The Union of India issued a notification under Section 4(1) of the Land Acquisition Act, 1894 on 9-2-1989 to acquire about 1328 bighas of land in the villages of Siraspur and Libaspur for the planned development of Delhi, specifically for shifting timber depots out of the walled city. Invoking Section 17(4), the Government dispensed with the Section 5-A inquiry and published a declaration under Section 6 on 7-2-1990. The landowners filed Writ Petition No. 936 of 1989 on 5-3-1990; the learned Single Judge of the Delhi High Court allowed the petition and quashed the Section 6 declaration, holding that the urgency clause was unjustified. Two awards (Nos. 8 and 9 of 1991) were made on 7-2-1992 for the remaining land, excluding the two bighas involved here.

The Government filed Letters Patent Appeal (LPA) No. 36 of 1992, but the Division Bench dismissed it on 14-7-1992 solely on the ground of a delay of more than 200 days. The Union of India obtained special leave to appeal to the Supreme Court, leading to the present decision.

Legal Issues Presented

  1. Whether the delay of over 200 days in filing the LPA before the Delhi High Court ought to have been condoned.
  2. Whether the Government validly invoked the urgency clause under Section 17(4) to dispense with the Section 5-A inquiry for acquiring land to shift timber depots outside the walled city of Delhi.

Arguments of the Parties

Appellant (Union of India)

  • The acquisition is urgently required to relocate the timber market from the congested walled city, thereby alleviating traffic problems; urgency justifies dispensing with the Section 5-A inquiry.
  • The decision on urgency is an administrative, subjective satisfaction of the Government and need not be supported by a speaking order.
  • Despite delay, the appeal should be entertained because large numbers of similar cases depend on the outcome, and initial inaction was due to the Government Pleader’s erroneous advice.
  • Relied on Jai Narain v. Union of India (1996) 1 SCC 9 to support the validity of invoking Section 17(4) in development-related acquisitions.

Respondents (Landowners)

  • No real urgency existed; an inquiry under Section 5-A would not have frustrated the public purpose.
  • The phrase “land is likely to be needed” in the notification itself demonstrates absence of true urgency.
  • According to the revised Master Plan, only 37 hectares were required for timber depots, rendering the large-scale acquisition excessive.
  • Relied on Narayan Govind Gavate v. State of Maharashtra (1977) 1 SCC 133; Dora Phalauli v. State of Punjab (1979) 4 SCC 485; and State of Punjab v. Gurdial Singh (1980) 2 SCC 471 to argue that Section 5-A inquiries should not be dispensed with in a cavalier manner.
  • Contended that the appellants failed to explain satisfactorily the prolonged delay in filing the LPA.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Narayan Govind Gavate v. State of Maharashtra (1977) 1 SCC 133 Urgency under Section 17(4) must be genuine; Section 5-A inquiry should not be dispensed with lightly. Distinguished; the Court noted later decisions holding that planned development projects can justify urgency.
Dora Phalauli v. State of Punjab (1979) 4 SCC 485 Enquiry under Section 5-A should not be waived without real urgency. Cited by respondents; Court held each case turns on its facts and found sufficient urgency here.
State of Punjab v. Gurdial Singh (1980) 2 SCC 471 Similar to Dora Phalauli on the need for genuine urgency. Cited by respondents; Court again distinguished on factual grounds.
Jai Narain v. Union of India (1996) 1 SCC 9 Affirmed that urgent public purposes can justify invocation of Section 17(4). Relied on by appellants; Court found the principle applicable even though the earlier acquisition there concerned a sewerage plant.

Court's Reasoning and Analysis

Condonation of Delay: The Supreme Court observed that the Government sought a certified copy within 18 days of the Single Judge’s order and immediately instructed its pleader to appeal. The original Government Pleader’s unjustified opinion against filing an appeal and subsequent corrective action by a new pleader explained the delay. Given that hundreds of similar cases hinged on the outcome, the Court held that refusing condonation would cause greater injustice. The delay was therefore condoned.

Validity of Invoking Section 17(4): The Court reiterated that the decision on urgency is an administrative matter resting on the Government’s subjective satisfaction, requiring no speaking order. The purpose—shifting timber depots from the overcrowded walled city to alleviate traffic congestion—was deemed inherently urgent. Delay between the Section 4(1) notification and Section 6 declaration was explained by ongoing consideration of objections at the Lieutenant-Governor’s level. The Court rejected the argument that the words “likely to be needed” negate urgency, holding that the statutory language does not constrain the Government’s power to invoke Section 17(4).

Master Plan Objection: An affidavit from the Under-Secretary (Land & Building) confirmed that acquisition of land in Siraspur and Libaspur for timber depots persisted under MPD-2001, preserving the public purpose. Hence, the planned extent of acquisition remained justified.

Having addressed both procedural and substantive challenges, the Court concluded that the learned Single Judge erred in quashing the Section 6 declaration and the Division Bench erred in dismissing the appeal on limitation grounds.

Holding and Implications

HOLDING: APPEAL ALLOWED; the orders of both the learned Single Judge and the Division Bench are set aside, and the Section 6 declaration is restored.

Implications: The Land Acquisition Officer must issue an award after notice to the respondents within three months. The judgment reinforces the principle that urban development projects aimed at decongesting cities may constitute sufficient urgency to dispense with Section 5-A inquiries, and it underscores the Court’s willingness to condone procedural delays when significant public interests are at stake. No new legal doctrine was created, but existing jurisprudence on urgency under Section 17(4) was affirmed.

Show all summary ...

Order

1. Leave granted.

2. We have heard learned counsel on both sides.

3. This appeal by special leave arises from the judgment of the Division Bench of the Delhi High Court made on 14-7-1992 in LPA No. 36 of 1992 dismissing the LPA. The learned Single Judge had allowed the Writ Petition No. 936 of 1989 on the ground that there was no justification for invoking the urgency clause in Section 17(4) of the Land Acquisition Act, 1894 (1 of 1894) (for short “the Act”). Accordingly, the learned Single Judge quashed the declaration under Section 6. The Division Bench dismissed the LPA on the ground that there was inordinate delay of more than 200 days in filing the appeal. Thus, this appeal by special leave.

4. When the matter had come up before us and the respondents pointed out that the land involved is only two bighas and, therefore, it is not a case warranting interference. We directed the learned counsel for the Union of India to find out as to why they are insisting upon decision on merits. A statement was made by Shri K.T.S Tulsi, learned Additional Solicitor General that there are number of cases of the similar nature pending in the High Court awaiting the decision of this Court and, therefore, decision on merits was necessary. We accordingly set the case for hearing on merits. The learned counsel for the parties have filed their written submissions.

5. We have heard Shri N.N Goswami, learned Senior Counsel for the appellants and Shri G.L Sanghi, learned Senior Counsel for the respondents. The admitted position is that the notification under Section 4(1) of the Act was published on 9-2-1989 acquiring 1328 bighas of land situated in Siraspur and Libaspur. The enquiry under Section 5-A was dispensed with. Declaration under Section 6 was published on 7-2-1990. The writ petition was filed on 5-3-1990. Two Awards Nos. 8 and 9 of 1991 came to be made on 7-2-1992 in respect of the land except these two bighas of land which are the subject-matter in this case. Since the learned Judge had quashed the notification, two questions have been raised and argued by the learned counsel for the parties. The first question relates to the delay in filing the LPA. It is seen that the learned Single Judge passed the order on 5-3-1990 and a certified copy of the judgment was obtained by the counsel appearing for the Government on 12-7-1990 and a letter was addressed immediately on 31-7-1990 directing the Government Pleader to file the appeal. Instead of filing the appeal, he had given the opinion two months thereafter on 4-11-1990 that it was not a fit case. Accordingly, he did not file the appeal. When the matter was re-examined since a large number of cases were involved, new Government Pleader opined on 16-4-1992 that it was a fit case for filing the appeal. Accordingly, LPA came to be filed. Shri Sanghi, learned Senior Counsel for the respondents, contended that delay has not been properly explained. The question is whether delay on the part of the appellants in filing the appeal has been explained? It is seen that as soon as the copy of the judgment of the learned Single Judge was received by the Government within 18 days from the date of the receipt of the judgment, letter was written to the Government Pleader to file the appeal. He had no business to give opinion at that stage that it is not a fit case for filing the appeal. After the lapse of two months, he sent the letter. Obviously, relying upon that opinion, no further action was taken. When the matter reached the Government of India, it got the same re-examined and the Government Pleader gave his opinion. Unless this matter is challenged, all the other cases would follow the suit and law being laid down in the appeal would be applicable and the notification would get quashed. Resultantly, the decision was taken to file the appeal. Under these circumstances, we are of the view that though there is considerable delay in filing the appeal, the Division Bench of the High Court was not justified in refusing to condone the delay and examine the matter on merits. Accordingly, we condone the delay in filing the appeal.

6. Two courses open to be considered are whether it is a fit case for remitting the matter for consideration by the High Court or whether this Court could decide the matter on merits. Having regard to the facts that more than 200 cases are pending disposal in the High Court, remitting the matter again after years for decision of the High Court would not be justified and we feel it expedient to avoid any further delay that the matter could be decided on merits in this Court. Accordingly, we requested the learned counsel for the parties to argue the case on merits. We have considered the written submissions and heard the arguments elaborately addressed by the counsel.

7. Shri Sanghi, learned Senior Counsel has pointed out that there is no real urgency in this matter and the respondents could have been given an opportunity to contend that land is not needed for any public purpose. In support thereof, he placed strong reliance on the judgments in Narayan Govind Gavate v. State of Maharashtra (1977) 1 SCC 133; Dora Phalauli v. State of Punjab (1979) 4 SCC 485 and State of Punjab v. Gurdial Singh (1980) 2 SCC 471. The decision in Narayan Govind case (1977) 1 SCC 133, has been distinguished by this Court in several cases. In the light of the ratio in a catena of decisions, this Court has consistently held that acquisition of the property for the planned development of the housing accommodation is urgent for acquisition and, therefore, dispensing with the enquiry under Section 5-A, exercising power under Section 17(4) has been held to be valid. It is true that in Dora Phalauli (1979) 4 SCC 485 and Gurdial Singh (1980) 2 SCC 471 cases, the two-Judge Bench of this Court in each of the cases held that enquiry under Section 5-A may not be dispensed with in a cavalier manner denying the opportunity to file the objections, unless real urgency is shown. Each case has to be considered on its own facts. The very object of enquiry under Section 5-A is whether the land proposed to be acquired is needed or is likely to be needed for the public purpose mentioned in the notification and whether any other suitable land other than the acquired land is needed for the said public purpose. In this case, the entire land in two villages was acquired. It is seen that timber business is being carried on in the walled city of Old Delhi. It has become a source of traffic congestion and that it requires to be shifted urgently from the existing place to relieve the congestion by acquiring the concerned land for the public purpose, namely, establishment of timber depots. It is true that a mention was also made that unauthorised construction has been made in the area proposed to be acquired. If the enquiry was conducted, delay would defeat the very public purpose of acquisition for shifting of timber business from the walled city and establishment of the timber depots outside the walled city. Therefore, the urgency mentioned in exercising the power under Section 4(1) was justified. Shri Goswami, learned Senior Counsel for the Union of India, has relied upon the judgment of this Court in Jai Narain v. Union of India (1996) 1 SCC 9. It is true, as pointed out by Shri Sanghi, that the acquisition in this reported decision was made for the establishment of sewerage plant as per the direction of this Court and, therefore, there was urgency.

8. But, as stated earlier, since the acquisition is for shifting of timber business from the walled city to the outskirts of the city, shifting itself is for urgent purpose, viz., to relieve the traffic congestion in the walled city. Under those circumstances, the exercise of power under Section 17(4) cannot be said to be unwarranted in this case. It is true that there was a delay, from the date of the notification under Section 4(1) of the Act in publication of the declaration under Section 6. When it was pointed out that no counter-affidavit was filed in the High Court explaining the delay, we directed the learned counsel for the State to produce the record. An averment has been made in the special leave petition that the delay was due to enquiry being conducted into the objections filed before the Lt. Governor in this behalf and until the objections were overruled, declaration under Section 6 could not be published. The note in the office file and the running file do indicate that certain persons kept on making representations right from 1983 and as far as present notification is concerned, objections had been received on 25-4-1990 and, thereafter, they have been considered after the Lt. Governor directed to enquire into the matter and submit the report. Consequently, they conducted the enquiry and submitted the report.

9. It is now settled legal position that decision on urgency is an administrative decision and is a matter of subjective satisfaction of the appropriate Government on the basis of the material available on record. Therefore, there was no need to pass any reasoned order to reach the conclusion that there is urgency so as to dispense with the enquiry under Section 5-A in exercise of power under Section 17(4). It is then contended by Shri Sanghi that as per the revised Master Plan, only 37 hectares of land was needed for establishment of timber depots, though extensive land was sought to be acquired. When that objection was taken, we passed the order directing the competent officer to file an affidavit. By our proceedings dated 24-8-1995, it was observed as under:

“In view of the specific averments made in the written submissions of the respondents regarding the location of the timber depots in terms of the master plan, it requires clarification by the Delhi Administration whether the lands in Siraspur and Libaspur are still required for the purpose mentioned in the notification, namely, planned development of Delhi and shifting of the timber depots from the Teliwara area into the new places.”

10. One G.S Meena, Under-Secretary (L and B) of the Government of National Capital Territory of Delhi has filed the affidavit. Therein, he has stated that the acquisition of the land in the said villages for shifting of the timber market is still under existence as per the provisions scheme of MPD-2001, as notified by the DDA. Under these circumstances, the public purpose still subsists. Even under the revised Master Plan, the acquisition is valid in law and dispensing with the enquiry under Section 5-A was justified. The learned Single Judge, therefore, was not right in quashing the declaration under Section 6. Shri Sanghi, learned Senior Counsel, further contended that the notification discloses that the land is likely to be needed which would indicate that there is no real urgency. The language of the notification is not conclusive but the Court is required to consider the material whether there is any urgency to exercise the power under Section 17(4) of the Act. The same view was taken by this Court in Jai Narain case (1996) 1 SCC 9 referred to earlier.

11. Accordingly, we are of the view that mere mention in the notification that the land is likely to be needed for the public purpose does not take away the power of the appropriate Government to exercise the power of urgency clause under Section 17(4).

12. The appeal is accordingly allowed. The order of the learned Single Judge as well as of the Division Bench of the High Court are set aside. The declaration under Section 6 stands restored. The Land Acquisition Officer is directed to pass the award after issue of the notice to the respondents within a period of three months from the receipt of the order. No costs.