K. Ramasamy v. State Of T.N. And Ors.

Supreme Court Of India
Apr 12, 2002
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The matter concerns appeals arising from a judgment of the High Court of Madras that interfered with an arbitral award. The dispute relates to claim item No. 1 in the award, described as an additional claim for extra distance (“extra lead”) from which earth/gravel was required to be sourced by the contractor for the work.

Under the agreement, a specified source location (chainage 1750–2000) was indicated, with an indicated lead distance of 1 to 4 km. That specified place was found unsuitable, and the competent authority ultimately directed the contractor to obtain earth/gravel from different sources, resulting in a lead of 6 to 18 km.

The contractor raised a claim, and the arbitrator awarded Rs. 27,95,215/- towards the extra lead. The superintendent engineer also entertained the claim and allowed Rs. 5,41,527/-. The High Court, however, set aside the arbitrator’s award on the view that the contractor was not entitled to any additional claim, relying on Clause 106.02 of the contract.

Legal Issues Presented

  1. Whether, under Clause 106.02 of the contract, the contractor was entitled to an allowance for increased cost due to an increase in the length of haul when the originally designated material source was found unacceptable and alternative sources were directed.
  2. Whether the High Court erred in setting aside the arbitrator’s award by misreading Clause 106.02.

Arguments of the Parties

The opinion does not contain a detailed account of the parties' legal arguments.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court focused on the proper interpretation of Clause 106.02 governing “Source of materials.” It noted that while the clause states the contractor “will not be reimbursed for any expense in developing the new source,” it also expressly provides that “allowance or deduction will be made as the case may be for the increase or decrease in cost due to an increase or decrease in the length of haul.”

On a “plain reading” of the clause, the Court held that the prohibition is limited to expenses for developing a new source, and does not bar compensation linked to changed haul length. Because the contractor was required (pursuant to direction of the competent authority) to obtain materials from different sources resulting in a longer lead, the clause unequivocally permitted an allowance for the increased cost attributable to the increased haul.

The Court concluded that the High Court committed a “serious error” in misreading Clause 106.02 when it held that no additional claim was permissible and set aside the award.

Holding and Implications

ALLOWED / DISPOSED OF: The Court set aside the impugned judgment of the High Court of Madras and directed that the arbitrator’s award be made a rule of court.

The direct effect is the restoration and enforcement of the arbitral award (including the award amount for extra lead) in favour of the contractor. The opinion does not discuss broader implications beyond correcting the High Court’s interpretation of the contractual clause, and it does not cite or establish any new precedent.

Show all summary ...

ORDER

1. Leave granted.

2. These are appeals against the judgment of the High Court of Madras interfering with an award of the arbitrator, in an appeal being filed against the same. We are concerned with the award relating to claim item No. 1, which in turn is the additional claim for the extra distance from which the earth was taken by the contractor for the work in question. Under the agreement in question, the place specified for earth/gravel was taken, the place being chainage 1750-2000, and the distance indicated was between 1 to 4 k.m, But that place was not suitable, and ultimately the competent authority directed different sources from which the contractor was required to take the earth/gravel for the project in question. A claim being made, the arbitrator awarded Rs. 27,95,215/- towards the extra lead for which the contractor had to take the materials from this distance of 6 to 18 k.m. It is also apparent that the superintendent engineer himself entertained the claim and allowed a sum of Rs. 5,41,527/-. The High Court, however, in the impugned judgment being of the opinion that the contractor will not be entitled to any additional claim, set aside the award of the arbitrator. In coming to the aforesaid conclusion, the court relied upon Clause 100.02 of the contract, the aforesaid clause is quoted herein below In extenso:

Clause 106.02 PS to SSRB Source of materials (1) All materials shall be obtained from the sources designated in the contract. The excavation of materials from sources designated in the contract shall be under the direction of the engineer at all times in so far as selection of material or exact location of excavation is involved.

(2) If the sources previously approved are found to be unacceptable at any time and fail to produce materials satisfactory to the engineer, the contractor shall furnish materials satisfactory to the engineer; the contractor shall furnish materials from other approved sources. The contractor will not be reimbursed for any expense in developing the new source, but allowance or deduction will be made as the case may be for the increase or decrease in cost due to an increase or decrease in the length of haul.

3. On a plain reading of the aforesaid clause, we are of the considered opinion that what the petitioner is not entitled to any expense in developing the source. But so far as the increase or decrease in cost due to increase or decrease in the length of haul is concerned, the same is unequivocally permissible, as is apparent from the later part of the aforesaid clause, and the High Court therefore committed serious error in misreading the aforesaid clause of the contract. We, therefore, set aside the impugned judgment of the High Court and direct that the award of the arbitrator be made a rule of court.

4. The appeals are disposed of.