Login
  • Bookmark
  • PDF
  • Share
  • CaseIQ

M.B Patel And Company v. Oil And Natural Gas Commission .

Supreme Court Of India
May 8, 2008
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The contractor raised six claims against the Oil and Natural Gas Commission (ONGC), including compensation for abandonment of contract, illegal deductions, delay in material supply, overhead losses, loss of profit, and interest. An arbitrator issued a lump-sum award of Rs 5,98,438 on 3-5-1985. ONGC challenged the award before the High Court of Gujarat in First Appeal No. 418 of 1986. By judgment dated 11-7-2000, the High Court set aside the award, citing several grounds of legal error and misconduct. The present appeal was filed against that High Court judgment.

Legal Issues Presented

  1. Whether the High Court correctly set aside the arbitral award on grounds that the arbitrator had misconducted the proceedings.
  2. Whether the award contained an error apparent on the face of the record by ignoring Clauses 14 and 18 of the arbitration agreement.
  3. Whether the arbitrator exceeded the scope of the contract in granting certain items and claims.
  4. Whether rendering the award as an unintelligible lump-sum justified its setting aside.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court concurred with the High Court’s four identified defects in the award:

  • Misconduct and scope of contract: The arbitrator travelled beyond the contractual terms on several claims, amounting to misconduct.
  • Error on the face of the record: Clauses 14 and 18 expressly barred compensation for delay caused by the Commission and prohibited interest on amounts payable. The arbitrator ignored these clauses and nonetheless awarded both damages and 12% interest, constituting a clear legal error.
  • Unintelligible lump-sum award: The award did not explain how the lump-sum figure of Rs 5,98,438 related to individual claims, rendering it “totally unintelligible.”

Because these defects went to the legality and comprehensibility of the award, the court found no reason to interfere with the High Court’s decision. However, it permitted the arbitration to recommence, directing the arbitrator to reconsider the matter strictly in line with the High Court’s reasoning, particularly the contractual limitations in Clauses 14 and 18.

Holding and Implications

Appeal Dismissed. The High Court’s order setting aside the arbitral award is affirmed, and the arbitrator is instructed to rehear the matter consistent with the contractual provisions identified.

Implications: The parties return to arbitration, where the arbitrator must explicitly honor Clauses 14 and 18 and provide a reasoned, itemized award. The decision has a direct effect on the parties and does not establish new precedent beyond reinforcing adherence to contractual terms in arbitral proceedings.

Show all summary ...

Order

1. This appeal is filed against the judgment and order dated 11-7-2000 of the High Court of Gujarat at Ahmedabad in First Appeal No. 418 of 1986 whereby the High Court set aside the award dated 3-5-1985 passed by the arbitrator. The High Court set aside the aforesaid award on the following reasonings:

(a) that an arbitrator or umpire has misconducted himself in the proceedings;
(b) that there appears to be an error on the face of the record inasmuch as the umpire has overlooked Clauses 14 and 18 of the arbitration agreement;
(c) that the umpire has travelled beyond the scope of the contract between the parties on certain items and claims; and
(d) that he has rendered lump sum award making it totally unintelligible.

On the aforesaid premises the award was set aside.

2. In the present case the contractor claimed Rs 30,425 for abandonment of contract. This was the first claim. The second claim was for Rs 30,213 for illegal deductions made by ongc. The third claim was for Rs 2,00,000 for not supplying the material in time by ongc. The fourth claim was loss occasioned by the contractor for keeping his establishment alive and on this head the claim was for Rs 3,50,000. The fifth claim was loss of profit at the rate of 20% amounting to Rs 1,80,000. Last claim was interest at the rate of 18% p.a

3. As already pointed out that the arbitrator awarded Rs 5,98,438 as lump sum, we agree with the reasoning of the High Court that the award is unintelligible.

4. Clause 14 of the arbitration agreement reads as under:

“14. Delay in construction (Commission's defaults).—The Commission will make every reasonable effort to furnish the materials under the contract and the right of user including the permits required to be furnished by the Commission under the contract in due time so as not to delay the construction related work of reconditioning. In case of any hold-up to site work of the contractor on account of non-availability of any one of these terms, no compensation by way of claims is admissible but only corresponding extension of time-limit would be granted.”

Under the aforesaid clause no claim for compensation is admissible even that foul (sic) of the Commission. Clause 18 of the arbitration agreement reads:

“18. Interest on amounts.—No interest will be payable on the security deposit or any other amount payable to the contractor under the contract.”

5. The arbitrator has awarded the interest at the rate of 12% on the amount with effect from 9-2-1984 to 3-5-1985 (pendente lite). He has also awarded interest from the date at the rate of 12% on the amount as shown in 1 and 3 above till the date of decree or actual date of payment, whichever is earlier.

6. In view of the aforesaid premises, the arbitrator has not at all considered Clause 14 of the arbitration agreement. The interest has been awarded in violation of Clause 14 of the agreement. Apart from others these two legal aspects have not been considered by the arbitrator. We are, therefore, in full agreement with the reasoning given by the High Court. The arbitrator may now proceed with the arbitration but in the light of the judgment of the High Court we direct the arbitrator to consider the matter afresh in the light of the reasoning of the High Court.

7. Subject to the aforesaid, the appeal is dismissed.