Calcutta Electric Supply Corporation Limited v. N.M Banka And Another

Supreme Court Of India
Nov 21, 1996
Smart Summary (Beta)

Factual and Procedural Background

N.M. Banka, a partner in the firm M/s Rajkumar Dyeing & Printing Works, applied to CESC Limited for a separate electricity connection at Premises No. 11, U.N. Mukherjee Road, Calcutta. The premises already had an existing connection in the name of the partnership firm, which was a substantial defaulter and had been drawing power far in excess of the sanctioned load of 50 hp.

When CESC discovered the affiliation between Banka and the defaulting firm, it placed Banka’s application “in abeyance” and ultimately refused a second supply line, citing both the outstanding arrears and safety concerns about two services at the same premises.

On 22-7-1988, Rajkumar Dyeing & Printing Works and Banka filed a writ petition seeking: (a) a mandamus preventing CESC from disconnecting power, and (b) a reference of disputed bills to arbitration. The Calcutta High Court granted ex-parte interim orders that kept the electricity supply running for over five years, despite mounting arrears. During this period the arrears reached Rs 67,40,948.10.

CESC alleged theft of electricity, repeated over-loading that damaged meters, and persistent non-payment. It argued the consumer had an adequate statutory remedy under Section 26 of the Indian Electricity Act to approach the Electrical Inspector, which was never pursued.

The present appeal reached the Supreme Court, which on 6-11-1996 issued an operative order (leave granted; appeal allowed) with financial and procedural directions. The opinion under review supplies the detailed reasons for that order.

Legal Issues Presented

  1. Whether a consumer who disputes electricity bills can bypass the statutory remedy under Section 26 of the Indian Electricity Act by invoking the High Court’s writ jurisdiction.
  2. Whether the High Court erred in granting prolonged interim orders compelling supply of electricity to a chronic defaulter, thereby enabling continued consumption without full payment.
  3. Whether CESC lawfully refused to grant a second electricity connection to the same premises when outstanding dues and safety considerations existed.

Arguments of the Parties

Appellant (CESC Limited)

  • Pointed to arrears of Rs 67,40,948.10 and persistent non-payment even during the pendency of the writ petition.
  • Alleged theft of electricity and over-loading that repeatedly damaged the meter.
  • Invoked Section 24 of the Electricity Act, asserting an unqualified right to disconnect supply after due notice when charges remain unpaid.
  • Contended the writ petitioners deliberately bypassed the statutory mechanism under Section 26, depriving CESC of prompt adjudication and enabling abuse of interim orders.

Respondent 1 (Consumer/Partner N.M. Banka and Firm)

  • Argued that the writ petition sought, in the alternative, a reference of the disputed bills to arbitration.
  • Maintained that abrupt disconnection would shut the factory and affect 90 workmen.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Supreme Court characterized the case as “a gross abuse of the process of the court.” It found:

  • The High Court allowed the writ petition to “linger on” for more than five years without deciding factual disputes that were unsuited to writ jurisdiction.
  • Section 24 of the Electricity Act empowers the supplier to disconnect service for non-payment after seven days’ notice; Section 26(4) and (6) furnish the consumer with a specific remedy before the Electrical Inspector for disputes over meters or bills. The respondents ignored this statutory avenue.
  • Granting successive interim orders had the practical effect of compelling CESC to supply electricity to a defaulter and facilitated the accumulation of massive arrears, contrary to the statutory scheme.
  • The attempt by Banka to secure a second connection in his personal name at the same premises, while the firm was in default, was viewed as a “fraudulent move,” legitimately resisted by CESC on both financial and safety grounds.

In light of these findings, the Court concluded that the High Court should have refused relief and directed resort to the statutory forum. Instead, the Supreme Court imposed conditions designed to protect CESC’s financial interest and to ensure expeditious adjudication by the competent authority.

Holding and Implications

Appeal ALLOWED. The Supreme Court’s operative order of 6-11-1996 stands, directing:

  • Deposit of Rs 30 lakhs by the consumer within one month toward arrears.
  • Automatic reference of the dispute to the Chief Electrical Inspector, Calcutta, for decision within two months of such deposit.
  • Liberty to CESC to recover arrears according to law if the deposit is not made.
  • Attachment of all respondent properties pending further orders.
  • Costs of Rs 50,000 payable by Respondent 1 to CESC.

Implications: The decision restores the primacy of the statutory mechanism under the Electricity Act and marks a caution against using prolonged interim writ relief to evade payment of undisputed dues. No new legal precedent was articulated, but the ruling underscores that High Courts should refrain from interdicting utility disconnections where statutory remedies exist.

Show all summary ...

Order

1. The following order in this case was passed by us on 6-11-1996:

“While we propose to give reasons for our order later, the following is the operative and final order in the special leave petition:
Leave granted.
The appeal is allowed with the following directions:
(1) Within one month from today, Respondent 1-consumer shall deposit a sum of rupees thirty lakhs towards the demand of arrears by the appellant-company against him.
(2) On such deposit being made, the dispute between the parties involved in the Transferred Case No. 42 of 1996 shall stand referred to the Chief Electrical Inspector, Calcutta who shall decide the same within two months from the date the dispute is referred to him.
(3) If the amount specified in Direction 1 is not deposited, it shall be open to the appellant-company to recover the arrears due to it according to law.
(4) Pending further orders in the matter, all the properties of the respondent are attached herewith.
(5) Respondent 1 shall pay the costs of the appellant which are estimated at rupees fifty thousand only.”

2. The reasons for passing the aforesaid order are as under:

This is a case of gross abuse of the process of the court. One N.M Banka had applied to CESC Limited which carries on business of generation, supply and distribution of electricity in Calcutta and its suburbs for a connection of electricity to Premises No. 11, U.N Mukherjee Road, Calcutta. After completion of inspection, the CESC agreed to supply electricity to N.M Banka by letter dated 5-2-1988 subject to compliance of usual conditions. Some time later, it came to the knowledge of CESC that N.M Banka was a partner of the firm M/s Rajkumar Dyeing & Printing Works which was carrying on business at the same premises. The partnership firm was an existing registered consumer from whom a very substantial sum of money was lying due. Moreover, the partnership firm was found drawing electricity far in excess of the sanctioned load of 50 hp. On coming to know that N.M Banka was a partner of Rajkumar Dyeing & Printing Works, which was a defaulter in payment of electricity charges, the CESC Limited by letter dated 22-9-1988 informed Banka that supply of electricity to him has been kept in abeyance. Apart from the huge liability of Rajkumar Dyeing & Printing Works, there was also a technical difficulty in giving a separate electric connection to Banka because it was not possible to give two separate electric connections to one particular premises. Existence of two services in the same premises would be hazardous.

3. On 22-7-1988, a writ petition was moved by Rajkumar Dyeing & Printing Works, the partnership firm and also Shri Banka, the partner for a direction in the nature of mandamus commanding CESC and their officers from disconnecting the electricity line of the factory situated at No. 11, U.N Mukherjee Road, Calcutta. A prayer was also made to refer the disputed bills to the arbitrator as provided in the Indian Electricity Act for adjudication. The allegation was that CESC had issued an inflated bill for the month of June 1988 and were threatening to disconnect electricity to the appellants if they failed to pay the said bill by 20-7-1988. It was further prayed that if the electricity line was disconnected, the factory will have to be closed down and about 90 workers will have to be laid off without any fault of the appellants. The writ petition was moved ex parte and a direction was given that the electricity supply will not be disconnected “till Wednesday next”. On 28-7-1988, the matter was once again heard ex parte and the interim order not to disconnect the supply was further continued. The matter, thereafter, has come up for hearing from time to time and the interim order has been continued with occasional directions to deposit some money. By this process, the writ petition was kept pending for more than five years. The appellant who was a defaulter when the writ petition was filed continued to get supply of electricity by making occasional payments pursuant to the direction of the Court. The writ petitioner did not pay the bills submitted in the usual course, the arrears kept mounting up and the CESC ultimately disconnected the line. By an order dated 16-2-1993, the Court directed the line to be restored and the writ petition was directed to remain heard in part.

4. It is difficult to understand how this writ petition was allowed to linger on for five years. The Court did not and could not possibly come to a finding on the disputed questions of fact. According to CESC, the bills were prepared properly. The appellants did not pay the bills. The total amount of arrears due to the CESC had mounted up to Rs 67,40,948.10 after giving due credit to the payments made by the appellants pursuant to the interim orders passed by the Court from time to time. On behalf of the CESC, very serious allegations have been made about theft of electricity and overloading as a result of which the meter was burnt out several times and non-payment of bills. Section 24 of the Electricity Act gives the right to the supplier to disconnect any electric supply line after giving seven days' notice if a consumer neglects to pay the charge for energy or any sum other than the charge for energy due from him in respect of supply of energy. In case of dispute or difference about the meter or the correctness of the bill, the consumer may apply to the Electrical Inspector. The Inspector in such a case shall estimate the amount of energy supplied to the consumer. The supplier shall not be at liberty to take off or remove any meter until the dispute has been determined by the Electrical Inspector. The writ petitioners did not avail of the statutory remedy provided by sub-sections (4) and (6) of Section 26 but approached the Court for interim relief and by this process, managed to continue to get supply of electricity even though there was a huge mounting default. It is difficult to understand how the Court allowed the question of these disputed bills to linger on for more than five years without disposing of the case on merits. It was also not proper for the Court to direct CESC to supply electricity to a defaulter indefinitely by interim orders passed from time to time. Specific statutory remedy provided by the Indian Electricity Act to the consumer should not have been allowed to be bypassed.

5. It has been contended on behalf of the consumer that the second prayer in the writ petition was for referring the matter for arbitration. We fail to see the sense of this prayer. If the consumer was aggrieved by the bills, he should have approached the Electric Inspector straightaway. When the consumer approached the Court, the Court should have declined to intervene in the matter and should have directed the consumer to avail of the statutory remedy. In any event, under the writ jurisdiction, the Court could not have decided about the correctness or otherwise of the bills. Serious allegations were made by CESC about the consumption of electricity beyond the sanctioned load and also of non-payment of valid bills. The allegation is also that when the electricity supply to Rajkumar Dyeing & Printing Works was stopped, a partner, Banka, wanted to get a service line in his own name at the same place to run the printing works. This was obviously a fraudulent move and the CESC rightly refused to grant the second line.