T.P George v. State Of Kerala And Another
Factual and Procedural Background
The appellant was awarded a contract to construct the main canal driving tunnel for the Kallada Irrigation Project, initially to be completed by 4-3-1983. Owing to delays, the parties executed a supplemental agreement on 20-10-1983 extending the completion period. Disputes concerning payment and delays were referred to a sole arbitrator who delivered a reasoned award on 12-8-1985 in favour of the appellant.
The respondents filed objections, but by judgment dated 31-3-1986 the trial court rejected those objections and made the award a rule of court. On appeal, the High Court (15-2-1989) set aside the arbitrator’s award on Claims 12(i) and 12(k) and disallowed interest from the date of the award, while upholding Claim 12(j). The present Supreme Court appeal challenges that partial reversal.
Legal Issues Presented
- Whether the arbitrator acted beyond his authority by allowing Claims 12(i) (price escalation) and 12(k) (revision of rates) in spite of the supplemental agreement dated 20-10-1983.
- Whether the arbitrator was competent to award interest from the date of the award until realisation.
Arguments of the Parties
Appellant’s Arguments
- Claim 12(i) arose under Clause 32 of the original contract for price escalation; Claim 12(k) concerned revision of rates.
- The delay was attributable to the respondents, forcing the appellant to sign the supplemental agreement under economic duress to secure payment of pending bills.
- Letters dated 5-10-1983, 6-10-1983, and 24-11-1983 were written “without prejudice,” reserving all claims; hence the supplemental agreement did not waive existing claims.
- The arbitrator expressly considered and accepted this position; his view being a plausible interpretation, the court should not substitute its own view.
Respondents’ Arguments
- Execution of the supplemental agreement barred the appellant from pursuing any additional monetary claims.
- By awarding amounts contrary to the supplemental agreement, the arbitrator misconducted himself, justifying High Court interference.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Jagdish Rai & Brothers v. Union of India (1999) 3 SCC 257 | Interest should ordinarily be granted on money decrees; identified four distinct stages for awarding interest. | Relied upon to conclude that interest from the date of award to realisation is permissible absent strong reasons to refuse. |
| Hindustan Construction Co. Ltd. v. State of J&K (1992) 4 SCC 217 | An arbitrator is competent to award interest from the date of the award. | Cited to rebut the High Court’s view that such interest was impermissible. |
| Secy., Irrigation Deptt., Govt. of Orissa v. G.C. Roy (1992) 1 SCC 508 | Arbitrator’s power to grant pendente lite interest. | Supported the broader proposition that arbitrators may award interest at different stages. |
| Executive Engineer, Dhenkanal Minor Irrigation Division v. N.C. Budharaj (2001) 2 SCC 721 | Arbitrator can award interest for the pre-reference period. | Used cumulatively with earlier cases to affirm that interest may be granted at all four recognised stages. |
Court's Reasoning and Analysis
The Supreme Court noted that the effect of the supplemental agreement on pending claims was explicitly referred to the arbitrator. The arbitrator, after reviewing contemporaneous correspondence, found that the supplemental agreement was executed under compulsion and expressly “without prejudice” to existing claims. This constituted a tenable and reasonable view; therefore, under settled law, a court cannot substitute its own interpretation merely because an alternative view is possible.
The High Court failed to consider the appellant’s letters of 6-10-1983 and 24-11-1983 or to analyse whether the agreement had been coerced. Consequently, its interference with Claims 12(i) and 12(k) was unwarranted.
On interest, the Court applied the quartet of precedents establishing that arbitrators may award interest for pre-reference, pendente lite, post-award, and post-decree periods. It found the High Court’s categorical denial of post-award interest “fallacious,” reinstating the arbitrator’s grant of interest from the date of the award.
Holding and Implications
Held: The appeal is allowed in part. The High Court’s judgment is set aside insofar as it annulled Claims 12(i) and 12(k) and disallowed interest from the date of the award. The High Court’s affirmation of Claim 12(j) remains undisturbed. No order as to costs.
Implications: The decision reinstates the arbitrator’s determinations, reinforcing the principle that courts must respect plausible arbitral interpretations of contract terms and confirming arbitrators’ authority to award interest through all recognised stages. No new precedent is created but existing jurisprudence on arbitral interest and judicial deference is reaffirmed.
S.N Variava, J.— This appeal is against a judgment dated 15-2-1989 wherein the appeal filed by the respondents was partly allowed.
2. Briefly stated the facts are as follows:
The appellant was awarded a contract for construction of a main canal driving tunnel of the Kallada Irrigation Project. The work was to be completed by 4-3-1983. A supplemental agreement dated 20-10-1983 extending the period of completion was entered into. As disputes arose between the parties the same were referred to a sole arbitrator, who gave a reasoned award dated 12-8-1985.
3. The respondents filed objections to the award, which were rejected by a judgment dated 31-3-1986 and the award was made a rule of court.
4. In the appeal, before the High Court, challenge was restricted to award of claims under Items 12(i), 12(j), 12(k) and award of interest from the date of award. The appeal filed by the respondents was partly allowed by the impugned judgment dated 15-2-1989. By this judgment the award of claims under Items 12(i) and 12(k) were set aside. Award of claim under Item 12(j) was upheld. Further the award of interest was also set aside. The only ground on which the claims under Items 12(i) and 12(k) have been set aside is that the arbitrator could not overlook the terms of the contract or agreement. It is held that the arbitrator could not have awarded these claims as they were contrary to the supplemental agreement dated 20-10-1983.
5. Mr Tripurari Ray, pointed out that Claim 12(i) was for loss in connection with the price escalation and that it was under clause 32 of the original agreement. He pointed out that Claim 12(k) was for revision of rates. He submitted that under the original contract the time for completion was fixed as 4-3-1983. He submitted that due to fault of the respondents the work could not be completed by that time. He submitted that the appellant was forced to execute the supplemental agreement in a form as dictated by the respondents as otherwise the respondents were not clearing the pending bills of the appellant. He drew attention of this Court to a letter dated 6-10-1983 addressed by the appellant to the Superintending Engineer wherein the appellant, before execution of the supplemental agreement, has recorded that he was protesting execution of the supplemental agreement and that he would be executing the supplemental agreement without prejudice to his claims. He submitted that even before writing of this letter the appellant had already, by a letter dated 5-10-1983, made his claims. He pointed out that after the supplemental agreement dated 20-10-1983 was executed the appellant addressed another letter dated 24-11-1983 to the Chief Engineer, stating that the supplemental agreement was got executed under coercion and undue influence and that the same was executed without prejudice to his claims.
6. Mr Tripurari Ray submitted that one of the questions before the arbitrator was whether this supplemental agreement was binding on the appellant and/or whether he had been forced to sign the agreement and/or whether the appellant was entitled to maintain his claims in view of the supplemental agreement. He pointed out that after hearing parties and considering the submissions of the respondents the arbitrator had by a reasoned award sanctioned the claims. He pointed out that in the award the arbitrator had held that the delay was not due to the fault of the appellant and that the supplemental agreement was got executed from the appellant. He pointed out that the arbitrator had held that the supplemental agreement was without prejudice to the claims which had already been made. The arbitrator held that the supplemental agreement did not debar the appellant from making or maintaining his claims. Mr Tripurari Ray submitted that this was a possible view of the matter. He submitted that the Court should be slow to interfere merely because another view was possible.
7. Mr G. Prakash supported the impugned judgment on the ground that once the appellant executed the supplemental agreement he could not make any claims. He submitted that the supplemental agreement provided that such claims could not be made. He submitted that the supplemental agreement was binding on the appellant. He submitted that the High Court was right in holding that the arbitrator had misconducted himself by awarding contrary to the supplemental agreement.
8. We have considered the rival submissions. It is to be seen that the question, whether the supplemental agreement dated 20-10-1983 debarred the appellant from pursuing his claims, was before the arbitrator. Such a question having been referred to the arbitrator, the view of the arbitrator would be binding if it is one which is possible. The arbitrator has taken note of the appellant's letters dated 6-10-1983 and 24-11-1983 and come to a conclusion that the supplemental agreement had been got executed and that the same was executed without prejudice to the claims which had already been made. This is a possible view.
9. We have seen the impugned judgment delivered by the High Court. The High Court has not at all considered the letter dated 6-10-1983 and 24-11-1983 nor dealt with the question as to whether or not the supplemental agreement was got executed. The High Court has not even considered the effect of the supplemental agreement having been executed without prejudice to the claims which had already been made. Even if the High Court had considered these aspects it could not have substituted its views for those of the arbitrator as it could not be said that the view taken by the arbitrator is unreasonable or one which cannot be arrived at by a reasonable person. In this view of the matter the impugned judgment cannot be sustained and is set aside in respect of claims under Items 12(i) and (k).
10. The next question is whether the High Court was right in setting aside the award of the interest from the date of the award. This Court has held in the case of Jagdish Rai and Bros. v. Union of India (1999) 3 SCC 257, (1999) 1 Arb LR 696, JT (1999) 2 SC 268 that the award of interest ought to be granted in all cases when there is a decree of money unless there are strong reasons to decline the same. In the case of Jagdish Rai & Bros. v. Union of India (1999) 3 SCC 257, (1999) 1 Arb LR 696, JT (1999) 2 SC 268 this Court has held that there are four stages of grant of interest, viz., (1) from the stage of accrual of cause of action till filing of the arbitration proceedings, (2) during pendency of the proceedings before the arbitrator, (3) future interest arising between date of award and date of the decree, and (4) interest arising from date of decree till realisation of the award. The power of court to grant interest from date of decree is not in doubt. In the case of Hindustan Construction Co. Ltd. v. State of J&K (1992) 4 SCC 217, AIR 1992 SC 2192 this Court has held that the arbitrator is competent to award interest from the date of the award. This Court has held in the case of Secy., Irrigation Deptt., Govt. of Orissa v. G.C Roy (1992) 1 SCC 508 that the arbitrator has power to grant interest pendente lite. Recently in the case of Executive Engineer, Dhenkanal Minor Irrigation Division v. N.C Budharaj (2001) 2 SCC 721, JT (2001) 1 SC 486 this Court has held that an arbitrator can award interest for the pre-reference period. Thus as per law laid down by this Court interest can be awarded at all four stages. The reasoning given by the High Court that interest cannot be awarded by the arbitrator is thus fallacious and cannot be sustained. In our view the direction to pay interest from the date of award, cannot be faulted. The impugned judgment to the extent that it disallows the interest from the date of the award, is set aside.
11. However, the impugned judgment to the extent that it upholds the award under Item 12(j) is upheld. The appeal stands disposed of accordingly. There shall be no order as to costs.