- Bookmark
- Share
- CaseIQ
Nirmala Anand v. Advent Corporation (P) Ltd. And Others
Factual and Procedural Background
The appellant (Plaintiff 4) entered into an agreement dated 8-9-1966 with Respondents 1 and 2 to purchase Flat No. 71 on the 7th floor of “Divya Prabha”, 12-A, Foreshore Road, Bombay, for Rs 60,000. By 30-6-1969, when possession was contractually due, she had already paid Rs 35,000. A few days before that date, the Bombay Municipal Corporation cancelled the lease of the land on which the building stood, leaving the structure incomplete (and it remains incomplete).
Several other purchasers sued for specific performance on 30-7-1969. All plaintiffs except Plaintiffs 4 and 7 later settled; Plaintiff 7 settled during the appellate stage. The trial court found the appellant ready and willing to perform, but exercised discretion to refuse specific performance, awarding damages and refund with interest instead. A Division Bench of the High Court affirmed that outcome.
On further appeal, a two-Judge Bench of the Supreme Court agreed that specific performance should be granted but split on whether the appellant must pay an additional Rs 40 lakh. Owing to this disagreement, the matter was referred to a three-Judge Bench, resulting in the present opinion.
Legal Issues Presented
- Whether the appellant is entitled to specific performance of the agreement dated 8-9-1966 despite the building remaining incomplete.
- If specific performance is granted, whether equity requires the appellant to pay an amount in addition to the contractual balance of Rs 25,000, and, if so, the quantum of such additional payment.
Arguments of the Parties
The opinion does not contain a detailed account of the parties' legal arguments.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Nirmala Anand v. Advent Corpn. (P) Ltd., (2002) 5 SCC 481 | Earlier two-Judge Bench opinions in the same litigation, reflecting differing views on imposing an additional payment of Rs 40 lakh as a condition for specific performance. | The three-Judge Bench considered the conflicting views in those opinions and replaced the figure of Rs 40 lakh with Rs 6.25 lakh while affirming the grant of specific performance. |
Court's Reasoning and Analysis
The Court reaffirmed that specific performance is a discretionary, equitable remedy. It noted the following factors:
- The appellant had consistently been ready and willing to perform her contractual obligations and had initiated the suit promptly after breach.
- Respondents 1 and 2 were the defaulting parties; they failed to complete the building and deliver possession.
- The appellant agreed to accept the flat on an “as-is-where-is” basis without any reduction in price and without holding the sellers liable for the building’s incompleteness.
- Although real-estate prices had escalated dramatically during the three decades of litigation, it would be inequitable to deny the appellant the benefit of that appreciation solely because of market conditions.
- Courts may impose reasonable monetary conditions when granting specific performance to balance equities. Given the sellers’ long deprivation of the remaining Rs 25,000, some additional payment was justified, but Rs 40 lakh was deemed “too onerous” and would effectively defeat specific performance.
Balancing these considerations, the Bench fixed a total outstanding payment of Rs 6.25 lakh (in lieu of Rs 25,000) as a fair and reasonable condition.
Holding and Implications
HELD: The appeal is allowed. Specific performance of the agreement dated 8-9-1966 is decreed on condition that the appellant pays Rs 6,25,000 to Respondents 1 and 2 within six weeks, in addition to amounts already paid. All other terms set out in paragraphs 8 and 9 of the judgment govern execution of the decree.
Implications: The decision grants the purchaser her contractual right to the flat while moderating the windfall from property appreciation through an equitable additional payment. It underscores that a non-defaulting purchaser will not ordinarily be denied specific performance merely because of price escalation, though courts may calibrate relief to prevent undue hardship to sellers. No new legal precedent is created beyond reaffirming discretionary principles under the Specific Relief Act.
Y.K Sabharwal, J.— The appellant, who was Plaintiff 4 in the suit, entered into an agreement dated 8-9-1966 with Respondents 1 and 2 for the purchase of Flat No. 71, on the 7th floor of the building known as “Divya Prabha” situated at 12-A, Foreshore Road, Bombay. The sale consideration payable under the agreement is Rs 60,000. The agreement stipulated that the building was to be completed and possession of the flat delivered to the appellant by 30-6-1969 up to which time, the appellant had already paid Rs 35,000 out of the sale consideration leaving a balance of Rs 25,000. Just a few days before the date fixed for completion and delivery of possession, the lease of the plot of land on which the flats were being constructed was cancelled by Bombay Municipal Corporation. At that stage, the building was incomplete. Admittedly, it is incomplete till date.
2. Similar agreements in respect of different flats were also entered into by the sellers with other flat purchasers. On 30-7-1969, a suit, out of which the present appeal has arisen, was filed seeking specific performance of the flat-purchase agreements. The plaintiffs other than Plaintiffs 4 and 7 settled their case with sellers during the pendency of the suit and Plaintiff 7 also settled during pendency of the appeal before the Division Bench of the High Court. There was, however, no settlement between the plaintiff-appellant and Respondents 1 and 2. In the decision of the suit, learned Single Judge of the High Court held that the appellant was always ready and willing to perform her part of the contract and it was the sellers who committed breach in not carrying out the terms of the agreement. Learned Single Judge was, however, of the view that the grant of specific performance being discretionary remedy in equity, taking into account several and serious imponderabilities and further considering that huge sums may be required to complete the building, which amount cannot be properly assessed, the appellant was not entitled to the relief of specific performance and instead it was directed that the seller shall pay to the appellant damages as assessed by the Commissioner for taking accounts with interest at 6% per annum from the date of the decree till the date of payment/realization, in addition to the repayment of Rs 35,000 with interest thereon at 9% per annum from 4-10-1967 till the date of decree and for the subsequent period, at 6% per annum till the date of payment/realization. The judgment and decree of the learned Single Judge was affirmed by a Division Bench of the High Court in appeal. Aggrieved therefrom, the present appeal was filed on grant of leave.
3. The appeal was heard by a two-Judge Bench. The learned Judges have concurred that the appellant is entitled to specific performance of the agreement dated 8-9-1966. There has, however, been difference of opinion between learned Judges on the condition in respect of additional amount that may be paid by the appellant to Respondents 1 and 2 and, therefore, the matter has been placed before this three-Judge Bench. The opinions of the learned Judges are reported in Nirmala Anand v. Advent Corpn. (P) Ltd. (2002) 5 SCC 481 In the opinion expressed by Brother Justice Doraiswamy Raju, the appellant has been directed to pay a sum of Rs 40,00,000 in addition to the sum already paid to Respondents 1 and 2 and in the view of Brother Justice Ashok Bhan, it would be unfair to impose the condition of payment of Rs 40,00,000 and the appellant is entitled to specific performance of agreement to sell on the price mentioned in the agreement.
4. We have heard learned counsel for the parties. The only question to determine is as to whether the appellant shall be directed to pay to Respondents 1 and 2 any additional sum and if so, what amount.
5. The appellant is prepared and willing to take possession of the incomplete flat without claiming any reduction in the purchase price and would not hold Respondents 1 and 2 responsible for anything incomplete in the building. It has been concurrently held that she did not commit breach of the agreement to sell. She has always been ready and willing to perform her part of the agreement. The appellant is ready and willing to pay to Respondents 1 and 2 interest on the sum of Rs 25,000. The breach was committed by Respondents 1 and 2 as noticed hereinbefore. It is evident that the appellant is ready to take incomplete flat and pay further sum as noticed, most likely on account of phenomenal increase in the market price of the flat during the pendency of this litigation for over three decades. We see no reason why the appellant cannot be allowed to have, for her alone, the entire benefit of manifold mega increase of the value of real estate property in the locality. In our view, it would not be unreasonable and inequitable to make the appellant the sole beneficiary of the escalation of real estate prices and the enhanced value of the flat in question. There is no reason why the appellant, who is not a defaulting party, should not be allowed to reap to herself the fruits of increase in value.
6. It is true that grant of decree of specific performance lies in the discretion of the court and it is also well settled that it is not always necessary to grant specific performance simply for the reason that it is legal to do so. It is further well settled that the court in its discretion can impose any reasonable condition including payment of an additional amount by one party to the other while granting or refusing decree of specific performance. Whether the purchaser shall be directed to pay an additional amount to the seller or converse would depend upon the facts and circumstances of a case. Ordinarily, the plaintiff is not to be denied the relief of specific performance only on account of the phenomenal increase of price during the pendency of litigation. That may be, in a given case, one of the considerations besides many others to be taken into consideration for refusing the decree of specific performance. As a general rule, it cannot be held that ordinarily the plaintiff cannot be allowed to have, for her alone, the entire benefit of phenomenal increase of the value of the property during the pendency of the litigation. While balancing the equities, one of the considerations to be kept in view is as to who is the defaulting party. It is also to be borne in mind whether a party is trying to take undue advantage over the other as also the hardship that may be caused to the defendant by directing specific performance. There may be other circumstances on which parties may not have any control. The totality of the circumstances is required to be seen.
7. In the present case, the suit was filed by the plaintiff within a month of the date when the possession under the agreement was to be delivered to her. By that time, she had already paid more than 50% of the sale consideration. There was no occasion for her to pay the balance consideration to the seller. The courts have concurrently found that the appellant has always been ready and willing to perform her part of the contract and the seller committed breach in not carrying out the terms of the agreement. While others left, the appellant has been single-handedly fighting for her rights under the agreement. She has agreed to take the flat on as-is-where-is basis without claiming any reduction in purchase price and without making the seller liable for anything incomplete in the building. Further the building except the flat in question has been sold by Respondents 1 and 2 to the 7th respondent. For the revival of the building plans, revival of lease and other such steps, the sellers and/or their assignees may have to take steps as per agreement between them but to ask the appellant to pay to Respondents 1 and 2, a sum of Rs 40,00,000 would be too onerous and would almost amount to denying her specific performance. It would also amount to putting a premium on the breach committed by Respondents 1 and 2. Along with the remaining amount of the sale consideration, the appellant can also be directed to pay to Respondents 1 and 2 some reasonable additional amount, they having been deprived of that amount of Rs 25,000 during all these years.
8. Having regard to the totality of the circumstances, we would direct the appellant to pay to Respondents 1 and 2 a sum of Rs 6,25,000 instead of Rs 25,000. The amount of Rs 40,00,000 wherever it appears in the opinion of Justice Doraiswamy Raju, would be read as Rs 6,25,000. All other conditions will remain.
9. The appeal is accordingly allowed and the impugned judgment and decree of the High Court shall stand modified and altered and there shall be a decree in Suit No. 744 of 1969 on the file of the original side of the High Court, Bombay in the following terms:
(i) There shall be conditional decree for specific performance of the agreement dated 8-9-1966 entered into between the 4th plaintiff and Defendants 1 and 2 and Defendants 1 and 2 shall execute a sale deed as envisaged in the agreement for sale of Flat No. 71 on the 7th floor of the building known as “Divya Prabha” situated at 12-A, Foreshore Road, Bombay, on “as-is-where-is condition”.
(ii) That appellant-Plaintiff 4, within a period of six weeks, shall pay defendant-Respondents 1 and 2, a sum of Rs 6,25,000 (Rupees six lakhs and twenty-five thousand only) in addition to the sum already paid by her. The appellant shall be entitled to have the sale deed executed in her favour only on prior compliance and satisfaction of this condition.
(iii) The rights and interest in the land shall be as agreed to between parties and as per scheme and arrangement contained in the agreement dated 8-9-1966.
(iv) Defendants 1 and 2 and/or the 7th respondent in this appeal viz. Gaurav Overseas Private Ltd., 92, Maker Chambers, Nariman Point, Bombay 400 020, as and when they secure the necessary renewal of the lease and revalidation of the building plan, the same shall be for the benefit of the appellant-Plaintiff 4 also, subject to the condition that she shall contribute her share of the monetary commitments and expenses incurred therefor, on being intimated by any of them in writing within four weeks from the date of such receipt of the intimation. In case of dispute about the quantum, the same shall be got determined and settled before the Commissioner for taking accounts, on being moved by either of them. The sum so determined shall be a charge on the property comprised in Flat No. 71, till it is paid and shall be entitled to be recovered, accordingly.
(v) The appellant and the 7th respondent shall be at liberty to mutually agree for completion of the incomplete building at such prevailing market rates as would be applicable for the work and manner of its completion and the mode of payment. If there can be no such mutual agreement among the appellant and the 7th respondent in this regard, as and when the sale deed is executed by the 1st and 2nd defendants, as per this decree, the appellant shall be at liberty to make her own arrangement to have her flat completed through approved and licensed architects.
(vi) The sale/conveyance pursuant to the decree in the suit shall be subject to all such rights and liabilities and obligations of respective parties (the appellant, Respondents 1, 2 and 7) under the suit agreement, as are available to each of them against the others, had the sale been effected even without the intervention of this Court, by mutual agreement of parties.
(vii) The appellant failing to comply with the terms of the conditional decree passed as above, shall stand denied and lose her right and entitlement to get specific performance of the agreement dated 8-9-1966 in her favour and consequently, the appeal shall stand dismissed with the appellant's rights secured as per the judgments and decrees dated 23-3-1981 and 15-7-1987 firmly affirmed and settled, and the rights to have them executed in the manner known to law, alone surviving to the appellant.
(viii) Each party shall bear their respective costs in this Court.
10. The appeal is allowed in the above terms.
Alert