Login
  • Bookmark
  • PDF
  • Share
  • CaseIQ

Premji Nathu v. State Of Gujarat And Another

Supreme Court Of India
Apr 9, 2012
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The appellant’s agricultural land was acquired by the State of Gujarat for the Mendarda-Amrapur Road Scheme. A notification under Section 4(1) of the Land Acquisition Act, 1894 was issued on 4 March 1982, followed by a declaration under Section 6(1) on 7 October 1982. The Special Land Acquisition Officer fixed compensation at Rs 110 per are for irrigated land and Rs 80 per are for non-irrigated land.

After the award, the Collector served the appellant with a notice under Section 12(2) on 22 February 1985; however, the notice did not enclose a copy of the award. The appellant obtained a certified copy independently and, on 8 April 1985, filed an application under Section 18(1) seeking a reference for higher compensation.

The Collector forwarded the reference as LR Case No. 1/2000, while references by other landowners were numbered LR Cases 2–15/2000. The Reference Court held that although higher rates were otherwise justified (Rs 450 per are for irrigated and Rs 280 per are for non-irrigated land with Rs 2 per sq m), the appellant’s application was time-barred under Section 18(2)(b). The Gujarat High Court affirmed this view, relying on a Full Bench decision in Land Acquisition Officer v. Nathaji Kacharaji (2001).

Legal Issues Presented

  1. Whether the appellant’s application under Section 18(1) of the Land Acquisition Act was barred by limitation prescribed in Section 18(2)(b).
  2. Consequently, whether the Reference Court was correct in refusing to entertain the prayer for enhancement of compensation.

Arguments of the Parties

Appellant's Arguments

  • The application dated 8 April 1985 was filed within six weeks because 5 April 1985 (Good Friday) and 6 April 1985 were holidays, making the next working day 8 April 1985.
  • The notice under Section 12(2) did not contain a copy of the award; without that document, computation of the six-week period should not run.
  • The Reference Court and High Court adopted a hyper-technical approach that deprived landowners of their statutory right to seek higher compensation.

Respondents' Arguments

  • Produced the 1985 Gujarat calendar showing that 6 April 1985 was a working day; therefore, counting six weeks from 22 February 1985 rendered the application late.
  • Maintained that the Reference Court and High Court correctly applied the limitation provisions of Section 18(2)(b).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Harish Chandra Raj Singh v. Land Acquisition Officer, AIR 1961 SC 1500 “Date of award” involves communication of the award; limitation begins when essential contents are known. Used to stress that notice under Section 12(2) must convey the award’s contents; absence of copy paused limitation.
State of Punjab v. Qaisar Jehan Begum, AIR 1963 SC 1604 Knowledge required is of the essential contents, not mere fact of award. Reinforced the need to supply award copy with notice for limitation to run.
Bhagwan Das v. State of U.P., (2010) 3 SCC 545 Laid down propositions on limitation under Section 18 and burden of proof regarding knowledge. Court cited to assign initial onus on claimant but noted State produced no evidence of serving award copy.
Land Acquisition Officer v. Nathaji Kacharaji, (2001) 3 Guj LH 312 (FB) High Court precedent holding applications time-barred in similar circumstances. Supreme Court overruled High Court’s reliance, distinguishing on facts (absence of award copy).
B.N. Nagarajan v. State of Mysore, AIR 1966 SC 1942 Power under Article 142 to extend benefits to non-petitioners. Invoked to grant enhanced compensation to landowners who had not appealed.
Bhupinderpal Singh v. State of Punjab, (2000) 5 SCC 262 Article 142 used for complete justice. Supported extension of relief to similarly situated landowners.
Nilabati Behera v. State of Orissa, (1993) 2 SCC 746 Broad remedial powers under Article 142. Cited for same purpose as above.
B. Prabhakar Rao v. State of A.P., 1985 Supp SCC 432 Granting relief beyond parties before Court. Formed part of chain of precedents justifying extension of benefits.

Court's Reasoning and Analysis

The Supreme Court noted that Section 18(2)(b) allows six weeks from the “receipt of notice under Section 12(2)” for filing a reference only when the notice conveys the award’s essential contents. Relying on Harish Chandra and subsequent cases, the Court emphasised that effective knowledge of the award is indispensable for the limitation clock to start.

Evidence on record showed that the Collector’s notice dated 22 February 1985 was unaccompanied by a copy of the award. The State produced no proof to the contrary. The appellant therefore had to secure a certified copy independently before he could meaningfully object. The application filed on 8 April 1985 was, thus, within time.

The Reference Court had “mechanically” concluded that the application was late and the High Court endorsed that view without examining the absence of the award copy. Both courts were found to have erred in law.

Having accepted that the limitation objection failed, the Supreme Court reinstated the Reference Court’s own assessment of market value—Rs 450 per are for irrigated land, Rs 280 per are for non-irrigated land, plus Rs 2 per square metre—and directed payment of statutory solatium and interest.

Invoking Article 142 and guided by precedents such as B.N. Nagarajan and Bhupinderpal Singh, the Court extended identical relief to other landowners affected by the same acquisition, regardless of whether they had pursued further appeals.

Holding and Implications

Appeal Allowed; High Court judgment and Reference Court award set aside. The respondents must pay enhanced compensation at the rates specified, together with solatium and interest, within three months. Identical benefits are extended to all similarly situated landowners.

Implications: The decision underscores that limitation under Section 18(2)(b) does not begin unless the notice under Section 12(2) communicates the award’s essential contents, preferably by supplying a copy. It also affirms the Supreme Court’s readiness to invoke Article 142 to ensure uniform relief where justice so demands, without setting new doctrinal precedent beyond the specific statutory interpretation.

Show all summary ...

G.S Singhvi, J.— Whether the application submitted by the appellant under Section 18(1) of the Land Acquisition Act, 1894 (for short “the Act”) was barred by time and the Civil Judge (Senior Division), Junagadh (hereinafter described as “the Reference Court”) rightly refused to entertain his prayer for enhancement of the compensation determined by the Special Land Acquisition Officer is the question which arises for consideration in this appeal filed against the judgment dated 16-8-2011 First Appeal No. 3502 of 2009 of the learned Single Judge of the Gujarat High Court.

2. The appellant's land was acquired by the State Government along with other parcels of land for implementation of Mendarda-Amrapur Road Scheme. The Notification under Section 4(1) was issued on 4-3-1982 and the declaration under Section 6(1) was published on 7-10-1982. The Special Land Acquisition Officer determined the amount of compensation at the rate of Rs 110 per are for irrigated land and Rs 80 per are for non-irrigated land.

3. After passing of the award, the Collector issued notice to the appellant under Section 12(2), which was received by him on 22-2-1985. Similar notices were received by the other landowners on 22-2-1985 and 23-2-1985. As the copy of the award was not annexed with the notice, the appellant obtained certified copy thereof through his advocate and then submitted an application dated 8-4-1985 to the Collector for making a reference to the court for award of higher compensation with solatium and interest.

4. The reference made by the Collector in the appellant's case was registered as LR Case No. 1 of 2000. The references made at the instance of the other landowners were registered as LR Cases Nos. 2 to 15 of 2000. In their claim petitions, the appellant and other landowners pleaded that their land had irrigation facilities; that they were taking crops of groundnut, wheat, fodder, etc. and they are entitled to compensation at the rate of Rs 1500 per are.

5. In the reply filed on behalf of the State Government, it was pleaded that the Special Land Acquisition Officer had correctly fixed the market value of the acquired land after taking into consideration the location, type and fertility of the acquired land. It was also pleaded that the landowners are not entitled to higher compensation because they had accepted the award without any protest.

6. It is not clear from the record whether in the reply filed on behalf of the State Government, an objection was taken to the maintainability of the applications filed by the appellant and other landowners on the ground that the same were barred by time but the Reference Court did frame an issue in that regard. This is evident from the tenor of the issues framed by the Reference Court, which are extracted below:

“(1) Whether the applicant proves that the compensation awarded is inadequate? How much?
(2) What additional compensation, if any, he is entitled to?
(3) Whether this application is in time?
(4) Whether this Court has jurisdiction to try this reference case?
(5) Whether this reference case is barred by Section 25 of the LA Act?
(6) Whether the applicants have accepted the awarded amount without raising any objection? If yes, what is the effect?
(7) Whether the applicant is entitled to get the amount of solatium and interest?
(8) What order?”

7. After considering the oral and documentary evidence produced by the parties, the Reference Court concluded that the landowners are entitled to Rs 450 per are for the irrigated land and Rs 280 per are for non-irrigated land with an additional amount of Rs 2 per square metre, but declined relief to the appellant and other landowners on the ground that the applications filed by them were beyond the time specified in Section 18(2)(b) of the Act.

8. The appellant and three other landowners challenged the judgment of the Reference Court by filing appeals under Section 54 of the Act which were dismissed by the learned Single Judge of the High Court vide judgment dated 16-8-2011 First Appeal No. 3502 of 2009, who relied upon the judgment of the Full Bench of the High Court in Land Acquisition Officer v. Nathaji Kacharaji (2001) 3 Guj LH 312 and held that the applications filed by the appellant and other landowners were barred by time.

9. The learned counsel for the appellant argued that the application filed by his client was within the period prescribed under Section 18(2)(b) of the Act and the Reference Court and the learned Single Judge of the High Court committed serious error by refusing to enhance the compensation by erroneously thinking that the application made on 8-4-1985 was barred by time. He submitted that 5-4-1985 and 6-4-1985 were holidays and, as such, the application filed by the appellant on 8-4-1985 could not have been treated as barred by time. The learned counsel further submitted that due to hypertechnical approach adopted by the Reference Court and the learned Single Judge, the landowners have been rendered remediless.

10. Shri Preetesh Kapur, learned counsel for the respondents produced copy of the calendar of Gujarat for 1985 to show that 5th April was a holiday being Good Friday but 6th April was a working day and argued that if the period of six weeks is counted from the date of receipt of the notice issued under Section 12(2), the conclusion recorded by the Reference Court and the learned Single Judge that the applications filed by the appellant and other landowners were beyond the time prescribed under Section 18(2)(b) of the Act cannot be faulted.

11. We have considered the respective arguments and carefully perused the record. Sections 12 and 18 of the Act, which have bearing on the decision of this appeal read as under:

“12. Award of Collector when to be final.—(1) Such award shall be filed in the Collector's office and shall, except as hereinafter provided, be final and conclusive evidence, as between the Collector and the persons interested, whether they have respectively appeared before the Collector or not, of the true area and value of the land, and the apportionment of the compensation among the persons interested.
(2) The Collector shall give immediate notice of his award to such of the persons interested as are not present personally or by their representatives when the award is made.
18. Reference to court.—(1) Any person interested who has not accepted the award may, by written application to the Collector, require that the matter be referred by the Collector for the determination of the court, whether his objection be to the measurement of the land, the amount of the compensation, the person to whom it is payable, or the apportionment of the compensation among the persons interested.
(2) The application shall state the grounds on which objection to the award is taken:
Provided that every such application shall be made—
(a) if the person making it was present or represented before the Collector at the time when he made his award, within six weeks from the date of the Collector's award;
(b) in other cases, within six weeks of the receipt of the notice from the Collector under Section 12 sub-section (2), or within six months from the date of the Collector's award, whichever period shall first expire.”

12. An analysis of the above reproduced provisions shows that by virtue of Section 12(1), an award made by the Collector is treated as final and conclusive evidence of the true area and value of the land and apportionment of the compensation among the persons interested. In terms of Section 12(2), the Collector is required to give notice of his award to the interested persons who are not present either personally or through their representatives at the time of making of award.

13. Section 18(1) provides for making of reference by the Collector to the court for the determination of the amount of compensation, etc. Section 18(2) lays down that an application for reference shall be made within six weeks from the date of the Collector's award, if at the time of making of award the person seeking reference was present or was represented before the Collector. If the person is not present or is not represented before the Collector, then the application for reference has to be made within six weeks of the receipt of notice under Section 12(2) or within six months from the date of the Collector's award, whichever period shall first expire.

14. The reason for providing six months from the date of the award for making an application seeking reference, where the applicant did not receive a notice under Section 12(2) of the Act, while providing only six weeks from the date of receipt of notice under Section 12(2) of the Act for making an application for reference where the applicant has received a notice under Section 12(2) of the Act is obvious. When a notice under Section 12(2) of the Act is received, the landowner or person interested is made aware of all relevant particulars of the award which enables him to decide whether he should seek reference or not. On the other hand, if he only comes to know that an award has been made, he would require further time to make enquiries or secure copies so that he can ascertain the relevant particulars of the award.

15. What needs to be emphasised is that along with the notice issued under Section 12(2) of the Act, the landowner who is not present or is not represented before the Collector at the time of making of award should be supplied with a copy thereof so that he may effectively exercise his right under Section 18(1) to seek reference to the court.

16. In Harish Chandra Raj Singh v. Land Acquisition Officer AIR 1961 SC 1500, this Court was called upon to decide whether the expression “date of award” is to be interpreted with reference to the time when the award is signed by the Collector or from the date the affected party comes to know about the same and held as under: (AIR pp. 1503-04, paras 5-6)

“5. … Therefore, if the award made by the Collector is in law no more than an offer made on behalf of the Government to the owner of the property then the making of the award as properly understood must involve the communication of the offer to the party concerned. That is the normal requirement under the contract law and its applicability to cases of award made under the Act cannot be reasonably excluded. Thus considered the date of the award cannot be determined solely by reference to the time when the award is signed by the Collector or delivered by him in his office; it must involve the consideration of the question as to when it was known to the party concerned either actually or constructively. If that be the true position then the literal and mechanical construction of the words ‘the date of the award’ occurring in the relevant section would not be appropriate.
6. There is yet another point which leads to the same conclusion. If the award is treated as an administrative decision taken by the Collector in the matter of the valuation of the property sought to be acquired it is clear that the said decision ultimately affects the rights of the owner of the property and in that sense, like all decisions which affect persons, it is essentially fair and just that the said decision should be communicated to the said party. The knowledge of the party affected by such a decision, either actual or constructive, is an essential element which must be satisfied before the decision can be brought into force. Thus considered the making of the award cannot consist merely in the physical act of writing the award or signing it or even filing it in the office of the Collector; it must involve the communication of the said award to the party concerned either actually or constructively. If the award is pronounced in the presence of the party whose rights are affected by it it can be said to be made when pronounced. If the date for the pronouncement of the award is communicated to the party and it is accordingly pronounced on the date previously announced the award is said to be communicated to the said party even if the said party is not actually present on the date of its pronouncement. Similarly if without notice of the date of its pronouncement an award is pronounced and a party is not present the award can be said to be made when it is communicated to the party later. The knowledge of the party affected by the award, either actual or constructive, being an essential requirement of fair play and natural justice the expression ‘the date of the award’ used in the proviso must mean the date when the award is either communicated to the party or is known by him either actually or constructively. In our opinion, therefore, it would be unreasonable to construe the words ‘from the date of the Collector's award’ used in the proviso to Section 18 in a literal or mechanical way.”
(emphasis supplied)

17. In State of Punjab v. Qaisar Jehan Begum AIR 1963 SC 1604, the principle laid down in Harish Chandra case AIR 1961 SC 1500 was reiterated and it was held: (AIR p. 1607, para 5)

“5. … It seems clear to us that the ratio of the decision in Harish Chandra case AIR 1961 SC 1500 is that the party affected by the award must know it, actually or constructively, and the period of six months will run from the date of that knowledge. Now, knowledge of the award does not mean a mere knowledge of the fact that an award has been made. The knowledge must relate to the essential contents of the award. These contents may be known either actually or constructively. If the award is communicated to a party under Section 12(2) of the Act, the party must be obviously fixed with knowledge of the contents of the award whether he reads it or not. Similarly when a party is present in court either personally or through his representative when the award is made by the Collector, it must be presumed that he knows the contents of the award. Having regard to the scheme of the Act we think that knowledge of the award must mean knowledge of the essential contents of the award.”
(emphasis supplied)

18. In Bhagwan Das v. State of U.P (2010) 3 SCC 545 this Court interpreted Section 18 and laid down the following propositions:

“(i) If the award is made in the presence of the person interested (or his authorised representative), he has to make the application within six weeks from the date of the Collector's award itself.
(ii) If the award is not made in the presence of the person interested (or his authorised representative), he has to make the application seeking reference within six weeks of the receipt of the notice from the Collector under Section 12(2).
(iii) If the person interested (or his representative) was not present when the award is made, and if he does not receive the notice under Section 12(2) from the Collector, he has to make the application within six months of the date on which he actually or constructively came to know about the contents of the award.
(iv) If a person interested receives a notice under Section 12(2) of the Act, after the expiry of six weeks from the date of receipt of such notice, he cannot claim the benefit of the provision for six months for making the application on the ground that the date of receipt of notice under Section 12(2) of the Act was the date of knowledge of the contents of the award.”

19. The Court in Bhagwan Das (2010) 3 SCC 545 then held:

“30. When a person interested makes an application for reference seeking the benefit of six months' period from the date of knowledge, the initial onus is on him to prove that he (or his representative) was not present when the award was made, that he did not receive any notice under Section 12(2) of the Act, and that he did not have the knowledge of the contents of the award during a period of six months prior to the filing the application for reference. This onus is discharged by asserting these facts on oath. He is not expected to prove the negative. Once the initial onus is discharged by the claimant/person interested, it is for the Land Acquisition Collector to establish that the person interested was present either in person or through his representative when the award was made, or that he had received a notice under Section 12(2) of the Act, or that he had knowledge of the contents of the award.
31. Actual or constructive knowledge of the contents of the award can be established by the Collector by proving that the person interested had received or drawn the compensation amount for the acquired land, or had attested the mahazar/panchnama/proceedings delivering possession of the acquired land in pursuance of the acquisition, or had filed a case challenging the award or had acknowledged the making of the award in any document or in statement on oath or evidence. The person interested, not being in possession of the acquired land and the name of the State or its transferee being entered in the revenue municipal records coupled with delay, can also lead to an inference of constructive knowledge. In the absence of any such evidence by the Collector, the claim of the person interested that he did not have knowledge earlier will be accepted, unless there are compelling circumstances not to do so.”

20. In the light of the above, it is to be seen whether the conclusion recorded by the Reference Court, which has been approved by the High Court that the application filed by the appellant was barred by time is legally sustainable.

21. A careful reading of the averments contained in Para 2 of the application filed by the appellant under Section 18(1) shows that the notice issued by the Collector under Section 12(2) was served upon him on 22-2-1985. Thereafter, his advocate obtained certified copy of the award and filed application dated 8-4-1985 for making a reference to the Court. This implies that the copy of the award had not been sent to the appellant along with the notice and without that he could not have effectively made an application for seeking reference.

22. On behalf of the State Government, no evidence was produced before the Reference Court to show that the copy of the award was sent to the appellant along with the notice. Unfortunately, while deciding Issue 3, this aspect has been totally ignored by the Reference Court which mechanically concluded that the application filed on 8-4-1985 was beyond the time specified in Section 18(2)(b). The learned Single Judge of the High Court also committed serious error by approving the view taken by the Reference Court, albeit without considering the fact that the notice issued by the Collector under Section 12(2) was not accompanied by a copy of the award which was essential for effective exercise of right vested in the appellant to seek reference under Section 18(1).

23. In the result, the appeal is allowed. The impugned judgment First Appeal No. 3502 of 2009 and the award passed by the Reference Court are set aside and the respondents are directed to pay enhanced compensation to the appellant at the rate of Rs 450 per are for the irrigated land and Rs 280 per are for non-irrigated land with an additional amount of Rs 2 per square metre. The appellant shall also be entitled to other statutory benefits like solatium and interest. The respondent shall calculate the amount payable to the appellant and make payment within three months from today.

24. Although, the other landowners are not shown to have prosecuted the matter further except that three of them filed appeals under Section 54 of the Act, we are convinced that this is a fit case in which the Court should exercise power under Article 142 of the Constitution and direct the respondents to pay enhanced compensation, solatium, etc. even to those who did not file appeals before the High Court and/or have not approached this Court by filing petitions under Article 136 of the Constitution.

25. This approach is consistent with the judgments of this Court in B.N Nagarajan v. State of Mysore AIR 1966 SC 1942, (1966) 3 SCR 682, Bhupinderpal Singh v. State of Punjab (2000) 5 SCC 262, Nilabati Behera v. State of Orissa (1993) 2 SCC 746 and B. Prabhakar Rao v. State of A.P 1985 Supp SCC 432 Therefore, we direct that other landowners shall also be paid enhanced compensation and other statutory benefits within three months from today.