- Bookmark
- Share
- CaseIQ
A.T Brij Paul Singh And Others v. State Of Gujarat .
Factual and Procedural Background
The appellant, a contractor based in Poona, successfully bid 7½ % below the estimated cost of Rs 16,59,900 to lay a cement-concrete surface on miles 18–40 of the Rajkot–Jamnagar Road in the erstwhile State of Saurashtra. The contract, accepted on 6 July 1954, required completion within 14 months of the written commencement order dated 26 July 1954.
The contractor completed sub-grading for 5 miles 5 furlongs and laid concrete for 2½ miles, but the State rescinded the contract, asserting time was of the essence and that the contractor was in breach. After accepting the final bill under protest, the contractor sued the State of Bombay for Rs 11 lakh in damages.
The trial court dismissed the suit, finding the rescission lawful and the damages unproved. On appeal, the Gujarat High Court reversed the finding on rescission, held the State in breach, but awarded only Rs 12,055.90, rejecting most damage claims for lack of proof. The Supreme Court granted a certificate under Article 133(1)(a) and heard the present appeal together with Civil Appeal No. 1998 of 1972 concerning a similar contract between the same parties.
Legal Issues Presented
- Whether the State’s rescission of the works contract was unjustified and therefore constituted a breach.
- If a breach occurred, what measure of damages—particularly for loss of expected profit—the contractor is entitled to recover.
- Whether additional claims for losses during execution and for extra items executed were proved and compensable.
Arguments of the Parties
Appellant's Arguments
- The High Court erred by refusing damages for loss of profit despite finding the State in breach; in a cognate appeal (First Appeal No. 384 of 1962) the same High Court accepted 15 % of the balance contract value as reasonable profit.
- The work and circumstances in both contracts were identical, warranting a consistent measure of damages.
- The claims for on-site losses (Rs 1,19,686) and extra items (Rs 1 lakh) were wrongly rejected.
Respondent's Arguments
- Sought to uphold the trial court’s finding that rescission was justified, attempting to have the Supreme Court re-examine the evidence.
- Contended that profit must be proved by primary documents; a mere percentage is insufficient.
- Objected that the record of the cognate appeal should not influence the present case.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| First Appeal No. 384 of 1962, Gujarat High Court (judgment dated 3/6 July 1970) | Held that 15 % of the value of the remaining work is a reasonable measure of loss of profit where the State is in breach of a similar works contract. | Used as persuasive authority to adopt 15 % as an appropriate benchmark for computing loss of profit in the present case. |
| First Appeal No. 89 of 1965, Gujarat High Court | Referenced by the High Court below for the proposition that actual loss of profit must be strictly proved. | The Supreme Court noted that the High Court relied on this decision but found the categorical approach in First Appeal No. 384 of 1962 more persuasive. |
Court's Reasoning and Analysis
1. Breach Established. The Supreme Court affirmed the High Court’s “categorical finding” that the State was not justified in rescinding the contract under clause (3). After reviewing the extensive evidence summarized by the High Court, the Supreme Court declined to re-appraise it, finding the High Court’s conclusion “persuasively correct.”
2. Entitlement to Profit Damages. The Court reiterated the settled principle that a contractor is entitled to loss-of-profit damages when the employer commits a breach. The debate centred on quantum and proof, not entitlement.
3. Consistency with Cognate Decision. The Court compared the present case with First Appeal No. 384 of 1962 concerning an adjacent stretch of the same road between the same parties. There, the High Court accepted 15 % of the remaining contract value as reasonable profit. The Court rejected the State’s “too technical” argument that this record was irrelevant, reasoning that identical work and proximity justified analogous treatment.
4. Assessment of Profit. Finding detailed arithmetical reconstruction unnecessary, the Court adopted a broad evaluation and fixed Rs 2 lakh as reasonable compensation for loss of expected profit—roughly consistent with the 15 % benchmark accepted in the cognate case.
5. Other Heads of Claim. The Court endorsed the High Court’s meticulous item-wise scrutiny that awarded Rs 12,055.90 for on-site losses and extra items, agreeing that the balance of those claims lacked proof.
Holding and Implications
Appeal Partly Allowed. In addition to the Rs 12,055.90 already decreed by the High Court, the respondent State must pay the appellant Rs 2 lakh as damages for loss of profit, with interest at 6 % from the date of the suit and proportionate costs. Court fees are to be recovered proportionately from both parties.
Implications: The decision reinforces that, in works-contract breaches, courts may award a reasonable percentage of the unperformed contract value as profit even absent exhaustive documentary proof, especially where a consistent measure has been recognized in closely related litigation. No new legal doctrine was set, but the judgment emphasizes consistency and fairness in quantifying expectation damages.
D.A Desai, J.— This appeal was heard along with CA No. 1998 of 1972 between the same parties and raising certain identical questions. In the course of hearing of both the appeals inevitably it was pointed out that with regard to identical questions the two Benches of the same High Court, though one learned Judge was common to both the Benches, arrived at irreconcilable conclusions which has to some extent resulted in denial of justice to the appellant. It would be our attempt to reconcile the approach of the Court in both the matters keeping in view the limitation on account of the two suits having not been consolidated and evidence recorded separately in each matter.
2. On an invitation to tender sought by the erstwhile State of Saurashtra for providing cement concrete surface to Rajkot Jamnagar Road for miles 18 to 40 measuring from the Rajkot end, the appellant submitted his tender quoting 7½ per cent lower than the estimated cost of the works in the amount of Rs 16,59,900 only. The tender of the appellant was accepted on July 6, 1954 as per the letter of the Executive Engineer, Road Development Division, Rajkot. As agreed to between the parties, the appellant furnished security deposit in the amount of Rs 24,885 and the contract documents were executed between the parties. The only term of the contract which at present needs noting is that the work was to be executed within a period of 14 months from the date fixed by the written order to commence the work. Indisputably, the appellant commenced the work and completed subgrading of the road in a distance of 5 miles and 5 furlongs and furnished cement concrete surface in the length of 2½ miles. Certain disputes arose between the parties as a result of which the respondent rescinded the contract imputing that as the time was of the essence of the contract and as the appellant failed to execute the work within the stipulated time he was guilty of committing breach of contract. The final bill in respect of the work done by the appellant was prepared but the payment thereunder was accepted by the appellant under protest. The appellant thereafter filed a suit claiming Rs 7 lakhs by way of damages, goodwill, prestige and loss of expected profit, Rs 3 lakhs by way of damages on account of loss sustained while executing the work and Rs 1 lakh as damages for the extra work done by the appellant. The total claim was of Rs 11 lakh. The State of Bombay as the defendant resisted the suit on diverse grounds inter alia contending that the rescission of the contract consequent upon the breach of contract committed by the appellant was just, legal and valid. It was contended that as the time was of the essence of the contract and the commencement order was served on the appellant on July 26, 1954 and as the appellant failed to complete the work within the stipulated period of 14 months from the date of the commencement order the defendant was justified in rescinding the contract. All the claims as to damages and damages for extra work and damages by way of loss of profit were denied and the plaintiff was put to strict proof thereof.
3. The learned Trial Judge framed as many as nine issues. Issue No. 4 was: “whether the plaintiff proves that the work contract has been illegally rescinded by the defendant”. The learned Judge held that the rescission of the contract by the defendant in the circumstances found proved by him was not illegal. With regard to the claim for damages the learned Judge held that even though Swarnsingh, the witness on behalf of the plaintiff has given minutest details and measurement of the work executed by the contractor orally, no documentary evidence is produced to substantiate the claim and therefore, the plaintiff has failed to prove the damages as claimed in the plaint. Accordingly, plaintiff's suit was dismissed. As the suit was filed in forma pauperis, a direction was given that the court fee be recovered from the plaintiff.
4. The plaintiff preferred Civil Appeal No. 599 of 1964 after paying the court fees as directed by the Court. In the petition of appeal, the plaintiff reduced his claim from Rs 11 lakhs in the plaint to Rs 6,50,000 comprising of Rs 4,30,314 on account of loss of profit, Rs 1,19,686 by way of compensation for loss sustained while executing the work and Rs 1lakh as compensation for extra items executed by the plaintiff while performing the contract.
5. The High Court substantially dismissed the appeal but allowed the appeal for a few items and decreed the plaintiff's suit to the extent of Rs 12,055.90p. However the High Court did not agree with the trial court on the question of justification or propriety of rescission of the contract by the defendant and reversed the finding. Consistent with the finding the High Court proceeded to examine the principal contention whether the appellant contractor was entitled to recover damages for loss of expected profits and rejected the claim for want of proof. Hence this appeal by certificate under Article 133(1)(a) of the Constitution.
6. It may be recalled that the plaintiff was also given a works contract for providing cement concrete surface in another portion of the same road for which a separate and independent contract was entered into. That contract was also rescinded by the defendant and the plaintiff had filed a suit for recovering the damages. In that suit the trial court gave a decree to the plaintiff in the amount of Rs 1,20,053.20p. Against the decree, the defendant preferred appeal to the High Court of Gujarat, being Civil Appeal No. 384 of 1962. This appeal was heard by a Division Bench of the Gujarat High Court. By its judgment and order dated July 3/6, 1970, the High Court held that the defendant was guilty of breach of contract and the plaintiff was entitled to damages for loss of expected profit reasonably calculated at 15 per cent of the balance of the value of the works contract. The decree was, however, modified by deleting certain items awarded by the trial court on the ground that they were barred by limitation. Against the decree so modified by the High Court, the original plaintiff preferred Civil Appeal No. 1998 of 1972 which was heard along with this appeal.
7. A Division Bench of the High Court examined the voluminous evidence bearing on the question whether the rescission of the contract by the respondent was justified and recorded a categorical finding which reads as under:
“In that view of the matter, therefore, we are of the opinion, that the respondent State was not justified in rescinding the contract under clause (3) of the contract document.”
This finding clearly establishes that the respondent was guilty of breach of contract. Mr T.U Mehta, learned counsel who appeared for the respondent attempted to persuade us to upset this finding by reading the evidence. We declined to undertake this exercise after reading with him the exhaustive judgment pronounced by the High Court discussing every item of evidence bearing on the subject. The conclusion reached by the High Court is persuasively correct and consistent with the weight of evidence and nothing could be pointed out to us to take a different view of the matter. Undoubtedly, the learned trial Judge in a very scrappy judgment held to the contrary. The High Court while hearing the first appeal having had the advantage of looking extensively at the evidence preferred to differ with the learned trial Judge and in our opinion rightly. We are therefore, in agreement with the High Court that the respondent State was guilty of breach of contract. A similar finding was recorded in cognate appeal which we have upheld.
8. Once it is held that the respondent was guilty of breach of works contract, part of which was already performed and for performing which the appellant, a Poona based contractor had transported machinery and equipment from Poona to the work site near Rajkot in Saurashtra, certainly he would be entitled to damages. One of the heads of damages under which claim is made is “loss of expected profit in the work”. The claim under this head as canvassed before the High Court was in the amount of Rs 4,30,314.
9. It was not disputed before us that where in a works contract, the party entrusting the work commits breach of the contract, the contractor would be entitled to claim damages for loss of profit which he expected to earn by undertaking the works contract. What must be the measure of profit and what proof should be tendered to sustain the claim are different matters. But the claim under this head is certainly admissible. Leaving aside the judgment of the trial court which rejected the claim for want of proof, the High Court after holding that the respondent was not justified in rescinding the contract proceeded to examine whether the plaintiff contractor was entitled to damages under the head “loss of profit”. In this connection, the High Court referred to Hudson's Building and Engineering Contracts (1970), tenth edition and observed that “in major contracts subject to competitive tender on a national basis, the evidence given in litigation on many occasions suggests that the head-office overheads and profit is between 3 to 7 per cent of the total price of cost” which is added to the tender. In other words, the High Court was of the view that the claim under this head was admissible. The High Court, however, addressed itself to the question whether adequate proof is tendered to sustain the claim. In this connection, it was observed that the loss of profit when it is sought to be recovered on the percentage basis has to be proved by proper evidence. Having settled the legal position in this manner, the High Court proceeded to reject the claim observing that the bare statement of the partner of the contractor's firm that they are entitled to damages in the nature of loss of profit at the rate of 20 per cent of the estimated cost is no evidence for the purpose of establishing the claim. The High Court further observed that the appellant has not proved by any primary documents the basis of its pricing for the purpose of quotation in reply to the tender and more so when it has quoted at 7½ per cent less than the original estimated cost and in this view of the matter the claim for loss of profit is unsustainable.
10. Mr Aneja, learned counsel for the appellant urged that the appellant was placed at a comparative disadvantage on account of his two appeals arising from two identical contracts inter partes being heard on two different occasions by two different Benches even though one learned Judge was common to both the Benches. Mr Aneja pointed out that in the appeal from which the cognate Civil Appeal No. 1998 of 1972 arises, the same High Court in terms held that the claim by way of damages for loss of profit on the remaining work at 15 per cent of the price of the work as awarded by the trial court was not unreasonable. The High Court had observed in the cognate appeal that “the basis adopted by the learned Civil Judge in computing the loss of profit at 15 per cent on the value of the remaining work contract cannot be said to be unreasonable”. In fact, the High Court had noticed that this computation was not seriously challenged by the State, yet in the judgment under appeal the High Court observed that actual loss of profit had to be proved and a mere percentage as deposed to by the partner of the appellant would not furnish adequate evidence to sustain the claim. In this connection the High Court referred to another judgment of the same High Court in First Appeal No. 89 of 1965 but did not refer to its own earlier judgment rendered by one of the Judges composing the Bench in First Appeal No. 384 of 1962 rendered on July 3/6, 1970 between the same parties. When this was pointed out to Mr Mehta, his only response was that the court cannot look into the record of the cognate appeal. We find the response too technical and does not merit acceptance. We are not disposed to accept the contention of Mr Mehta for two reasons: Firstly, that in an identical contract with regard to another portion of the same Rajkot-Jamnagar Road and for the same type of work, the High Court accepted that loss of profit at 15 per cent of the price of the balance of works contract would provide a reasonable measure of damages if the State is guilty of breach of contract. The present appeal is concerned with the same type of work for a nearby portion of the same road which would permit an inference that the work was entirely identical. And the second reason to reject the contention is that ordinarily a contractor while submitting his tender in response to an invitation to tender for a works contract reasonably expects to make profits. What would be the measure of profit would depend upon facts and circumstances of each case. But that there shall be a reasonable expectation of profit is implicit in a works contract and its loss has to be compensated by way of damages if the other party to the contract is guilty of breach of contract cannot be gainsaid. In this case we have the additional reason for rejecting the contention that for the same type of work, the work site being in the vicinity of each other and for identical type of work between the same parties, a Division Bench of the same High Court has accepted 15 per cent of the value of the balance of the works contract would not be an unreasonable measure of damages for loss of profit. We are therefore, of the opinion that the High Court was in error in wholly rejecting the claim under this head.
11. Now if it is well-established that the respondent was guilty of breach of contract inasmuch as the rescission of contract by the respondent is held to be unjustified, and the plaintiff contractor had executed a part of the works contract, the contractor would be entitled to damages by way of loss of profit. Adopting the measure accepted by the High Court in the facts and circumstances of the case between the same parties and for the same type of work at 15 per cent of the value of the remaining parts of the work contract, the damages for loss of profit can be measured.
12. Mr Aneja then attempted to take us through the maze of evidence and requested us that the claim under this head in the amount of Rs 4,30,314 is reasonable, fair and just. The value of the works contract was Rs 16,59,900 and the appellant had offered the rate at 7½ per cent less of the estimate made by the State. The appellant had executed some part of the contract. How much work he had completed and what was the balance of the work contract was attempted to be spelt out by a reference to Ex. 77/1 (Line Plan of Road) read with Exs. 77/2 and 77/3 showing the widening of the side strips near Kankawati Bridge as well as Longitudinal Sections of the Roads. In our opinion, while estimating the loss of profit that can be claimed for the breach of contract by the other side, it would be unnecessary to go into the minutest details of the work executed in relation to the value of the works contract. A broad evaluation would be sufficient. We in this connection, invited both Mr Aneja, learned counsel for the appellant and Mr T.U Mehta, learned counsel for the respondent to give broad features of the work as well as the portion of the work executed by the appellant. Having heard them, we are satisfied that the appellant should be awarded Rs 2 lakhs under the head “loss of estimated (sic expected) profit” for breach of contract by the respondent.
13. Mr Aneja next contended that the High Court was in error in substantially rejecting the claim in the amount of Rs 1,19,686 by way of compensation for loss sustained while executing the work and the claim of Rs 1 lakh for extra items executed by the contractor while performing the contract. The High Court has examined the claim under both the heads. The items claimed under various sub-heads under each major head have been separately examined by the High Court bringing to bear upon each sub-head the detailed evaluation of the evidence. In the process the High Court had allowed an amount of Rs 12,055.90p. under various sub-heads under major heads 2 and 3. While reaching this conclusion, the High Court minutely examined the evidence and substantially rejected the claim. Having read the judgment, we are not disposed to take a different view of the matter. Therefore, the claim under these two heads except to the extent allowed by the High Court have been rightly rejected and we agree with the reasoning and conclusion of the High Court in this behalf.
14. Accordingly, this appeal is partly allowed and over and above the amount awarded by the High Court, respondent State shall pay Rs 2 lakhs as and by way of damages for loss of profit for breach of contract committed by the respondent with interest at 6 per cent from the date of the suit and proportionate costs. The court fee shall be recovered proportionately from the appellant and the respondent. We order accordingly.
Alert