Distt. Magistrate, Allahabad v. Harminder Pal Singh
Factual and Procedural Background
A 30-year lease over Nazul land (Plot No. 8, Nashibpur, Baskhtiara, Allahabad) was originally granted on 21-8-1940 to Begum Mehdi Husain, with two further renewals of equal duration. On 4-12-1987 the lease was renewed in favour of several individuals, including Smt Jagjit Kaur Gulati and others. A Government Order dated 22-1-1987 informed all District Magistrates in Uttar Pradesh that construction of multi-storey buildings on Nazul land was permissible if (a) the remaining lease term exceeded 15 years and (b) building laws allowed such construction.
Relying on this order, the respondents applied on 10-3-1989 for approval of a plan to construct a multi-storey residential complex. The Vice-Chairman, Allahabad Development Authority (ADA) sanctioned the plan on 24-5-1989, but required countersignature by the District Magistrate (DM). The DM withheld countersignature, asserting that a subsequent Government Order dated 10-11-1989 mandated payment of premium and rent at commercial rates before permission could issue. The respondents filed a writ petition in the Allahabad High Court, which directed the Vice-Chairman, ADA to release the sanctioned plan, holding that further approval from the Collector or Board was unnecessary. The State of Uttar Pradesh and the Vice-Chairman, ADA appealed to the Supreme Court of India by special leave.
Legal Issues Presented
- Whether, after the Government Order dated 22-1-1987, additional approval or countersignature from the Collector or District Magistrate was legally required for construction on Nazul land.
- Whether the subsequent Government Order dated 10-11-1989, demanding premium and enhanced rent at commercial rates, applied to a building plan already sanctioned on 24-5-1989.
Arguments of the Parties
Appellants' Arguments
- The respondents’ building plan, although sanctioned by the Vice-Chairman, ADA, could not be acted upon without the District Magistrate’s countersignature.
- Under the order dated 10-11-1989, permission for group housing required prior payment of premium and annual rent at commercial rates; hence the respondents were obliged to comply.
Respondents' Arguments
This information was not available in the provided opinion.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The Supreme Court examined the original 1940 lease and noted that it was an instrument executed on behalf of the Government under Article 299 of the Constitution. The Court emphasized that the Government Order dated 22-1-1987 expressly authorised District Magistrates to permit multi-storey construction on Nazul land, provided building laws were satisfied and more than 15 years of the lease remained.
Because the Uttar Pradesh Urban Planning and Development Act, 1973 requires development plans to be sanctioned by the Development Authority, the Vice-Chairman, ADA was the competent authority to approve the plan. The Court rejected the contention that additional approval from the Collector or Board was necessary, finding such a requirement “untenable” in view of the Government Order.
The later order of 10-11-1989 could not retrospectively affect a plan that had already received sanction on 24-5-1989. Consequently, the District Magistrate had no lawful basis to withhold countersignature or to insist on additional premium and rent.
Accordingly, the Court held that the High Court’s direction to release the sanctioned plan was correct and required no interference.
Holding and Implications
APPEAL DISMISSED.
The Supreme Court affirmed the High Court’s order, confirming that once the Development Authority has sanctioned a building plan pursuant to the Government’s 22-1-1987 directive, no further approval from the Collector or District Magistrate is required, and subsequent administrative orders cannot impose new financial conditions on an already-sanctioned plan. The decision resolves the dispute between the parties but does not announce a new legal precedent beyond applying the existing Government Order and statutory framework to the facts.
S. Rajendra Babu, J.— A lease was granted for a piece of Nazul land bearing Plot No. 8, Nashibpur, Baskhtiara, Allahabad to one Begum Mehdi Husain for a period of 30 years from 21-8-1940 with the provision of two further renewals of 30 years. In 1983 (sic 1989) the Vice-Chairman, Allahabad Development Authority (ADA) sanctioned a plan subject to countersigning by the District Magistrate. The lease was renewed on 4-12-1987 in the names of Smt Jagjit Kaur Gulati, Shri Harminder Pal Singh, Shri Jitendra Singh, Smt Bhulari Devi, Shri Rajendra Singh, Shri Pramod Kumar Agarwal and Nazir Faiyaz Khan. By a letter dated 22-1-1987 all the District Magistrates in Uttar Pradesh were informed regarding construction of multi-storey buildings on Nazul land to the effect that the Government has no objection for building up multi-storey building on Nazul land as per the procedure prescribed by the Government in the order dated 16-10-1986 provided the balance lease period is more than 15 years and that as per the building construction laws, the construction of the proposed building is permissible. It was also made clear therein that in case of sale of such flats, the real rent should be realised after proportionately distributing the rent between the flat-owners. Based on this Government Order it is stated that the plan had been sanctioned by the Vice-Chairman, ADA. When the District Magistrate did not countersign the said sanctioned plan, a writ petition was filed before the High Court. The High Court directed the Vice-Chairman, ADA to release the sanctioned plan dated 20-5-1989 in favour of the respondents. This petition was contested both by the State and by the Vice-Chairman, ADA. The stand of the appellants is that the respondents filed an application for a plan on 10-3-1989 for the construction of the multi-storey residential complex which was sanctioned by the Vice-Chairman, ADA as communicated to them on 24-5-1989. It was stated that the plan could be released after countersignature was obtained from the District Magistrate. The District Magistrate did not countersign the sanctioned plan and when the matter was pending before him, another order dated 10-11-1989 had been issued which provided that before allowing residential construction of the group housing the premium and rent should be realised on commercial rates from the lessee and thus the respondents had to pay a certain sum towards premium and annual rent at certain rate. The High Court felt that the only objection raised on behalf of the District Magistrate is the payment of the premium and the rent as provided in the order dated 10-11-1989. The High Court examined the provisions of the lease deed and is of the opinion that the sanction of both the Collector and the Board was not essential and it was sufficient if the Board gave its approval and, in the present case, the Vice-Chairman, ADA had given such sanction. After analysing the relevant enactments, it took the view that the powers of the Board stood transferred to different authorities and ultimately vested in the Development Authority and, therefore, the Vice-Chairman, ADA could grant sanction to the plan. The High Court, therefore, rejected the contention raised on behalf of the appellants thereby allowing the writ petition. Hence this appeal by special leave.
2. The lease deed has been made available to us which has been executed on behalf of the Governor of the United Provinces on the one part and Begum Mehdi Husain on the other part to be effective for a period of 30 years from 21-8-1940, which has been renewed from time to time on certain terms of agreed rent. The lease deed also provides as follows:
“And also will within twenty-four calendar months next after the date of these presents at his expense and to the satisfaction of the Collector for the time being or/Board of Allahabad in a good substantial and workman-like manner erect and complete on such parts of the said premises as are marked out on the plan hereto annexed a dwelling house and outbuildings according to the plan and elevation to be approved by such Collector/Board which dwelling house and outbuildings shall be of the value of Rs 5000 at least and also that no part of the external elevation or plan of such dwelling house and outbuildings shall at any time be altered or varied from the original elevation or plan thereof without the written consent of such Collector/Board and no other building shall be erected on the said premises without the like consent.”
That this lease deed had been granted for and on behalf of the Government is clear in terms of Article 299 of the Constitution and it is also clear by Communication No. 278/9-Nazul-87/485N/86 that the Government had instructed all the District Magistrates as to the manner of construction of multi-storey buildings also to be made on Nazul land, to which we have adverted to. By letter dated 22-1-1987 when that procedure had been prescribed and the lease itself is under the Nazul Rules framed pursuant to the executive orders of the Government, we fail to understand as to how any other procedure is required in matters of this nature. The argument that the permission of the Collector or the Board is required in spite of orders made by the Government dated 22-1-1987 is untenable. Under the terms of the orders of the Government all the District Magistrates are bound to act and permit construction on such land. Such buildings can be constructed under the Building Construction Laws. Under the Uttar Pradesh Urban Planning and Development Act, 1973, the development can take place in terms of Section 14 of the Urban Planning and Development Act, 1973 and whenever any development takes place, sanction of the Development Authority is required. Thus the construction had to be made only under the Building Construction Laws as stated in the Government Order and there is no other requirement to be complied with. Therefore, it is unnecessary to engage our attention to the argument advanced on behalf of the appellants that the sanction of the Collector as well as the Board is required in a matter of this nature. Apart from the ambiguity arising on account of non-striking off of irrelevant portions in the lease deed, the Government Order makes clear the manner of construction of multi-storey buildings on Nazul land; the same can be complied with. If that is so, the District Magistrate's or the Collector's permission, though required, will have to be in terms of the Government Order dated 22-1-1987. Thus the later order issued on 10-11-1989 had no application to the case since sanction had been given to the plan by the Vice-Chairman, ADA on 24-5-1989. Thus the view taken by the High Court is unexceptionable and calls for no interference.
3. Therefore, we dismiss this appeal.