Swarnam Ramachandran (Smt) And Another v. Aravacode Chakungal Jayapalan .

Supreme Court Of India
Aug 25, 2004
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The appellants (vendors) and the respondent (purchaser) executed an agreement on 18-02-1981 for sale of a bungalow and land in Chembur, Mumbai, for Rs 10,00,000. An earnest sum of Rs 1,00,000 was paid at execution, with Rs 1,25,000 due by 18-04-1981 and the balance on or before 31-08-1981. Clause 8 permitted the vendors to extend the completion date to 31-12-1981.

The purchaser paid only Rs 50,000 of the Rs 1,25,000 on 31-03-1981. By letter dated 03-09-1981 the vendors extended the completion date to 31-12-1981 but demanded the remaining Rs 75,000 within three days. Their follow-up letter of 12-09-1981 purported to make 30-09-1981 the “essence” for that payment. On 30-09-1981 the purchaser sent two cheques: Rs 30,000 (dated 29-09-1981) and a post-dated cheque of Rs 45,000 (15-10-1981). Treating this as a breach, the vendors terminated the agreement on 03-10-1981 and forfeited the amounts received.

The purchaser filed Suit No. 1985 of 1981 in the Bombay High Court on 02-12-1981 seeking specific performance. A learned Single Judge decreed the suit on 03-10-1994, holding that time had not been made the essence and that the purchaser was ready and willing to perform. A Division Bench dismissed the vendors’ intra-court appeal on 17-06-2000. The vendors then approached the Supreme Court by special leave.

Legal Issues Presented

  1. Whether time was of the essence for payment of Rs 75,000 on or before 30-09-1981, thereby entitling the vendors to rescind the contract upon non-payment.
  2. Whether the purchaser had proved continuous readiness and willingness to perform his contractual obligations as required by Section 16 of the Specific Relief Act, 1963.

Arguments of the Parties

Appellants’ (Vendors’) Arguments

  • The contract fixed specific dates for payment, showing an intention to make time of the essence; the notice of 12-09-1981 validly crystallised this.
  • Because the purchaser tendered only a post-dated cheque for part of the Rs 75,000, he was not ready and willing to perform.
  • The property is an urban house whose value was rising rapidly; delay prejudiced the vendors, attracting the principle in K.S. Vidyanadam v. Vairavan.
  • Earlier default in paying Rs 1,25,000 by 18-04-1981 justified the vendors in making time essential thereafter.

Respondent’s (Purchaser’s) Position

  • Time was never agreed to be of the essence; the vendors themselves extended completion to 31-12-1981 and orally extended the Rs 1,25,000 payment to 30-09-1981.
  • The purchaser had always been ready and willing; the quick filing of the suit (02-12-1981) after notice of termination evidences this.
  • The post-dated cheque was given because other cheques were due to be cleared; no cheque was dishonoured.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
K.S. Vidyanadam v. Vairavan (1997) 3 SCC 1 Rising property values and delay may justify refusal of specific performance. Held inapplicable; lower courts had already decreed specific performance and facts differed.
Jamshed Khodaram Irani v. Burjorji Dhunjibhai, AIR 1915 PC 83 Equity treats contractual time-limits for immovable property as subordinate to the main purpose unless intention shows otherwise. Cited to support finding that original agreement did not make time essential.
V. Pechimuthu v. Gowrammal (2001) 7 SCC 617 Time is ordinarily essential in reconveyance agreements; price escalation may bar relief. Distinguished: case involved reconveyance; principles could not override concurrent findings below.
Nannapaneni Subayya Chowdary v. Garikapati Veeraya, AIR 1957 AP 307 Purchaser need only show readiness and willingness and that the contract remained subsisting. Applied to affirm that purchaser satisfied Section 16 readiness-and-willingness requirement.

Court's Reasoning and Analysis

Time not of the essence. The Court reiterated the presumption that time is generally not essential in contracts for sale of immovable property. It examined four indicia from Pollock & Mulla—contract wording, nature of property, nature of contract, and surrounding circumstances—and found no express stipulation or factual matrix showing an intention to make punctual payment vital.

The vendors themselves had extended the overall completion date to 31-12-1981, undermining their assertion that strict adherence to 30-09-1981 for Rs 75,000 was fundamental. Moreover, the vendors produced no evidence to rebut the purchaser’s testimony of an oral agreement extending that payment date. The purchaser’s conduct was not a “gross default” warranting rescission.

Validity of the vendors’ notice. A vendor may make time essential only if (a) he is ready and willing himself and (b) the purchaser’s default is sufficiently serious. Neither condition was met; the notice of 12-09-1981 was therefore ineffective to rescind.

Readiness and willingness. Assessing evidence, the Court affirmed concurrent factual findings that the purchaser had capacity to pay, offered cheques before termination, and promptly sued for performance. The post-dated cheque never bounced and the overall delay was minor, so Section 16 was satisfied.

Price escalation argument. Relying on Vidyanadam was rejected because (i) that decision concerned first-instance discretion, whereas two courts had already decreed performance, and (ii) the vendors had not adduced evidence of prejudice or unwillingness to perform.

Holding and Implications

APPEAL DISMISSED. The decree of specific performance in favour of the purchaser stands affirmed. The respondent’s obligation to deposit Rs 75,000 within eight weeks of the High Court judgment remains; the appellants may withdraw that sum with accrued interest if already deposited.

The ruling reinforces established principles that: (1) time is rarely of the essence in sales of immovable property; (2) vendors cannot unilaterally impose essentiality absent gross default; and (3) readiness and willingness are assessed on overall conduct. No new precedent was set, but the decision underscores strict evidentiary requirements for vendors seeking rescission.

Show all summary ...

S.H Kapadia, J.— Being aggrieved by the suit for specific performance being decreed, the defendant vendors have filed this appeal by special leave against judgment and order passed by the Division Bench of the Bombay High Court dated 17-6-2000 in Appeal No. 813 of 1994 confirming the judgment of the learned Single Judge dated 3-10-1994.

2. The facts giving rise to this civil appeal, briefly, are as follows:

By an agreement for sale dated 18-2-1981 entered into between the appellants as vendors and the respondent as purchaser, the appellants agreed to sell all that piece or parcel of land admeasuring 481.25 square metres bearing Plot No. 423-C out of the larger piece of land bearing City Survey No. 1285 (Part) of Suburban Scheme III of Chembur with bungalow bearing Municipal No. 1137(2) standing thereon (hereinafter for the sake of brevity referred to as “the suit property”) for lump sum consideration of Rs 10,00,000. Prior to the execution of the agreement, the respondent paid Rs 1,00,000 as earnest money. Under clause (1) of the said agreement, a sum of Rs 1,25,000 was to be paid by the respondent within two months from the date of the agreement i.e by 18-4-1981 and the balance of Rs 7,75,000 was payable by him on completion of the sale i.e by 31-8-1981. Under clause (8) of the agreement, the sale was to be completed on or before 31-8-1981. However, there was a proviso to clause (8) under which an option was given to the appellants to extend the date of sale up to 31-12-1981.

3. On 31-3-1981, the respondent herein paid Rs 50,000 by cheque to the appellants. By letter dated 3-9-1981, addressed by the appellants, it was alleged that Rs 1,25,000 was payable by the respondent on or before 18-4-1981; that the full amount was not paid; that the respondent was, therefore, called upon to make the balance payment of Rs 75,000 within three days from the date of receipt of the said letter. However, by the said letter, time to complete the sale was extended by the appellants under clause (8) up to 31-12-1981. In reply, the respondent stated that out of Rs 1,25,000, a sum of Rs 50,000 had been paid on 31-3-1981, when it was agreed by and between the parties that the balance amount of Rs 75,000 would be paid by 30-9-1981. By letter dated 12-9-1981, the appellants denied having agreed to receive the balance amount of Rs 75,000, payable on or before 18-4-1981, by 30-9-1981. At the same time, by the same letter dated 12-9-1981, the appellants agreed to accept the amount of Rs 75,000 on or before 30-9-1981 and purported to make time the essence for such payment. On 30-9-1981, the respondent's advocate forwarded two cheques to the appellants i.e cheque dated 29-9-1981 for Rs 30,000 and another cheque dated 15-10-1981 for Rs 45,000 (post-dated cheque). In the said letter, it was pointed out that the cheque for Rs 45,000 was post-dated as the respondent would be realising the effects of certain cheques deposited by him in his account. By letter dated 3-10-1981, the appellants alleged that time to pay balance amount of Rs 75,000 by 30-9-1981 was made the essence of the contract; that since the respondent had failed to pay the said amount, the agreement for sale stood terminated. Consequently, the appellants forfeited the amounts paid by the respondent under the agreement. By letter dated 17-10-1981, the respondent herein contended that time was not the essence of the agreement; that the agreement had been terminated with mala fide intentions; that the respondent had complied with all his obligations and that he was ready and willing to perform his obligations under the said agreement.

4. In the circumstances, on 2-12-1981, the respondent herein instituted Suit No. 1985 of 1981 on the original side of the Bombay High Court. In the suit, the respondent alleged that sometime in the last week of March 1981, he was informed that the appellants desired to extend the date of completion of sale till 31-12-1981, to which he agreed; that on that occasion he paid Rs 50,000; that it was agreed that in view of the postponement of the sale, the part-payment of Rs 75,000 be made by 30-9-1981. That, in terms of the said arrangement, on 30-9-1981, the respondent forwarded his two cheques for Rs 30,000 and Rs 45,000; that the cheque for Rs 45,000 was post-dated as the respondent would be realising the effects of certain cheques deposited by him by 15-10-1981. That contrary to the said arrangement, the appellants vide notice dated 3-10-1981 illegally terminated the agreement alleging that time to pay the balance amount by 30-9-1981 was the essence of the contract as indicated by the letter dated 12-9-1981; that the respondent was always ready and willing to perform his part of the contract and in the circumstances, he was entitled to the decree for specific performance.

5. In the written statement, the appellants pleaded that there was delay in payment of Rs 1,25,000 on or before 18-4-1981; that although time was the essence of the contract and the same was communicated to the respondent, he committed default and, therefore, the appellants were entitled to terminate the agreement for sale and that the respondent was neither entitled to the specific performance of the contract nor damages, as prayed for.

6. On examination of the evidence on record, both documentary and oral, the High Court found that on the plain reading of the agreement, the same did not provide for time to be the essence; that circumstances did not exist enabling the appellants herein to make time the essence of the contract. That there was no ground, whatsoever, made out in the correspondence or in the written statement to suggest that the behaviour of the respondent was such as to prompt the appellants to make time the essence of the contract. That if causing delay was the grievance, how could the appellants justify their behaviour of extending the time for completion of the sale till 31-12-1981 vide clause (8) of the agreement. That the very letter dated 12-9-1981, which made time the essence for payment of Rs 75,000 by 30-9-1981, extended time for completion to 31-12-1981. That the appellants had failed to prove that the respondent was guilty of such grave defaults entitling the appellants to make time of the essence. That although several suggestions were made to the respondent, during his cross-examination, as to the oral agreement between the parties, about time being made the essence of the contract, no evidence was led by the appellants. The appellants failed to rebut the assertion of the respondent of the circumstances under which Rs 50,000 was paid and the oral arrangement to extend the time for payment of Rs 75,000 up to 30-9-1981. In the circumstances, it was held that time was not made the essence of the contract; that the appellants were not justified in making time of the essence in the matter of payment of Rs 75,000.

7. Before the learned Single Judge, it was argued that the respondent had failed to prove, though he had so pleaded, that he was ready and willing to perform his part of the contract. In this connection, it was urged that the respondent had sent a post-dated cheque for Rs 45,000 dated 15-10-1981 which indicated that he had no funds on the due date i.e on 30-9-1981 and, therefore, he had failed to prove that he was ready and willing to perform his part of the contract. This plea of the appellants was rejected as the High Court found on evidence that time to pay Rs 1,25,000 was extended to 30-9-1981; that it cannot be argued that there was non-compliance on the part of the respondent when the appellants themselves extended the completion date to 31-12-1981. The learned Single Judge found that taking into account the overall conduct of the respondent, it could be said that the respondent was ready and willing to perform his part of the contract; that the agreement was wrongly terminated on 3-10-1981 and the present suit was filed on 2-12-1981, which indicates that the respondent was eager to complete the transaction. In the above circumstances, the suit was decreed.

8. Aggrieved, the appellants herein instituted LPA No. 813 of 1994, which was dismissed by the impugned judgment. Hence, this civil appeal.

9. Mr T.L Vishwanath Iyer, learned Senior Counsel for the appellants contended that parties intended to make time the essence of the contract, since the agreement stipulated specific dates for the payment of the purchase price. That the appellants had validly made time the essence of the contract on 12-9-1981 and since part of the purchase price was not paid on or before 30-9-1981, the appellants were justified in terminating the agreement dated 18-2-1981. That the property in question consisted of a house in an urban area whose price rose continuously, which fact was relevant and which has not been taken into account by the High Court. It was urged that in the aforestated circumstances, any delay on the part of the respondent disentitled him to the relief of specific performance. In this connection, reliance was placed on the judgment of this Court in the case of K.S Vidyanadam v. Vairavan (1997) 3 SCC 1. It was urged that the appellants had made time the essence of the payment of Rs 75,000 on or before 30-9-1981 of which the respondent was made aware and, therefore, on failure to pay the said amount on the due date, the respondent herein had committed breach for which the appellants were entitled to terminate the agreement. Learned counsel further submitted that the respondent, on his own evidence, was aware that he had to pay Rs 75,000 on or before 30-9-1981 and yet on that day, the respondent forwards two cheques for Rs 30,000 dated 29-9-1981 and the other for Rs 45,000 dated 15-10-1981 which showed that the respondent agreed to the term of payment of Rs 75,000 on or before 30-9-1981 and at the same time, he was not ready and willing to perform his obligation. It was further urged that in his evidence, the respondent herein had conceded that he did not have funds to pay Rs 75,000 on 30-9-1981 which indicated that he was not continuously ready and willing to fulfil his obligations. It was further urged that under the agreement, an amount of Rs 1,25,000 had to be paid by 18-4-1981; that the said amount was not paid and that this lapse was sufficient ground for the appellants to make the time the essence of the contract. In the circumstances, it was urged that the High Court had erred in decreeing the suit for specific performance.

10. The key issue which is to be decided in this civil appeal is: whether time was the essence for payment of Rs 75,000 on or before 30-9-1981 and whether the said term was breached. This question does not depend only upon express stipulation made by the parties, but it also depends upon the intention of the parties. Notwithstanding that a specific date was mentioned in the agreement, one has not only to look at the letter but also at the substance of the contract. Whether time is of essence is a question of fact and the real test is the intention of the parties. It depends upon the facts and circumstances of each case.

11. According to Pollock & Mulla: Indian Contract & Specific Relief Acts [(2001), 12th Edn., p. 1086], the intention can be ascertained from:

“(i) the express words used in the contract;
(ii) the nature of the property which forms the subject-matter of the contract;
(iii) the nature of the contract itself; and
(iv) the surrounding circumstances.”

12. That time is presumed not to be of the essence of the contract relating to immovable property, but it is of the essence in contracts of reconveyance or renewal of lease. The onus to plead and prove that time was the essence of the contract is on the person alleging it, thus giving an opportunity to the other side to adduce rebuttal evidence that time was not of essence. That when the plaintiff pleads that time was not of essence and the defendant does not deny it by evidence, the court is bound to accept the plea of the plaintiff. In cases where notice is given making time of the essence, it is duty of the court to examine the real intention of the party giving such notice by looking at the facts and circumstances of each case. That a vendor has no right to make time of the essence, unless he is ready and willing to proceed to completion and secondly, when the vendor purports to make time of the essence, the purchaser must be guilty of such gross default as to entitle the vendor to rescind the contract.

13. Applying the above principles to the facts of the present case, we find that there was no justification in claiming, in the circumstances, to treat time as of the essence. At the outset, referring to the original agreement dated 18-2-1981, there is nothing in the express stipulation between the parties to show that the intention was to make the rights of the parties dependent upon the observance of the time-limits. Prima facie, equity treats the importance of such time-limits as being subordinate to the main purpose of the parties. (See Jamshed Khodaram Irani v. Burjorji Dhunjibhai AIR 1915 PC 83.)

14. In the present case, it was submitted on behalf of the appellants that time to pay Rs 75,000 on or before 30-9-1981 was made the essence of the contract by notice dated 12-9-1981 as the respondent was a chronic defaulter. We do not find any merit in this argument. In his evidence, the respondent asserted that when he paid Rs 50,000 on 31-3-1981, the appellants orally agreed to extend the time for payment of Rs 75,000 from 18-4-1981 to 30-9-1981; that at that time there was no agreement to make time the essence of the contract. This assertion has not been rebutted by the appellants. No evidence in rebuttal has been led by the appellants. Further, as rightly held by the courts below, the conduct of the respondent was not a gross conduct so as to justify giving of notice making time of the essence of the contract. That on the contrary, time was extended by the appellants in furtherance of clause (8) of the agreement up to 31-12-1981. In the circumstances, we are in agreement with the conclusion that time was not of the essence.

15. Mr Iyer, learned counsel for the appellants placed reliance on the judgment of this Court in V. Pechimuthu v. Gowrammal (2001) 7 SCC 617 in support of his above contention that time was the essence of the contract. We do not find merit in this argument. Firstly, as stated above, whether time is the essence of the contract would depend upon the facts and circumstances of each case. It would depend on intention of the parties. Secondly, the facts of the above judgment show that the matter dealt with an agreement for reconveyance, which as stated above, presumes that time is of essence. We have referred to Contract Law by Mulla hereinabove, which states that in cases of reconveyance or renewal of lease, time is of essence as a matter of presumption which is rebuttable. Lastly, in the case of V. Pechimuthu (2001) 7 SCC 617 it has been held that rise in price of land agreed to be conveyed may be a relevant factor in denying relief of specific performance when court is considering whether to grant decree for the first time. That it is not a relevant factor, however, before the Supreme Court of India at SLP stage where all the courts below have granted decree. It was, therefore, held that judgment of this Court in K.S Vidyanadam (1997) 3 SCC 1 was inapplicable. In the present case, the appellants, in any event, have not stepped into the witness box nor have they led evidence on any of their allegations. In the circumstances, we do not wish to burden this judgment by citing various authorities.

16. Mr Iyer, learned counsel for the appellants next contended that the respondent has failed to prove that he was always and that he continued to be ready and willing to fulfil his obligations under the agreement as required by Section 16 of the Specific Relief Act. It was urged that on 30-9-1981, the respondent herein offered two cheques to the appellants for Rs 30,000 dated 29-9-1981 and a post-dated cheque for Rs 45,000 dated 15-10-1981. That in his evidence, the respondent had conceded that he had no funds on 30-9-1981. That under Section 16, the burden is on the respondent to show that he was always ready and willing to comply with his obligations. Hence, it was urged that the courts below erred in granting specific performance to the respondent.

17. We do not find any merit in the above arguments. The courts below have examined the evidence on record and have recorded a finding of fact that the respondent was in a position to raise the wherewithal for implementing the contract. However, on facts, it is clear that time to complete the sale was extended up to 31-12-1981. That notice terminating the contract was given by the appellants on 3-10-1981 and the respondent had instituted the suit on 2-12-1981 which indicates that the respondent was eager to fulfil his part of the contract. That it is nobody's case that the post-dated cheque had bounced. That there was no unreasonable delay in payment of consideration and, therefore, it cannot be said that the respondent was not ready and willing to perform his part of the contract.

18. In the case of Nannapaneni Subayya Chowdary v. Garikapati Veeraya AIR 1957 AP 307, 1955 An LT 713 it has been held, after examining various authorities, that in a suit for specific performance, all that is necessary for the purchaser to show is that he was ready and willing to fulfil the terms of the agreement; that he had not abandoned the contract; that he had kept the contract subsisting. Applying the above tests to the facts of the present case, we are of the view that the courts below were right in their conclusion that the respondent was always ready and willing to comply with his obligations under the contract. In the circumstances, the courts below were right in decreeing the suit for specific performance.

19. Before concluding, it may be pointed out that under the impugned judgment, the respondent was ordered to deposit Rs 75,000 payable under the second instalment within eight weeks from 17-6-2000. If the aforestated amount has been so deposited, the appellants herein would be entitled to withdraw the same with interest, if any.

20. For the aforesaid reasons, we do not find any merit in this civil appeal, which is, accordingly, dismissed, with no order as to costs.