Oil And Natural Gas Corporation Limited v. Western Geco International Limited .
Factual and Procedural Background
The appellant, Oil and Natural Gas Corporation Ltd. (“ONGC”), contracted with the respondent, Western Geco International Ltd., in October 2000 for technical up-gradation of ONGC’s seismic survey vessel MV Sagar Sandhani. A critical component was the fitting of “Nessie 4” streamers equipped with U.S.-origin “Geopoint” hydrophones. Although the vessel was handed over to the respondent in April 2001, delivery back to ONGC by the contractual date of 9-7-2001 became impossible because the respondent was unable to secure an export licence from U.S. authorities for the hydrophones. Several months of correspondence ensued: Western Geco sought to substitute Canadian “M-2” hydrophones, while ONGC insisted the respondent continue efforts to obtain the U.S. licence.
On 23-3-2002 ONGC conditionally accepted substitution of the Canadian hydrophones, reserving its right to levy liquidated damages and “excess engagement” charges. The vessel was finally returned on 6-5-2002—9 months and 28 days late. ONGC deducted over US $5 million in excess engagement charges and additional sums for alleged Indian tax liabilities. The respondent invoked arbitration pursuant to the contract. A three-member Arbitral Tribunal partly upheld ONGC’s deductions but directed refund of US $2,445,246.54 (with interest) for the period 1-11-2001 to 22-3-2002 and disallowed the tax-based deductions. ONGC’s Section 34 petition failed before a Single Judge of the Bombay High Court; a Division Bench partly allowed ONGC’s appeal by deleting pendente lite and future interest. ONGC then appealed to the Supreme Court.
Legal Issues Presented
- Whether the Arbitral Tribunal erred in attributing the entire delay from 1-11-2001 to 22-3-2002 to ONGC, thereby directing refund of excess engagement charges for that period.
- Whether deductions made by ONGC for non-payment of Indian taxes were contractually and legally permissible.
- Whether the arbitral award, as confirmed by the High Court, was liable to be set aside or modified under Section 34(2)(b)(ii) of the Arbitration and Conciliation Act, 1996 on the ground of conflict with the “public policy of India”, particularly the “fundamental policy of Indian law”.
Arguments of the Parties
Appellant (ONGC) Arguments
- The Tribunal wrongly held that delay between 14-9-2001/1-11-2001 and 22-3-2002 was not attributable to the respondent; ONGC was entitled to retain excess engagement charges for that entire period.
- Deductions toward Indian taxes (US $410,641.20 and US $80,530.10) were contractually justified.
- Award of pendente lite and future interest was unsustainable (this aspect had been conceded before the Division Bench).
- The award was contrary to public policy because the Tribunal failed to adopt a proper “judicial approach” and drew perverse inferences from the evidence.
Respondent (Western Geco) Arguments
- Jurisdiction under Section 34 is confined to the grounds specified; none were attracted except the narrowly construed “public policy” ground.
- Even if another view of the facts was possible, courts cannot re-appraise evidence or substitute their own view for that of the Tribunal.
- The Tribunal correctly found that ONGC’s indecision and insistence on a formal U.S. licence caused the relevant delay and that tax deductions were impermissible because work was executed entirely in Singapore.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705 | Expanded meaning of “public policy of India”; award can be set aside if patently illegal or contrary to fundamental policy of Indian law. | Relied upon to examine whether the arbitral award’s treatment of delay was “patently illegal” or contrary to fundamental policy. |
| Renusagar Power Co. Ltd. v. General Electric Co., 1994 Supp (1) SCC 644 | Narrow meaning of public policy (pre-Saw Pipes); serves as backdrop for the widened test. | Referenced while recounting evolution of the public-policy test. |
| Ridge v. Baldwin, 1964 AC 40 (HL) | Requirement that bodies affecting rights must act judicially; natural justice. | Cited to underline that “judicial approach” is a component of fundamental policy of Indian law. |
| R. v. Electricity Commissioners, ex p London Electricity Joint Committee Co. (1920) Ltd., (1924) 1 KB 171 | Jurisdictional control over bodies with duty to act judicially. | Cited via Ridge v. Baldwin to support the above proposition. |
| Associated Cement Companies Ltd. v. P.N. Sharma, AIR 1965 SC 1595 | Adoption of Ridge v. Baldwin principles in Indian law. | Used to demonstrate domestic recognition of the “judicial approach” requirement. |
| Associated Provincial Picture Houses Ltd. v. Wednesbury Corporation, (1948) 1 KB 223 | Wednesbury unreasonableness as a measure of perversity/irrationality. | Cited to explain that perverse or irrational decisions violate fundamental policy. |
| ONGC Ltd. v. Western Geco International Ltd., 2005 SCC OnLine Bom 1412; (2006) 3 Bom CR 848 | High Court orders under challenge. | Forms part of procedural history; Division Bench partly modified Single-Judge order. |
Court's Reasoning and Analysis
1. Scope of Judicial Review under Section 34. The Court reaffirmed that an award may be interfered with if it conflicts with the “public policy of India”, which includes violation of the “fundamental policy of Indian law”. Fundamental policy encompasses: (i) the duty to adopt a judicial approach; (ii) observance of natural justice, including application of mind and reasoned decision-making; and (iii) avoidance of perversity or irrationality.
2. Analysis of Delay Attribution. The Tribunal had attributed the entire period 1-11-2001 to 22-3-2002 (4 months 22 days) to ONGC, thereby ordering refund of US $2.445 million. The Supreme Court dissected this aggregate into four intervals:
- 1-11-2001 to 26-11-2001: ONGC’s indecision — delay correctly attributed to ONGC.
- 27-11-2001 to 7-1-2002: 42-day delay in which the respondent failed to file the licence application promptly — should be attributed to Western Geco.
- 8-1-2002 to 7-3-2002: Time taken by U.S. authorities to decide the application — attributable to ONGC (because it insisted on filing the application).
- 8-3-2002 to 21-3-2002: 14-day delay by respondent in conveying rejection — attributable to Western Geco.
The Court held that the Tribunal’s failure to segregate these intervals and its consequent blanket attribution of the entire period to ONGC was a manifestly erroneous inference amounting to perversity and offending the fundamental policy of Indian law. Accordingly, 56 days (42 + 14) had to be shifted from ONGC’s account to the respondent’s account.
3. Tax Deductions. The work was performed wholly in Singapore on a turnkey basis; hence no Indian income-tax liability arose. The Tribunal’s finding disallowing US $410,641.20 and US $80,530.10 deductions was affirmed as consistent with contract terms and law.
4. Pendente Lite Interest. The respondent had waived pendente lite and future interest before the Division Bench; that modification remained undisturbed.
Holding and Implications
Held: The appeal is ALLOWED IN PART. Of the 4 months 22 days earlier debited to ONGC, a period of 56 days is now debited to Western Geco. Consequently, ONGC’s deductions for excess engagement charges corresponding to those 56 days stand affirmed, and the arbitral award is proportionately reduced. No order as to costs.
Implications: The judgment clarifies the Supreme Court’s power to interfere with arbitral awards where the Tribunal’s inference-drawing process violates the “fundamental policy of Indian law” by ignoring evident factual segmentation and thereby producing a perverse outcome. At the same time, it upholds limits on tax-based deductions in offshore contracts. The ruling modifies, but does not annul, the arbitral award and sets no new precedent on interest, as that relief was waived.
T.S Thakur, J.— This appeal arises out of an order dated 10-2-2006 passed by a Division Bench of the High Court of Judicature of Bombay whereby OSA No. 24 of 2006 filed by the appellant Corporation has been partly allowed and the order passed by a Single Bench of the High Court in ONGC Ltd. v. Western Geco International Ltd. 2005 SCC OnLine Bom 1412, (2006) 3 Bom CR 848 affirmed with the modification that award of pendente lite and future interest by the Arbitral Tribunal shall stand deleted.
2. The appellant Corporation is engaged in the business of drilling and exploration of oil and natural gases. In November 1999, the appellant invited offers for technical upgradation of seismic survey vessel, MV Sagar Sandhani (hereinafter referred to as “the vessel”) with a view to modernising the same. According to the tender conditions, one of the main items of equipment required for upgradation of the vessel was “streamers” fitted with hydrophones. The specifications, however, did not stipulate the national origin of such hydrophones.
3. In response to the tender notice, respondent M/s Western Geco International Ltd. submitted a bid offering to supply Nessie 4 streamers equipped with “Geopoint” hydrophones of US origin. The appellant's case is that the term relating to supply of such Geopoint hydrophones formed a material part of the offer made by the respondent Company in whose favour the appellant Corporation eventually awarded a contract in terms of its letter dated 10-10-2000 duly accepted by the respondent on 25-10-2000. The vessel was resultantly handed over to the respondent on 10-4-2001 for carrying on the proposed modernisation and upgradation work. A formal contract was in due course executed between the parties on 18-6-2001.
4. It is common ground that “Geopoint” hydrophones of US origin were in terms of the contract fitted in the vessel and test trials of the same conducted. Even so the vessel could not be delivered back to the appellant on 9-7-2001, the due date for that purpose, because of some problem which the respondent encountered in obtaining licence from the US authorities for sale of such hydrophones. The appellant Corporation asserts that the respondent had for the first time made an application to the US authorities for issuance of a licence as late as on 1-8-2001 i.e nearly a month after the due date for delivery of the vessel back to the Corporation. No formal rejection of the request for a licence was according to the Corporation communicated to it as the matter appeared to be under some kind of negotiations between the respondent and the authorities in US.
5. The respondent's case per contra is that it continued its efforts to obtain a licence only to be informed by its sources in the US that the latter was likely to impose certain onerous conditions one of which could be that US-made hydrophones can be used only on loan basis that too for a short duration of 24 months only. The respondent's further case is that its source in US had informed it that the US authorities were not likely to grant a licence to sell hydrophones to India. Be that as it may while the matter was pending with the Defence Department, a massive terrorist attack on 11-9-2001 shook America. The respondent's hope of getting a licence for sale of US-made hydrophones receded further with this unexpected development. The respondent accordingly informed the appellant Corporation about the new development and pleading force majeure the respondent informed the appellant Corporation of the former's inability to equip the vessel with US-made hydrophones.
6. The appellant Corporation refuted the invocation of force majeure by its letter dated 20-9-2001 and informed the respondent that since the field season was starting shortly any further delay in the delivery of the vessel would adversely affect its operation. The respondent on its part started looking for and offering alternatives to the US-made hydrophones and argued with the appellant Corporation that since the origin of the hydrophones was not indicated in the bid documents it was testing replacement by M-2 US Geo Spectrum hydrophones made in Canada at its Norway facilities to check their suitability which exercise the respondent hoped to complete by 27-9-2001. The respondent informed the appellant Corporation that if the Corporation accepted the replacement, those hydrophones could be substituted for the US hydrophones within a short time.
7. The appellant Corporation was, however, in no mood to accept a substitute for the contracted hydrophones. It was on the contrary keen to have US-made hydrophones fitted on the vessel. The Corporation, therefore, required the respondent to continue its efforts to secure a licence from the US Government in which direction the appellant Corporation on its own moved the Ministry concerned in the Government of India to secure a licence. Further information and details in respect of the proposed Canadian hydrophones was all the same called for by the Corporation from the respondent.
8. Since, however, the efforts to secure a licence from the US Government were making no progress, the respondent sought approval of the appellant Corporation to remove the US hydrophones from the vessel and transfer them to their repair facility in Singapore to facilitate replacement by the Canadian-made hydrophones. The respondent also wrote a detailed letter dated 10-10-2001 to the appellant Corporation informing the latter that the US Government was not likely to grant a licence and that it had withdrawn the application made for that purpose to prevent a denial. What is important is that by the letter dated 16-10-2001 the respondent clearly stated that it was not in a position to deliver the vessel with streamers containing the Geopoint hydrophones of US make. This letter was followed by letter dated 21-10-2001 addressed to the appellant Corporation with a request to permit removal of US hydrophones and replacement of Canadian hydrophones which had been extensively tested in 1999 in connection with supply of Seismic Survey Vessel delivered to NOIC for the Iran project. Further information required by the appellant Corporation was also supplied by the respondent by its letter dated 24-10-2001 with a request to the Corporation to approve the proposed replacement. The respondent also agreed to give additional warranty of one year for the replaced hydrophones. By another letter dated 13-11-2001 the respondent assured the appellant Corporation that if the latter agreed to the replacement proposal there would be no financial implications and the additional cost involved in fixing the Canadian hydrophones would also be borne by the respondent.
9. It was only on 23-3-2002 that the appellant conditionally agreed to the proposed replacement of the US-made hydrophones by those made in Canada. One of the conditions imposed for the replacement by the appellant Corporation was the right to recover liquidated damages as per Clause 16 and for excess engagement of vessel as per Clause 14 of the subject contract. The replacement accordingly took place and the vessel was eventually delivered back to the Corporation with Canadian hydrophones on 6-5-2002. On 24-5-2002, a formal amendment to the contract was also effected to record the substitution of the US hydrophones by those made in Canada.
10. With the upgradation and modernisation work completed as per the amended contract, the respondent raised invoices for payment due to it but realised that the appellant Corporation had deducted from its dues a sum of US $5,114,300.98 towards excess engagement charges in terms of Clause 14 of the contract. By another letter dated 20-8-2002, the appellant Corporation further deducted a sum of US $410,641.20 based on a change in tax law applicable at 4.8% followed by a deduction of a sum of US $80,530.10 based on correction for price charges inclusive of income tax at 4.8%. These deductions gave rise to disputes which were referred for adjudication to an Arbitral Tribunal comprising three former Chief Justices of India before whom the respondent claimed a sum of US $7,327,610.68 towards principal dues plus US $1,205,564.13 by way of interest for the period from 20-8-2003 to 15-11-2003 totalling US $8,533,174,81 with interest pendent lite at 12% per annum from the date of the filing of the claim till the award at the same rate.
11. The appellant Corporation stoutly contested the claim made against it and alleged that hydrophones being an important component, the respondent had not only offered to fit US-made hydrophones in the streamer section of the vessel but actually fitted the same. The appellant's case was that the claimant having contracted to supply US-made hydrophones was legally obliged to hand over the vessel duly fitted with such hydrophones within the stipulated period of 90 days which expired on 9-7-2001. The appellant's further case was that the requirement of a licence was first mentioned by the respondent when letter dated 9-7-2001 was delivered to the appellant's representative on board the vessel at Singapore in an attempt to explain the respondent's failure to hand over the vessel on the due date. The appellant Corporation asserted that the respondent had not even applied for a licence till then and had simply asked for an extension of time. It was only when the appellant Corporation asked the respondent to specify on a realistic basis, the period for which extension was being demanded that the respondent had by letter dated 26-7-2001 stated that according to their understanding the licence will be issued towards the first week of September, 2001. Since time was the essence of the contract between the parties, the respondent's failure to return the vessel duly upgraded within 9 months from the date of letter of acceptance or 90 days from the delivery of the vessel i.e on or before 9-7-2001 was a clear breach of its contractual obligation rendering the respondent liable to payment of liquidated damages and for excess engagement of the vessel, argued the appellant Corporation.
12. The Corporation also disputed the invocation of force majeure clause in the fact situation of the case especially when securing of a licence for the equipment was not a part of the contract between the parties, it being the sole responsibility of the respondent to determine the type and make of hydrophones. The terrorist attack on the twin towers was, according to the appellant Corporation a post-contractual period issue as the date of the delivery of the vessel under the contract had since long expired by the time the attack took place. It was also contended that the delay in the completion of the contract was entirely attributable to the respondent who when called upon by the appellant Corporation to submit the performance report of the M-2 hydrophones used in Seismic Survey Vessel pejwak suggested that the appellant Corporation should obtain the same directly from NIOC forcing the appellant Corporation to send a representative to Oslo to verify the parameters of the M-2 hydrophones at their own expense. It was asserted that once the respondent informed the appellant Corporation that the US Department of Commerce had finally rejected the licence, the appellant Corporation was left with no alternative except to agree to the replacement of the US-made hydrophones by Canadian M-2 hydrophones resulting in the delivery of the vessel back to the Corporation on 6-5-2002 after considerable delay.
13. On the pleadings of the parties the Arbitral Tribunal framed the following issues for determination:
13.1 (1) Was the national origin of hydrophones used in the Nessie 4 streamers, a material term of the contract between the parties?
13.2 (2) Was the appellant justified in refusing to allow substitution of the Canadian M-2 hydrophones for the US Geopoint hydrophones?
13.3 (3) Was the claimant's declaration of force majeure justified under the terms of the contract?
13.4 (4) Whether there was any delay in the performance of the contract?
13.5 (5) If the answer to Point 4 is in the affirmative, who is responsible for such delay?
13.6 (6) If the answer to Point 4 is in the affirmative, whether the claimant is entitled to damages?
13.7 (7) Whether the respondent was entitled to adjust the sum of US $491,000 out of the sum payable, in whole or in part, as alleged in para 30 of the statement?
13.8 (8) Is the respondent entitled to both liquidated damages and excess engagement charges for the same periods of time under the provisions of the contract?
14. In the award which the Tribunal made and published Issue 1 was answered in the negative holding that since the choice of the hydrophones was left to the bidders subject to the equipment meeting the specifications prescribed for the purpose and since the stipulations did not indicate the make or the country of origin of the hydrophones, the national origin of such hydrophones was not a material term of the contract between the parties.
15. Issue 2 was, however, answered by the Tribunal in the affirmative, who took the view that once the respondent had made the choice and contracted to supply hydrophones made in the US the appellant Corporation was entitled to insist on the supply of the contracted equipment. The arbitrators further held that once the respondent had informed the appellant that the option of US-made hydrophones was closed, the latter was not justified in insisting that the request for a licence with the US authorities should be pursued further.
16. The Arbitral Tribunal decided Issue 3 against the respondent holding that none of the events mentioned in the contract had taken place and since the parties to the contract did not belong to US, the force majeure clause could not have been validly invoked by the respondent.
17. Dealing with the question of delay in the performance of the contract and its consequences covered by Issues 4 to 8, the arbitrators held that the respondent claimant had completed the performance of the contractual obligations within the stipulated time-frame and would have but for the US licence requirement delivered the vessel to the appellant on 9-7-2001 in which event there would have been no necessity to invoke the force majeure clause or to seek extension of time or to offer the Canadian hydrophones. Even so the fact remained that the respondent had not delivered the vessel back to the appellant Corporation on time.
18. The Tribunal then examined whether the respondent was responsible for the entire delay between 9-7-2001 and 6-5-2002 when the vessel was actually returned. The Tribunal rejected the contention on behalf of the respondent that extension of time for completing the contracted works had the effect of waiving the rights vested in the appellant under Clauses 14 and 16 of the contract. The Tribunal held that waiver ought to be express or the fact situation must be necessary implication manifest an intention to waive. Mere extension of time did not signify waiver of the rights flowing from Clauses 15 and 16 of the contract, observed the Arbitral Tribunal. Having said so the Tribunal held that since the respondent had informally intimated to the appellant Corporation as early as on 24-10-2001 that it did not desire to pursue the request for a licence with the US authorities any further and since by a letter dated 25-10-2001 the final particulars in regard to the Canadian hydrophones were duly supplied, allowing some time to the respondent to take a decision, the delay post-21-10-2001 could not be attributed to the respondent. That finding, observed the Tribunal, did not impact the amount deducted by the respondent towards liquidated damages as the capping provision limited to 10% was less than the sum payable for the delay up to 31-10-2001.
19. As regards the excess engagement charges the arbitrators held that except for the period commencing 1-11-2001 to 22-3-2002 the appellant Corporation was justified in making deductions for the rest of the period from the claim of the respondent. The arbitrators held that the deductions in relation to the period from 1-11-2001 to 22-3-2002 amounting to US $2,445,246.54 were wrongly made by the appellant Corporation which amount the respondent was entitled to get from the appellant together with interest at the rate indicated in the award.
20. As regards deductions based on change of tax law or non-payment of taxes under the Indian law, the Tribunal held that the same were not permissible in the facts and circumstances of the case especially when the contracted work was to be executed and completed at the ship repair unit of the respondent claimant in Singapore and so was the handing over of the completed vessel to the appellant Corporation. No part of the work having been undertaken outside Singapore no deduction could be made on account of non-payment of any tax. The arbitrators held that since no taxes were attracted under the Indian Income Tax Act the price could not include the said tax component. The arbitrators accordingly held that the deductions made on two counts, being of US $410,641.20 and US $80,530.10 were also unjustified and unwarranted by law or contract.
21. Aggrieved by the award made by the Arbitral Tribunal, the appellant Corporation preferred a petition under Section 34 of the Arbitration and Conciliation Act, 1996 which failed and was dismissed 2005 SCC OnLine Bom 1412, (2006) 3 Bom CR 848 by a Single Judge of the High Court but was allowed in part in ONGC Ltd. v. Western Geco International Ltd. by the Division Bench of the High Court to the extent of deleting pendente lite in future interest from the award made by the Tribunal. Before the Division Bench, a threefold submission was urged on behalf of the appellant Corporation:
21.1 Firstly, it was contended that the Tribunal had fallen in error in holding that the delay between 14-9-2001 and 21-3-2002 was not attributable to the respondent Company.
21.2 Secondly, it was contended that the Arbitral Tribunal was not right in holding that the deductions made by the appellant towards taxes was not legally permissible.
21.3 Thirdly, it was contended that the award by the Arbitral Tribunal for the pendente lite and future interest was not justified.
22. While the Division Bench rejected the first two contentions the respondent appears to have made a statement before the High Court waiving pendente lite interest and agreeing to the modification of the award to that extent. The High Court held that the Arbitral Tribunal's findings to the effect that the delay between 16-10-2002 and 21-3-2002 is not attributable to the respondent, was based on the consideration of the material placed before the Arbitral Tribunal which called for no interference. So also deductions towards payment of taxes were, according to the High Court, rightly disallowed by the arbitrators.
23. The present appeal assails the correctness of the award of the Arbitral Tribunal and the orders passed by the High Court as noticed in the beginning of this order.
24. We have heard the learned counsel for the parties at length who have taken us through the award made by the Arbitral Tribunal, provisions of the contract executed between the parties and the correspondence exchanged between them.
25. There is no denying the fact that there was delay in the return of the vessel to the Corporation after upgradation. In terms of the contractual time schedule the vessel ought to have been returned to the Corporation by 9-7-2001 which was instead returned to the Corporation only on 6-5-2002 i.e after a delay of 9 months and 28 days. Who is responsible for this delay is the essence of the dispute between the parties. According to the appellant Corporation the delay is entirely attributable to the respondent while according to the respondent the delay is attributable to the appellant.
26. The arbitrators have after examining the material placed before them recorded a finding to the effect that the delay between 10-7-2001 and 31-3-2001 was entirely attributable to the respondent. That finding was not challenged by the respondent before the High Court nor is it under challenge before us. The arbitrators have on the basis of the finding recorded by them allowed to the appellant Corporation excess engagement charges under Clause 14 besides liquidated damages under Clause 16 of the contract executed between the parties. But for the period between 1-11-2001 and 22-3-2002 which comes to 4 months and 22 days the arbitrators have found the delay to be attributable to the appellant Corporation. Deduction made by the Corporation in regard to this period has been faulted by the arbitrators and the amount directed to be released in favour of the respondent Company. The award deals with this period and the amount deducted for the same in the following words:
“In the result we are of the opinion that except for the period from 1-11-2001 to 23-3-2002 for which deduction has been made from the claimant's invoices, no exception can be taken for the rest of the deduction made from the claim of the claimant. The deduction in relation to the period from 1-11-2001 to 22-3-2002 (4 months + 22 days) works out to a sum of US $2,445,246.53 which the claimant would be entitled to from the respondent together with interest at the rate as indicated hereafter.”
27. The above period of 4 months and 22 days between 1-11-2001 and 22-3-2002, in our opinion, comprises four separate intervals:
27.1 The first of these four intervals is the period between 1-11-2001 and 26-11-2001 which period was taken by the appellant Corporation to take a final decision whether or not an application should be made to the US authorities for the issue of a licence.
27.2 The second interval comprises time taken by the respondent claimant to make an application between 27-11-2001 and 7-1-2002, both days inclusive. The application for grant of a licence was filed by the respondent only on 8-1-2002.
27.3 The third interval comprises time taken by the US authorities between 8-1-2002 and 7-3-2002 to formally decline the issue of a licence for sale of US-made hydrophones to India.
27.4 The fourth interval comprises time taken by the respondent claimant to convey the decision of the US authorities between 8-3-2002 and 21-3-2002. It is common ground that while the US authorities had rejected the request for grant of a licence on 8-3-2002, the said rejection was conveyed to the appellant Corporation only on 22-3-2002.
28. From the findings of the fact recorded by the arbitrators with which we see no reason to interfere or disagree, it is evident, that the appellant Corporation was solely responsible for the delay in taking a decision in the matter between 24-10-2001 and 26-11-2001. The arbitrators have found and, in our opinion, rightly so that the respondent claimant had by its letter dated 24-10-2001 clearly informed the appellant that there was no use pursuing the matter with the US authorities any further. Even particulars regarding Canadian hydrophones were supplied to the appellant in terms of a letter dated 25-10-2001. The arbitrators have held that delay in taking a decision whether or not any formal application should be made and a formal rejection obtained by the respondent was attributable only to the appellant Corporation. There is, in our opinion, no legal flaw, infirmity or perversity in that finding which we hereby affirm. Deduction made by the appellant Corporation for the first interval that comprises period between 1-11-2001 and 25-11-2001, both days inclusive, cannot, therefore, be sustained and the arbitral award to that extent cannot be faulted.
29. That brings us to the second interval comprising period between 26-11-2001, the date when the appellant Corporation issued instructions for making of a formal application for the grant of a licence and 8-1-2002 when such an application was actually made by the respondent Company. This period reckoned from 27-11-2001 to 7-1-2002 works out to 42 (forty-two) days which must be attributed to the respondent claimant, who could and indeed ought to have acted diligently and with reasonable dispatch in the matter instead of taking the same easy, and if we may say so somewhat reluctantly. We cannot help saying with utmost respect at our command for the eminence and erudition of the distinguished jurists comprising the Arbitral Tribunal that the Tribunal failed to appreciate this aspect hence fell in a palpable error leading to miscarriage of justice. The test adopted by the Tribunal for holding the appellant Corporation responsible for the delay ought to have been applied to the respondent as well for its failure to take action in the right earnest instead of sitting over the matter leading to detention of the vessel for a period more than what was absolutely necessary.
30. The period between 8-1-2002 and 8-3-2002 comprising the third interval during which the US authorities decided the application for the grant of a licence has been rightly counted against the appellant Corporation as it was at the instance of the Corporation that a formal application was made. The time spent by the US authorities for disposal of the request could not in the facts and circumstances be attributed to or counted against the respondent claimant who had advised the appellant against any such move. The Arbitral Tribunal, therefore, rightly held that deduction for this period was not justified.
31. That leaves us with the fourth and the last interval comprising the period between 8-3-2002 and 22-3-2002 when the rejection of the application was conveyed to the appellant Corporation. There is, in our opinion, no valid reason why this period should not be counted against the respondent, who could and indeed should have conveyed the rejection to the appellant Corporation forthwith, instead of taking nearly two weeks to do so. To sum up: the period of 4 months and 22 days which the arbitrators have attributed to the appellant Corporation shall have to be reduced by 42 days comprising the first interval and 14 days comprising the fourth making a total of 56 days. Resultantly, deduction made by the appellant Corporation for 56 days referred to above deserve to be affirmed, and the award made by the arbitrators modified to that extent. It follows that the amount awarded to the respondent Company shall on a proportionate basis, stand reduced.
32. We may at this stage deal with the contention urged on behalf of the respondent that the jurisdiction of the Court to set aside an arbitral award being limited to grounds set out in Section 34 of the Arbitration and Conciliation Act, 1996, this Court ought not to interfere with the same. It was contended that none of the grounds on which a court is authorised to interfere with an arbitral award are present in the case at hand. Alternatively, it was contended that even if a contrary view is possible on the facts proved before the Arbitral Tribunal, the Court cannot, in the absence of any compelling reason, interfere with the view taken by the arbitrators as if it was sitting in appeal over the award made by the Tribunal.
33. Section 34 of the Arbitration and Conciliation Act, 1996 reads:
“34. Application for setting aside arbitral award.—(1) Recourse to a court against an arbitral award may be made only by an application for setting aside such award in accordance with sub-section (2) and sub-section (3).
(2) An arbitral award may be set aside by the court only if—
(a) the party making the application furnishes proof that—
(i) a party was under some incapacity; or
(ii) the arbitration agreement is not valid under the law to which the parties have subjected it or, failing any indication thereon, under the law for the time being in force; or
(iii) the party making the application was not given proper notice of the appointment of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or
(iv) the arbitral award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration:
Provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, only that part of the arbitral award which contains decisions on matters not submitted to arbitration may be set aside; or
(v) the composition of the Arbitral Tribunal or the arbitral procedure was not in accordance with the agreement of the parties, unless such agreement was in conflict with a provision of this Part from which the parties cannot derogate, or, failing such agreement, was not in accordance with this Part; or
(b) the court finds that—
(i) the subject-matter of the dispute is not capable of settlement by arbitration under the law for the time being in force, or
(ii) the arbitral award is in conflict with the public policy of India.
Explanation.—Without prejudice to the generality of sub-clause (ii), it is hereby declared, for the avoidance of any doubt, that an award is in conflict with the public policy of India if the making of the award was induced or affected by fraud or corruption or was in violation of Section 75 or Section 81.”
34. It is true that none of the grounds enumerated under Section 34(2)(a) were set up before the High Court to assail the arbitral award. What was all the same urged before the High Court and so also before us was that the award made by the arbitrators was in conflict with the “public policy of India”, a ground recognised under Section 34(2)(b)(ii) (supra). The expression “public policy of India” fell for interpretation before this Court in ONGC Ltd. v. Saw Pipes Ltd. (2003) 5 SCC 705 and was, after a comprehensive review of the case law on the subject, explained in para 31 of the decision in the following words:
“31. Therefore, in our view, the phrase ‘public policy of India’ used in Section 34 in context is required to be given a wider meaning. It can be stated that the concept of public policy connotes some matter which concerns public good and the public interest. What is for public good or in public interest or what would be injurious or harmful to the public good or public interest has varied from time to time. However, the award which is, on the face of it, patently in violation of statutory provisions cannot be said to be in public interest. Such award/judgment/decision is likely to adversely affect the administration of justice. Hence, in our view in addition to narrower meaning given to the term ‘public policy’ in Renusagar case 1994 Supp (1) SCC 644 it is required to be held that the award could be set aside if it is patently illegal. The result would be—award could be set aside if it is contrary to:
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality, or
(d) in addition, if it is patently illegal.
Illegality must go to the root of the matter and if the illegality is of trivial nature it cannot be held that award is against the public policy. Award could also be set aside if it is so unfair and unreasonable that it shocks the conscience of the court. Such award is opposed to public policy and is required to be adjudged void.”
35. What then would constitute the “fundamental policy of Indian law” is the question. The decision in ONGC (2003) 5 SCC 705 does not elaborate that aspect. Even so, the expression must, in our opinion, include all such fundamental principles as providing a basis for administration of justice and enforcement of law in this country. Without meaning to exhaustively enumerate the purport of the expression “fundamental policy of Indian law”, we may refer to three distinct and fundamental juristic principles that must necessarily be understood as a part and parcel of the fundamental policy of Indian law. The first and foremost is the principle that in every determination whether by a court or other authority that affects the rights of a citizen or leads to any civil consequences, the court or authority concerned is bound to adopt what is in legal parlance called a “judicial approach” in the matter. The duty to adopt a judicial approach arises from the very nature of the power exercised by the court or the authority does not have to be separately or additionally enjoined upon the fora concerned. What must be remembered is that the importance of a judicial approach in judicial and quasi-judicial determination lies in the fact that so long as the court, tribunal or the authority exercising powers that affect the rights or obligations of the parties before them shows fidelity to judicial approach, they cannot act in an arbitrary, capricious or whimsical manner. Judicial approach ensures that the authority acts bona fide and deals with the subject in a fair, reasonable and objective manner and that its decision is not actuated by any extraneous consideration. Judicial approach in that sense acts as a check against flaws and faults that can render the decision of a court, tribunal or authority vulnerable to challenge.
36. In Ridge v. Baldwin 1964 AC 40, (1963) 2 WLR 935, (1963) 2 All ER 66 (HL), the House of Lords was considering the question whether a Watch Committee in exercising its authority under Section 191 of the Municipal Corporations Act, 1882 was required to act judicially. The majority decision was that it had to act judicially and since the order of dismissal was passed without furnishing to the appellant a specific charge, it was a nullity. Dealing with the appellant's contention that the Watch Committee had to act judicially, Lord Reid relied upon the following observations made by Atkin, L.J in R. v. Electricity Commissioners, ex p London Electricity Joint Committee Co. (1920) Ltd. (1924) 1 KB 171, 1923 All ER Rep 150 (CA): (KB p. 205)
“… Wherever any body of persons having legal authority to determine questions affecting the rights of subjects, and having the duty to act judicially, act in excess of their legal authority, they are subject to the controlling jurisdiction of the King's Bench Division exercised in these writs.”
37. The view taken by Lord Reid was relied upon by a Constitution Bench of this Court in Associated Cement Companies Ltd. v. P.N Sharma AIR 1965 SC 1595 wherein Gajendragadkar, C.J speaking for the Court observed: (AIR p. 1601, para 14)
“14. … In other words, according to Lord Reid's judgment, the necessity to follow judicial procedure and observe the principles of natural justice, flows from the nature of the decision which the Watch Committee had been authorised to reach under Section 191(4). It would thus be seen that the area where the principles of natural justice have to be followed and judicial approach has to be adopted, has become wider and consequently, the horizon of writ jurisdiction has been extended in a corresponding measure. In dealing with questions as to whether any impugned orders could be revised under Article 226 of our Constitution, the test prescribed by Lord Reid in this judgment 1964 AC 40, (1963) 2 WLR 935, (1963) 2 All ER 66 (HL) may afford considerable assistance.”
38. Equally important and indeed fundamental to the policy of Indian law is the principle that a court and so also a quasi-judicial authority must, while determining the rights and obligations of parties before it, do so in accordance with the principles of natural justice. Besides the celebrated audi alteram partem rule one of the facets of the principles of natural justice is that the court/authority deciding the matter must apply its mind to the attendant facts and circumstances while taking a view one way or the other. Non-application of mind is a defect that is fatal to any adjudication. Application of mind is best demonstrated by disclosure of the mind and disclosure of mind is best done by recording reasons in support of the decision which the court or authority is taking. The requirement that an adjudicatory authority must apply its mind is, in that view, so deeply embedded in our jurisprudence that it can be described as a fundamental policy of Indian law.
39. No less important is the principle now recognised as a salutary juristic fundamental in administrative law that a decision which is perverse or so irrational that no reasonable person would have arrived at the same will not be sustained in a court of law. Perversity or irrationality of decisions is tested on the touchstone of Wednesbury principle (1948) 1 KB 223, (1947) 2 All ER 680 (CA) of reasonableness. Decisions that fall short of the standards of reasonableness are open to challenge in a court of law often in writ jurisdiction of the superior courts but no less in statutory processes wherever the same are available.
40. It is neither necessary nor proper for us to attempt an exhaustive enumeration of what would constitute the fundamental policy of Indian law nor is it possible to place the expression in the straitjacket of a definition. What is important in the context of the case at hand is that if on facts proved before them the arbitrators fail to draw an inference which ought to have been drawn or if they have drawn an inference which is on the face of it, untenable resulting in miscarriage of justice, the adjudication even when made by an Arbitral Tribunal that enjoys considerable latitude and play at the joints in making awards will be open to challenge and may be cast away or modified depending upon whether the offending part is or is not severable from the rest.
41. Inasmuch as the arbitrators clubbed the entire period between 16-10-2001 and 21-3-2002 for the purposes of holding the appellant Corporation responsible for the delay, they committed an error resulting in miscarriage of justice apart from the fact that they failed to appreciate and draw inferences that logically flow from such proved facts. We have, therefore, no hesitation in rejecting the contention urged on behalf of the respondent that the arbitral award should not despite the infirmities pointed out by us be disturbed.
42. That brings us to the last submission that deduction on account of taxes not paid should have been allowed by the respondent Arbitral Tribunal. The Tribunal has, in our opinion, correctly held that no part of the work was undertaken outside Singapore which was to be executed on a turnkey basis for a price that was predetermined. The arbitrators have, in our opinion, rightly held that no taxes were payable under the Indian Income Tax Act so as to entitle the Corporation to deduct any amount on that account by reason of non-payment of such taxes. The challenge to the award to that extent must fail and is, hereby, rejected.
43. In the result, we allow this appeal but only to the extent that out of the period of 4 months and 22 days which the arbitrators have attributed to the appellant Corporation a period of 56 days comprising 42 days of the first interval and 14 days of the second interval referred to in the judgment shall be reduced. Resultantly, deductions made by the appellant Corporation for the said period of 56 days shall stand affirmed and the award made by the arbitrators modified to that extent with a proportionate reduction in the amount payable to the respondent. No costs.