- Bookmark
- Share
- CaseIQ
Chief Engineer Of Bpdp/Reo, Ranchi v. Scoot Wilson Kirpatrick India (P) Ltd. .
Factual and Procedural Background
The appellant had filed an appeal before the Jharkhand High Court challenging an order made under the Arbitration and Conciliation Act, 1996. A learned Single Judge of the High Court dismissed that appeal on the ground that it was not maintainable because, in the High Court’s view, the impugned order did not fall within the ambit of Section 37 of the 1996 Act. The present proceedings are a further appeal to the Supreme Court of India questioning that ruling on maintainability.
Legal Issues Presented
- Whether an appeal lies under Section 37(1)(b) of the Arbitration and Conciliation Act, 1996 against the order in question.
- Whether previous Supreme Court decisions dealing with limitation (Union of India v. Popular Construction Co. and State of Goa v. Western Builders) preclude such an appeal.
Arguments of the Parties
Appellant's Arguments
- The appeal squarely falls within Section 37(1)(b) of the 1996 Act, which permits appeals from orders “setting aside or refusing to set aside an arbitral award.”
- Section 37(1)(b) is in pari materia with Section 39(1)(vi) of the Arbitration Act, 1940; therefore, the jurisprudence under the old Act supports maintainability.
Respondent's Arguments
- The matter is governed by Union of India v. Popular Construction Co. (2001) 8 SCC 470 and State of Goa v. Western Builders (2006) 6 SCC 239, which emphasise that Section 34(3) is a special limitation provision excluding Section 5 of the Limitation Act.
- Points raised orally but not found in the written grounds before the Supreme Court should not be entertained.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Union of India v. Popular Construction Co. (2001) 8 SCC 470 | Section 34(3) is a special provision overriding Section 5 of the Limitation Act for condonation of delay. | Distinguished; Court noted that the present case turns on appealability, not limitation. |
| State of Goa v. Western Builders (2006) 6 SCC 239 | Reiterated Popular Construction on exclusion of Section 5 in arbitration matters. | Distinguished for the same reason; limitation not in issue here. |
| Dharma Prathishthanam v. Madhok Construction (P) Ltd. (2005) 9 SCC 686 | Award void ab initio can be set aside by the court even dehors Section 30 of the 1940 Act; courts have suo motu power. | Cited to underline breadth of judicial powers when considering validity of awards. |
| Chhabba Lal v. Kallu Lal, AIR 1946 PC 72 | “An award on a reference presupposes a valid reference.” | Referenced illustratively in the discussion on void awards. |
| Union of India v. Ajit Mehta & Associates, AIR 1990 Bom 45 | Court may suo motu set aside an award that is ab initio void. | Used as part of comparative survey under the old Act. |
| Union of India, S.E. Railway v. K.S. Kalra, AIR 1992 MP 47 | Court can set aside an award without a Section 30 application if award is void. | Cited in same comparative context. |
| Rajendra Dayal v. Govind, 1970 MPLJ 322 | Similar proposition on court’s power to set aside void awards. | Again part of historical survey. |
| Union of India v. Shri Om Prakash (1976) 4 SCC 32 | Invalid reference falls within “or is otherwise invalid” in Section 30 of 1940 Act. | Examined while comparing 1940 and 1996 regimes. |
| Essar Constructions v. N.P. Rama Krishna Reddy (2000) 6 SCC 94 | Appeal is maintainable against dismissal of objections on limitation grounds; Section 5 may apply before judgment is pronounced. | Relied on to support the proposition that similar appeals were entertained under Section 39(1)(vi) of the 1940 Act. |
| Union of India v. Manager, Jain and Associates (2001) 3 SCC 277 | Reaffirmed Essar Constructions; dismissal of time-barred objection amounts to “refusal to set aside” an award and is appealable. | Cited to bolster argument on maintainability under Section 37(1)(b). |
| Fairgrowth Investments Ltd. v. Custodian (2004) 11 SCC 472 | Confirmed Popular Construction on exclusion of Section 5. | Mentioned while summarising the limitation jurisprudence. |
Court's Reasoning and Analysis
The Supreme Court first noted that Section 37(1)(b) of the 1996 Act is textually identical to Section 39(1)(vi) of the 1940 Act. Under the older provision, appeals were consistently entertained against orders “setting aside or refusing to set aside” an award. Decisions such as Essar Constructions and Manager, Jain and Associates illustrate this practice.
The respondent’s reliance on Popular Construction and Western Builders was held to be misplaced because those cases dealt exclusively with limitation and the inapplicability of Section 5 of the Limitation Act to applications under Section 34(3). The present matter does not concern condonation of delay; the only question is whether the statutory right of appeal exists.
Given the statutory language and the consistent line of authority under the 1940 Act, the Court concluded that an appeal does in fact lie under Section 37(1)(b). The High Court, by focusing on limitation jurisprudence instead of the scope of Section 37, failed to determine maintainability correctly.
Holding and Implications
ORDER SET ASIDE; APPEAL ALLOWED.
The Supreme Court quashed the Jharkhand High Court’s order and directed the High Court to hear the appeal on merits, recognising it as maintainable. The ruling primarily affects the parties by restoring their right to appellate scrutiny; it does not set a new substantive precedent but reaffirms earlier interpretations equating Section 37(1)(b) with Section 39(1)(vi) of the 1940 Act.
Arijit Pasayat, J.— Leave granted.
2. Challenge in this appeal is to the order passed by a learned Single Judge of the Jharkhand High Court holding that the appeal filed before it was not maintainable as the same does not fall within the ambit of Section 37 of the Arbitration and Conciliation Act, 1996 (in short “the Act”).
3. Learned counsel for the appellant submitted that the appeal was clearly maintainable under Section 37(1)(b) of the Act.
4. Per contra, learned counsel for the respondent submitted that the case is covered by the decision of this Court in Union of India v. Popular Construction Co. (2001) 8 SCC 470 and State of Goa v. Western Builders (2006) 6 SCC 239 and the High Court was justified in holding that the appeal was not maintainable. Therefore, it is submitted that certain aspects which have not been raised specifically in the grounds raised before this Court but submitted during the course of arguments cannot be taken note of.
5. Section 37(1)(b) of the Act is in pari materia with Section 39(1)(vi) of the Arbitration Act, 1940 (in short “the old Act”). The provisions in the Acts read as follows:
1996 Act
“37. (1) An appeal shall lie from the following orders (and from no others) to the court authorised by law to hear appeals from original decrees of the court passing the order, namely—
(b) setting aside or refusing to set aside an arbitral award under Section 34.”
1940 Act
“39. Appealable orders.—(1) An appeal shall lie from the following orders passed under this Act (and from no others) to the court authorised by law to hear appeals from original decrees of the court passing the order:
An order—
(vi) setting aside or refusing to set aside an award:”
6. In Dharma Prathishthanam v. Madhok Construction (P) Ltd. (2005) 9 SCC 686 it has been held by this Court as follows:
“27. In the event of the appointment of an arbitrator and reference of disputes to him being void ab initio as totally incompetent or invalid the award shall be void and liable to be set aside dehors the provisions of Section 30 of the Act, in any appropriate proceedings when sought to be enforced or acted upon. This conclusion flows not only from the decided cases referred to hereinabove but also from several other cases which we proceed to notice.
28. In Chhabba Lal v. Kallu Lal (1945-46) 73 IA 52, AIR 1946 PC 72 Their Lordships have held that an award on a reference presupposes a valid reference. If there is no valid reference, the purported award is a nullity.
29. On this point, there is near unanimity of opinion as amongst the High Courts of the country as well. Illustratively, we may refer to a few cases. In Union of India v. Ajit Mehta and Associates AIR 1990 Bom 45, (1989) 3 Bom CR 535 (AIR para 34) the Division Bench held that the court has suo motu power to set aside an award on ground other than those covered by Section 30 such as an award made by arbitrators who can never have been appointed under Section 8, as such an award would undoubtedly be ab initio void and non est. In Union of India v. K.S Kalra AIR 1992 MP 47 and Rajendra Dayal v. Govind 1970 MPLJ 322 both Division Bench decisions, the High Court of Madhya Pradesh has held that in certain situations the court may set aside an award even without there being an application under Section 30 or even if the petition under Section 30 has not been filed within the period of limitation if the court finds that the award is void or directs a party to do an act which is prohibited by law or is without jurisdiction or patently illegal. We need not multiply the number of authorities on this point as an exhaustive and illuminating conspectus of judicial opinion is found to be contained in Law of Arbitration and Conciliation — Practice and Procedure by S.K Chawla (2nd Edn., 2004 at pp. 181-84) under the caption — ‘Whether the court has suo motu power to set aside an arbitral award’ — and the answer given in the discussion thereunder is in the affirmative.
30. Though it has been held in Union of India v. Om Prakash (1976) 4 SCC 32 that an objection on the ground of invalidity of a reference is not specifically covered by Clauses (a), (b) and (c) of Section 30, yet it is included in the residuary expression ‘or is otherwise invalid’ and could have been set aside on such an application being made. However, the above decision cannot be treated as an authority to hold that an award which is void ab initio and hence a nullity consequent upon an invalid appointment and an invalid reference in clear breach of the provisions contained in Sections 8, 9 and 20 of the Act, can still be held to be valid if not objected to through an objection preferred under Section 30 of the Act within the prescribed period of limitation.
31. Three types of situations may emerge between the parties and then before the court. Firstly, an arbitration agreement, under examination from the point of view of its enforceability, may be one which expresses the parties' intention to have their disputes settled by arbitration by using clear and unambiguous language, then the parties and the court have no other choice but to treat the contract as binding and enforce it. Or, there may be an agreement suffering from such vagueness or uncertainty as is not capable of being construed at all by culling out the intention of the parties with certainty, even by reference to the provisions of the Arbitration Act, then it shall have to be held that there was no agreement between the parties in the eye of the law and the question of appointing an arbitrator or making a reference or disputes by reference to Sections 8, 9 and 20 shall not arise. Secondly, there may be an arbitrator or arbitrators named, or the authority may be named who shall appoint an arbitrator, then the parties have already been ad idem on the real identity of the arbitrator as appointed by them beforehand; the consent is already spelled out and binds the parties and the court. All that may remain to be done in the event of an occasion arising for the purpose, is to have the agreement filed in the court and seek an order of reference to the arbitrator appointed by the parties. Thirdly, if the arbitrator is not named and the authority who would appoint the arbitrator is also not specified, the appointment and reference shall be to a sole arbitrator unless a different intention is expressly spelt out. The appointment and reference — both shall be by the consent of the parties. Where the parties do not agree, the court steps in and assumes jurisdiction to make an appointment, also to make a reference, subject to the jurisdiction of the court being invoked in that regard. We hasten to add that mere inaction by a party called upon by the other one to act does not lead to an inference as to implied consent or acquiescence being drawn. The appellant not responding to respondent's proposal for joining in the appointment of a sole arbitrator named by him could not be construed as consent and the only option open to the respondent was to have invoked the jurisdiction of court for appointment of an arbitrator and an order of reference of disputes to him. It is the court which only could have compelled the appellant to join in the proceedings.”
7. Reference may be made to some observations in Essar Constructions v. N.P Rama Krishna Reddy (2000) 6 SCC 94 where it was held that appeal is maintainable against the dismissal of objections on the ground of limitation. Similar views were expressed in Union of India v. Manager, Jain and Associates (2001) 3 SCC 277. Paras 11, 12 and 19 read as follows:( & 288)
“11. In view of the aforequoted sections, it can be stated that—
(a) after receipt of an award, the court can suo motu refuse to make award rule of the court on the ground that (i) part of the award is upon a matter not referred to arbitration; and (ii) the award is imperfect in form or contains any obvious error. The court can also remit the award to arbitrator in case (i) where the award has left undetermined any matter referred to arbitration; or (ii) where it has determined any matter not referred to arbitration; or (iii) the award is so indefinite as to be incapable of execution; or (iv) is on the face of it illegal. This is also provided under parenthesis clause of Section 17 which provides ‘where the court sees no cause to remit the award or any of the matters referred to arbitration for reconsideration or to set aside the award, the court shall … proceed to pronounce judgment …’. Therefore, it cannot be stated that in case where objections under Section 30 or 33 are not filed the court is bound to pass decree in terms of the award.
(b) Section 5 of the Limitation Act gives discretion to the court to extend the time for filing application under Section 30 or 33 raising objections to the award.
(c) The Civil Procedure Code including Order 9 Rule 13 is applicable to the proceedings initiated by producing award before the court for passing a decree.
(d) The power of the court to modify the award under Section 15 or to remit the award to the arbitrator for reconsideration under Section 16 varies from the jurisdiction of the court to set aside the award under Section 30 or to determine the validity of the arbitration agreement or an award under Section 33.
12. The result is — before pronouncing judgment, the court has to apply its mind to arrive at the conclusion whether there is any cause to modify or remit the award. Further the phrase ‘pronounce judgment’ would itself indicate judicial determination by reasoned order for arriving at the conclusion that decree in terms of award be passed. One of the meanings given to the word ‘judgment’ in Webster's Comprehensive Dictionary [International Edn., Vol. I (1984)] reads thus: ‘the result of judging; the decision or conclusion reached, as after consideration or deliberation’. Further, Order 20 Rule 4(2) CPC in terms provides that ‘judgment’ shall contain a concise statement of case, the points for determination, the decision thereon, and the reasons for such decision. This is antithesis to pronouncement of non-speaking order.
19. Further, large part of the controversy involved in this appeal is covered by the decision rendered by this Court in Essar Constructions v. N.P Rama Krishna Reddy (2000) 6 SCC 94. The Court observed that because of the applicability of Section 5 of the Limitation Act, 1963, if the court has not pronounced judgment for whatever reason, although the time prescribed for making the application has expired and an application for setting aside the award is made with a prayer for condonation of delay, the court cannot pronounce judgment until the application is rejected. The court also observed that even after a decree is passed under Section 17, an application under Section 30 can be entertained provided sufficient cause is established. In either case, the rejection of the application would be a refusal to set aside the award. In case where such application is rejected on the ground that it is delayed and no sufficient cause has been made out under Section 5 of the Limitation Act, it would be an appealable order under Section 39(1)(vi) of the Act.”
(emphasis in original)
8. The decision in Popular Construction case (2001) 8 SCC 470 did not deal with specific issues in this case. In that decision it was held that in respect of “sufficient cause cases” the provisions of Section 34(3) of the Act which are special provisions relating to condonation of delay override the general provisions of Section 5 of the Limitation Act, 1963 (in short “the Limitation Act”). The position was reiterated in the Western Builders case (2006) 6 SCC 239 and also in Fairgrowth Investments Ltd. v. Custodian (2004) 11 SCC 472. There can be no quarrel with the proposition that Section 5 of the Limitation Act providing for condonation of delay is excluded by Section 34(3) of the Act.
9. But the question in the instant case is not about the applicability of Section 5 of the Limitation Act, and the question really is whether the appeal was maintainable. The High Court did not consider this aspect. The appeal is clearly maintainable. Therefore, the order of the High Court is set aside. The High Court shall deal with the matter and examine the respective stand on merits treating the appeal to be maintainable.
10. The appeal is accordingly disposed of with no order as to costs.
Alert