Electrical Manufacturing Company Limited v. Power Grid Corporation Of India Limited And Another
Factual and Procedural Background
Electrical Manufacturing Co. Ltd. (“EMC”), a private contractor established in 1951 and engaged in transmission-line projects, participated in three tenders floated by Power Grid Corporation of India Ltd. (“PGCIL”), a Government of India public sector undertaking. The tenders—Packages A-1, A-2 and A-7—were opened on 8-1-2008 and 9-1-2008, and EMC emerged as the lowest (L-1) bidder in each case. However, on 6-5-2008 PGCIL’s Board decided not to award the contracts to EMC, citing EMC’s alleged failure to satisfy the “technical experience” requirements in Clause 1.1 of Annexure A to the Special Conditions of Contract.
EMC filed Writ Petition (Civil) No. 3668 of 2008 before the Delhi High Court seeking to quash PGCIL’s decision. The High Court rejected the petition on 26-5-2008. EMC then appealed to the Supreme Court of India. The Supreme Court granted leave, heard counsel from both sides, and delivered the present judgment.
Legal Issues Presented
- Whether EMC possessed the “requisite technical experience” under Clause 1.1 of Annexure A, specifically the requirement of having “satisfactorily completed” at least 100 km of 345/400 kV double-circuit (or higher) transmission lines within the previous seven years.
- Consequently, whether PGCIL’s refusal to award Packages A-1, A-2, and A-7 to EMC—despite EMC being the lowest bidder—was arbitrary and illegal.
Arguments of the Parties
Appellant — EMC
- Clause 1.1 merely requires surveying, optimisation, erection and stringing of the specified cumulative route length; it does not insist on “commissioning” or full operational testing.
- EMC had completed the requisite lengths: 100 km each for Packages A-1 and A-7 and 200 km for Package A-8, thereby meeting all technical criteria.
- The decision to deny the contract was therefore arbitrary despite EMC’s lowest bid, which was allegedly ₹16.34 crore less than the next lowest bidder.
Respondent — PGCIL
- Clause 1.1 must be read as a whole: the phrase “satisfactorily completed” precedes and governs sub-clause (i).
- As of the bid-opening dates, EMC had “satisfactorily completed” only 83 km, not the required 100 km, because two of its projects—Trivenveli-Udmalpet and Tapp-Kankaroli—were still unfinished.
- Incomplete segments cannot be aggregated to reach the threshold, and partial or untested lines cannot be deemed “satisfactorily completed.”
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The Supreme Court focused on interpreting Clause 1.1. It held that:
- The words “satisfactorily completed” are integral to Clause 1.1 and apply to sub-clause (i); mere physical erection or stringing does not suffice.
- “Satisfactory completion” entails two components:
- Completion of the entire route length from one designated point to another; partial completion is irrelevant because a transmission line is an indivisible whole.
- Subsequent testing to confirm that the line functions effectively; without energisation and testing, completion cannot be termed “satisfactory.”
- EMC’s chart showed only 83 km of satisfactorily completed lines; the remaining lengths were either unfinished or untested. Therefore, EMC did not meet the 100 km threshold.
- Because the technical requirement was not met, PGCIL’s decision to reject EMC’s bid was neither arbitrary nor illegal.
Holding and Implications
APPEAL DISMISSED.
The Supreme Court affirmed the Delhi High Court’s judgment and upheld PGCIL’s decision to deny the contracts to EMC. The immediate consequence is that EMC remains ineligible for the disputed tenders, and no costs were awarded. The Court’s interpretation clarifies that “satisfactory completion” in similar tender clauses encompasses both full physical completion and functional testing, but the decision does not establish new precedent beyond the specific contractual language at issue.
Markandey Katju, J.— Leave granted.
2. This appeal has been filed against the impugned judgment dated 26-5-2008 of the Delhi High Court in Writ Petition (Civil) No. 3668 of 2008. Heard Shri Sudhir Chandra, learned Senior Counsel for the appellant and Shri K.K Venugopal, learned Senior Counsel for the respondent and perused the record.
3. The appellant, Electrical Manufacturing Co. Ltd., (hereinafter as “EMC”) has alleged that it is a leading modern power system company in India and is the first ISO 9001 certified company in India in transmission line projects. It was established in 1951 and carries out such projects in India as well as overseas.
4. The appellant filed a writ petition in the Delhi High Court with the following prayer:
“To quash the decision taken by the Board of Directors in its meeting held on 6-5-2008 with respect to not awarding of contract to the petitioner with respect to Packages A-1, A-2 and A-7 in spite of the fact that it is L-1, technically qualified as per the requirement and more so its bid is Rs 16.34 crores less than L-2 bidders.”
5. Respondent 1, Power Grid Corporation of India Ltd. (hereinafter as “Pgcil”) is a public sector undertaking of the Government of India working under the Ministry of Power. The petitioner has been carrying out the contract of Respondent 1 for a long time.
6. On 5-11-2007, a notice inviting tender with respect to Packages A-1 and A-2 was made by Respondent 1 Pgcil. On 8-11-2007, a notice inviting tender with respect to Package A-7 was made by Respondent 1. These tenders were for setting up electrical transmission lines. On 8-1-2008 and 9-1-2008, bids were opened for the abovementioned packages, respectively. In both, the petitioner was declared the lowest quoted bidder (L-1).
7. On 16-4-2008 the petitioner made representations to Respondent 1 with respect to Packages A-1, A-2 and A-7 explaining as to how the petitioner was fully qualified and met the requirements of technical experience stipulated in Clause 1.1 of Annexure A of the Special Conditions of the Contract. On 6-5-2008, Respondent 1, decided not to award the contract for the abovementioned packages to the petitioner as it was of the opinion that the appellant did not have the requisite technical experience as set out in Clause 1.1 of Annexure A of the special conditions of the contract.
8. The appellant has alleged that the above refusal by Respondent 1 to award the contract for the abovementioned packages was arbitrary and illegal since the appellant's bid was the lowest among all the bidders.
9. Shri Sudhir Chandra, learned Senior Counsel for the appellant has submitted that the appellant has been denied the contract in question on an erroneous interpretation of Clause 1.1 of Annexure A of the special conditions of the contract. The aforesaid Clause 1.1 states:
“1.1 Technical experience.—The bidder shall have satisfactorily completed as a prime contractor or as a sub-contractor or as a member in a joint venture, 345/400 kV double circuit or higher voltage class transmission line(s) within the last seven (7) years as on date of bid opening. The bidder's experience should include the following:
(i) The bidder should have surveyed, optimised tower locations, erected and strung with tension stringing equipment, not less than following cumulative route length of transmission lines of 345/400 kV double circuit or higher voltage class involving bundle conductor.
Package A-7 : 100 km
Package A-8 : 100 km”
10. Learned counsel for the appellant submitted that the appellant fully satisfied the requirements mentioned in Clause 1.1, namely, that the petitioner has surveyed, optimised tower locations, erected and strung with tension stringing equipment, not less than following cumulative route length of transmission lines of 345/400 kV double circuit or higher voltage class involving bundle conductor, which insofar as the petitioner is concerned is 100 km for Packages A-1 and A-7 and 200 km for Package A-8. Hence learned counsel submits that the appellant should have been given the contract in question.
11. On the other hand Shri K.K Venugopal, learned Senior Counsel for the respondent submitted that sub-clause (i) of Clause 1.1 has to be read along with the main Clause 1.1 which stipulates that the bidder should have satisfactorily completed the requisite length of 100 km. He submitted that the petitioner has only satisfactorily completed 83 km of transmission line as on 9-1-2008 and therefore, did not fulfil the technical experience required by Clause 1.1
12. The dispute thus in this case is whether the appellant has the requisite technical experience mentioned in Clause 1.1 of the special conditions of the contract.
13. Shri K.K Venugopal, learned Senior Counsel for the respondent submitted that the appellant has satisfactorily completed only 83 km of transmission lines as on the date of the opening i.e 8-1-2008/9-1-2008 instead of the requisite 100 km. He submitted that the appellant had in addition laid various incomplete transmissions lines, but these cannot be added to the lines satisfactorily completed because they are incomplete.
14. The chart showing the work done by the appellant is as follows:
Transmission line Extent completed by the petitioner as on 8-1-2008/ 9-1-2008 Total extent of the line in question Lines satisfactorily completed by the petitioner Meerut-Mandola 60 km (on 29-9-2003) 60 km 60 km Bhadrawati-Chandrapur 23 km (on 13-4-2006) 23 km 23 km Trivenveli-Udmalpet 134 km (on 8-1-2008/9-1-2008; 2 km incomplete) 136 km Tapp-Kankaroli 87 km (on 8-1-2008/9-1-2008; 10.3 km incomplete) 97.3 km Total 304 km 83 km
A perusal of the above chart shows that the appellant has only satisfactorily completed 83 km of transmissions lines. The line Trivenveli-Udmalpet in Tamil Nadu was incomplete because only 134 km out of the total extent of the line of 136 km had been completed by the appellant. Hence this transmission line could not be treated to be satisfactorily completed. Similarly the line Tapp-Kankaroli was also incomplete as it was laid only for 87 km but the entire line had to be 97.3 km.
15. Shri Sudhir Chandra, learned Senior Counsel for the appellant has submitted that the view taken by the High Court that satisfactorily completing the line means commissioning the line is not correct. We are of the opinion that even if satisfactory completion may not necessary mean commissioning of the line but it certainly means completion of the entire length of the line and thereafter testing the line to find out whether it is functioning satisfactorily. Without testing it how can one be sure that it has been completed satisfactorily. For instance, if an electrical line is laid inside a person's house, the only way to find out whether the electrical line has been laid satisfactorily is to find out by pressing the switch and seeing whether the bulb in the house is lighted or the fan starts running. Merely putting wires dangling inside the house but which do not light the bulb or turn the fan on cannot be said to be satisfactory completion of the electrical line.
16. In the present case, as can be seen from the chart set out above the appellant has not completed the lines from Trivenveli to Udmalpet nor from Tapp to Kankaroli. Unless the entire line is laid and is found to be functioning satisfactorily, it cannot be said that there was satisfactory completion of the line.
17. As regards the interpretation of Clause 1.1 we cannot agree with Shri Sudhir Chandra that the words “satisfactorily completed” would not govern sub-clause (i) of Clause 1.1 A fair reading of the entire Clause 1.1 along with sub-clause (i) clearly indicates that the requisite technical experience requires satisfactory completion of the requisite length of the line.
18. Sub-clause (i) is a part of Clause 1.1 and hence mere surveyance, optimising tower locations, erecting and stringing with tension stringing equipment, etc. is not sufficient to give the requisite technical experience to the bidder unless such work was satisfactorily completed, which means that it was tested and found to be functioning satisfactorily. If the bidder has surveyed, optimised tower locations, erected and strung with tension stringing equipment, the requisite length of transmission lines, but these transmission lines do not function, surely it cannot be said that there was satisfactory completion of these transmission lines.
19. In our opinion the expression “satisfactory completion” governs sub-clause (i) of Clause 1.1 also. Hence mere surveying, optimising tower locations, erecting and stringing with tension stringing equipment the requisite length of transmission lines will not be enough to give the necessary technical experience because it is possible that even after doing the above work the transmission lines may not function. Unless after doing the above works the line is tested and found to be successfully functioning it surely cannot be said that there was satisfactory completion of the transmission lines.
20. Apart from the above, completion of a part of the line will be of no avail and the entire line from one location to another has to be completed before there can be said to be satisfactory completion of the line. Completion of part of the line has to be totally ignored as a line is one integral whole and cannot be divided into sections.
21. Thus there is no force in this appeal and it is dismissed. No costs.