National Building Construction Corporation Ltd. And Another v. State Of Haryana And Another

Punjab & Haryana High Court
Jan 9, 2007
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The petition under Article 226 of the Constitution was filed by a Government of India owned registered company (the petitioner), through its General Manager (Law) holding a Power of Attorney, seeking a declaration that paras VIII and XV of Clause 25 of an arbitration agreement dated 8.11.2002 were illegal and ultra vires, and praying for quashing of the Arbitrator's letter dated 18.8.2006 (Annexure P-8) which called upon the petitioner to deposit 10% of the amount of the claim before arbitration.

Background facts recorded in the opinion: the State of Punjab (respondent No.1) awarded the petitioner a contract (agreement dated 8.11.2002) for construction work valued at Rs. 2832.85 lakhs with an 18-month completion period. The petitioner alleges it began work but was prevented from timely execution due to breaches/defaults by respondents; it completed work valued at Rs. 1345 lakhs up to 31.3.2005 and left the work incomplete on 1.4.2005. The contract was allegedly terminated by the respondent by a letter dated 2.8.2005 (Annexure P-3). The petitioner submitted a final bill on 27.9.2005 and lodged a claim of Rs. 721.34 lakhs (Annexure P-4). The Executive Engineer rejected those claims by letter dated 10.1.2006 (Annexure P-5) as not in accordance with the agreement and barred by limitation; the petitioner replied on 20.1.2006.

The petitioner made a claim before the Arbitrator-cum-Superintending Engineer (respondent No.2) on 7.3.2006. On 18.8.2006 the Arbitrator (respondent No.2) required a "deposit-at-call" of 10% of the amount claimed in terms of Clause 25 sub-clauses VIII and XV of the agreement to proceed with arbitration. The petitioner challenged those clauses and the demand for deposit in this writ petition.

Legal Issues Presented

  1. Whether paras VIII and XV of Clause 25 of the arbitration agreement (dated 8.11.2002) are illegal and ultra vires.
  2. Whether the Arbitrator's letter dated 18.8.2006 (Annexure P-8) calling for a 10% deposit of the claimed amount should be quashed.
  3. Whether the challenged clauses (Clause 25 sub-clauses VIII and XV) are confiscatory, arbitrary or violative of Article 14 of the Constitution or the provisions of Section 28 of the Contract Act, 1872.
  4. Whether a writ under Article 226 is a proper remedy to challenge contractual provisions alleged to be unfair, particularly when the respondent is an agency/instrumentality of the State.

Arguments of the Parties

Petitioner's Arguments (as presented in the opinion)

  • The impugned clauses (Clause 25 sub-clauses VIII and XV) are confiscatory in nature and effectively take away the right of arbitration.
  • The clauses are arbitrary and violate Article 14 of the Constitution.
  • The clauses infringe the provisions of Section 28 of the Contract Act, 1872 (as alleged).
  • The petitioner relied on authority (ABL International Ltd. v. Export Credit Guarantee Corporation of India Ltd.) to submit that a writ against an instrumentality/agency of the State is competent.

The opinion does not set out any detailed or specific arguments advanced by the respondents in opposition to these contentions.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Central Inland Water Transport Corporation Limited v. Brojo Nath Ganguly, (1986) 3 SCC 156; AIR 1986 SC 1571 Examined concept of unconscionable clauses in contracts and the role of unequal bargaining power in justifying judicial intervention in standard form contracts. The court relied on this authority to explain that unconscionability/reasonableness is relevant only in specified circumstances where bargaining power is so unequal that one party lacks real freedom to contract; it found those circumstances absent in the present case.
A. Schroeder Music Publishing Co. Ltd. v. Macaulay (1974) 1 WLR 1308 Lord Diplock's exposition distinguishing two kinds of standard form contracts and the presumptions regarding fairness where bargaining power is matched or unmatched. Quoted (via Central Inland Water Transport discussion) to support the proposition that unequal bargaining power is a prerequisite for treating a clause as unconscionable; applied to hold that presumption of fairness applies where parties have comparable bargaining power.
Photo Production Ltd. v. Securior Transport Ltd., (1980) AC 827 Consideration of reasonableness of contractual terms and the role of judicial assessment of reasonableness where implied obligations are displaced by express clauses; references to the Unfair Contract Terms Act and Lord Diplock's speech. The court referred to the reasoning as part of the broader discussion on reasonableness and unconscionability and treated it as supportive of the position that reasonableness inquiries are triggered by unequal bargaining power or other specified circumstances.
LIC of India v. Consumer Education & Research Centre, (1995) 5 SCC 482 Supported the proposition that a clause in a contract may be examined for unreasonableness or unfairness particularly where relative bargaining power makes a party effectively unable to negotiate. Relied upon as further support for the principle that reasonableness/unfairness review arises in contexts of marked inequality of bargaining power; applied to conclude those conditions are not present in the instant contract.
ABL International Ltd. v. Export Credit Guarantee Corporation of India Ltd., JT 2003 (10) SC 300 Authority indicating that a writ under Article 226 may lie against an instrumentality/agency of the State for enforcement of contractual rights. The petitioner invoked this decision to contend that a writ was maintainable. The court acknowledged that a writ is competent against a State instrumentality but held that competence did not compel exercise of the jurisdiction where the impugned clauses were not found unfair or unconscionable.

Court's Reasoning and Analysis

The court first considered the legal test for striking down contractual terms as unconscionable or unreasonable. Drawing on the authorities cited (notably Central Inland Water Transport and the speech of Lord Diplock quoted therein), the court emphasized that scrutiny for unconscionability or unfairness arises primarily in situations where a standard form contract reflects a marked inequality of bargaining power such that one party is left without meaningful freedom to contract.

The court observed that the petitioner's case did not disclose such an inequality of bargaining power. Consequently, the circumstances that would justify judicial intervention on the ground of unreasonableness or unconscionability were not present. The court also referred to decisions and commentary concerning the assessment of reasonableness (including Photo Production and LIC of India v. CERC) to explain the context in which reasonableness review is appropriate.

Turning specifically to the impugned clauses, the court analyzed Clause 25 sub-clause VIII (the "deposit-at-call" of 10% of the claimed amount) and sub-clause XV (forfeiture of rights if arbitration is not invoked within the prescribed period). The court found that:

  • The requirement to deposit 10% has a legitimate purpose: to deter frivolous claims before the Arbitrator-cum-Superintending Engineer.
  • The clauses are mutual in effect because either party invoking arbitration is required to comply with the deposit condition; therefore the clauses do not lack mutuality.
  • On the available material, the clauses could not be characterized as irrational, unreasonable or unconscionable.

Regarding the petitioner's reliance on ABL International (to support writ jurisdiction against a State instrumentality), the court accepted that a writ under Article 226 is competent against an instrumentality or agency of the State. However, it held that competence does not mandate exercise of the jurisdiction in every case; given that the impugned clauses were not found unfair or unconscionable, the extraordinary remedy was not warranted here.

Holding and Implications

HOLDING: The petition is dismissed. The court upheld the validity of paras VIII and XV of Clause 25 of the arbitration agreement and did not quash the Arbitrator's letter dated 18.8.2006 requiring deposit of 10% of the claimed amount.

Implications:

  • Direct effect: The challenged contractual provisions (Clause 25 sub-clauses VIII and XV) were sustained and the petition seeking their annulment and quashing of the demand for a 10% deposit failed; the petitioner’s writ was dismissed.
  • The court did not find or declare any new legal principle; it applied existing authorities on unconscionability, reasonableness and unequal bargaining power to the facts and concluded the predicates for interference were absent. The opinion does not state any broader or novel precedent created by this decision.

Petition dismissed.
Show all summary ...

M.M Kumar, J.:— The prayer made by the petitioners in this petition filed under Article 226 of the Constitution is to declare paras VIII and XV of Clause 25 of the arbitration agreement, dated 8.11.2002 (Annexure P-2) as illegal and ultra vires. It has further been prayed to quash letter dated 18.8.2006 (Annexure P-8), issued by the Arbitrator-cum-Supenntending Engineer, respondent No. 2, to the petitioner calling upon it to deposit 10% of the amount of the claim submitted by him as per Clause VIII of the contract agreement before entering into arbitration.

2. Brief facts of the case are that the petitioner, which is a registered company owned by the Government of India is engaged, inter alia, in execution of construction projects of national importance. It has its registered office at New Delhi. The instant petition is filed through the General Manager (Law) Mrs. Meera Shankar, who has Power of Attorney in her favour (Annexure P-1). The State of Punjab, respondent no. 1, issued tenders for the erection, testing, commissioning, starting, stabilization and operation, monitoring and performance of 152 MLD STP based on USAB Technology at Balloke Zone C Ludhiana under Satluj Action Plan. The tender submitted by the petitioner was accepted and the work was awarded to it, which was valued at Rs. 2832.85 lakhs. Accordingly, agreement dated 8.11.2002 (Annexure P-2) was executed between the parties which stipulated a period of 18 months for completion of the work. It has been alleged that the petitioner started the work but on account of breaches and defaults on the part of the respondents it was prevented from timely execution. As a result, the petitioner could complete the work to the extent of Rs. 1345 lakhs only upto 31.3.2005 It had left the work incomplete on 1.4.2005 It has further been alleged that the respondent vide letter dated 2.8.2005 (Annexure P-3), illegally and arbitrarily terminated the contract. The petitioner submitted final bill on 27.9.2005 He had also lodged a claim amounting to Rs. 721.34 lakhs (Annexure P-4), which is claimed to be in accordance with the provisions of the contract. The Executive Engineer, however, declined the prayer of the petitioner as is evident from the letter dated 10.1.2006 by holding that the such claims are not as per the provisions of the agreement and were barred by limitation (Annexure P-5). The petitioner sent his reply to the afore mentioned rejection on 20.1.2006 (Annexure P-5 A).

3. The petitioner eventually lodged a claim before the Arbitrator-cum-Superintending Engineer, respondent No. 2 on 7.3.2006 However, the Arbitrator-cum-Supenntending Engineer, respondent No. 2, on 18.8.2006 called upon the petitioner to deposit the amount of 10% in pursuance to Clause 25 sub-clauses VIII and XV of the agreement so as to enable him to proceed further in the matter (P-8). It was claimed by the petitioner that the requirement of ‘deposit at call’ amount at the rate of 10% of the claimed amount, as provided by Clause 25 sub-clauses VIII and XV, were void and requested the Arbitrator to adjudicate upon the said claim without insisting on the requirement of ‘deposit at call’ amount at the rate of 10% (P-6). A reminder was sent on 7.6.2006 (P-7). The aforementioned clauses have now been challenged in this petition. It is appropriate to extract the aforementioned clauses, which reads as under:—

“VIII. It shall be an essential term of this contract that in order to avoid frivolous claims the party invoking arbitration shall specify the dispute based on facts and calculations stating the amount claimed under each claim and shall furnish a “deposit-at-call” for ten percent of the amount claimed, on a schedule bank in the name of the Arbitrator, by his official designation who shall keep the amount in deposit till the announcement of the award. In the event of an award in favour of the claimant, the deposit shall be refunded to him in proportion to the amount awarded w.r.t the amount claimed and the balance, if any, shall be forfeited and paid to the other party.”

“XV. If the matter is not referred to Arbitrator within the period prescribed above, all the rights and claims of either party under the contract shall be deemed to have been forfeited and absolutely barred by time for arbitration and even for civil litigation.”

4. Mr. Arvind Minocha, learned counsel for the petitioners has argued that the aforementioned clauses are confiscatory in nature and in fact take away the right of arbitration. He has further submitted that both the clauses are arbitrary and vio-lative of Article 14 of the Constitution apart from infringing the provisions of Section 28 of the Contract Act, 1872. Learned counsel has maintained that a writ arising out of a contract executed by an instrumentality or an agency of the State would be competent as has been held by Hon'ble the Supreme Court in the case of ABL International Ltd. v. Export Credit Guarantee Corporation of India Ltd., JT 2003 (10) SC 300.

5. We have given thoughtful consideration to the submissions made by the learned counsel and are of the view that the instant petition is liable to be dismissed. The concept of unconscionable clauses in a contract would arise only in specified circumstances. In a standard form contract where the bargaining power of the parties is unequal to an extent that one party is virtually left without any freedom to contract then the Courts have come to the rescue of the weaker party. There is elaborate discussion in respect of those clauses including a large number of English cases in a judgment of Hon'ble the Supreme Court in the case of Central Inland Water Transport Corporation Limited v. Brojo Nath Ganguly, (1986) 3 SCC 156 : AIR 1986 SC 1571. A reference has been made to the speech of Lord Diplock in the case of A. Schroeder Music Publishing Co. Ltd. v. Macaulay (Formerly Instone) (1974) 1 WLR 1308 and distinction has been recognized between the standard form contracts between the parties enjoying fairly matching bargaining powers and those who are not enjoying such a freedom. In the concluding part of para 85 it has been observed as under:—

“Lord Diplock then proceeded to point out that there are two kinds of standard forms of contracts. The first is of contracts which contain standard clauses which “have been settled over the years by negotiation by representatives of the commercial interests involved and have been widely adopted because experience has shown that they facilitate the conduct of trade”. He then proceeded to state, “If fairness or reasonableness were relevant to their enforceability the fact that they are widely used by parties whose bargaining power is fairly matched would raise a strong presumption that their terms are fair and reasonable”. Referring to the other kind of standard form of contract Lord Diplock said (at page 1316):

(emphasis added)

“The same presumption, however, does not apply to the other kind of standard form of contract. This is of comparatively modern orgin. It is the result of the concentration of particular kinds of business in reakatuvely few hands. The ticket cases in the 19th centary provide what are provide what are probably the first examples. The terms of this kind of standard form of contract have not been the subject of negotiation between the parties to it, or approved by any organization representing the interests of the weaker party. They have been dictated by that party whose bargaing power, either exercised alone or in conjunction with others providing similar goods or services, enables him to say. ‘If you want these goods of services at all these are the only terms on which they are obtainable. Take it of leave it’ To be in a position to adapt this attitude towards a party desirous of entering into a contact to obtain goods of services provides a classic instance of superior bargaining power.”

(Emphasis supplied)”

6. Reference lias also been made to the I etusla-jon enacted in U.K known as “Unfair Contract Terms Act. 1977, which was subject matter of Jiscussion m Photo Production Ltd. v. Seeurior Transport Ltd., (1980) AC 827. The speech, If Lord Diplock again has been quoted and the same reads as under—

“Since the obligations implied be law iii a commercial contract are those which, by judicial consensus over the years or by judicial consensus over the years or by parliament in passing a statute have been regarded as obligations, which a rettsdiiahlc businessman wouldrealize that he was accepiuigwhen he entered into a contrai I of a particular kind, the court's view of the reasonableness of any departure from the implied obligations which would be involved in construing the express words of an exclusion clause in one sense that they are capable of bearing rather than another, is a relevant consideration in deciding what meaning the words were intended by the parties to bear.”

(Emphasis supplied.)”

7. The aforementioned view as extracted by Hon'ble the Supreme Court show's that the concept of reasonableness and fairness of a clause in a contract could be examined in cases where the barganing power of the parties is unequal to the extent that the liberty given to one of the party is liberty of a ‘Limb befor the Lion’. However in the present case no such un-equal bargaining power of the parties to the contact is discermible which may warrant examination of sub-clauses viii and xv of Clause 25 of the contract. Therefore, we do not find any substance in the argument raised by the learned counsel for the petitioner and we cannot be invited to examine the validity of the aforementioned impugned claused on the ground of unreasonableness. Which are in fact necessary attributes of Articles 14 of the consititution. The asforementioned view as supported by the judgement of Hon'ble the Supreme Court in case L.I.C of India v. Consumer Education & Research Centre, (1995) 5 SCC 482. After citing various judgments from England and Legislative provisions in U.S.A, ther Lordship' have observed in para 47 as under:—

“47. It is therefore, the settled law that if a contract of a clause in contracts is found unreasonable or unfair or irrational. One must look to the relative bargaining power of the contracting there would be no occasion for a weaker party to bargain or to assume to have equal bargaining power. He has either to accept or leave the services or goods in terms of the dotted line contract. His option would be either to accept the unreasonalble of unfair terms or forgo the service for ever. With a view to have the services if goods, the party enters into a contact with unreasonable or unfair terms contained therin and he would be left with no option but to sign the contract.”

8. We are further of the view that the impugned clauses requiring the petitioner to deposit 10% of the amount claimed has a laudable object, namely, that no one should file frivolous claims before the Arbitrator-cum-Superintending Engineer, respondent No. 2. Furthermore the impugned clauses do not lack mutuality as any one of the parlies invoking arbitration is required to comply with the condition of depositing 10% of the amount claimed. Therefore, there is mutuality in the impugned clauses. In any case, it cannot be concluded that the impugned clauses are irrational, unreasonable or unconscionable.

9. The argument of the learned counsel with regard to the judgment of Hon'ble the Supreme Court 111 the case of ABL International Limited (supra), does not advance his case as the writ petition undisputedly is maintainable against the respondent, which is an agency and instrumenttality of a State within the ambit of Article 12 of the Constitution. It appears to be well settled that for enforcement of contract against an instrumentality or an agency of the State, the aggrieved party can invoke the extra ordinary jurisdiction of this Court under Article 226 of the Constitution. Having said that it does not lead to conclusion that in every case the jurisdiction are required to be exercised and present is the case where impugned clauses have not been found to be unfair or unconscionable.

10. For the reasons aforementioned, this petition fails and the same is dismissed.

Petition dismissed.