Dwaraka Das v. State Of M.P And Another

Supreme Court Of India
Feb 10, 1999
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The appellant, a building contractor, was awarded a contract by the respondent State for constructing a 100-bed boys’ hostel at Polytechnic, Ujjain. The agreement (executed on 26 December 1960) required completion within 29 months, with intermediate milestones for ¼, ½ and ¾ of the work. Alleging obstruction by the Superintending Engineer, the appellant failed to meet these milestones. On 19 June 1961 the State rescinded the contract for non-performance.

Contending that the rescission was unlawful, the appellant sued for Rs 32,000 (including Rs 20,000 as loss of expected profit). The trial court decreed the entire amount with future interest at 6% per annum.

Subsequently, the appellant invoked Section 152 of the Code of Civil Procedure (CPC) seeking pendente lite interest, which the trial court granted by “correcting” its decree. The State challenged:

  • First Appeal No. 86 of 1973 – against the money decree, and
  • Civil Revision No. 145 of 1974 – against the order awarding pendente lite interest.

The High Court reduced the decree to Rs 4,783.33 with 6% future interest and allowed the revision, setting aside the pendente lite interest. The present appeal is from that judgment.

Legal Issues Presented

  1. Whether the trial court could, under Section 152 CPC, award pendente lite interest by treating its earlier omission as an “accidental slip or omission”.
  2. Whether the High Court erred in disallowing the contractor’s claim of Rs 20,000 as damages representing expected profit from the rescinded contract.

Arguments of the Parties

Appellant's Arguments

  • Non-grant of pendente lite interest in the original decree was a mere clerical/accidental omission rectifiable under Section 152 CPC.
  • Cited several authorities (e.g., Jainab Bai, Firozshaw, Maharaj Puttu Lal, W.B. Financial Corporation) to support liberal construction of Section 152 and entitlement to interest.
  • On damages, asserted that 10% of the contract value was a reasonable estimate of expected profit lost due to the State’s breach.

Respondent-State's Arguments

The opinion does not contain a detailed account of the respondent’s legal arguments.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Jainab Bai v. M.P. S.R.T.C. (1969 MPLJ 716) Section 152 can be used to award interest omitted from a decree. Held distinguishable; Supreme Court declined to follow its broad observations favouring correction of judicial omissions.
Thirugnanavalli Ammal v. P. Venugopala Pillai AIR 1940 Mad 29 Correction permissible only when decree mis-records what is already in the judgment. Approved as the correct statement of law on the limited scope of Section 152.
Maharaj Puttu Lal v. Sripal Singh AIR 1937 Oudh 191 Accidental omission of mesne profits in decree can be rectified. Distinguished; example of genuinely accidental omission, unlike present case.
Firozshaw v. State AIR 1957 MB 50 Future interest added where omission found accidental. Held inapplicable; present omission was part of conscious judicial decision.
W.B. Financial Corpn. v. Bertram Scott (I) Ltd. AIR 1983 Cal 381 Entitlement to interest under Section 34 CPC. Noted as irrelevant because scope of Section 152 was not examined there.
A.T. Brij Paul Singh v. State of Gujarat (1984) 4 SCC 59 Contractor may recover loss of profit (often 15% of remaining work) when State wrongfully rescinds contract. Relied on to reinstate damages; court accepted 10% of contract value as reasonable here.
Mohd. Salamatullah v. Govt. of A.P. (1977) 3 SCC 590 Court should not disturb trial court’s damage assessment (even if by estimate) once breach is established. Used to criticise High Court’s interference and to uphold trial court’s award of expected profit.

Court's Reasoning and Analysis

On Section 152 CPC and Interest: Section 152 is confined to correcting clerical or arithmetical mistakes or accidental slips. Once a judgment is signed, the court becomes functus officio and cannot alter its substantive decision. The trial court’s original decree expressly granted only future interest, implicitly rejecting pendente lite interest; hence the later order added a substantive benefit, beyond the scope of Section 152. The High Court was therefore correct in setting aside that order.

On Damages for Loss of Profit: The High Court disallowed Rs 20,000, reasoning that the contractor failed to prove actual loss. The Supreme Court found this erroneous: the claim was not for actual expenditure but for expected profit, a recognised head of damages when a works contract is wrongfully rescinded. Citing Brij Paul Singh and Mohd. Salamatullah, the Court held that a broad evaluation is permissible and 10% of the contract value (as awarded by the trial court) was reasonable. Given the High Court’s own finding that the State had breached the contract, the contractor was entitled to that sum.

Other Claims: Apart from reinstating the Rs 20,000, the Court accepted the High Court’s figure of Rs 4,783.33 on the remaining heads because the appellant conceded their correctness.

Holding and Implications

Holding: APPEAL PARTLY ALLOWED. The appellant is granted a decree for Rs 24,783.33 with 6% interest per annum from the date of decree until realisation; parties shall bear their own costs.

Implications: The judgment re-affirms the limited ambit of Section 152 CPC, cautioning courts against using it to revisit substantive determinations. Simultaneously, it strengthens the principle that contractors may recover reasonable loss-of-profit damages when the State improperly rescinds works contracts, even where precise proof of loss is impracticable.

Show all summary ...

R.P Sethi, J.— In response to the tenders invited by the respondent-State, the appellant herein was allotted the work for the construction of a hostel for 100 boys at Polytechnic Ujjain for which agreement (Ex. P-22) was executed between the parties on 26-12-1960. The entire work was required to be completed within 29 months with further condition that ¼th of the work was to be completed within 5 months, half the work to be completed within 10 months and ¾th work was to be completed within 15 months. The work order was issued to the appellant on 26-12-1960 who started construction on 28-12-1960. The Superintending Engineer is alleged to have obstructed the progress of the work with the result that the work could not be completed within the time schedule. The contract executed between the parties was rescinded by the respondents vide letter dated 19-6-1961 on the ground that the appellant had not completed even 10 per cent of the work despite lapse of more than 9 months. The appellant, however, contended that the termination of the contract was in breach thereof. He claimed Rs 20,000 as damages for breach of contract besides claiming other amounts payable by the respondent to him. Suit for the recovery of Rs 32,000 filed by the appellant was decreed with a direction that the appellant would also be entitled to future interest @ 6 per cent per annum.

2. After the decree of the trial court the appellant filed an application under Section 152 of the CPC praying for awarding of interest from the date of the suit till the date of the decree by correcting the judgment and decree on the ground that non-awarding of interest pendente lite was an accidental omission. The trial court allowed this application and directed the correction of the judgment and decree by awarding interest pendente lite.

3. Aggrieved by the judgment and decree of the trial court, the respondent-State filed First Appeal No. 86 of 1973 and against the order passed in application under Section 152, Revision Application No. 145 of 1974. The High Court, vide the order impugned herein, partly allowed the appeal by holding the respondent-State liable to pay only a sum of Rs 4783.33 to the plaintiff with interest at the rate of 6 per cent per annum. Civil Revision No. 145 of 1974 was allowed and the order of the trial court granting interest pendente lite was set aside.

4. We have heard learned counsel for the parties and perused the record.

5. Learned counsel appearing for the appellant has vehemently argued that the High Court was not justified in setting aside the order of the trial court passed on 30-11-1973 by which his client was granted pendente lite interest. It is submitted that non-granting of the interest for the period of litigation was an accidental omission which was rectified by the trial court. In support of his contention he has relied upon the judgments in Jainab Bai v. M.P SRTC 1969 MPLJ 716, 1969 ACJ 274, Firozshaw v. State AIR 1957 MB 50, Maharaj Puttu Lal v. Sripal Singh AIR 1937 Oudh 191, W.B Financial Corpn. v. Bertram Scott (I) Ltd. AIR 1983 Cal 381

6. Section 152 CPC provides for correction of clerical or arithmetical mistakes in judgments, decrees or orders of errors arising therein from any accidental slip or omission. The exercise of this power contemplates the correction of mistakes by the court of its ministerial actions and does not contemplate of passing effective judicial orders after the judgment, decree or order. The settled position of law is that after the passing of the judgment, decree or order, the court or the tribunal becomes functus officio and thus being not entitled to vary the terms of the judgments, decrees and orders earlier passed. The corrections contemplated are of correcting only accidental omissions or mistakes and not all omissions and mistakes which might have been committed by the court while passing the judgment, decree or order. The omission sought to be corrected which goes to the merits of the case is beyond the scope of Section 152 for which the proper remedy for the aggrieved party is to file appeal or review application. It implies that the section cannot be pressed into service to correct an omission which is intentional, however erroneous that may be. It has been noticed that the courts below have been liberally construing and applying the provisions of Sections 151 and 152 of the CPC even after passing of effective orders in the lis pending before them. No court can, under the cover of the aforesaid sections, modify, alter or add to the terms of its original judgment, decree or order. In the instant case, the trial court had specifically held the respondent-State liable to pay future interest only despite the prayer of the appellant for grant of interest with effect from the date of alleged breach which impliedly meant that the Court had rejected the claim of the appellant insofar as pendente lite interest was concerned. The omission in not granting the pendente lite interest could not be held to be accidental omission or mistake as was wrongly done by the trial court vide order dated 30-11-1973. The High Court was, therefore, justified in setting aside the aforesaid order by accepting the revision petition filed by the State.

7. The reliance of the learned counsel for the appellant on Jainab Bai case 1969 MPLJ 716, 1969 ACJ 274 is misplaced inasmuch as in that case the aggrieved party had sought for award of interest after the decree by filing the application under Section 152 CPC and under Order 47 Rule 1 of the CPC. The Division Bench relied upon the decision of the Madras High Court in Thirugnanavalli Ammal v. P. Venugopala Pillai AIR 1940 Mad 29, (1939) 2 MLJ 751 wherein it was held that where a mistake had occurred in the decree in spite of mention of the future interest in the judgment, the Court had the power to rectify the mistake and if it occurred in the decree because of omission of it in the judgment, the mistake could not be corrected. We agree with the view taken by the Madras High Court but cannot subscribe to the general observations made by the Madhya Bharat High Court in Jainab Bai case 1969 MPLJ 716, 1969 ACJ 274. In Maharaj Puttu Lal v. Sripal Singh AIR 1937 Oudh 191 the Court had awarded the mesne profits to the decree-holder by correction upon satisfaction that the plaintiff had specifically claimed such profits and its pleader was admitted to have made an oral statement requesting the Court to determine the amount of mesne profits in the execution department which was accepted but not mentioned in the decree sheet. Under the facts and circumstances of that case the Court held that such being an accidental omission the same could be corrected in exercise of the powers vested in the Court under Section 152 of the CPC.

8. In Firozshaw case AIR 1957 MB 50 future interest was allowed by the Court on being satisfied that the omission in the decree was accidental and that no grounds existed for the defendant therein to resist the claim of the decree-holder. The W.B Financial Corpn. case AIR 1983 Cal 381 does not in any way help the appellant inasmuch as in that case the scope of Section 152 was not at all considered as the only point decided was that a plaintiff is entitled as of right to the grant of interest under Section 34 of the CPC. In view of what we have held in this case regarding the ambit and scope of Section 152 of the CPC, we are of the opinion that the view of the Madhya Bharat High Court cannot be held to be based upon sound principles.

9. The claim of the petitioner for payment of Rs 20,000 as damages on account of breach of contract committed by the respondent-State was disallowed by the High Court as the appellant was found to have not placed the material on record to show that he had actually suffered any loss on account of the breach of contract. In this regard, the appellate court observed:

“It is not his case that for due compliance of the contract he had advanced money to the labourers or that he had purchased materials or that he had incurred any obligations and on account of breach of contract by the defendants he had to suffer loss on the above and other heads. Even in regard to the percentage of profit he did not place any material on record but relied upon assessment of the profits by the Income Tax Officer while assessing the income of the contractors from building contracts.”

Such a finding of the appellate court appears to be based on wrong assumptions. The appellant had never claimed Rs 20,000 on account of alleged actual loss suffered by him. He had preferred his claim on the ground that had he carried out the contract, he would have earned profit of 10% on Rs 2 lakhs which was the value of the contract. This Court in A.T Brij Paul Singh v. State of Gujarat (1984) 4 SCC 59 while interpreting the provisions of Section 73 of the Contract Act, 1872 has held that damages can be claimed by a contractor where the Government is proved to have committed breach by improperly rescinding the contract and for estimating the amount of damages, the court should make a broad evaluation instead of going into minute details. It was specifically held that where in the works contract, the party entrusting the work committed breach of contract, the contractor is entitled to claim the damages for loss of profit which he expected to earn by undertaking the works contract. Claim of expected profits is legally admissible on proof of the breach of contract by the erring party. It was observed:

“What would be the measure of profit would depend upon facts and circumstances of each case. But that there shall be a reasonable expectation of profit is implicit in a works contract and its loss has to be compensated by way of damages if the other party to the contract is guilty of breach of contract cannot be gainsaid. In this case we have the additional reason for rejecting the contention that for the same type of work, the work site being in the vicinity of each other and for identical type of work between the same parties, a Division Bench of the same High Court has accepted 15 per cent of the value of the balance of the works contract would not be an unreasonable measure of damages for loss of profit.

Now if it is well established that the respondent was guilty of breach of contract inasmuch as the rescission of contract by the respondent is held to be unjustified, and the plaintiff-contractor had executed a part of the works contract, the contractor would be entitled to damages by way of loss of profit. Adopting the measure accepted by the High Court in the facts and circumstances of the case between the same parties and for the same type of work at 15 per cent of the value of the remaining parts of the works contract, the damages for loss of profit can be measured.”

To the same effect is the judgment in Mohd. Salamatullah v. Govt. of A.P (1977) 3 SCC 590, AIR 1977 SC 1481 After approving the grant of damages in case of breach of contract, the Court further held that the appellate court was not justified in interfering with the finding of fact given by the trial court regarding quantification of the damages even if it was based upon guesswork. In both the cases referred to hereinabove, 15% of the contract price was granted as damages to the contractor. In the instant case however, the trial court had granted only 10% of the contract price which we feel was reasonable and permissible, particularly when the High Court had concurred with the finding of the trial court regarding breach of contract by specifically holding that “we, therefore, see no reason to interfere with the finding recorded by the trial court that the defendants by rescinding the agreement committed breach of contract”. It follows, therefore, as and when the breach of contract is held to have been proved being contrary to law and terms of the agreement, the erring party is legally bound to compensate the other party to the agreement. The appellate court was, therefore, not justified in disallowing the claim of the appellant for Rs 20,000 on account of damages as expected profit out of the contract which was found to have been illegally rescinded.

10. The appellate court further slashed the other claims of the appellant and held him entitled to the payment of Rs 4783.33 only. The learned counsel for the appellant has been very fair to concede that such finding returned by the appellate court is reasonable and that the appellant would not insist upon the payment of further amount and be satisfied with the amount decreed by the High Court in addition to the sum of Rs 20,000 claimed as damages.

11. Under the circumstances, this appeal is partly allowed modifying the judgment decrees of the courts below and holding the appellant-plaintiff entitled to the grant of decree to the extent of Rs 24,783.33 with future interest at 6% per annum payable from the date of decree till realization. The parties to bear their own costs in this appeal.