Haryana Urban Development Authority v. Som Nath .
Factual and Procedural Background
The respondent was allotted Plot No. 408, MGA Sector, Hissar on 23 March 1992 by the Haryana Urban Development Authority (HUDA). Possession was to be delivered within 90 days. Despite the respondent having paid substantial amounts, possession was not given, prompting the respondent to file a consumer complaint.
The District Consumer Forum awarded the respondent interest at 15% p.a. on the amounts deposited, payable after two years from each deposit. The State Commission dismissed the appeal filed by HUDA and affirmed the District Forum’s order. HUDA then approached the National Consumer Disputes Redressal Commission, which, relying on its earlier decision in Haryana Urban Development Authority v. Darsh Kumar, enhanced the interest to 18% p.a. HUDA challenged that order before the Supreme Court.
Legal Issues Presented
- Whether the National Commission could award uniform interest at 18% p.a. in consumer matters irrespective of the facts of each case.
- What amount of interest and other monetary relief, if any, the respondent is entitled to receive from HUDA for delayed possession and excess recovery.
Arguments of the Parties
The opinion does not contain a detailed account of the parties' legal arguments.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Ghaziabad Development Authority v. Balbir Singh, (2004) 5 SCC 65 | Interest at 18% p.a. should not be granted mechanically; compensation must be linked to actual loss/injury and a finding of deficiency in service or misfeasance. | The Court applied these guidelines, holding that the National Commission erred in awarding blanket 18% interest and must assess compensation case-wise. |
| Haryana Urban Development Authority v. Darsh Kumar, RP No. 1197 of 1998, 31-8-2001 (NC) | National Commission precedent used to justify granting 18% interest in similar allotment cases. | The Supreme Court rejected reliance on this precedent for automatic 18% interest and set aside the order based on it. |
Court's Reasoning and Analysis
The Supreme Court reiterated the principles laid down in Balbir Singh that consumer fora cannot award a flat 18% interest without examining the specific facts, the existence of deficiency in service, and resulting loss or injury. Applying those principles, it found the National Commission’s order unsustainable.
Examining the allotment letter, the Court noted that the original price of the plot was Rs 1,89,000, yet the respondent had paid Rs 2,37,000. Clause 5 of the allotment letter stipulated that interest would accrue only from the date of offer of possession. Since possession was first offered on 22 April 1997—five years after the promised date—HUDA could not levy interest for any period before that date.
Because counsel for HUDA could not explain the excess recoveries and adjustments made, the Court directed HUDA to:
- Recalculate dues, paying the respondent 15% p.a. interest on each deposit until payment.
- Forgo any interest on alleged delayed instalments before 22 April 1997.
- Refund any excess amount recovered, with 15% p.a. interest from the date of wrongful recovery.
- Return any amount deducted as TDS, along with 15% p.a. interest.
HUDA may approach the Court for clarification or modification if it believes further amounts are recoverable, but until permitted, it cannot demand sums beyond the allotment price.
Holding and Implications
The appeal is allowed; the National Commission’s order is set aside. The Supreme Court directed HUDA to deliver possession (if not already delivered) without further demand, recalculate payments as instructed, and file a compliance report within one month. No order as to costs.
Implications are confined to the parties: the respondent receives recalculated interest and possible refunds, while HUDA must comply with the detailed directions. The Court expressly stated that this order is not to be treated as a precedent, though future fora must adhere to the principles enunciated in Balbir Singh.
S.N Variava, J.— Before this Court, a large number of appeals have been filed by the Haryana Urban Development Authority and/or the Ghaziabad Development Authority challenging orders of the National Consumer Disputes Redressal Commission, granting to the complainants, interest at the rate of 18% per annum irrespective of the facts of each case. This Court has, in the case of Ghaziabad Development Authority v. Balbir Singh (2004) 5 SCC 65 deprecated this practice. This Court has held that interest at the rate of 18% cannot be granted in all cases irrespective of the facts of the case. This Court has held that the Consumer Forum could grant damages/compensation for mental agony/harassment where it finds misfeasance in public office. This Court has held that such compensation is a recompense for the loss or injury and it necessarily has to be based on a finding of loss or injury and must correlate with the amount of loss or injury. This Court has held that the Forum or the Commission thus had to determine that there was deficiency in service and/or misfeasance in public office and that it has resulted in loss or injury. This Court has also laid down certain other guidelines which the Forum or the Commission has to follow in future cases.
2. This Court is now taking up the cases before it for disposal as per principles set out in earlier judgment. On taking the cases we find that the copies of the claim/petitions made by the respondent complainant and the evidence, if any, led before the District Forum are not in the paper-book. This Court has before it the order of the District Forum. The facts are thus taken from that order.
3. In this case, the respondent was allotted a plot bearing No. 408.MGA Sector, Hissar on 23-3-1992. Delivery was to be given within 90 days. The respondent paid substantial amounts but the possession was not delivered. Thus the respondent filed a complaint. On these facts, the District Forum awarded interest @ 15% p.a on the amounts deposited. The interest was directed to be payable after two years from the date of each deposit.
4. The State Forum dismissed the appeal and confirmed the order of the District Forum. The appellants went in revision before the National Commission. The National Commission dismissed the revision filed by the appellants relying upon its own decision in the case of Haryana Urban Development Authority v. Darsh Kumar RP No. 1197 of 1998 dated 31-8-2001 (NC) and observing that interest @ 18% p.a has been allowed by them under similar circumstances. As has been stated in so many matters, the order of the National Commission cannot be sustained. It cannot dispose of the matters by confirming award of interest in all matters irrespective of the facts of that case. It must, on facts of a case, award compensation/damages under appropriate heads if it comes to the conclusion that such award is justified/necessary. Accordingly the order of the National Commission is set aside.
5. We are informed that the appellants have offered possession on 22-4-1997. Counsel had no instructions whether the respondent had taken possession or not. Undoubtedly the respondent will be entitled to take possession, if he has not already taken possession. The appellants will deliver possession without demanding any further or other amounts.
6. We are informed that the respondent has paid a sum of Rs 2,37,000. We however find from the copy of the allotment letter, filed in this Court along with the affidavit of the Estate Officer dated 29-7-2004, that only a sum of Rs 1,89,000 was payable. As per the affidavit, interest payable to the respondent, as per the orders mentioned hereinabove, is supposed to have been adjusted against alleged outstanding dues and only a sum of Rs 26,392 has been paid to the respondent on 23-7-2004.
7. Counsel had no instructions and could not explain what were the amounts due from the respondent. As stated above the respondent has paid more than what he was bound to pay. Also neither before the District Forum nor the State Forum nor the National Commission and nor even in the appeal memo before this Court is there a claim that the appellants have to recover amounts from the respondent. When the dispute has been sub judice, the appellants are bound to put before the Court/Forum not just their defence but also their claim/counterclaim, if any. Without permission of the Court, the appellants cannot set at naught awards of the Forum by raising, outside court, demands against the respondents. It must be remembered that the appellants were to deliver possession in 90 days from 23-3-1992. They did not offer possession till 1997. As can be seen from the order of the District Forum possession was not being offered because development work had not taken place. As they were not in a position to deliver possession they cannot expect parties like the respondent i.e allottees to keep on paying instalments to them. In such cases i.e where the appellants are not in a position to deliver possession they cannot charge interest on delayed payments till after they offer possession. Clause 5 of the letter of allotment also so provides. It reads as follows:
“5. The balance amount i.e Rs 1,41,750 of the above price of the plot/building can be paid in lump sum without interest within 60 days from the date of issue of the allotment letter or in six half-yearly equal instalments. The first instalment will fall due after the expiry of one year of the date of issue of this letter. Each instalment would be recoverable together with interest on the balance price at 15% (fifteen per cent) interest on the remaining amount. The interest shall, however, accrue from the date of offer of possession.”
Thus, interest could only have been charged from the date of offer of possession.
8. As we are unable to understand and counsel has no instructions to be able to explain why extra payment has been collected and what adjustments are purported to have been made, we direct that the appellants shall now recalculate in the manner set out hereunder. In this case, the appellants must pay interest at 15% from the date of each deposit till the date of payment. They will not charge interest on delayed payments prior to 22-4-1997. If by that date the original price of Rs 1,89,000 had been paid they will not be entitled to and will not charge any interest. If anything extra is recovered they will repay that back to the respondent with interest thereon at 15% from the date of such wrongful recovery till payment. We, however, clarify that if the appellants have a claim and feel that they have to recover such amounts from the respondent, they are at liberty to approach this Court for clarification/modification of the order and if on that application they are permitted to so recover, they may. But in the absence of any such permission, they shall not recover anything extra/over and above the allotment price of Rs 1,89,000.
9. Further, if TDS amount is deducted they will now pay that over to the respondent with interest thereon at the rate of 15% from the date it was so deducted till payment. Such recalculation to be made within 15 days from today and the amounts found due and payable to the respondent to be paid to him within 15 days thereafter. A compliance report to be filed in this Court within one month from date. A copy of the recalculation to be annexed to the compliance report.
10. We clarify that this order shall not be taken as a precedent in any other matter as the order is being passed taking into account the special features of the case. The Forum/Commission will follow the principles laid down by this Court in the case of Ghaziabad Development Authority v. Balbir Singh (2004) 5 SCC 65 in future cases.
11. With these observations, the appeal stands disposed of with no order as to costs.