court to determine amounts.

Court's Reasoning and Analysis

The court addressed the limitation point first, noting an execution application by the 1st plaintiff dated 20-12-1113 remained pending; C.M.P. 5413 was treated as continuatory rather than as a fresh application. It reviewed precedent: Palaniappa Chettiar was distinguished by a subsequent Full Bench (Venkatachalam Chetti), which interpreted section 146 and Order 21, rule 16 as permitting substitution of legal representatives in pending execution petitions; the court adopted that Full Bench view and concluded substitution was permissible and a fresh application was unnecessary.

On the tarwad/assignment challenge, the court found nothing on the decree's face indicating plaintiffs 1 and 2 sued on behalf of the tarwad; the decree suggested individual rights of plaintiffs 1 and 2, making their rights heritable and transferable. Exhibit A (a document executed pendente lite) was noted but the court declined to construe or give it effect in execution proceedings where the decree expressly conferred redemption rights on the plaintiffs; execution courts cannot go behind the decree. The court held petitioners in C.M.P. 5413 entitled to execute the decree and left any contest over proprietary rights (tarwad claims or rights under Ext. A) to separate proceedings.

Regarding the 49th defendant, the court relied on the earlier review judgment in A.S. 439 of 1103 recognizing his entitlement to proportionate mortgage money and value of improvements prior to surrender. The respondents' plea to adopt the commissioner's earlier report as the basis for valuation was rejected because the review court had left valuation to the execution court and because the earlier report assessed improvements from year 1072 whereas the 49th defendant's mortgage claim related to 1092 onward. An earlier offer by the 49th defendant to accept the commissioner's figure (in 1114) was not treated as binding after nearly 12 years. The court therefore directed fresh ascertainment (including issuing a commission) of the value of improvements from the date of the mortgage and computation of proportionate mortgage money, to be paid before delivery of possession.

Holding and Implications

Core Ruling: A.S. 251 is allowed to the extent that the lower court must ascertain and award to the 49th defendant the proportionate mortgage money and the value of improvements (to be ascertained by commission) and pay them before delivering the property in his possession; A.S. 251 is dismissed in all other respects. A.S. 231 and A.S. 250 are dismissed. Parties shall bear their own costs in the appeals.

Direct consequences: the petitioners in C.M.P. 5413 are entitled to proceed with execution of the decree (the application is treated as continuation of earlier execution proceedings), and the 49th defendant must receive the ascertained mortgage proportion and improvement value before surrendering possession. Challenges based on tarwad or Ext. A were left open for fresh proceedings; the execution court must not go behind the decree in execution proceedings.

Show all summary ...

Gangadhara Menon, J.:— These appeals were heard together. The matter arises in execution. The decree in the case allows the plaintiffs to recover possession of plots 5 and 7 in Ext. Z, plan on payment of the mortgage money and the value of improvements. Before the lower court, in C.M.P 5413 of 1122, the 2nd plaintiff and the legal representatives of the deceased 1st plaintiff and their assignees stated that the rights of the decree-holders in block No. 5 have been assigned in favour of petitioners Nos. 5 and 6 under a sale deed dated 21-5-1121 and prayed that delivery of 3 acres and 75 cents in block No. 7 may be given to petitioners Nos. 1 to 3 and that block No. 5 may be delivered over to petitioners Nos. 5 and 6 on payment of the mortgage money and the value of improvements. One Govinda Pillai Sankara Pillai who is a member of the tarwad of plaintiffs 1 and 2 resisted the execution of the decree by the petitioners in C.M.P 5413, on the ground that the rights under the decree belong to the tarwad and that the assignment of the decree is invalid and prayed that he may be permitted to execute the decree. One Ouseph Ouseph, on the strength of the sale deed from the members of the tarwad in his favour, also resisted the application in C.M.P 5413 and prayed that he may be permitted to execute the decree in respect of block No. 5 and obtain delivery.

2. The 49th defendant who is in possession of 9 acres in block No. 5 in C.M.P 2024 of 1124 while questioning the rights of the petitioners to execute the decree on the same grounds as those taken by the above parties further pleaded that the execution is barred by limitation and that in any event he is entitled to have the proportionate mortgage money as per the mortgage of 1092 in his favour and also the value of improvements from the date ascertained in execution and paid to him before delivery is ordered.

3. The learned Judge under one order disposed of all the above civil miscellaneous petitions and allowed the petitioners in C.M.P 5413 to execute the decree and obtain delivery of possession of the properties as prayed for in their application. From the above order the 49th defendant has preferred A.S 251 of 1124. Govinda Pillai Sankara Pillai petitioner in C.M.P 5532 of 1123 is the appellant in A.S 231 of 1124 and Ouseph Ouseph, the petitioner in C.M.P 5188 of 1123 is the appellant in A.S 250/1124.

4. The contention that the decree is barred by the 12 years' rule is without any substance. The 1st plaintiff had on 20-12-1113 applied for execution of the decree and recovery of possession of the properties. That execution application is still pending and if C.M.P 5413 is only in continuation of that application, it cannot be said that the decree is barred by 12 years' rule. It is however contended that since the 1st plaintiff died, any application for execution thereafter either by the 2nd plaintiff or the legal representatives of the deceased 1st plaintiff or by their assignees could be made only in a substantive execution application and that any such application could not be treated as a continuation of the prior execution application. For this position reliance is placed on the ruling reported in — ‘Palaniappa Chettiar v. Valliammai Achi’, AIR 1927 Mad 184 in which it is held that:

“On the death of a decree-holder who is in course of executing his decree, his legal representative cannot be substituted in the execution petition to continue it.”

5. This decision has come up for consideration in a later Full Bench decision of the Madras High Court reported in — ‘Venkatachalam Chetti v. Ramaswami Servai’, AIR 1932 Mad 73. The Full Bench after a review of the case law has come to the conclusion that “though order 22 has no application to execution proceedings, still by reason of section 146 and Order 21, rule 16, the legal representative of a decree-holder who dies during the pendency of an execution petition can be substituted in the execution petition and be allowed to continue it.”

6. It is not obligatory on him to me a fresh application for execution. The decision in — ‘Perraju v. S. Bapireddi’, AIR 1927 Mad 284 has been expressly dissented from in the above ruling. We are in entire agreement, with the view taken in AIR 1932 Mad. 73. We may also state that the practice as far as we are aware both the Courts in Travancore and Cochin has all along been to substitute the name of the legal representative in the place of the decree-holder who died in the course of execution. This practice is quite warranted by the provisions of the Code and any change therefrom would result in serious consequence vitally affecting the rights of the legal representatives of a deceased decree-holder. C.M.P 5413 of 1122 is in effect an application to continue the execution application filed by the 1st plaintiff after the substitution of the legal representatives of the deceased 1st plaintiff and their assignees in his place. We are therefore unable to treat the C.M.P 5413 of 1122 as a fresh application and are of the view that it has to be treated as an application in continuation of the previous pending execution application of the 1st plaintiff. Therefore the execution of the decree is not barred as contended for by the appellants.

7. Next the question of the right of the petitioners in C.M.P 5413 to execute the decree has to be considered. The main ground on which it is challenged is that the rights under the decree belong to the tarwad of plaintiffs 1 and 2. It is contended that plaintiffs 1 and 2 had at best only a power conferred on them and that the power had ceased with the death of the 1st plaintiff. There is nothing on the face of the decree to indicate that plaintiffs 1 and 2 have obtained the decree on behalf of the tarwad. As far as it could be gathered from the decree and the other records available in the case we are inclined to think that plaintiffs 1 and 2 sued and obtained the decree for redemption by virtue of their separate individual rights. Their rights in the decree are therefore both heritable and transferable. The legal representatives of the 1st plaintiff and their transferees petitioners Nos. 5 and 6 have consequently obtained valid rights to execute the decree. Reliance is placed on Ext. A udampadi to show that whatever rights that plaintiffs 1 & 2 had over the properties had been surrendered in favour of the tarwad and that at any rate after the date of Ext. A the rights in the decree vested in the tarwad. It is also contended that Ext. A, if at all, only authorises the plaintiffs 1 and 2 to recover the property on behalf of the tarwad. It has to be noted that Ex. A came into existence while the case was pending in appeal before the High Court. The rights that were created under Exhibit A whatever they be, have not been availed of in the suit and nobody moved the court for a decree in the light of the alleged rights obtained by the tarwad on the basis of Ext. A. It is not for the execution court to go into the rights of the parties on the basis of a document that has come into existence ‘pendente lite’ and on that footing override the express provisions in the decree that has been passed subsequently. Therefore we do not think it necessary in this case to construe Ext. A and ascertain the exact rights which the plaintiffs 1 and 2 have over the properties comprised in the decree. The decree as it stands confers on plaintiffs 1 and 2 the right to redeem the decree schedule properties and the petitioners in C.M.P 5413 of 1122 are entitled to execute the decree and recover possession of the properties as prayed for by them. The execution court is concerned only with the execution of the decree as it stands and cannot go behind it. It may be open to the appellants in A.S 231 of 1124 and A.S 250/1124 to work out their rights, if any, in a fresh suit. But we do not think they can question the rights of plaintiffs 1 & 2 or their assignees or legal representatives to execute the decree. We would therefore, repeal their contentions in these proceedings and leave the question of their rights to the properties open to be agitated in appropriate proceedings if so advised.

8. The claim of the 49th defendant for the value of improvements and the mortgage money stands on a different footing. The 49th defendant has a mortgage right over 9 acres of the property comprised in block No. 5 on the basis of a mortgage executed by the plaintiffs in his favour in 1092. In the judgment in A.S 439 of 1103 passed on review this right has been recognised. It states:

“The appellant is the 17th defendant” (i.e, the present 49th defendant). “The plaintiff is directed to recover item No. 5 even though one-half of it coming to 9 acres is in his possession under an otti executed by the plaintiff himself. Before he surrenders that he should certainly get proportionate mortgage amount and value of improvements. Unfortunately this court in its prior judgment, did not refer to this aspect at all. We have, therefore, to hold that the 17th defendant is entitled to proportionate mortgage amount and value of improvements before the area which he is holding under the said otti should be surrendered. What this amount will be is left for the execution court to decide. To this extent, the prior judgment of this court is altered.”

9. But it is contended that the 2nd plaintiff was no party to this appeal and that decree in appeal will not bind him. There is no substance in this contention. It has to be remembered in this connection that O.S 25/1095 was tried along with O.S 30 of 1089 and appeals filed against the decrees in the two suits were heard and disposed of together by the High Court. All the parties in the two suits were before the court. There were review petitions in most of the appeals and they were also heard and disposed of together, when both plaintiffs 1 and 2 were before the Court. Further 1st plaintiff was admittedly a party in A.S 439 of 1103 itself and in the execution application filed by him he has recognised the right of the 49th defendant as determined by the above judgment by the High Court passed on review. In fact the decree was sought to be executed by the 1st plaintiff only on that basis. The 2nd plaintiff and the legal representatives of the 1st plaintiff now want to execute the decree in continuation of the application of the 1st plaintiff. In these, circumstances we do not think that it is open to them to put forward contentions inconsistent with the prayers in execution application of the 1st plaintiff and contend that the judgment in review will not bind them. The 49th defendant is therefore entitled to the proportionate mortgage money as well as the value of improvements ascertained in execution and paid to him.

10. The learned advocate for respondents does not question the right of the 49th defendant for the value of improvements. All that he contends for is that since there has already been a commission issued at the trial that report has to be adopted as the basis of the value of improvements. That report was there in the case at the time when the review was heard. But in spite of it the court left open the question of the value of improvements to be determined by the execution court. Therefore there is no warrant in the plea that the 49th defendant should be pinned down to that report. Further in that report the value of improvements assessed was frohi the year 1072. The claim of the 49th defendant which was recognised in the judgment in review was that of the mortgage of 1092 and value of improvements effected as per that mortgage from the year 1092. It is difficult to understand how the report could be made a basis of ascertaining the value of improvements effected in the property from the year 1092. The learned advocate for the respondents relies on an admission in an objection petition filed by the 49th defendant on 31-1-1114 to the effect that he will be satisfied with the value of improvements as fixed in the report of the commissioner at the trial side. The offer contained in that objection petition hast not been accepted by the decree-holders then, and we do not think that it is just to fix the defendant to that offer now, after the lapse of nearly 12 years from that date. We are therefore clear that the claim of the 49th defendant for the proportionate mortgage money as well as for the value of improvements have to be determined in execution afresh and the amount due to him paid before the property in his possession is delivered over as prayed for by the respondents.

11. We would, therefore, allow A.S 251 to the above extent and direct the lower court to ascertain the proportionate mortgage money due to the 49th defendant and also to ascertain by the issue of a commission the value of improvements effected by him in the property from the date of the mortgage in his favour. The proportionate mortgage money and the value of improvements thus determined by the court below will be awarded to him before the property in his possession is delivered over. A.S 251 is allowed to the above extent and dismissed in all other respects. A.S 231 and A.S 250 are also dismissed. In the circumstances of this case we direct the parties to suffer their costs in the appeals.

12. Order accordingly.