Jabalpur Development Authority v. V.V Shrivastava And Another

Supreme Court Of India
Oct 19, 2010
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The appellant, Jabalpur Development Authority (a statutory body under Section 38 of the Madhya Pradesh Nagar Tatha Gram Nivesh Adhiniyam, 1973), resolved in May 1980 to frame Town Planning Scheme No. 14 covering 104.25 hectares, including the respondents’ land (Khasra No. 164/2). A series of statutory notifications followed:

  • 4-7-1980 – intention to prepare the Scheme under Section 50(2).
  • 19-6-1981 – publication of the draft Scheme under Section 50(3).
  • 29-4-1983 – publication of the final Scheme (Ext. D-1) after approval.

Notices dated 26-8-1983 and 31-10-1983 were served on the respondents to submit claims for compensation, but they remained unanswered. Most other landowners accepted compensation, and substantial construction ensued.

Nearly nine years after the final notification, the respondents instituted a suit seeking a declaration and injunction, alleging non-compliance with Section 50, lack of legal basis for acquisition, and automatic lapse of the Scheme after three years.

The suit was decreed by the Trial Court (17-11-1997) and the decree affirmed by the Lower Appellate Court (21-4-1999). A second appeal filed by the Development Authority was dismissed in limine by a Single Judge of the Madhya Pradesh High Court on 17-8-2001, who also rejected an application under Order 41 Rule 27 CPC for additional evidence.

The present Supreme Court appeal challenges the High Court’s order.

Legal Issues Presented

  1. Whether Notification dated 29-4-1983 (Ext. D-1) constituted valid final publication of Town Planning Scheme No. 14 under Section 50(7) of the Act.
  2. Whether the Scheme had lapsed owing to alleged non-compliance with Sections 50 and 56 or non-acquisition within three years.
  3. Whether the High Court erred in refusing to accept additional evidence under Order 41 Rule 27 CPC and in dismissing the second appeal without framing substantial questions of law.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Supreme Court identified two major errors in the concurrent findings below:

  • Mistaken Construction of Ext. D-1: All lower fora had read the 29-4-1983 notification as one under Section 50(4). The Supreme Court held it was, in fact, the notification mandated by Section 50(7), evidencing final publication of the Scheme. Read together with earlier notifications dated 4-7-1980 and 19-6-1981, it demonstrated full statutory compliance.
  • Refusal to Admit Additional Evidence: The High Court declined to consider documents showing that possession of most of the land had been taken and compensation paid. The Supreme Court ruled that the application under Order 41 Rule 27 CPC should have been entertained because the materials were relevant to determine whether the Scheme had, in fact, been implemented.

Because these errors were foundational, the Court found the High Court had not applied Section 100 CPC correctly: it failed first to decide the admissibility of additional evidence, then to frame substantial questions of law, and finally to adjudicate the appeal on that basis.

Holding and Implications

Appeal Allowed; Impugned Order Set Aside.

The matter is remitted to the Madhya Pradesh High Court with directions to:

  • Decide the pending second appeal afresh after hearing the parties.
  • First dispose of the existing and any future applications under Order 41 Rule 27 CPC.
  • Frame substantial questions of law in terms of Section 100 CPC and then adjudicate the appeal.

The immediate effect is revival of the second appeal; no final adjudication on merits has yet occurred. The decision clarifies procedural duties of appellate courts under Order 41 Rule 27 CPC and Section 100 CPC but does not establish a new substantive precedent on town-planning law.

Show all summary ...

G.S Singhvi, J.— Whether Town Planning Scheme No. 14 (hereinafter described as “the Scheme”) framed by the appellant, Jabalpur Development Authority could not be implemented in respect of the land of the respondents due to the alleged non-compliance with Sections 50 and 56 of the Madhya Pradesh Nagar Tatha Gram Nivesh Adhiniyam, 1973 (for short “the Act”) is the question which arises for consideration in this appeal filed against the order dated 17-8-2001 by which the learned Single Judge of the Madhya Pradesh High Court dismissed in limine the second appeal preferred by the appellant against the judgment and decree dated 21-4-1999 passed by the IXth Additional District Judge, Jabalpur (hereinafter referred to as “the lower appellate court”) in Civil Appeal No. 36-A of 1998 whereby the decree passed by the 15th Civil Judge, Grade II, Jabalpur (hereinafter referred to as “the trial court”) in a suit for declaration and injunction was upheld.

2. The appellant is a body corporate constituted under Section 38 of the Act. In May 1980, the appellant decided to prepare the Scheme covering an area of 104.25 ha including the land of the respondents comprised in Khasra No. 164/2 for construction of bus terminus, Major Road No. 4, housing scheme and sites for offices of the State, Central Governments and public corporations. As a follow up, a Notification dated 4-7-1980 was issued under Section 50(2) of the Act whereby the appellant declared its intention to prepare the Scheme. The draft scheme was published in the Madhya Pradesh Gazette dated 19-6-1981 issued under Section 50(3) and objections and suggestions were invited from the public. The Scheme was approved by the appellant on 14-9-1982 and Notification dated 29-4-1983 (Ext. D-1) was published under Section 50(7).

3. As a sequel to publication of the Scheme, the appellant issued notice dated 26-8-1983 to Respondent 1 and called upon him to submit claim for compensation in lieu of acquisition of Khasra No. 164/2. Another letter dated 31-10-1983 was sent to Respondent 1 and he was asked to submit some documents necessary for determination of the amount of compensation. Similar notices were issued to other landowners, majority of whom agreed to accept the amount of compensation offered by the appellant. It is not in dispute that after acquiring the major portion of the land by agreement several multi-storeyed buildings have been constructed and a housing colony has also been developed.

4. Since the respondents did not reply to either of the communications sent by the appellant, the State Government was requested to acquire the land under the Land Acquisition Act, 1894.

5. After almost 9 years of the publication of notification under Section 50(7) of the Act, the respondents filed a suit for declaration and permanent injunction by alleging that the predecessor of the defendant (the appellant herein), namely, Town Improvement Trust, Jabalpur had made an attempt to acquire their land in 1977 by issuing a notification under Section 48 of the Madhya Pradesh Town Improvement Trusts Act, 1960 but after filing of objections, no further action was taken; that the Scheme has not been framed/published in accordance with the provisions of the Act; that there was no legal basis or justification to acquire their land and the same will be deemed to have lapsed because the land was not acquired within three years from the date of publication of notification, Ext. D-1.

6. The trial court vide its judgment dated 17-11-1997 decreed the suit primarily on the ground that the defendant (the appellant herein) has failed to prove that the draft scheme was published under Section 50(3) and was approved under Section 50(4). The trial court took cognizance of the notification, Ext. D-1 and observed that even if compliance with various sub-sections of Section 50 is presumed, the Scheme will be deemed to have lapsed because the same was not implemented within three years from the date of its final publication.

7. The appeal preferred by the appellant was dismissed by the lower appellate court which expressed its agreement with the trial court that the Scheme had not been published as per the mandate of Section 50 and, in any case, the same will be deemed to have lapsed because the land was not acquired within three years of the publication of notification under Section 50(7).

8. The appellant challenged the judgment of the lower appellate court by filing an appeal under Section 100 of the Code of Civil Procedure (CPC). It also filed an application under Order 41 Rule 27 CPC for placing on record documents marked “A” to “H” to show that the Scheme has already been implemented. A reading of the impugned order shows that the learned Single Judge took cognizance of the statement made by the counsel appearing on behalf of the appellant that the land of the respondents has not been acquired in accordance with law and held that the courts below had rightly restrained the appellant from interfering with their possession without following due process of law. The learned Single Judge further held that Ext. D-1 cannot be treated as publication of final Scheme as per the requirement of Section 50(7) of the Act. The learned Single Judge also observed that the documents produced along with the application filed under Order 41 Rule 27 CPC do not prove publication of notifications under Sections 50(2) and 50(7) of the Act, which are mandatory in character.

9. Along with the special leave petition out of which the present appeal arises, the appellant filed IA No. 2 of 2001 for placing on record copies of Notification dated 4-7-1980 (Annexure P-6) issued under Section 50(2), Notification dated 19-6-1981 (Annexure P-7) by which the draft scheme was published under Section 50(3), notice dated 26-8-1983 (Annexure P-8) by which Respondent 1 was asked to submit his claim for compensation and letter dated 31-10-1983 (Annexure P-9) by which he was called upon to submit true copy of the sale deed, khasra panchshal duly certified by the Tahsildar, diversion certificate, etc., partition deed and khasra plan of the land.

10. We have heard the learned counsel for the parties and perused the record.

11. In response to the notice of the special leave petition issued on 7-12-2001, the respondents filed a detailed counter-affidavit dated 17-3-2002 along with copy of the plaint and statement of DW 1 Kedar Prasad Sharma, who was then working as Section-in-charge in the establishment of the appellant. The appellant filed rejoinder-affidavit dated 10-4-2002 along with copy of the written statement. An additional counter-affidavit dated 21-9-2002 was filed by Respondent 1 to which supplementary affidavit dated 27-10-2002 was filed on behalf of the appellant. The respondents then filed an application dated 15-1-2003 for placing on record additional documents to which counter-affidavit was filed by the appellant on 14-2-2003.

12. After grant of leave, the respondents filed an application dated 12-6-2009 for placing on record copies of minutes of the meeting of the appellant held on 10-11-1993 (Annexure R-7), letter dated 16-5-2005 (Annexure R-8) sent by the Joint Director, Nagar Tatha Gram Nivesh, Jabalpur to the Chief Executive Officer of the appellant, letter dated 16-12-2005 (Annexure R-9) sent by the Land Acquisition Officer to Shri Brij Bihari Nagaria, general power-of-attorney holder for Shri Najuk Jain, Shri Jambo Jain and Shri Jagat Jain, Letter dated 26-12-1994 sent by the State Government to the Commissioner, Jabalpur Division and Chairman of the appellant and details of the Scheme framed under the Act (Annexure R-9). Lastly, IA No. 11 of 2009 was filed on behalf of the appellant for filing additional affidavit of Shri G.N Singh, Land Acquisition Collector along with the Letter dated 25-7-2007 sent by the State Government to the Chief Executive Officer of the appellant.

13. We have made a mention of these pleadings and documents to show that after the judgment of the trial court, the lower appellate court and the High Court, the parties have exchanged correspondence and apparently conflicting communications have been issued by the functionaries of the Government and the appellant. However, it is not necessary to consider additional pleadings and documents because we are convinced that the High Court committed an error by not entertaining the application filed by the appellant under Order 41 Rule 27 CPC for producing additional evidence to show that the possession of the major portion of the land covered by the Scheme was taken after paying compensation to the landowners and the Scheme has been implemented.

14. We are also of the view that the courts below have gravely erred in holding that Ext. D-1 dated 29-4-1983 is a notification issued under Section 50(4) and the final Scheme was not published as per the requirement of Section 50(7). A perusal of Ext. D-1, a copy of which has been placed on the record of this appeal as Annexure P-2 shows that this is the notification by which the final Scheme was published in the Madhya Pradesh Gazette dated 29-4-1983. Reference to Section 50(4) has been made in this notification to signify that the Scheme was approved by the appellant. All the courts have misinterpreted this notification as a notification issued under Section 50(4). That apart, a conjoint reading of the Notifications—Annexures P-6 dated 4-7-1980, P-7 dated 19-6-1981 and P-2 dated 29-4-1983 makes it clear that the Scheme was finalised after complying with the mandate of various sub-sections of Section 50 of the Act.

15. In the result, the appeal is allowed. The impugned order is set aside and the matter is remitted to the High Court with the direction that the second appeal filed by the appellant be decided afresh after giving opportunity of hearing to the parties. The parties may, if so advised, file applications under Order 41 Rule 27 CPC for permission to adduce additional evidence. The High Court shall first dispose of the application already filed by the appellant along with the second appeal and the applications which may be filed hereafter by either party. Thereafter, the High Court shall frame substantial questions of law as per the mandate of Section 100 CPC and decide the appeal with reference to those questions of law.