New India Assurance Company Limited v. Protection Manufacturers Private Limited .

Supreme Court Of India
Jul 8, 2010
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The respondent’s factory at Bhatkuri suffered a major fire at about 8:45 a.m. on 29-3-2000. The premises were insured under a fire policy covering 19-2-2000 to 18-2-2001. Preliminary and joint surveys by A.S. Asthana and Bhaskar Joshi assessed the loss at Rs 2,37,09,372.12. The insurer later appointed M/s J. Basheer & Associates, whose six investigation reports eventually suggested a far lower loss (approx. Rs 1.10 crore) and advanced a theory of arson.

Dissatisfied with the non-settlement, the respondent filed OP No. 60 of 2003 before the National Consumer Disputes Redressal Commission, claiming Rs 2.48 crore plus interest and compensation. On 24-10-2005 the National Commission directed the appellant-insurer to pay Rs 2,26,36,179 with 12% interest from 1-7-2000 and Rs 1 lakh as compensation. The insurer appealed to the Supreme Court under Section 23 of the Consumer Protection Act, 1986.

Legal Issues Presented

  1. What was the cause of the fire that broke out in the respondent’s factory on 29-3-2000?
  2. What was the extent of loss and damage suffered by the respondent and therefore indemnifiable under the fire policy?

Arguments of the Parties

Appellant (Insurance Company)

  • The National Commission relied only on the joint surveyors’ report and the opinion of former CJI Y.V. Chandrachud, while improperly discarding four of the six reports of M/s J. Basheer & Associates.
  • No conclusive evidence established the cause of fire; joint surveyors themselves noted it was “not known” and merely “probable” short-circuit. Reports collectively suggested the possibility of arson.
  • Opinion of Justice Chandrachud was inadmissible without examination under Section 45 Evidence Act.
  • The matter should be remanded for fresh determination, citing Supreme Court precedents where remand was ordered in comparable circumstances.

Respondent (Protection Manufacturers (P) Ltd.)

  • The Suryanagar unit had ceased operations; all manufacturing (and the loss) pertained to Bhatkuri.
  • Joint surveyors thoroughly verified computerised inventory, cross-checked vendor ledgers, and assessed loss at about Rs 2.37 crore; the Basheer reports were perfunctory and “tailor-made” to the insurer’s predetermined figure.
  • Section 64-UM Insurance Act required any second opinion to be obtained through the Insurance Regulatory and Development Authority; unilateral appointment of M/s J. Basheer & Associates was contrary to the statute.
  • The National Commission correctly awarded interest from 1-7-2000; delay was solely attributable to the insurer.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
National Insurance Co. Ltd. v. Harjeet Rice Mills (2005) 6 SCC 45 Remand appropriate where allegations of fraud require fresh inquiry. Appellant relied on it to seek remand; Court found facts distinguishable and declined remand.
United India Insurance Co. Ltd. v. Roshan Lal Oil Mills Ltd. (2000) 10 SCC 19 Remand in similar insurance dispute for fresh hearing. Cited by appellant; Supreme Court distinguished factual matrix and did not remand.
Ramesh Chandra Agrawal v. Regency Hospital Ltd. (2009) 9 SCC 709 Expert evidence under Section 45 Evidence Act is only advisory. Appellant invoked to challenge reliance on Justice Chandrachud’s opinion; Court held Section 45 inapplicable because opinion was an analytical assessment, not expert testimony.
Sovintorg (India) Ltd. v. SBI (1999) 6 SCC 406 Consumer forums may grant interest on principles of justice, equity and good conscience. Cited by respondent to justify 12% interest; Court upheld Commission’s discretionary award.
GDA v. Balbir Singh (2004) 5 SCC 65 Compensation under Consumer Act must vary with facts of each case. Referenced on interest/compensation; Court accepted Commission’s discretion.

Court's Reasoning and Analysis

Cause of Fire: The joint surveyors reported the exact cause as unknown though probably a short-circuit; M/s J. Basheer & Associates belatedly suggested arson without factual basis. The insurer itself obtained an independent opinion from former CJI Y.V. Chandrachud, who, after analysing all material (including both survey reports), concluded the fire was accidental. The Supreme Court held that Justice Chandrachud’s analysis was a neutral assessment, not expert evidence within Section 45, and could be considered. With no substantive material supporting arson, the Court affirmed the National Commission’s finding that the fire was accidental.

Quantum of Loss: The Court noted the striking similarity between the insurer’s in-house estimate (Rs 1.10 crore) and the Basheer reports, describing the latter as a “tailor-made” cursory investigation. By contrast, the joint surveyors undertook detailed verification of computerised inventory, supplier accounts, and physical inspection, leading to a figure of Rs 2.26 crore (after adjustments). The Court saw no reason to depart from the National Commission’s reliance on this figure.

Interest and Compensation: Award of 12% interest from three months after the fire was upheld as a just and equitable discretionary exercise, absent any contractual rate. The respondent’s plea for enhancement was rejected.

Statutory Compliance: The Court accepted the respondent’s contention that, under Section 64-UM of the Insurance Act, any second survey should have been routed through the regulatory authority; unilateral appointment of M/s J. Basheer & Associates further undermined the credibility of their reports.

Holding and Implications

Appeal Dismissed. The Supreme Court upheld the National Commission’s direction that the insurer pay Rs 2,26,36,179 with 12% interest from 1-7-2000 and Rs 1 lakh compensation, and dismissed the insurer’s statutory appeal.

Implications: The decision affirms consumer forum findings where an insurer appoints multiple surveyors to downplay loss, stresses that unfounded arson theories will not defeat claims, and underscores the statutory route for second surveys under Section 64-UM. No new legal precedent was expressly set, but the judgment reinforces principles of fair claims assessment and insurer accountability.

Show all summary ...

Altamas Kabir, J.— This is a statutory appeal filed under Section 23 of the Consumer Protection Act, 1986 (hereinafter referred to as “the 1986 Act”), from an order dated 24-10-2005 passed by the National Consumer Disputes Redressal Commission, New Delhi (hereinafter referred to as “the National Commission”), in OP No. 60 of 2003. By the said order, the National Commission accepted the claim of the respondent herein, M/s Protection Manufacturers (P) Ltd., in respect of an insurance claim on account of a fire which had broken out in its factory at about 8.45 a.m on 29-3-2000, and directed the appellant Insurance Company to pay Rs 2,26,36,179 to the respondent with interest at the rate of 12% per annum from three months after the date of the fire. In other words, the interest was to be reckoned from 1-7-2000 till date.

2. Although the scope of the appeal is to some extent limited, a few facts may be stated for proper appreciation of the case made out by the respondent complainant. On 29-3-2000, at about 8.45 a.m, there was a devastating fire in the factory of the respondent complainant. The same was noticed by the factory workers who had assembled in front of the factory premises and were waiting for the factory to open. On being informed, the fire brigade reached the site at about 9.10 a.m and began their operations immediately. However, the fire was so severe that it continued to flicker for the next three to four days and was completely extinguished only on 4-4-2000.

3. As the factory premises of the respondent was covered by a fire insurance policy for the period from 19-2-2000 to 18-2-2001, against the risk of fire, the respondent made its claim to the Insurance Company amounting to Rs 2,85,50,000 on account of damage and loss suffered to the building, plant and machinery, stocks and stock-in-process and the transformer for which the respondent Company had paid Rs 1,16,636 as premium. It appears that while the policy was in force, the insurance coverage was enhanced.

4. On the very same day when the fire broke out, the Insurance Company appointed Mr A.S Asthana, Surveyor, to conduct a preliminary spot survey. On 30-3-2000, Mr Asthana and the representatives of the Insurance Company took joint stock of burnt motors and air coolers which were being manufactured by the respondent complainant. Mr Asthana submitted his preliminary report on 3-4-2000, but did not specify the cause of fire. Thereafter, on 9-4-2000, one Mr Bhaskar Joshi was appointed as joint surveyor to conduct a final survey along with Mr Asthana. On 13-4-2000, a status report was submitted by Mr Bhaskar Joshi. The joint surveyors prepared a draft assessment report and estimated the loss suffered by the respondent complainant to be Rs 2,37,09,372.12p. The joint assessment report which was submitted on 28-8-2000 clearly stated that the exact cause of fire was not known, though it could be due to a short circuit.

5. Thereafter, on 30-10-2000, the Regional Manager of the Insurance Company appointed M/s J. Basheer & Associates as investigator to conduct an investigation into the cause of fire and to assess the loss. As many as six independent investigation reports were filed by M/s J. Basheer & Associates on 28-5-2001, 3-7-2001, 27-8-2002, 4-10-2002, 7-11-2002 and 10-12-2002. According to M/s J. Basheer & Associates, the net amount of loss suffered by the respondent Company on account of the fire would be Rs 1,10,57,034, which tallies almost exactly with the assessment made by the Insurance Company amounting to Rs 1,10,67,230.

6. Interestingly, although in the report submitted by M/s J. Basheer & Associates it has been mentioned in Clause 6 that their appointment was for investigation into (i) cause of fire, and (ii) assessment of loss, there is nothing definite in the 67 page report as to the cause of fire, except for a reference to the reply sent by the Fire Officer, Cuttack to the Khurda Branch Manager of the Insurance Company on 5-5-2001, stating that the estimate of fire amount was about Rs 15 lakhs and the cause of fire was “short circuit” in the raw material section.

7. On 25-6-2001, the appellant Insurance Company requested Mr Bhaskar Joshi to make his observations on the report submitted by M/s J. Basheer & Associates on 28-5-2001. In his comments submitted on 10-8-2001, Mr Bhaskar Joshi severely criticised the report filed by M/s J. Basheer & Associates and even went to the extent of observing that they had failed to measure up to the faith and responsibility reposed on them by the insurers. The report seemed to suggest that the same had been tailor-made in order to fit the loss assessed by the Insurance Company at Rs 1,10,67,230, which uncannily tallied with the estimate of M/s J. Basheer & Associates, namely, Rs 1,10,57,034.

8. After receipt of the views expressed by the joint surveyors, the appellant Insurance Company decided to obtain the views of Justice Y.V Chandrachud, former Chief Justice of India, on the question as to the cause of fire. In his report, Chief Justice Chandrachud arrived at the conclusion that the report of M/s J. Basheer & Associates was unfounded and speculative while that of the joint surveyors contained a careful analysis of the events. Chief Justice Chandrachud was of the view that he had no doubt that the fire was accidental and could not by any reasonable norm or standard be characterised as an act of arson.

9. Mr Bhaskar Joshi also commented on the reports submitted by M/s J. Basheer & Associates on 3-7-2001 and 29-11-2001, and castigated the same in no uncertain terms. Mr Joshi observed that M/s J. Basheer & Associates had not gone into the roots of documentation and had not even bothered to verify the original documents. On the other hand, they had gone around creating confusion and controversies and to create an air of suspicion, which was a classic example of tabletop investigation.

10. Thereafter, as the claim of the respondent Company was not being settled by the appellant Insurance Company, a complaint was filed by the respondent Company with the National Commission on 13-2-2003 for a direction to the Insurance Company to pay compensation of Rs 2,48,94,000 for the loss suffered by it, together with interest @ 18% p.a and to also grant compensation of Rs 10 lakhs for the delay in settlement of the claim, which had caused mental agony and harassment to the respondent complainant.

11. The claim of the respondent Company was repudiated by the appellant Insurance Company on 20-2-2003, when the National Commission admitted the complaint filed by the respondent Company and directed notice to issue to the Insurance Company limited to the question of deficiency of service. After considering the reply filed by the Insurance Company and after examining one Mr Amit Biswas, the representative of the Insurance Company, and Mr J. Basheer of M/s J. Basheer & Associates, who admitted that he had not visited the Excise Office, the vendors and had also not provided any supporting evidence to bolster his findings, the National Commission, by its order dated 24-10-2005, directed the appellant Insurance Company to pay to the respondent Company a sum of Rs 2,26,36,179 with interest @ 12% p.a with effect from 1-7-2000 and to also pay a sum of Rs 1 lakh by way of compensation. The Insurance Company was given liberty to recover the said amount from its defaulting officers. Incidentally, it may be indicated that in the final assessment report of the joint surveyors the loss suffered by the respondent Company was assessed at Rs 2,26,36,180.23p.

12. Aggrieved by the said award of the National Commission, the appellant Insurance Company has filed this appeal and questioned the said award on several grounds.

13. Appearing for the Insurance Company, Mr Jaideep Gupta, learned Senior Advocate, submitted that the National Commission had erroneously approached the problem by concentrating only on the reports submitted by the joint assessors and the opinion given by the former Chief Justice of India, Y.V Chandrachud, while rejecting the several reports submitted by M/s J. Basheer & Associates. It was submitted that the specific issues and the allegations made in respect thereof were not seriously considered by the National Commission.

14. Mr Gupta submitted that the National Commission had not considered the evidence in its totality. Out of the six reports submitted by M/s J. Basheer & Associates only two were taken into consideration, while the other four, including the final report submitted on 10-12-2002, were ignored and were wrongly rejected. The National Commission relied only on the joint report submitted by M/s Asthana and Joshi and the views expressed by Chief Justice Chandrachud, which was only an opinion and hence not admissible in evidence.

15. Mr Gupta urged that the only certificate available as to the cause of the fire was the fire certificate issued by the Fire Officer, Orissa, Cuttack on 17-5-2000, indicating that the fire was the result of an electrical short circuit, but except for a bald statement, no evidence was produced to corroborate such opinion.

16. Mr Gupta also referred to Para 6 of the final assessment report on the basis of the joint survey conducted by M/s A. Asthana & Co. and Bhaskar Joshi, which deals with the cause of the fire. It was pointed out that the very first sentence of Para 6 indicates that the exact cause of the fire was not known, but the police had attributed it to short circuit. Sub-para 2 records the fact that nothing specific as to the cause of the fire could be found even on further probe and hence it had to be presumed that short circuit could be one of the probable causes out of other probables. It was also indicated that in the light of the reports issued by the local authorities, such as the police and the fire brigade, the cause of the fire could only be attributed to a short circuit, since no evidence could be found that would point towards a deliberate act of arson. The final opinion expressed in sub-para (a) of Para 6 was that the fire appeared to be accidental and the loss would be indemnifiable under the fire policy issued to and held by the insured.

17. Mr Gupta also referred to the opinion of Chief Justice Y.V Chandrachud, wherein His Lordship indicated that on a perusal of the survey report and the investigation report it was quite clear that the report of M/s J. Basheer & Associates was unfounded and speculative, whereas the report of the joint surveyors contained a careful analysis and assessment of the cause of fire and the facts incidental to and attendant upon the event of fire.

18. Mr Gupta reiterated his earlier submission that except the fire certificate issued by the Fire Officer, Orissa, Cuttack, there were no other reports as to the cause of the fire and the views expressed by the joint surveyors and also Chief Justice Chandrachud were without foundation and were themselves speculative and conjectural and could not, therefore, be relied on. If, however, all the reports submitted by M/s J. Basheer & Associates were taken together, it would point towards an act of arson as to the cause of the fire.

19. Mr Gupta then referred to the decision of the National Commission on the question of cause of the fire. It was pointed out that the National Commission in considering the report of M/s J. Basheer & Associates and the opinion of Chief Justice Y.V Chandrachud and the views expressed by Bhaskar Joshi which had been accepted by the Insurance Company, observed as follows:

“Undisputedly, this report is accepted by the Insurance Company and the learned counsel for the Insurance Company had stated that the Insurance Company accepted that the fire was accidental and could not be characterised as an act of arson.”

20. Mr Gupta submitted that the said observation was made on the basis of a concession which had been made by the counsel for the Insurance Company and not on the pleadings, wherein it had been consistently stated that the cause of the fire had not been finally determined by any of the assessors or investigators and that the opinion of M/s J. Basheer & Associates, that an act of arson was the cause of fire, could not be ruled out. Mr Gupta reiterated that even in the joint survey report of M/s Asthana and Joshi it had been mentioned that the exact cause of fire is not known but that the police had attributed it to a short circuit. But it had also been indicated that the same was only a probable hypothesis. Mr Gupta submitted that it is on such improved probability that an opinion was given that the fire appeared to be accidental and the loss would be indemnifiable under the fire policy issued to and held by the insured. Mr Gupta submitted that in the circumstances when the cause of fire had not been established with any certainty, the direction given by the Commission to make payment of insurance on the fire policy was not justifiable.

21. Mr Gupta urged that this was a fit case for remand to enable the National Commission to ascertain the cause of the fire before making any award for payment of insurance under the aforesaid policy. In support of his submission, Mr Gupta firstly referred to the decision of this Court in National Insurance Co. Ltd. v. Harjeet Rice Mills (2005) 6 SCC 45 wherein it was held that since the High Court had failed to consider the allegations of the Insurance Company, that the claim of the complainant was fraudulent, though there was adequate prima facie material available to warrant a proper inquiry, the matter was required to be remanded for a decision afresh for adjudication on such submissions made on behalf of the Insurance Company. The learned counsel also referred to the decision of this Court in United India Insurance Co. Ltd. v. Roshan Lal Oil Mills Ltd. (2000) 10 SCC 19 where in a somewhat similar situation as existing in the instant case, the matter was remanded to the Commission for a fresh hearing.

22. Mr Gupta submitted that the National Commission had wrongly relied on the opinion of Justice Y.V Chandrachud, former Chief Justice of India, in contravention of the provisions of Section 45 of the Evidence Act, 1872. The learned counsel urged that if the Commission wanted to rely on the opinion given by Justice Y.V Chandrachud, as if it were an expert opinion, it could only have done so after examining His Lordship in order to satisfy the provisions of Section 45 of the aforesaid Act.

23. In support of his said submission Mr Gupta relied on the decision of this Court in Ramesh Chandra Agrawal v. Regency Hospital Ltd. (2009) 9 SCC 709 wherein, while considering the evidence of experts in the light of Section 45 of the Evidence Act, it was held that such evidence is only advisory in character since such expert is not a witness of fact.

24. Mr Gupta urged that in view of the inconclusive nature of the reports as submitted, the matter was required to be sent back on remand to the National Commission for a fresh determination in accordance with law.

25. Mr Piyush Gupta, who appeared in person on behalf of the respondent Company, submitted that the allegations made about inclusion of the damage in respect of the products manufactured at the manufacturing unit at SCR 14, Suryanagar, Bhubaneshwar, was misleading, since after the establishment of the new factory premises at Bhatkuri, the Suryanagar factory ceased to exist. A request was made to the Central Excise Authorities to cancel the licence for production of air coolers at Suryanagar with effect from 1-7-1999 and all manufacturing operations were being carried on by the insured at its new location at Bhatkuri which was affected by the fire.

26. Mr Piyush Gupta submitted that the Company maintained computerised financial accounts which combined financial accounting as well as inventory management in one software. The learned counsel submitted that in making their report the joint surveyors, M/s Asthana and Joshi, had relied on the same after carrying out a detailed check of the system to ascertain its integrity. A substantial quantity of raw materials which had been damaged during the super cyclone in October 1999, had been found to be subtracted from the other material which had been damaged on account of the fire.

27. The learned counsel pointed out that in their report, M/s Asthana and Joshi had in Para 8.03.1.14 indicated that they had verified the integrity of the system by making dummy entries and the results were found to be reliable. In order to further cross-check the account, ledger entries of the Company's accounts in the vendor's books were also called for and the same when reconciled with the Company's system produced corroborative results. Mr Piyush Gupta submitted that based on their examination of the stock and the entries in the computer which were reconciled with the accounts of the suppliers (vendors), they submitted a draft assessment report assessing the loss incurred by the Company on account of the fire amounting to Rs 2,37,09,372.12. However, upon visiting the Regional Office of the appellant Insurance Company for discussions, they were given the version of the assessment made by the Insurance Company amounting to Rs 1,10,67,230. As against this, the loss assessed by M/s J. Basheer & Associates was almost identical, namely, Rs 1,10,67,034. Mr Gupta urged that it was obvious that the assessment made by the investigators was based on the Insurance Company's assessment of the loss suffered by the Company on account of the fire.

28. Mr Piyush Gupta then submitted that Section 64-UM of the Insurance Act, 1938, which provides for licensing of surveyors and loss assessors, would be attracted to the facts of this case and instead of appointing another surveyor, as was done in the instant case by the appointment of M/s J. Basheer & Associates, the Insurance Company ought to have gone to the Regulatory Authority under the Insurance Regulatory and Development Authority Act, 1999, and under sub-section (3) it was for the said Authority to call for an independent report from any other approved surveyor or loss assessor specified by it.

29. Mr Gupta urged that by appointing another surveyor/assessor/investigator after M/s Asthana and Joshi had submitted their report, the Insurance Company had presented two different reports as to the loss caused and had also introduced a third opinion as to the cause of the fire from a former Chief Justice of India, Justice Y.V Chandrachud, although an attempt was made to play down the same since it went completely against the case of the Insurance Company. It was pointed out that Chief Justice Chandrachud had observed that the report submitted by M/s J. Basheer & Associates was unfounded and was in any way short of speaking, speculative, while the joint surveyors' report contained a careful analysis of the event. It was further pointed out that Chief Justice Chandrachud came to the conclusion that he had no doubt that the fire was accidental and could not by any reasonable norm or standard be characterised as an act of arson.

30. On the merits of the report submitted by M/s J. Basheer & Associates, Mr Piyush Gupta submitted that one Mr J. Basheer had been deputed by M/s J. Basheer & Associates to visit the factory premises of the respondent Company, which had been damaged by the fire, only on 14-11-2000 i.e 8 months after the fire had occurred and by that time rehabilitation work had already been commenced after obtaining due permission from the appellant Insurance Company. Even then, Mr Basheer was in the factory for barely half an hour and did not visit the factory ever again.

31. On the point of non-consideration of the last three reports filed by M/s J. Basheer & Associates, the learned counsel submitted that the same was nothing but a repetition of what had been mentioned in the earlier reports and did not reflect anything new which deserved separate consideration.

32. On the quantum of damages, Mr Piyush Gupta referred to the assessment made by the Commission on a comparison of the reports submitted by M/s Asthana and Joshi and M/s J. Basheer & Associates. It was submitted that the conclusion arrived at by the Commission holding that the report submitted by M/s J. Basheer & Associates was totally unreliable and tailor-made with regard to the loss suffered by the respondent Company on the basis of the suggestions made by its Regional Office at Orissa and its agreement with the observations made by the joint surveyors to the effect that the whole exercise of M/s J. Basheer & Associates was beyond their competence, cannot be called into question and the ultimate award directing the appellant Assurance Company to pay Rs 2,26,36,179 with interest @ 12% per annum from 3 months after the date of occurrence of the fire i.e from 1-7-2000 till payment, was fully justified and the further direction to the Insurance Company to pay a further sum of Rs 1 lakh to the respondent Company by way of compensation for unjustly repudiating the claim of the respondent Company did not also call for any interference.

33. A further submission was made by Mr Gupta claiming payment of interest from the date of the fire and not from the date of the final decision of the Commission as the delay was on account of the Insurance Company, whose repudiation of the claim of the respondent Company was found to be unjust. In this regard reference was made to the decision of this Court in Sovintorg (India) Ltd. v. SBI (1999) 6 SCC 406 wherein Section 14 of the Consumer Protection Act, 1986 fell for consideration and it was observed that where no contract existed between the parties regarding payment of interest on delayed deposit or service, interest could not be claimed under Section 34 CPC as the provisions of CPC have not been made applicable to proceedings under the 1986 Act. However, the general provisions of Section 34 of the Code being based on justice, equity and good conscience, would authorise the consumer courts to grant interest according to the circumstances of each case. It was submitted that in the said case the direction to pay interest @ 12% given by the State Commission was enhanced by the National Commission to 15% per annum.

34. Reference was also made to the decision of this Court in GDA v. Balbir Singh (2004) 5 SCC 65 where somewhat similar views were expressed in the context of Section 73 of the Contract Act, 1872, and it was observed that the award of compensation had to be made under different and separate set of circumstances and must vary from case to case depending on the facts of each case and no hard-and-fast rule, could, therefore, be laid down.

35. Mr Gupta submitted that no interference was called for with the impugned award of the National Commission and the appeal was liable to be dismissed.

36. The nature of the controversy between the parties has made us dwell on the facts of the case at some length. Despite the extensive submissions made on behalf of the parties, the issues to be resolved in this appeal are confined to two questions, namely:

(i) What was the cause of fire which broke out in the factory premises of the assured at Bhatkuri at about 8.45 a.m on 29-3-2000?
(ii) What was the extent of loss and damage suffered by the assured on account of such fire?

37. As far as the answer to the first question is concerned, the report of the joint surveyors, M/s Asthana & Joshi, dated 28-8-2000 indicates that the exact cause of the fire was not known, though it could be due to a short circuit. Interestingly, while referring in its report dated 28-5-2001 to the reply given by the Fire Officer, Cuttack to the Khurda Branch Manager of the Insurance Company on 5-5-2001, stating that the cause of fire was a “short circuit” in the raw material section of the factory premises, M/s J. Basheer & Associates ultimately observed that the fire could reasonably be attributed to an act of “arson” by vested interests, for some pecuniary benefit, without any factual basis for the same. Apart from the aforesaid observation made at the end of the report, no foundation has been laid down in the report for such an observation which literally appears out of the blue.

38. Even if the views expressed by the joint surveyors, M/s Asthana and Joshi, on the reports submitted by M/s J. Basheer & Associates are discounted, although they were appointed by the Insurance Company itself, one cannot ignore the views obtained by the Insurance Company from the former Chief Justice, Y.V Chandrachud, although an attempt has been made on behalf of the Insurance Company to exclude the said views from consideration or at least to water down the same by taking refuge in Section 45 of the Evidence Act. Such a stand has no legs to stand upon, since the opinion given by Justice Chandrachud was based on an analysis of the materials placed before him by the Insurance Company, including the reports submitted by the joint surveyors, M/s Asthana and Joshi and M/s J. Basheer & Associates.

39. Section 45 of the Evidence Act empowers the court, in order to form an opinion upon a point of foreign law or of science or of art, or as to identity of handwriting or finger impressions, to rely upon the opinions of persons specially skilled in such matters. The case in hand is quite different, as the views expressed by Justice Chandrachud were not meant to be an opinion within the meaning of Section 45 of the Evidence Act, but an analysis of the reports and the materials provided to His Lordship by the Insurance Company. In fact, the attempt made on behalf of the appellant Insurance Company to exclude the views expressed by Justice Chandrachud with regard to the cause of fire from the area of consideration does not commend itself to us as the same is a completely independent and unbiased assessment of the events relating to the cause of fire on the basis of the materials made available to His Lordship.

40. Without any material to support the theory of arson projected by M/s J. Basheer & Associates and sufficient material to hold otherwise, it would be entirely unjust and inequitable to accept such a theory without any evidence whatsoever in support thereof. Reference can be made in this context to the submission made by the counsel for the Insurance Company before the National Commission and quoted in para 19 above. Accordingly, we endorse the views expressed by the National Commission that the cause of fire was accidental and that the attempt made by M/s J. Basheer & Associates to show that the fire had been caused by an act of arson was motivated and intended to benefit the appellant Insurance Company. The decisions cited by the parties were rendered in their own particular fact situations in accordance with law which is not disputed. The fact situations are, however, distinguishable.

41. This brings us to the second question regarding the quantum of loss suffered by the respondent Company on account of the fire. As has been commented upon by the joint surveyors and Chief Justice Chandrachud and subsequently by the National Commission, the almost identical amounts, barring a few rupees, arrived at by the Insurance Company and M/s J. Basheer & Associates speak volumes of the exercise carried out by the latter on a wholly cursory investigation which has quite aptly been described as “tailor-made”. The amount of loss suffered by the respondent Company on account of the fire has been calculated by the joint surveyors on the basis of the amounts mentioned by the respondent Company and the computer data available in support thereof and also upon cross-checking with the accounts of suppliers and vendors of raw materials to the respondent Company. We see no reason to differ with the views expressed by the National Commission in this regard.

42. We also accept the discretion exercised by the National Commission regarding the rate of interest awarded from three months after the date of the award (sic fire). The submissions made on behalf of the respondent Company for enhancement of the same are rejected as we are of the view that such exercise of discretion was just and equitable in the absence of any agreement between the parties regarding payment of interest or the quantum thereof.

43. The submissions of Mr Piyush Gupta in regard to Section 64-UM of the Insurance Act, 1938 are also of substance, as the appellant Insurance Company should have applied to the Regulatory Authority under the Act for a second opinion instead of appointing M/s J. Basheer & Associates for the said purpose unilaterally. The reports submitted by M/s J. Basheer & Associates are liable to be discarded on such ground as well.

44. The appeal filed by the Insurance Company, therefore, fails on all counts and is dismissed. There will be no order as to costs.

45. Having regard to the judgment delivered today, no further orders are required to be passed on the application for directions filed on 30-4-2010 on behalf of the respondent Company and supported by an affidavit dated 27-4-2010 affirmed by Mr Piyush Gupta and the same is disposed of accordingly.