Login
  • Bookmark
  • PDF
  • Share
  • CaseIQ

Harsha Constructions v. Union Of India And Others

Supreme Court Of India
Sep 5, 2014
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The Union of India engaged M/s Harsha Constructions (“the contractor”) to construct a road bridge. The General Conditions of Contract contained an arbitration clause (Clause 63) that expressly excluded (“excepted”) certain matters—among them, disputes governed by Clause 39 dealing with rates for extra items of work—from the scope of arbitration.

Extra work not covered by the scheduled rates was entrusted to the contractor. Negotiations between the contractor and the Engineer failed to yield an agreed rate; nevertheless, the Railway made part-payment, which the contractor accepted under protest. Several disputes, including the rate for this extra work, were referred to a sole arbitrator (a former High Court judge), who rendered an award on 21-9-2002 in favour of the contractor.

The Union of India challenged the award before the City Civil Court, Hyderabad under Section 34 of the Arbitration and Conciliation Act, 1996. That court set aside the award, holding that the rate-dispute was an “excepted matter” and hence non-arbitrable. The contractor’s appeal to the High Court (CMA 476 of 2005) was dismissed on 9-9-2005. The present appeal before the Supreme Court followed.

Legal Issues Presented

  1. Whether disputes expressly “excepted” from arbitration by the contract (specifically, rate-determination under Clause 39) can nevertheless be decided by an arbitrator.
  2. What is the legal consequence if an arbitrator decides such non-arbitrable (“excepted”) issues.

Arguments of the Parties

Appellant's Arguments

  • The Engineer never took a final decision on rates; therefore no appeal to the Chief Engineer arose, and the matter did not fall within the “excepted” category of Clause 39/63.
  • Because no “excepted matter” was actually decided by the Engineer or the Chief Engineer, Clause 64’s bar on arbitration of those issues was inapplicable, making the entire award valid.
  • Cited Supreme Court judgments in Northern Railway v. Sarvesh Chopra (2002) 4 SCC 45 and Madnani Construction Corpn. (P) Ltd. v. Union of India (2010) 1 SCC 549 to support arbitrability.

Respondent's Arguments

No submissions were recorded before the Supreme Court as the Union of India was unrepresented.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Northern Railway v. Sarvesh Chopra, (2002) 4 SCC 45 Cited by appellant to argue that absence of a final departmental decision keeps the dispute arbitrable. The judgment is referenced only in counsel’s submissions; the Court’s reasoning does not rely on it.
Madnani Construction Corpn. (P) Ltd. v. Union of India, (2010) 1 SCC 549 Cited by appellant for the proposition that parties can submit disputes to arbitration despite contractual bars if departmental remedies were not exhausted. The judgment is referenced only in counsel’s submissions; the Court’s reasoning does not rely on it.

Court's Reasoning and Analysis

The Supreme Court examined Clause 39 and Clause 63 of the contract and concluded that disputes concerning fixation of rates for extra work are expressly classified as “excepted matters.” Under the Arbitration and Conciliation Act, 1996, an arbitration agreement must be in writing (Section 7). Because the contract itself excludes these matters from arbitration, no such written agreement existed to submit them to the arbitrator.

Even though the arbitrator framed issues on the rate-dispute and rendered a decision, the Court held that doing so could not create jurisdiction by waiver or consent, particularly where the respondent had objected to arbitrability. A dispute that is contractually non-arbitrable cannot be converted into an arbitrable one merely because it was included in the reference or decided in the award.

Consequently, the portion of the arbitral award dealing with the rate for the extra work was ultra vires and liable to be set aside. The Court, however, found no infirmity in the arbitrator’s determinations on disputes that were within the scope of arbitration, and therefore preserved those parts of the award.

Holding and Implications

PARTLY ALLOWED. The Supreme Court:

  • Quashed the portion of the arbitral award determining the rate for extra work, holding it non-arbitrable.
  • Upheld the remainder of the award concerning arbitrable disputes.
  • Left it open to the contractor to pursue appropriate legal remedies for payment of the extra work outside arbitration.

Implications: The decision reinforces the principle that contractual “excepted matters” remain outside arbitral jurisdiction. Arbitrators and courts must strictly honor such exclusions; an arbitral award that ventures into non-arbitrable territory is vulnerable to being set aside. No new precedent is set, but the ruling reiterates and applies established doctrines on arbitrability and jurisdictional limits.

Show all summary ...

Anil R. Dave, J.— Aggrieved by the judgment dated 9-9-2005 delivered by the High Court of Judicature of Andhra Pradesh at Hyderabad, in Harsha Constructions v. Union of India 2005 SCC OnLine AP 730, (2005) 6 ALD 287, this appeal has been filed by M/s Harsha Constructions, a contractor, against the Union of India and its authorities. Hereinafter, the appellant has been described as “the contractor”.

2. The Union of India had entered into a contract for construction of a road bridge at a level crossing and in the said contract there was a clause with regard to arbitration. The issue with which we are concerned in the instant case, in a nutshell, is as under:

“When in a contract of arbitration, certain disputes are expressly ‘excepted’, whether the arbitrator can arbitrate on such excepted issues and what are the consequences if the arbitrator decides such issues?”

3. For the purpose of considering the issue, in our opinion, certain clauses incorporated in the contract are relevant and those clauses are reproduced hereinbelow:

“Clause 39.—Any item of work carried out by the contractor on the instructions of the Engineer which is not included in the accepted schedule of rates shall be executed at the rates set forth in the ‘Schedule of Rates, South Central Railway’ modified by the tender percentage and where such items are not contained in the latter at the rates agreed upon between the Engineer and the contractor before the execution of such items of work and the contractor shall be bound to notify the Engineer at least seven days before the necessity arises for the execution of such items of work that the accepted schedule of rates does not include a rate or rates for the extra work involved.
The rates payable for such items shall be decided at the meeting to be held between the Engineer and the contractor in as short a period as possible after the need for the special item has come to the notice. In case the contractor fails to attend the meeting after being notified to do so or in the event of no settlement being arrived at, the Railway shall be entitled to execute the extra works by other means and the contractor shall have no claim for loss or damage that may result from such procedure. Provided that if the contractor commences work or incurs any expenditure in regard thereto before the rates are determined and agreed upon as lastly mentioned, then and in such a case the contractor shall only be entitled to be paid in respect of the work carried out or expenditure incurred by him prior to the date of the rates as aforesaid according to the rates as shall be fixed by the Engineer. However, if the contractor is not satisfied with the decision of the Engineer in this respect he may appeal to the Chief Engineer within 30 days of getting the decision of the Engineer supported by the analysis of the rates claimed. The Chief Engineer's decision after hearing both the parties in the matter would be final and binding on the contractor and the Railway.
***
Clause 63.—All disputes and differences of any kind whatsoever arising out of or in connection with the contract whether during the progress of the work or after its completion and whether before or after the determination of the contract shall be referred by the contractor to the Railway and the Railway shall within a reasonable time after receipt of the contractor's presentation make and notify decisions on all matters referred to by the contractor in writing provided that matters for which provision has been made in Clauses 18, 22(5), 39, 45(a), 55, 55-A(5), 61(2) and 62(1)(xiii)(B)(e)(b) of the general conditions of contract or in any clause of the special conditions of the contract shall be deemed as “excepted matters” and decisions thereon shall be final and binding on the contractor; provided further that excepted matters shall stand specifically excluded from the purview of the arbitration clause and shall not be referred to arbitration.”

4. Upon perusal of Clause 63 of the aforestated contract, it is quite clear that the matters for which provision had been made in Clauses 18, 22(5), 39, 45(a), 55, 55-A(5), 61(2) and 62(1)(xiii)(B)(e)(b) of the general conditions of contract were “excepted matters” and they were not to be referred to the arbitrator.

5. In the instant case, we are concerned with a dispute which had arisen with regard to the amount payable to the contractor in relation to extra work done by the contractor.

6. Upon perusal of Clause 39, we find that in the event of extra or additional work entrusted to the contractor, if rates at which the said work was to be done was not specified in the contract, the amount payable for the additional work done was to be discussed by the contractor with the Engineer concerned and ultimately the rate was to be decided by the Engineer. If the rate fixed by the Engineer was not acceptable to the contractor, the contractor had to file an appeal to the Chief Engineer within 30 days of getting the decision of the Engineer and the Chief Engineer's decision about the amount payable was to be final.

7. It is not in dispute that some work, which was not covered under the contract had been entrusted to the contractor and for determining the amount payable for the said work, certain meetings had been held by the contractor and the Engineer concerned but they could not agree to any rate. Ultimately, some amount was paid in respect of the additional work done, which was not acceptable to the contractor but the contractor accepted the same under protest.

8. In addition to the aforestated dispute with regard to determination of the rate at which the contractor was to be paid for the extra work done by it, there were some other disputes also and in order to resolve all those disputes, Respondent 5, a former Judge of the High Court of Andhra Pradesh, had been appointed as an arbitrator.

9. The learned arbitrator decided all the disputes under his award dated 21-9-2002 though the contractor had objected to the arbitrability of the disputes which were not referable to the arbitrator as per Clause 39 of the contract. Being aggrieved by the award, the Union of India had preferred an appeal before the Chief Judge, City Civil Court, Hyderabad under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “the Act”) and the said appeal was allowed, whereby the award was set aside.

10. Before the City Civil Court, in the appeal filed under Section 34 of the Act, the following two issues had been framed:

(a) Whether the dispute was in relation to an “excepted matter” and was not arbitrable?
(b) Whether the claimant was entitled to the amounts awarded by the arbitrator?

The court decided the appeal in favour of the respondent and against the contractor. Being aggrieved by the order dated 8-4-2005 passed by the XIVth Additional Chief Judge, City Civil Court, Hyderabad, CMA No. 476 of 2005 was filed by the contractor before the High Court and the High Court was pleased to dismiss the same by virtue of the impugned judgment 2005 SCC OnLine AP 730, (2005) 6 ALD 287 and therefore, the contractor has filed this appeal.

11*. The learned counsel appearing for the appellant contractor had mainly submitted that as per Clause 39 of the contract, the Engineer of the respondent authorities was duty-bound to decide the rate at which payment was to be made for the extra work done by the contractor, through negotiations between the parties. A final decision on the said subject was taken by the respondent authorities without the contractor's approval and therefore, there was a dispute between the parties. He had further submitted that no specific decision was taken by the Engineer and therefore, there was no question of filing any appeal before the Chief Engineer and as the Chief Engineer did not take any decision, the aforestated clauses viz. Clauses 39 and 64 would not apply because Clause 64 would “except” a decision of the Chief Engineer, but as the Chief Engineer had not taken any decision, there was no question with regard to referring to Clause 39. He had, therefore, submitted that the award in toto was correct and the High Court had wrongly upheld the dismissal of the award by the trial court.

12. The learned counsel had, thereafter, referred to the judgments delivered by this Court in Northern Railway v. Sarvesh Chopra (2002) 4 SCC 45 and Madnani Construction Corpn. (P) Ltd. v. Union of India (2010) 1 SCC 549 to substantiate his case. The learned counsel had, thereafter, submitted that the appeal deserves to be allowed and the judgment delivered by the High Court confirming the order passed by the City Civil Court deserves to be quashed and set aside.

13. There was no representation on behalf of the Union of India and therefore, we are constrained to consider the submissions made by the learned counsel for the appellant only.

14. Upon perusal of both the clauses included in the contract, which have been referred to hereinabove, it is crystal clear that all the disputes were not arbitrable. Some of the disputes which had been referred to in Clause 39 were specifically not arbitrable and in relation to the said disputes the contractor had to negotiate with the Engineer concerned of the respondent and if the contractor was not satisfied with the rate determined by the Engineer, it was open to the contractor to file an appeal against the decision of the Engineer before the Chief Engineer within 30 days from the date of communication of the decision to the contractor.

15. In the instant case, there was no finality so far as the amount payable to the contractor in relation to the extra work done by it is concerned, because the said dispute was never decided by the Chief Engineer. In the aforestated circumstances, when the disputes had been referred to the arbitrator, the disputes which had been among “excepted matters” had also been referred to the learned arbitrator.

16. Upon perusal of the case papers we find that before the learned arbitrator, the contractor did object to the arbitrability of the disputes covered under Clause 39, but the arbitrator had decided the said issues by holding that the same were not “excepted matters” but arbitrable.

17. The question before this Court is whether the arbitrator could have decided the issues which were not arbitrable.

18. Arbitration arises from a contract and unless there is a specific written contract, a contract with regard to arbitration cannot be presumed. Section 7(3) of the Act clearly specifies that the contract with regard to arbitration must be in writing. Thus, so far as the disputes which have been referred to in Clause 39 of the contract are concerned, it was not open to the arbitrator to arbitrate upon the said disputes as there was a specific clause whereby the said disputes had been “excepted”. Moreover, when the law specifically makes a provision with regard to formation of a contract in a particular manner, there cannot be any presumption with regard to a contract if the contract is not entered into by the mode prescribed under the Act.

19. If a non-arbitrable dispute is referred to an arbitrator and even if an issue is framed by the arbitrator in relation to such a dispute, in our opinion, there cannot be a presumption or a conclusion to the effect that the parties had agreed to refer the issue to the arbitrator. In the instant case, the respondent authorities had raised an objection relating to the arbitrability of the aforestated issue before the arbitrator and yet the arbitrator had rendered his decision on the said “excepted” dispute. In our opinion, the arbitrator could not have decided the said “excepted” dispute. We, therefore, hold that it was not open to the arbitrator to decide the issues which were not arbitrable and the award, so far as it relates to disputes regarding non-arbitrable disputes is concerned, is bad in law and is hereby quashed.

20. We also take note of the fact that the contract had been entered into by the parties on 24-4-1995 and the contractual work had been finalised on 31-3-1997. The award was made on 21-9-2002 and therefore, we uphold the portion of the award so far as it pertains to the disputes which were arbitrable, but so far as the portion of the arbitral award which determines the rate for extra work done by the contractor is concerned, we quash and set aside the same. Needless to say that it would be open to the contractor to take appropriate legal action for recovery of payment for work done, which was not forming part of the contract because the said issue decided by the arbitrator is now set aside.

21. For the reasons recorded hereinabove, the appeal is partly allowed with no order as to costs.