Jethmull Bhojraj v. State Of Bihar And Others
Factual and Procedural Background
The appeals arose from writ petitions dismissed by the Patna High Court. The appellant owned lands situated in the villages of Telaiya and Debipur, Bihar. These lands were:
- Declared private forest land in 1948 under Sections 14 and 21 of the Bihar Private Forest Act, 1947.
- Subsequently notified in 1953–1954 under Section 29 of the Indian Forest Act.
- Notified for acquisition in 1959 under Section 4 of the Land Acquisition Act, 1894, with simultaneous invocation of Section 17(4) (dispensing with Section 5-A inquiry) and issuance of Section 6 declarations.
Proceedings under Sections 9 and 11 continued until, before an award was finalized, the Government of Bihar withdrew a substantial portion of the land from acquisition. The Additional Land Acquisition Officer excluded compensation for the withdrawn parcels. Aggrieved, the appellant sought a writ of mandamus in the High Court to compel inclusion of compensation for those lands. The High Court dismissed the petitions, leading to the present Supreme Court appeals by certificate.
Legal Issues Presented
- Whether, in the circumstances of the case, the Government of Bihar retained statutory competence under Section 48(1) of the Land Acquisition Act to withdraw from acquisition of lands for which notifications under Sections 4 and 6 had been issued.
- Whether the lands had already vested in the Government because:
- the Forest Department allegedly took possession in 1953–1954; or
- possession was taken under the urgency provisions of Section 17(1); or
- vesting occurred automatically on issuance of notices under Section 9(1).
Arguments of the Parties
Appellant's Arguments
- Government unlawfully took possession of the lands in 1953–1954 after notification under Section 29 of the Indian Forest Act; hence ownership had already transferred to the State before withdrawal.
- In the alternative, ownership vested either upon issuance of Section 6 notifications or upon publication of notices under Section 9(1).
- Possession had in any event been taken under Section 17(1), triggering automatic vesting under that provision.
State of Bihar's Arguments
- Denied taking possession in 1953–1954 and denied any possession under Section 17(1).
- Asserted that mere issuance of Section 6 or Section 9(1) notices does not transfer title; vesting occurs only after lawful possession under Sections 16 or 17(1).
- Invoked Section 48(1), maintaining an unqualified right to withdraw so long as possession had not been legally taken.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Lt. Governor of Himachal Pradesh v. Avinash Sharma (1970) 2 SCC 23; AIR 1970 SC 1582 | Where possession had already been taken and urgency provisions invoked, vesting is deemed to occur 15 days after notice under Section 9(1). | Distinguished: Unlike Avinash Sharma, no direction under Section 17(1) and no prior possession were proved; therefore deemed vesting was inapplicable. |
Court's Reasoning and Analysis
The Supreme Court addressed each of the appellant’s vesting theories:
- Alleged possession in 1953–1954. The Court found the documentary evidence (letters and requisitions by the Divisional Forest Officer) inconclusive and explained by the officer’s subsequent affidavit stating he had misunderstood the legal effect of a Section 29 notification. The Court agreed with the High Court that the materials were insufficient to establish actual possession and declined to resolve the disputed factual issue in writ proceedings.
- Possession under Section 17(1). Possession vesting the land in the Government requires:
- a direction by the Government under Section 17(1); and
- expiry of 15 days after publication of Section 9(1) notice.
- Automatic vesting on Section 9(1) notice. Relying on its earlier decision in Avinash Sharma, the Court clarified that deemed vesting after 15 days arises only when urgency provisions have been properly invoked and possession has in fact been taken or directed. Since neither condition was satisfied, the argument failed.
Because lawful possession had not been taken under Sections 16 or 17(1), Section 48(1) entitled the Government to withdraw from acquisition. The Court rejected the appellant’s statutory construction that urgency alone sufficed for vesting, noting the clear wording that the Government must also direct the Collector to take possession.
Holding and Implications
Appeals Dismissed. The Supreme Court upheld the Government of Bihar’s competence to withdraw from acquisition, with each party bearing its own costs.
Implications are confined to the parties: the appellant receives no compensation for the withdrawn lands, while the State, through an assurance recorded by the Court, will not charge interest on development loans from the dates of the Section 29 notifications. No new precedent was created; the decision largely applies settled principles governing vesting and withdrawal under the Land Acquisition Act.
K.S Hegde, J.— In these appeals by certificate, the only question that arises for decision is whether on the facts and in the circumstances of these cases, the Government of Bihar was competent to withdraw from acquisition certain lands sought to be acquired under Acquisition Cases Nos. 3 and 4 of 1959-60 before the Additional Land Acquisition Officer, Hazaribagh.
2. The lands concerned in these cases were notified for acquisition in 1959 under Section 4 of the Land Acquisition Act, 1894 (to be hereinafter referred to as “the Act”) under two different notifications. At about the same time, the Government also took action under Section 17(4) of the Act and dispensed with proceedings under Section 5-A. Simultaneously notifications under Section 6 were also issued. Thereafter proceedings under Sections 9 and 11 were taken. When the acquisition proceedings were pending before the Land Acquisition Officer, the Government withdrew from acquisition some of the lands earlier notified under Sections 4 and 6. Consequently the Land Acquisition Officer excluded the compensation in respect of those lands from the computation made by him earlier. The appellant (common appellant in both the appeals) being aggrieved by that exclusion moved the High Court of Patna under Article 226 of the Constitution seeking directions from that Court to the Land Acquisition Officer to award him compensation in respect of those lands as well. The High Court rejected those writ petitions. Hence these appeals.
3. The lands in question are situate in the villages of Telaiya and Debipur. On June 11, 1948, they were notified under Sections 14 and 21 of the Bihar Private Forest Act, 1947. Thereafter they were again notified under Section 29 of the Indian Forest Act in 1953 and 1954. Later on the Government felt that in order to include those lands in the adjoining Government forest, it would be necessary to acquire them. Consequently they were notified for acquisition. But after the lands in question were tentatively valued, the Government thought that it was not worthwhile to acquire entire area notified for acquisition. Hence it withdrew from acquisition a substantial portion of lands notified for acquisition. These in brief are the material facts.
4. The allegation of the appellant is that after the lands in question were notified under Section 29 of the Indian Forest Act, the Forest Department unlawfully took possession of those lands and continued to be in possession of the same and therefore when notifications under Section 6 were issued, the Government became the owner of those lands and thereafter, it was not competent for the Government to withdraw from acquisition any of the lands notified under Section 6. Alternatively it was contended that the Government became the full owner of those lands when the Collector caused a public notice to be given under Section 9(1) of the Act. Lastly it was contended that the lands in question had been actually taken possession of by the Collector under Section 17(1) of the Act and hence they vested in the Government.
5. The Government of Bihar has denied all the above allegations. It denied that the Government took possession of the lands in question in 1954. It further denied that those lands had been taken possession of under Section 17(1). The Government denied the allegation of the appellant that it became the owner of the lands in question either when notifications under Section 6 or notices under Section 9(1) were issued.
6. The High Court was not satisfied from the evidence adduced by the appellant that the Government had taken possession of the lands in question in 1954. It thought that this was a disputed question of fact and on the material before it, it was not possible to decide that question conclusively and hence it declined to pronounce on that question. The High Court repelled the contention of the appellant that possession had been taken under Section 17(1). It also did not accept the contention of the appellant that on the issue of notices under Section 9(1), Government had become the owner of the lands in question. In the result the High Court dismissed the writ petitions. The very contentions taken before the High Court were repeated in this Court.
7. Now coming to the question whether the Government took possession of the lands in question in 1954, it was conceded that the Government was not competent to take possession of those lands either under the notifications issued under Sections 14 and 21 of Bihar Private Forest Act, 1947 or under the notifications issued under Section 29 of the Indian Forest Act. The case of the appellant is that the Government unlawfully took possession of the properties. In support of that contention reliance was mainly placed on the letter written by the Divisional Forest Officer, Kodarma Division to the Range Officer, Kodarma on October 1, 1958 as well as on the requisition sent to the Land Acquisition Officer by the same officer on January 24, 1959 (Annexure II). The concerned Divisional Forest Officer was one Brij Mohan Prasad. In the letter in question he stated:
“The forest in the above villages are in possession of the Forest Department since sometime past….”
In the requisition again, he mentioned:
“The land was previously notified under Section 29(3) of the IFA and it was demarcated and possession taken. Later on it was found that the land in question was raiyati, it was necessary to acquire under the Land Acquisition Act.”
In Para 12 of that requisition, he further stated:
“it is already under possession and this is to be formally handed over immediately”.
8. This officer has filed an affidavit before the High Court. Therein he explained that he made the statements in question under an erroneous impression that the Government came into possession of the lands in question in view of the notification issued under Section 29 of the Indian Forest Act. This statement of his receives support from his letter written to the Land Acquisition Officer on August 11, 1959 wherein he mentioned:
“With reference to your above letters, I have to say that Debipur Forest was notified under the Indian Forest Act on 8th December, 1953 and that of the Telaiya on 22nd November, 1954. Thus, date of possession is 8th December, 1953 and 22nd November, 1954, respectively.”
9. It is possible that this officer had an erroneous impression as to the effect of a notification under Section 29 of Indian Forest Act. The other documents relied on by the appellant are wholly inconclusive. Hence there is no need to refer to them. We are in agreement with the High Court that there is no satisfactory evidence to show that the Government had taken possession of these lands in 1953 or 1954. As the parties had not enough opportunity to adduce evidence on this point, we will not be justified in finally deciding this question. It is sufficient if we say that on the material on record, the High Court was justified in not pronouncing on this question in a petition under Article 226 of the Constitution. It is open to the appellant to seek such other remedy as may be available to him under law if the Government had unlawfully taken possession of those lands. The question whether the Government had unlawfully taken possession of those lands in 1954, as we shall presently see, is wholly irrelevant for the decision of these appeals.
10. The next point that arises for decision is whether delivery of the lands notified for acquisition was taken under Section 17(1) as contended by the appellant. The Government becomes the owner of the lands notified for acquisition only when the Collector takes possession of those lands either under Section 16 or under Section 17(1). Both those provisions provide that when the Collector takes possession under those provisions, the lands notified for acquisition shall vest absolutely in the Government free from all encumbrances. Until and unless possession is taken under either of those provisions, the lands notified for acquisition do not vest in the Government. Section 48(1) of the Act provides:
“Except in the case provided for in Section 36, the Government shall be at liberty to withdraw from the acquisition of any land of which possession has not been taken.”
11. Section 36 is not relevant for our present purpose. Possession referred to in Section 48 necessarily is the possession taken either under Section 16 or under Section 17(1). Section 17(1) says:
“In cases of urgency, whenever the appropriate Government so directs, the Collector, though no such award has been made, may on the expiration of fifteen days from the publication of the notice mentioned in Section 9, sub-section (1), take possession of any waste or arable land needed for public purposes or for a Company. Such land shall thereupon vest absolutely in the Government free from all encumbrances.”
Ordinarily possession of any land notified for acquisition is taken when the Collector has made an award under Section 11 and not before it. But an exception is provided under Section 17(1). In cases of urgency, if the Government so directs, the Collector may, though no award has been made under Section 11, on the expiration of the 15 days from the publication of the notice mentioned in Section 9(1) take possession of any waste or arable land and the land shall thereupon vest absolutely with the Government free from all encumbrances. From this provision, it is plain that the Collector cannot take possession of the land in question unless the Government directs him to do so. The Government can direct him to do so only in cases of urgency. Even when the Government directs the Collector to take possession, he cannot do so until expiration of 15 days from the publication of a notice under Section 9(1). There is no material on record to show that the Government had given to the Collector any direction under Section 17(1); nor is there any material to show that the lands in question had been taken possession of by the Collector under Section 17(1). It is true that in the order-sheet maintained by the Land Acquisition Officer, a note was made on October 17, 1959:
“Shri B.P Yadav kgo, to deliver possession at the spot to the representative of the R.O on November 16, 1959. Draft addressed to R.O is signed.”
But there is nothing to show that this order was implemented. According to the respondent this order was not implemented.
12. Relying on the decision of this Court in Lt. Governor of Himachal Pradesh v. Avinash Sharma (1970) 2 SCC 23, AIR 1970 SC 1582, (1971) 1 SCR 413 it was contended by Mr R.K Garg, the learned counsel for the appellant that once it is established that the possession of the land notified for acquisition was taken in 1953 or 1954, it was unnecessary for his client to establish that any possession was taken under Section 17(1). According to him on the expiration of 15 days after the issue of notices under Section 9(1), the lands in question vested in the Government. The decision in question does not lend any support for this contention. In that case not only the property had been taken possession of by the Government even before the acquisition proceedings had started but appropriate proceedings under Section 9(1) and Section 17(1) were also taken though there was no actual taking of possession under Section 17(1). Under those circumstances this Court observed:
“In the present case a notification under Section 17(1) and (4) was issued by the State Government and possession which had previously been taken must, from the date of expiry of fifteen days from the publication of the notice under Section 9(1), be deemed to be the possession of the Government.”
13. In the present case, as mentioned earlier, no material has been placed before the Court to show that action under Section 17(1) had been taken.
14. It was next contended by Mr Garg and Mr A.K Sen, that the expression “whenever the appropriate Government so directs” in Section 17(1) refers to urgency and not to the taking of possession of the lands notified for acquisition. Their further contention was that no sooner the Government issued the notification under Section 17(4), the factum of urgency was established and hence on the expiration of the fifteen days from the publication of notice under Section 9(1) the lands which were already in the possession of the Government vested in the Government. We are unable to accept this construction of Section 17(1). In our judgment Section 17(1) is plain and unambiguous. The expression “whenever the appropriate Government so directs” in that section refers to the taking of possession and not to the declaration of urgency. Even in case of urgency, the Government may not think it necessary to take immediate possession for good reasons. Neither the language of Section 17(1) nor public interest justifies the construction sought to be placed by the learned counsel for the appellant.
15. For the reasons mentioned above, these appeals fail and they are dismissed; but in the circumstances of the case, we direct the parties to bear their own costs in these appeals.
16. Before concluding the case, it is necessary to record the assurance given by the Attorney-General on behalf of the State Government of Bihar that the Government of Bihar will not realise from the appellant any interest on the loans advanced for the development of the lands notified for acquisition in the two Land Acquisition cases from the dates they were notified under Section 29 of the Indian Forest Act. A Memo. to that effect has been filed.
Alert