Food Corporation Of India v. Chandu Construction And Another
Factual and Procedural Background
The Food Corporation of India (FCI) awarded the respondents (“claimants”) a turnkey contract dated 19-09-1984 for construction of ten conventional godowns (50,000 MT capacity) at Panvel, District Raigad. The work was to be completed within ten months and was governed by Central Public Works Department (CPWD) Specifications, 1967.
The claimants failed to finish the project even after one extension; FCI terminated the contract on 15-11-1987. Invoking the arbitration clause, the claimants sought appointment of an arbitrator through the Bombay High Court. An award dated 27-08-1998 was set aside with consent and the dispute remitted for fresh adjudication.
In the fresh proceedings the sole arbitrator, by award dated 31-12-2003, allowed Claim 9 for Rs 8,23,101, holding that the tender rate for Item 1.7 covered only labour for plinth-sand filling and not supply of sand.
FCI’s objections under Section 30 of the Arbitration Act, 1940 were dismissed by a Single Judge and, on appeal, by a Division Bench of the Bombay High Court (14-10-2005). FCI then appealed to the Supreme Court.
Legal Issues Presented
- Whether the arbitrator, in allowing Claim 9, disregarded the explicit terms of the contract—particularly CPWD Specification para 2.9.4—and thereby exceeded his jurisdiction, amounting to legal misconduct under Section 30 of the Arbitration Act, 1940.
Arguments of the Parties
Food Corporation of India (Appellant)
- Clause 2 of the contract and CPWD Specification 2.9.4 made it clear that quoted rates were inclusive of both labour and materials; therefore, no extra payment for sand could be claimed.
- The arbitrator committed legal misconduct by awarding Rs 8,23,101 contrary to the unambiguous contractual provisions.
Claimants (Respondents)
- The arbitrator was competent to construe the contract in light of evidence, including similar FCI contracts where separate payment for materials was allowed.
- The interpretation adopted was at least a plausible view; hence, the High Court correctly refused to interfere.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Union of India v. Jain Associates (1994) 4 SCC 665 | “Misconduct” under Section 30 includes actions opposed to rational principles producing unjust results. | Used to frame the standard for when a court may set aside an award on the ground of misconduct. |
| Associated Engg. Co. v. Govt. of A.P. (1991) 4 SCC 93 | An arbitrator acts without jurisdiction if he wanders outside the contract. | Relied on to characterise the arbitrator’s departure from contractual terms as a jurisdictional error. |
| Rajasthan State Mines & Minerals Ltd. v. Eastern Engg. Enterprises (1999) 9 SCC 283 | Reaffirms the boundary between errors within and beyond jurisdiction. | Cited to support interference where the arbitrator exceeds contractual limits. |
| Alopi Parshad & Sons Ltd. v. Union of India, AIR 1960 SC 588 | Courts cannot depart from express contract terms based on equitable considerations. | Invoked to underline that contract rates are decisive and cannot be varied by the arbitrator. |
| Naihati Jute Mills Ltd. v. Khyaliram Jagannath, AIR 1968 SC 522 | No implied term can override an express term of a contract. | Supports rejection of the arbitrator’s implied assumption that sand cost was excluded from rates. |
| Continental Construction Co. Ltd. v. State of M.P. (1988) 3 SCC 82 | An arbitrator must decide according to law and can be corrected if an error appears on the face of the award. | Provides authority for judicial correction of the award once the contractual breach is apparent. |
| Bharat Coking Coal Ltd. v. Annapurna Construction (2003) 8 SCC 154 | Distinction between errors within jurisdiction and in excess of jurisdiction; arbitrator must act within contract. | Used to characterise the award of extra payment as an error in excess of jurisdiction. |
Court's Reasoning and Analysis
The Supreme Court examined Clause 1 of the contract and CPWD Specification 2.9.4, which expressly state that quoted rates include the cost of materials and labour. Because the tender was for a turnkey project, the bidders were expected to quote a consolidated rate without separating labour from material costs. The claimants neither split their quotation nor raised any contemporaneous protest concerning sand supply.
The arbitrator nonetheless relied on the absence of the words “providing and supplying” in Item 1.7 and on payments made in a separate contract with M/s Gupta & Co. The Court held that such extraneous considerations could not override the parties’ own express agreement. In awarding additional payment for sand, the arbitrator disregarded the clear contractual stipulation that rates were all-inclusive.
Accordingly, the arbitrator travelled beyond the scope of his authority. This was not a mere error of interpretation within jurisdiction; it was a jurisdictional error amounting to legal misconduct. The award on Claim 9 was therefore illegal on its face and liable to be set aside under Section 30(a) of the Arbitration Act, 1940.
Holding and Implications
APPEAL ALLOWED; the High Court’s judgment upholding Claim 9 is set aside. No order as to costs.
Immediate Effect: the claimants are not entitled to Rs 8,23,101 for supply of sand. Broader Impact: the decision reiterates that arbitrators must remain within the four corners of the contract and that courts will intervene where an award ignores unambiguous contractual terms; however, it creates no new legal doctrine beyond reaffirming established principles.
D.K Jain, J.— Leave granted.
2. Challenge in this appeal, by Food Corporation of India (for short “FCI”), is to the final judgment and order dated 14-10-2005 passed by the Division Bench of the High Court of Judicature at Bombay, affirming the judgment of the learned Single Judge in Arbitration Petition No. 334 of 2004. By the impugned order, the award of an amount of Rs 8,23,101 by the sole arbitrator against Claim 9 has been upheld.
3. A brief factual background giving rise to the appeal is as follows:
FCI undertook construction of godowns at Panvel, District Raigad and issued notice inviting tenders for construction of 50,000 MT capacity conventional godowns in 10 units along with ancillary work and services. Pursuant thereto, the respondents (hereinafter referred to as the claimants) submitted tender, which was accepted by FCI. A formal contract was executed between FCI and the claimants on 19-9-1984. As per the terms of the contract, the work was to be completed within 10 months from the 30th day of issue of the orders and the time was deemed to be of the essence of the contract.
4. As the claimants could not complete the work within the stipulated time, which was once extended, FCI issued a show-cause notice to them seeking to terminate the contract. Ultimately, the contract was terminated vide order dated 15-11-1987. The claimants invoked the arbitration agreement and requested FCI to appoint an arbitrator. Since there was no response from FCI, the claimants filed a suit in the High Court for appointment of an arbitrator. An arbitrator was appointed, who gave his award on 27-8-1998. As payment in terms of the award was not made, the claimants again moved the High Court. FCI, in turn, filed a petition in the High Court for setting aside of the award. With the consent of parties, the award was set aside and the matter was remitted to the arbitrator for fresh adjudication.
5. In fresh proceedings before the arbitrator, the stand of the claimants, qua Claim 9 was that the rate quoted by them for filling the plinth under floors including watering, ramming, consolidation and dressing; in terms of Item 1.7 of the Schedule of rates was only for labour and did not cover “providing or supplying” sand for the said purpose and yet they were required to supply sand for filling. As such the claimants were entitled to be paid extra for supply of sand. Accordingly, they made a claim of Rs 8,23,101 for providing and supplying 5487.34 cubic metres of sand.
6. The claim was resisted by FCI on the ground that the scope of work, specifications and the item rates were governed by the terms of the contract and as per clause (2) of the agreement dated 19-9-1984, the claimants were to be paid the “respective amount for the work actually done by him at the ‘schedule of rates’ as contained in the appended Schedule and such other sums as may become payable to the contractor under the provisions of this contract”. The contract clearly stipulated that the work was to be carried out as per specifications contained in Volumes I and II of CPWD Manual, para 2.9.4 whereof provided that the “rate” includes the cost of materials and labour. Therefore, the claimants were not entitled to any extra amount for supply of sand. The arbitrator gave his award on 31-12-2003 accepting the said claim. For reference, the relevant portion of the award is extracted below:
“According to defence under the provision of 1967 CPWD specification Volumes I and II, the nature of the item includes sand also and not merely the labour charges, similarly the rate of sand-filling is for consolidated thickness or loose thickness or voids to any extent and this claim is denied in toto. Now here the dispute between the two parties is over the words supplying and providing and in respect of this item the particular words are missing whereas as observed earlier they were being found in respect of certain other items. According to the claimants since these words were missing in respect of this item of work, they took it that the material i.e sand would be supplied and, therefore, they quoted only the labour rate. The tender of M/s Gupta and Co. as pointed out to me, shows that in respect of this item of work, these words providing and supplying were used. It is submitted that there can't be two different phrapavlogies (sic phraseologies) in respect of the same item and as observed earlier, nothing prevented FCI from using those words and not giving rise to any confusion. Comparative statement showing contents and details of schedule items based on tender working with PWD, Bombay which clearly provides for rates for quantity of work for schedule items. The claimants here are trying to establish that their quotations were based without including the cost of materials supplied. If we see the figures in respect of the items, we find substantial force in the say of the claimants that the rate quoted by them is so low that it could not be in respect of price inclusive of cost of sand. If we see the wording of specification with contractor M/s Gupta & Co., we find additional words supplying and providing have been added under similar items of the schedule. Why these words were missing in case of the claimants is difficult to follow. The respondents contend that 1967 CPWD's specification in Volumes I and II covers the specifications not only for labour charges but also for providing and supplying of the materials required. It is very difficult to understand this defence, for if we look at the figures quoted in the tenders it would make it absolutely clear that the inclusion of cost of sand could not have to be in the mind of the contractor claimants. The figures are very low and I may be permitted to say that these figures do not cover the cost of sand. There is force in the say of the claimant that he did not vouch that he himself was to supply sand. Of course, I must say that there is no very satisfactory evidence about the quantity of sand used, its price and amount paid by the claimant to his suppliers but when the work was done FCI was bound to take upon it to make the payment though it may appear to be somewhat arbitrary. I allow this claim of Rs 8,23,101 (Rupees eight lakhs twenty-three thousand one hundred and one only).”
7. Being aggrieved, FCI filed objections against the award under Section 30 of the Arbitration Act, 1940 praying for setting aside of the award on Claim 9, but without any success. The learned Single Judge affirmed the view taken by the arbitrator that the rate quoted by the claimant did not include the cost of the material. FCI carried the matter in appeal before the Division Bench. Before the Division Bench, FCI also attempted to raise the issue of award of interest by the arbitrator, which was not permitted on the ground that the issue was neither taken up before the arbitrator nor was raised before the learned Single Judge. As noted above, the Division Bench has dismissed the appeal. Hence, the present appeal.
8. Learned counsel for the petitioner has submitted that the claim for supply of sand against Claim 9 was patently opposed to the terms of the contract between the parties. It is urged that the relevant clause of the contract is clear, unambiguous and admits of no such interpretation as has been given by the arbitrator. It is, thus, pleaded that the arbitrator has misconducted himself in awarding additional amount of Rs 8,23,101 in favour of the claimants, which part of the award deserves to be set aside.
9. On the other hand, learned counsel for the claimants submitted that it was within the domain of the arbitrator to construe the terms of contract in the light of the evidence placed on record by the claimants, particularly the terms of similar contracts entered into by FCI with the other contractors. It is asserted that the view taken by the arbitrator being plausible the High Court was justified in declining to interfere with the award.
10. While considering objections under Section 30 of the Arbitration Act, 1940 (for short “the Act”), the jurisdiction of the court to set aside an award is limited. One of the grounds stipulated in the section on which the court can interfere with the award is when the arbitrator has “misconducted” himself or the proceedings. The word “misconduct” has neither been defined in the Act nor is it possible for the court to exhaustively define it or to enumerate the line of cases in which alone interference either could or could not be made. Nevertheless, the word “misconduct” in Section 30(a) of the Act does not necessarily (sic only) comprehend or include misconduct or fraudulent or improper conduct or moral lapse but does comprehend and include actions on the part of the arbitrator, which on the face of the award, are opposed to all rational and reasonable principles resulting in excessive award or unjust result. (Union of India v. Jain Associates (1994) 4 SCC 665)
11. It is trite to say that the arbitrator being a creature of the agreement between the parties, he has to operate within the four corners of the agreement and if he ignores the specific terms of the contract, it would be a question of jurisdictional error on the face of the award, falling within the ambit of legal misconduct which could be corrected by the court. We may, however, hasten to add that if the arbitrator commits an error in the construction of contract, that is an error within his jurisdiction. But, if he wanders outside the contract and deals with matters not allotted to him, he commits a jurisdictional error (see Associated Engg. Co. v. Govt. of A.P (1991) 4 SCC 93 and Rajasthan State Mines & Minerals Ltd. v. Eastern Engg. Enterprises (1999) 9 SCC 283).
12. In this context, a reference can usefully be made to the observations of this Court in Alopi Parshad & Sons Ltd. v. Union of India AIR 1960 SC 588 wherein it was observed that the Contract Act does not enable a party to a contract to ignore the express covenants thereof, and to claim payment of consideration for performance of the contract at rates different from the stipulated rates, on some vague plea of equity. The Court went on to say that in India, in the codified law of contracts, there is nothing which justifies the view that a change of circumstances, “completely outside the contemplation of parties” at the time when the contract was entered into will justify a court, while holding the parties bound by the contract, in departing from the express terms thereof. Similarly, in Naihati Jute Mills Ltd. v. Khyaliram Jagannath AIR 1968 SC 522 this Court had observed that where there is an express term, the court cannot find, on construction of the contract, an implied term inconsistent with such express term.
13. In Continental Construction Co. Ltd. v. State of M.P (1988) 3 SCC 82 it was emphasised that not being a conciliator, an arbitrator cannot ignore the law or misapply it in order to do what he thinks is just and reasonable. He is a tribunal selected by the parties to decide their disputes according to law and so is bound to follow and apply the law, and if he does not, he can be set right by the court provided his error appears on the face of the award.
14. In Bharat Coking Coal Ltd. v. Annapurna Construction (2003) 8 SCC 154 while inter alia, observing that the arbitrator cannot act arbitrarily, irrationally, capriciously or independent of the contract, it was observed, thus:
“22. There lies a clear distinction between an error within the jurisdiction and error in excess of jurisdiction. Thus, the role of the arbitrator is to arbitrate within the terms of the contract. He has no power apart from what the parties have given him under the contract. If he has travelled beyond the contract, he would be acting without jurisdiction, whereas if he has remained inside the parameters of the contract, his award cannot be questioned on the ground that it contains an error apparent on the face of the record.”
15. Therefore, it needs little emphasis that an arbitrator derives his authority from the contract and if he acts in disregard of the contract, he acts without jurisdiction. A deliberate departure from contract amounts to not only manifest disregard of his authority or a misconduct on his part, but it may tantamount to a mala fide action (also see Associated Engg. Co. v. Govt. of A.P (1991) 4 SCC 93).
16. Thus, the issue which arises for determination is whether in awarding Claim 9, the arbitrator has disregarded the agreement between the parties and in the process exceeded his jurisdiction and has, thus, committed legal misconduct.
17. For deciding the controversy, it would be necessary to refer to the relevant clauses of the contract, which read thus:
“1. General specifications
1.1. The civil, sanitary, water supply and road works shall be carried out as per Central Public Works Department specification of works at Delhi, 1967, Volumes I and II with correction slips up to date .… In the case of civil, sanitary, water supply and road works and electrical works should there be any difference between the Central Public Works Department specifications mentioned above and the specifications of schedule of quantities, the latter i.e the specification of schedule of quantities, shall prevail. For items of work not covered in the CPWD specifications or where the CPWD specifications are silent on any particular point, the relevant specifications or code of practice of the Indian Standard Institution shall be followed.
1.2. Should any clarification be needed regarding the specifications for any work the written instructions from the Engineer-in-charge shall be obtained.”
18. Para 2.9.4 of the CPWD specifications insofar as it is relevant for the present appeal, reads as follows:
“2.9.4 Rate.— It includes the cost of materials and labour involved in all the operations described above.”
19. From the above extracted terms of the agreement between FCI and the claimants, it is manifest that the contract was to be executed in accordance with the CPWD specifications. As per para 2.9.4 of the said specifications, the rate quoted by the bidder had to be for both the items required for construction of the godowns, namely, the labour as well as the materials, particularly when it was a turnkey project. It is to be borne in mind that filling up of the plinth with sand under the floors for completion of the project was contemplated under the agreement but there was neither any stipulation in the tender document for splitting of the quotation for labour and material nor was it done by the claimants in their bid. The claimants had submitted their tender with eyes wide open and if according to them the cost of sand was not included in the quoted rates, they would have protested at some stage of execution of the contract, which is not the case here. Having accepted the terms of the agreement dated 19-9-1984, they were bound by its terms and so was the arbitrator. It is, thus, clear that the claim awarded by the arbitrator is contrary to the unambiguous terms of the contract. We are of the view that the arbitrator was not justified in ignoring the express terms of the contract merely on the ground that in another contract for a similar work, extra payment for material was provided for. It was not open to the arbitrator to travel beyond the terms of the contract even if he was convinced that the rate quoted by the claimants was low and another contractor, namely, M/s Gupta and Company had been separately paid for the material. The claimants' claim had to be adjudicated by the specific terms of their agreement with FCI and no other.
20. Therefore, in our view, by awarding extra payment for supply of sand the arbitrator has outstepped confines of the contract. This error on his part cannot be said to be on account of misconstruing of the terms of the contract but it was by way of disregarding the contract, manifestly ignoring the clear stipulation in the contract. In our opinion, by doing so, the arbitrator misdirected and misconducted himself. Hence, the award made by the arbitration in respect of Claim 9, on the face of it, is beyond his jurisdiction; is illegal and needs to be set aside.
21. Consequently, the appeal is allowed and the impugned judgment of the High Court to the extent it pertains to Claim 9 is set aside. However, on the facts and circumstances of the case, there shall be no order as to costs.