Union Of India v. Sandur Manganese And Iron Ores Limited And Others
Factual and Procedural Background
The Union of India, Ministry of Mines, filed a review petition seeking reconsideration of the Supreme Court’s judgment dated 13 September 2010 in Sandur Manganese & Iron Ores Ltd. v. State of Karnataka (2010) 13 SCC 1. In the original decision, the Court interpreted key provisions of the Mines and Minerals (Development and Regulation) Act, 1957 (“MMDR Act”) and the Mineral Concession Rules, 1960, ultimately quashing State and Central Government decisions that had denied a mining lease to Sandur and directing a fresh consideration of all applications.
The Ministry of Mines contended that it had not been served with the special leave petition in the earlier proceedings because, after a 2003 bifurcation, the pleadings were erroneously addressed to the “Ministry of Coal and Mines.” Claiming lack of notice and opportunity of hearing, the Ministry sought review and requested condonation of a 320-day delay in filing. The Supreme Court condoned the delay and heard the Review Petitioner (Union of India) as well as counsel for Sandur, the State of Karnataka, and other contesting respondents.
Legal Issues Presented
- Whether the Union of India demonstrated “sufficient cause” for condoning a delay of 320 days in filing the review petition.
- Whether the Supreme Court’s 2010 judgment misquoted the “Report of the Committee to Review the Existing Laws and Procedures for Regulation and Development of Minerals,” and, if so, whether that misquotation warranted substantive alteration of the earlier judgment under review jurisdiction.
- Whether Sections 11(2) and 11(4) of the MMDR Act apply to both virgin mineral areas and previously held areas, thereby necessitating a reconsideration of the 2010 interpretation.
Arguments of the Parties
Union of India (Review Petitioner)
- The Ministry was a necessary party but was never served; principles of natural justice were violated.
- The Expert Committee Report was misquoted in four additional lines, rendering the ratio of the 2010 judgment legally erroneous.
- Sections 11(2) and 11(4) of the MMDR Act should apply uniformly to virgin and previously held areas; the contrary view in the 2010 judgment constituted an apparent error.
Respondents (Sandur, State of Karnataka and others)
- Delay was inadequately explained and the review petition sought to re-argue matters already decided.
- Any misquotation was merely clerical; deletion of the lines would not alter the substantive reasoning.
- The scope of review under Article 137 and Order XL Rule 1 of the Supreme Court Rules is limited to errors apparent on the face of the record, not to re-litigate competing interpretations.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Sandur Manganese & Iron Ores Ltd. v. State of Karnataka, (2010) 13 SCC 1 | Impugned judgment under review; interpretation of MMDR Act §11 and MC Rules 35, 59, 60 | Examined to assess alleged misquotation and substantive correctness |
| Chhajju Ram v. Neki, (1921-22) 49 IA 144 | Meaning of “any other sufficient reason” in review proceedings | Used to clarify statutory grounds available under Order 47 Rule 1 CPC |
| Moran Mar Basselios Catholicos v. Mar Poulose Athanasius, AIR 1954 SC 526 | Approved interpretation of “any other sufficient reason” | Cited to confirm narrow scope of review jurisdiction |
| Parsion Devi v. Sumitri Devi, (1997) 8 SCC 715 | Error apparent on the face of the record; review cannot be an appeal in disguise | Relied upon to reject re-arguing statutory interpretation as a review ground |
| Monnet Ispat & Energy Ltd. v. Union of India, (2012) 11 SCC 1 | Subsequent affirmation of the 2010 Sandur ratio | Highlighted to show consistent judicial approval of the earlier reasoning |
Court's Reasoning and Analysis
Condonation of Delay: The Court accepted the Ministry’s explanation that internal processing across different departmental levels accounted for the 320-day delay and therefore condoned it.
Ground 1 — Misquotation of Expert Committee Report: The Court found that four lines quoted in para 2.1.21 of the Report had indeed been erroneously inserted in the 2010 judgment. Exercising its review power, the Court ordered deletion of those lines and a related passage in para 51 of the earlier judgment. However, it held that the substantive reasoning of the 2010 decision remained intact even without the misquoted text.
Ground 2 — Applicability of Sections 11(2) & 11(4): The Court reiterated that differing interpretations are insufficient for review. No “error apparent” or “glaring omission” was shown; the issue had already been fully addressed in the 2010 judgment. Citing Parsion Devi, the Court held that review cannot be used as an appeal in disguise.
Other Contentions: Assertions concerning Memoranda of Understanding, prior commitments by the State, and mineral policies had been considered and rejected in the 2010 decision and could not be reopened. The Court also noted that a coordinate Bench had followed the same ratio in Monnet Ispat, reinforcing the correctness of the earlier interpretation.
Holding and Implications
Holding: The review petition is DISMISSED, save for the limited correction deleting the misquoted lines in the 2010 judgment. Impleadment applications were also dismissed.
Implications: The substantive directions in Sandur (2010) 13 SCC 1 remain operative. The State Government receives an additional four-month period to comply with para 98 of the original judgment. No new precedent was established; the decision reinforces the constrained scope of Supreme Court review jurisdiction and corrects a clerical error without altering the legal ratio.
P. Sathasivam, J.— This review petition has been filed by the Union of India, Ministry of Mines, seeking review of the judgment and order dated 13-9-2010 passed in Sandur Manganese & Iron Ores Ltd. v. State of Karnataka (2010) 13 SCC 1.
2. In Sandur (2010) 13 SCC 1, this Court had interpreted various provisions of the Mines and Minerals (Development and Regulation) Act, 1957 (in short “the MMDR Act”) and the Mineral Concession Rules, 1960 (in short “the MC Rules”) framed thereunder. It is the grievance of the petitioner herein that this review is instituted since the Ministry of Mines, Government of India, could not put forth its view on the interpretation of the provisions of the MMDR Act in Sandur (2010) 13 SCC 1 for the reason that the copy of the special leave petition was not served upon the review petitioner which is a necessary and relevant party to the subject-matter in issue/dispute and the review petitioner did not get an opportunity of being heard.
3. It is also brought to our notice that vide Notification dated 30-1-2003, the Ministry of Coal and Mines was bifurcated into separate ministries since the petitioners in various SLPs furnished the name of the ministry as “Ministry of Coal and Mines” in all the matters and according to them, it was not noticed by the department concerned, namely, the Department of Mines.
4. We are conscious of the fact that the principles of natural justice guarantee every person the right to represent his/her case in the court of law, wherein the final verdict of the court would adversely affect his/her interest. Considering the above principle, this Court, vide order dated 4-10-2012 (2012) 9 SCC 683, granted the opportunity to the Union of India to represent its case.
5. Before considering the claim of the Union of India about acceptability or otherwise of various conclusions in the impugned judgment (2010) 13 SCC 1, we have to consider whether the petitioner has shown sufficient cause for condoning the delay of 320 days.
6. The details furnished in IA No. 1 of 2011 filed for condoning the delay in filing the above review petition sufficiently prove that steps were taken at various levels in the Ministry of Mines, accordingly, we accept the reasons furnished therein. In view of the same, the delay is condoned.
7. Taking note of the reasons stated for the delay and the stand of the Department that the Ministry concerned, namely, Department of Mines was not duly projected and represented before this Court, we heard Mr Goolam E. Vahanvati, learned Attorney General for the review petitioner, on merits, particularly, with reference to the points formulated for consideration and ultimate conclusion arrived at therein and Mr Fali S. Nariman, Mr Mukul Rohatgi, Mr A.M Singhvi, Mr Krishnan Venugopal, Mr L.N Rao, learned Senior Counsel for the contesting respondents and Ms Anita Shenoy, learned counsel for the State of Karnataka.
8. Now, let us consider whether the review petitioner has made out a case for reviewing the judgment and order dated 13-9-2010 (2010) 13 SCC 1 and satisfies the criteria for entertaining the matter in review jurisdiction.
Review jurisdiction
9. Article 137 of the Constitution of India provides for review of judgments or orders by the Supreme Court which reads as under:
“137. Review of judgments or orders by the Supreme Court.—Subject to the provisions of any law made by Parliament or any rules made under Article 145, the Supreme Court shall have power to review any judgment pronounced or order made by it.”
10. Further, Part VIII Order 40 of the Supreme Court Rules, 1966 deals with the review and consists of four rules. Rule 1 is important for our purpose which reads as under:
“1. The Court may review its judgment or order, but no application for review will be entertained in a civil proceeding except on the ground mentioned in Order 47 Rule 1 of the Code and in a criminal proceeding except on the ground of an error apparent on the face of the record.”
11. Order 47 Rule 1(1) of the Code of Civil Procedure, 1908 provides for an application for review which reads as under:
“1. Application for review of judgment.—Any person considering himself aggrieved—
(a) by a decree or order from which an appeal is allowed, but from which no appeal has been preferred,
(b) by a decree or order from which no appeal is allowed, or
(c) by a decision on a reference from a Court of Small Causes,
and who, from the discovery of new and important matter or evidence which, after the exercise of due diligence, was not within his knowledge or could not be produced by him at the time when the decree was passed or order made, or on account of some mistake or error apparent on the face of the record, or for any other sufficient reason, desires to obtain a review of the decree passed or order made against him, may apply for a review of judgment to the court which passed the decree or made the order.”
12. Thus, in view of the above, the following grounds of review are maintainable as stipulated by the statute:
12.1 Discovery of new and important matter or evidence which, after the exercise of due diligence, was not within the knowledge of the petitioner or could not be produced by him.
12.2 Mistake or error apparent on the face of the record.
12.3 Any other sufficient reason. The words “any other sufficient reason” have been interpreted in Chhajju Ram v. Neki (1921-22) 49 IA 144, (1922) 16 LW 37, AIR 1922 PC 112 and approved by this Court in Moran Mar Basselios Catholicos v. Mar Poulose Athanasius AIR 1954 SC 526, (1955) 1 SCR 520, to mean “a reason sufficient on grounds, at least analogous to those specified in the rule”.
13. With the above statutory provisions, let us discuss the claim of the petitioner Union of India.
Discussion
14. The respondent Company (Sandur Manganese and Iron Ores Ltd.) by filing SLP (C) No. 22077 of 2009 (converted into Civil Appeal No. 7944 of 2010) challenged before this Court the final judgment and order dated 5-6-2009 passed by the High Court of Karnataka at Bangalore in Sandur Manganese and Iron Ores Ltd. v. State of Karnataka Writ Appeal No. 5084 of 2008 and allied matters wherein the High Court dismissed the appeals and held that the decision of the State Government in not recommending mining lease to Sandur Manganese and Iron Ores Ltd. and instead of preferring two other companies for grant of mining lease does not suffer from any irregularity, illegality, discrimination, arbitrariness, unreasonableness or violative of principles of natural justice.
15. This Court, in Sandur (2010) 13 SCC 1, allowed the appeal filed by Sandur Manganese and Iron Ores Ltd. and quashed the impugned order dated 5-6-2009 passed by the Division Bench of the High Court of Karnataka in Sandur Manganese and Iron Ores Ltd. v. State of Karnataka Writ Appeal No. 5084 of 2008, etc., etc. as well as the decision of the State Government dated 26-2-2002/27-2-2002 and the subsequent decision of the Central Government dated 29-7-2003 and directed the State Government to consider all applications afresh in the light of this Court's interpretation of Section 11 of the MMDR Act and Rules 35, 59 and 60 of the MC Rules in particular, and make recommendation to the Central Government within a period of four months.
16. Consequently, the Union of India has raised mainly two issues on merits of the case, thereby challenging the impugned judgment (2010) 13 SCC 1. They are:
16.1 Firstly, that the impugned judgment (2010) 13 SCC 1 has incorrectly reported the Report of the Committee to Review the Existing Laws and Procedures for Regulation and Development of Minerals. As a consequence, the ratio of impugned judgment (2010) 13 SCC 1, which relies on this Expert Committee Report, shall stand erroneous in the eye of the law.
16.2 Secondly, Section 11(2) and Section 11(4) should be applicable to both virgin and previously held areas.
17. Now we shall discuss the abovementioned issues respectively.
First contention
18. The first contention of the learned Attorney General is twofold viz. that the Expert Committee's Report was misquoted and as a result the impugned judgment (2010) 13 SCC 1 which relies on the same, shall stand erroneous on the face of law. We accede to the above contention partially. It is true that the Expert Committee's Report has been misquoted to the extent of adding four lines, which was originally not a part of the report. Thus, this Court has the power to modify the impugned judgment (2010) 13 SCC 1 to the extent of deletion of the misquoted statement under review jurisdiction.
19. The Report of the Committee to Review the Existing Laws and Procedures for Regulation and Development of Minerals, referred in the impugned judgment (2010) 13 SCC 1 reads as under:
Para 2.1.21 of the Report:
“49. … ‘… The concept of first-come, first-serve has become necessary in view of the fact that the Act does not provide for inviting applications through advertisement for grant of PL/ML in respect of virgin areas. No doubt, there is provision in Rule 59 of the MC Rules for advertisement of an area earlier held under PL/ML with provision for relaxation. In this background, the Committee recommended the introduction of the proviso to Section 11(2) permitting calling for applications by way of a notification. There is a distinction between virgin areas and areas covered under Rule 59 and Section 11(2) ought to be interpreted to cover virgin areas alone.’”
(emphasis supplied)
Hence, the above underlined portion of the Report which is misquoted in the impugned judgment (2010) 13 SCC 1 owing to clerical mistake requires to be deleted, accordingly, we do so.
20. However, we are not in agreement with the learned Attorney General that the impugned judgment (2010) 13 SCC 1 is erroneous on the face of law merely because the Expert Committee's Report was misquoted. In our considered view, the impugned judgment (2010) 13 SCC 1 stands good of reason even without these misquoted lines as well. Hence, mere deletion of these lines along with removal of certain portion of para 51 of the impugned judgment (2010) 13 SCC 1 will clarify the mistake.
21. Portion of para 51 of Sandur (2010) 13 SCC 1 to be deleted:
“51. … The analysis of the Report makes it clear that the main provision in Section 11(2) applies to ‘virgin areas’. It further makes it clear that to the extent that an area that is previously held or reserved would require a notification for it to become available.”
Thus the first contention is considered as per the above terms.
Second contention
22. With regard to the second contention that both Section 11(2) and Section 11(4) should be applicable to both virgin and previously held areas, the same has been well reasoned in the impugned judgment (2010) 13 SCC 1 and the mere fact that different views on the same subject are possible is no ground to review the earlier judgment passed by this Bench.
23. It has been time and again held that the power of review jurisdiction can be exercised for the correction of a mistake and not to substitute a view. In Parsion Devi v. Sumitri Devi (1997) 8 SCC 715, this Court held as under:
“9. Under Order 47 Rule 1 CPC a judgment may be open to review inter alia if there is a mistake or an error apparent on the face of the record. An error which is not self-evident and has to be detected by a process of reasoning, can hardly be said to be an error apparent on the face of the record justifying the court to exercise its power of review under Order 47 Rule 1 CPC. In exercise of the jurisdiction under Order 47 Rule 1 CPC it is not permissible for an erroneous decision to be ‘reheard and corrected’. A review petition, it must be remembered has a limited purpose and cannot be allowed to be ‘an appeal in disguise’.”
24. This Court, on numerous occasions, had deliberated upon the very same issue, arriving at the conclusion that review proceedings are not by way of an appeal and have to be strictly confined to the scope and ambit of Order 47 Rule 1 CPC.
25. In the present case, the error contemplated in the impugned judgment (2010) 13 SCC 1 is not one which is apparent on the face of the record rather the dispute is wholly founded on the point of interpretation and applicability of Sections 11(2) and 11(4) of the MMDR Act. In review jurisdiction, mere disagreement with the view of the judgment cannot be the ground for invoking the same. As long as the point is already dealt with and answered, the parties are not entitled to challenge the impugned judgment (2010) 13 SCC 1 in the guise that an alternative view is possible under the review jurisdiction. Hence, in review jurisdiction, the Court shall interfere only when there is a glaring omission or patent mistake or when a grave error has crept in the impugned judgment (2010) 13 SCC 1, which we fail to notice in the present case.
26. For the above reasons, the second ground for review petition is liable to be rejected.
27. Further, the contention regarding MoU entered into by the State Government and investments made thereunder is concerned, this Court has noticed this fact and rejected the contention made by the respondents in Sandur (2010) 13 SCC 1. It is relevant to point out that the State of Karnataka is stated to have committed to JSW Steels Limited on 11-10-1994 for grant of mining leases but the same has been invoked by JSW Steels after a lapse of 8 years and more precisely, after 5 years of commencing commercial operations in its steel plant by making an application on 24-10-2002. Once an area is notified for regrant and applications are invited from the mining public for grant of mining lease, the applications must be disposed of in terms of the provisions of the MMDR Act and the MC Rules and not dehors.
28. In para 80 of Sandur Manganese (2010) 13 SCC 1, this Court has held as follows:
“80. It is clear that the State Government is purely a delegate of Parliament and a statutory functionary, for the purposes of Section 11(3) of the Act, hence it cannot act in a manner that is inconsistent with the provisions of Section 11(1) of the MMDR Act in the grant of mining leases. Furthermore, Section 2 of the Act clearly states that the regulation of mines and mineral development comes within the purview of the Union Government and not the State Government. As a matter of fact, the respondents have not been able to point out any other provision in the MMDR Act or the MC Rules permitting grant of mining lease based on past commitments. As rightly pointed out, the State Government has no authority under the MMDR Act to make commitments to any person that it will, in future, grant a mining lease in the event that the person makes investment in any project. Assuming that the State Government had made any such commitment, it could not be possible for it to take an inconsistent position and proceed to notify a particular area. Further, having notified the area, the State Government certainly could not thereafter honour an alleged commitment by ousting other applicants even if they are more deserving on the merit criteria as provided in Section 11(3).”
Hence, the petitioner cannot be permitted to reargue the very same point.
29. Regarding the issue of mineral policies, this Court has already held in Sandur (2010) 13 SCC 1 that:
“40. In view of the specific parliamentary declaration as discussed and explained by this Court in various decisions, there is no question of the State having any power to frame a policy dehors the MMDR Act and the MC Rules.”
30. In view of the above, the petitioner Union of India has not invoked any valid ground for exercising the power under review jurisdiction. In addition to the same, after the judgment in Sandur (2010) 13 SCC 1, another coordinate Bench of this Court followed the ratio decidendi in Monnet Ispat and Energy Ltd. v. Union of India (2012) 11 SCC 1.
31. For the aforesaid reasons, we are unable to accept any of the contentions raised by the learned Attorney General, therefore, the review petition is disposed of by deleting the misquoted lines in the Expert Committee's Report.
32. In view of the above order and the directions issued by us in para 98 of Sandur (2010) 13 SCC 1, we grant a further period of 4 months from the date of receipt of copy of this order to comply with the same.
33. In view of the dismissal of the review petition filed by the Union of India, the impleadment applications stand dismissed.