Rachakonda Narayana v. Ponthala Parvathamma And Another

Supreme Court Of India
Aug 23, 2001
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

On 12 December 1975, Defendant 1 agreed to sell two plots to the plaintiff for Rs 17,900: Plot A (2 acres of patta land) and Plot B (1.30 acres of sivaijama land). The plaintiff paid Rs 2,900 as earnest money. After a third party, Bhima Naik, asserted ownership of Plot B, the plaintiff sought specific performance of the agreement—initially asking either for proportionate price reduction or substitution of land for Plot B. The trial court dismissed the suit, holding that the plaintiff was impermissibly seeking enforcement of a new contract.

The plaintiff’s first appeal succeeded after the appellate court allowed him to amend the plaint: he relinquished all rights over Plot B and any compensation, and offered to pay the full contract price for Plot A alone. The appellate court decreed specific performance accordingly. The High Court, in second appeal by the defendant, reversed that decree, reasoning that the plaintiff had not pleaded readiness and willingness for full performance in the original plaint as required by Section 16(c) of the Specific Relief Act, 1963. The plaintiff then approached the Supreme Court by special leave.

Legal Issues Presented

  1. Whether, under Section 12(3) of the Specific Relief Act, 1963, a plaintiff may at the appellate stage amend the plaint to seek specific performance of only the performable portion of a contract after relinquishing claims to the non-performable part and to compensation.
  2. Consequently, whether the plaintiff is entitled to a decree for specific performance of Plot A alone despite the defendant’s inability to convey Plot B.

Arguments of the Parties

Appellant's Arguments

  • Relief under Section 12(3) can be invoked at any stage, including on appeal; the High Court erred in insisting it be pleaded at the time of filing the suit.
  • The plaintiff has demonstrated readiness and willingness by offering the full consideration and relinquishing rights over Plot B and compensation.

Respondent's Arguments

  • Section 16(c) requires the plaintiff to aver and prove readiness and willingness in the original plaint; later amendment should not be permitted once evidence is closed.
  • Allowing amendment at the appellate stage would unfairly prejudice the defendant and circumvent statutory requirements.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Kalyanpur Lime Works Ltd. v. State of Bihar, AIR 1954 SC 165; 1954 SCR 958 Relief based on Sections 13–17 of the Specific Relief Act, 1877 may be granted at any stage of litigation. Used to support the view that Section 12(3) relief in the 1963 Act can likewise be claimed on appeal.
A.L. Parthasararhi Mudaliar v. Venkata Kondiah Chettiar, AIR 1965 Mad 188 A purchaser may, at the appellate stage, relinquish part of the contract and pay full consideration to obtain specific performance of the performable portion. Cited to affirm the plaintiff’s right to amend the plaint and seek performance of Plot A alone after relinquishing rights over Plot B.

Court's Reasoning and Analysis

The Supreme Court analysed Section 12(3) of the Specific Relief Act, 1963, noting its two-part structure: (a) mandatory refusal of full specific performance where part of the contract cannot be performed, and (b) discretionary power to decree performance of the performable portion if the non-defaulting party pays the full price and relinquishes all further claims. The Court held that:

  • An appeal is a continuation of the suit; therefore, all rights existing on the suit’s filing date remain justiciable at the appellate stage.
  • The plaintiff only learned during the first appeal that Defendant 1 lacked title to Plot B; accordingly, amendment to plead Section 12(3) ingredients at that stage was permissible.
  • The plaintiff satisfied both statutory preconditions: he deposited the full contract price and unequivocally relinquished rights over Plot B and any compensation.
  • The precedents cited establish that courts may grant partial specific performance even when such relief is sought later in the proceedings.
  • The High Court’s strict insistence on initial-stage pleading under Section 16(c) misapplied the discretionary nature of specific performance and ignored the continuing jurisdiction of appellate courts.

Holding and Implications

APPEAL ALLOWED; High Court judgment set aside.

Consequences: the decree of the first appellate court—granting specific performance in favour of the plaintiff for Plot A upon payment of the entire consideration and relinquishment of Plot B and compensation—stands restored. No costs were awarded. The decision clarifies that relief under Section 12(3) of the Specific Relief Act can be sought through amendment at the appellate stage, reinforcing the principle that appellate courts may mould relief according to established rights even if not originally pleaded.

Show all summary ...

V.N Khare, J.— This is a plaintiff's appeal. On 12-12-1975, Defendant 1 executed an agreement to sell two plots of land — Plot A comprising 2 acres patta land and Plot B comprising Ac. 1.30 cents Sivaijama land for a sum of Rs 17,900 in favour of the plaintiff. Under the agreement to sell, a sum of Rs 2900 was paid to Defendant 1 as earnest money. Subsequently, one Bhima Naik issued a registered notice to the appellant stating therein that he is the owner of the land comprising in Plot B measuring Ac. 1.30 cents and that Defendant 1 has no right to sell the same to the appellant herein. The appellant sent notice to Defendant 1 for executing the sale deed. However, the defendant evaded to perform his part of the contract. It is under such circumstances, on 15-3-1976, the appellant herein brought a suit for specific performance, being OS No. 19 of 1976 in the Court of Subordinate Judge, Medanapalle. The plaintiff's case was that the appellant always was and is ready and willing to perform his part of the contract. Since the title of Defendant 1 was found to be defective as one Bhima Naik set up title on sivaijama land, hence the plaintiff prayed for specific performance of agreement to sell off two acres of patta land only after proportionate deduction of the price for the land or in the alternative, substitute the patta land for the price agreed upon between the parties. Defendant 1 contested the suit by filing a written statement. The defendant took the plea that the plaintiff cannot seek to enforce a new contract and that the plaintiff under the pretext of notice having been received by him from Bhima Naik, did not come forward to perform his part of the contract and his plea for proportionate deduction of the price or in the alternative, substitute the property is untenable and the suit is liable to be dismissed. The trial court held that the plaintiff is not entitled to seek enforcement of a new contract either by way of substitution of the patta land or for proportionate deduction of the agreed price of the land. The trial court further found that the title set up by Bhima Naik in respect of one item of the land did not entitle the plaintiff to vary the contract. With the aforesaid finding, the plaintiff's suit was dismissed.

2. The plaintiff thereafter filed an appeal before the first appellate court. Before the first appellate court for the first time it was stated by Defendant 1 that he has no title in respect of Plot B land and the same belonged to his wife and she has refused to assign the said land in his favour. Under such circumstances, the plaintiff moved an application for amendment of the plaint to the effect that the plaintiff is ready and willing to purchase Ac. 2 acres of land in Plot A by paying the entire sale consideration of Rs 17,900 and further he is relinquishing his claim in respect of the land contained in Plot B and that he would not claim any compensation. The said amendment was allowed by the appellate court. The first appellate court having found that Defendant 1 has no title in respect of land comprising in Plot B, and the plaintiff is ready and willing to pay up the whole of the agreed consideration amount, after relinquishing his claim in respect of Plot B land and the compensation, the plaintiff is entitled to a decree for specific performance. In that view of the matter, the appeal was allowed and the suit was decreed in respect of land comprised in Plot A measuring two acres of patta land.

3. Aggrieved, the defendant preferred a second appeal before the High Court. The High Court was of the view that since the plaintiff did not come with the suit claiming the benefit of sub-section (3) of Section 12 of the Specific Relief Act, 1963 (hereinafter referred to as “the Act”), and claimed performance of only part of the whole agreement, and therefore he was not ready and willing to perform his part of the whole contract and thus not entitled to a decree for specific performance of the agreement to sell. Consequently, the second appeal was allowed and the suit stood dismissed. It is against the said judgment of the High Court, the plaintiff has preferred this appeal by way of special leave petition.

4. Learned counsel for the appellant urged that the relief under sub-section (3) of Section 12 of the Act can be claimed even at the appellate stage and the High Court committed serious mistake of law in holding that such relief ought to have been claimed when the suit was filed. Learned counsel appearing for the respondents contended that in view of Section 16(c) of the Act, the plaintiff is to aver and establish that he has performed or has been ready and willing to perform the essential terms of the contract. The averment has to come in the plaint itself. An amendment to the pleading at a later point of time to bring in the statement is to be refused after the parties have gone into evidence.

5. On the arguments of the parties, the question that arises for consideration is whether the relief under sub-section (3) of Section 12 of the Act can be claimed at the appellate stage by amendment in the plaint. We would first examine whether the plaintiff was entitled to relinquish a portion of his claim under the agreement at the appellate stage and seek performance of the remaining part of the contract in conformity with Section 12(3) of the Act when the plaintiff for the first time came to know that Defendant 1 has no title in respect of sivaijama land.

6. Pomercy on Specific Performance stated thus:

“When the vendor's title proves to be defective in some particulars, or his estate is different from that which he agreed to convey, or is subject to encumbrances or outstanding rights to third persons, or the subject-matter generally the land is deficient in quantity, quality or value, it is plain that the contract cannot be specifically performed, according to its exact terms, at the suit of either party. In such a case there are only three possible alternatives for a court of equity to pursue, either to refuse this remedy entirely; or to enforce the contract without any regard to the partial failure, compelling the purchaser to take what there is to give and to pay the full price as agreed; or to decree the conveyance of the vendor's actual interest and allow to the vendee pecuniary compensation or abatement from the price, proportional to the amount and value of the defect in title or deficiency in the subject-matter.”

7. Sub-section (3) of Section 12 of the Specific Relief Act, 1963 runs as under:

“12. (3) Where a party to a contract is unable to perform the whole of his part of it, and the part which must be left unperformed either—
(a) forms a considerable part of the whole, though admitting of compensation in money; or
(b) does not admit of compensation in money;
he is not entitled to obtain a decree for specific performance; but the court may, at the suit of other party, direct the party in default to perform specifically so much of his part of the contract as he can perform, if the other party—
(i) in a case falling under clause (a), pays or has paid the agreed consideration for the whole of the contract reduced by the consideration for the part which must be left unperformed and a case falling under clause (b), pays or had paid the consideration for the whole of the contract without any abatement; and
(ii) in either case, relinquishes all claims to the performance of the remaining part of the contract and all right to compensation, either for the deficiency or for the loss or damage sustained by him through the default of the defendant.”

8. A perusal of sub-section (3) of Section 12 shows that the first part of the said provisions mandates refusal of specific performance of a contract on certain conditions. However, the latter part of the provisions permits a court to direct the party in default to perform specifically so much of his part of the contract as he can perform if the other party pays or has paid the agreed consideration for the whole of the contract and relinquishes all claims to the performance of the remaining part of the contract and all the rights to compensation for the loss sustained by him. If a suit is laid by the other party, the court may direct the defaulting party to perform that part of the contract which is performable on satisfying two preconditions i.e (i) the plaintiff pays or has already paid the whole of the consideration amount under the agreement, and that (ii) the plaintiff relinquishes all claims to the performance of the other part of the contract which the defaulting party is incapable to perform and all rights to compensation for loss sustained by him. Thus, the ingredients which would attract specific performance of the part of the contract, are: (i) if a party to an agreement is unable to perform a part of the contract, he is to be treated as defaulting party to that extent, and (ii) the other party to an agreement must, in a suit for such specific performance, either pay or has paid the whole of the agreed amount, for that part of the contract which is capable of being performed by the defaulting party and also relinquish his claim in respect of the other part of the contract which the defaulting party is not capable to perform and relinquishes the claim of compensation in respect of loss sustained by him. If such ingredients are satisfied, the discretionary relief of specific performance is ordinarily granted unless there is delay or laches or any other disability on the part of the other party.

9. Now, the question is whether relief under Section 12(3) of the Act is required to be pleaded in the plaint when the suit is laid or it can also be taken at the appellate stage. The view taken by the High Court is that the readiness and willingness to perform the terms of the contract by the plaintiff based on the latter part of sub-section (3) of Section 12 must be pleaded in the plaint itself when the suit is laid and in its absence the relief being discretionary cannot be granted by amendment of the plaint at the appellate stage. In Kalyanpur Lime Works Ltd. v. State of Bihar AIR 1954 SC 165, 1954 SCR 958 an identical question came up for consideration before the Supreme Court. In the said case, the Apex Court held that relief based on Sections 13, 14, 15 and 17 of the Specific Relief Act, 1877 can be granted at any stage of the litigation. In A.L Parthasarathi Mudaliar v. Venkata Kondiah Chettiar AIR 1965 Mad 188 it is held that it is open to the plaintiff to relinquish part of the performance of the contract after paying the entire consideration of the contracted amount at the appellate stage of the proceedings if the defaulting party is not capable to perform the whole of the contract.

10. We are in agreement with the statement of law expressed in the aforesaid decisions. In the present case, what we find is that it was for the first time at the appellate stage, Defendant 1 stated that he had no title in respect of Plot B sivaijama land which belonged to his first wife and his wife has refused to assign the said plot of land in his favour. It is on account of the said statement the plaintiff filed an application for amendment of the plaint relinquishing his claim in respect of Plot B of land as well as compensation for the loss he sustained for non-performance of part of the contract while agreeing to pay the entire contracted amount. An appeal is a continuation of the suit. When an appellate court hears an appeal, the whole matter is at large. The appellate court can go into any question relating to rights of the parties which a trial court was entitled to dispose of provided the plaintiff possesses that right on the date of filing of the suit. Defendant 1 prior to filing of appeal by the plaintiff never informed the plaintiff that his wife has refused to assign Plot B of land in his favour and he having no title over the said plot of land is incapable to perform the whole part of the contract. Under such circumstances, it was open to the plaintiff to move for amendment of the plaint, pleading therein the ingredients for part-performance of the contract as provided under sub-section (3) of Section 12 of the Act. It is not disputed that the plaintiff had deposited the entire contracted amount in the trial court. He further relinquished his claim in respect of Plot B of land as well as claim for compensation. Under such circumstances, the first appellate court was justified in allowing the amendment of the plaint and thereafter decreeing the suit of the plaintiff. We, therefore, find that the view taken by the High Court in holding that the plea taken by the plaintiff at the appellate stage having not been taken at the time of filing of suit, the suit would fail, is erroneous. For the aforesaid reasons the appeal deserves to be allowed.

11. We, accordingly, set aside the judgment under appeal. The appeal is allowed. There shall be no order as to costs.