Union Of India v. Harbhajan Singh .
Factual and Procedural Background
This revision petition was filed against the judgment of the learned District Judge, Chandigarh, which dismissed the Union of India's appeal against the Sub Judge First Class, Chandigarh's order making an arbitrator's award rule of the Court. The Arbitrator had made awards on multiple claims by the contractor-respondent; the Union of India challenged several claims as not being sustainable under the contract terms. The District Judge upheld the lower court's decision, prompting this revision.
Legal Issues Presented
- Whether Claim Nos. 1, 2, 3, 4 and 7 awarded to the contractor were admissible under the terms of the agreement and whether the courts could substitute their view to set aside the arbitrator's award on those claims.
- Whether the amount of Rs. 61,152 awarded under Claim No. 6 for prolongation of the contract (for non-supply of stores and delay in handing over the site) is sustainable in view of the specific bar under Section 11(C) of the contract agreement.
Arguments of the Parties
Union of India
- Challenged the Arbitrator's award on the ground that Claim Nos. 1, 2, 3, 4, 6 and 7 raised by the contractor-respondent were not sustainable in view of the terms of the contract.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| CR No. 3884 of 2001 AKM Construction v. Commander Works Engineer | Referred to for detailed reasons relevant to setting aside part of an arbitrator's award. | The court relied on the detailed reasons given in that decision to set aside the portion of the award awarding Rs. 61,152 to the respondent-contractor. |
Court's Reasoning and Analysis
The court reviewed the lower appellate court's findings and agreed that Claim Nos. 1, 2, 3, 4 and 7 were admissible under the contract and that courts should not substitute their opinion to overturn an arbitrator's award on those heads. The sole challenge meriting interference related to Claim No. 6 (Rs. 61,152) awarded for prolongation due to non-supply of stores and delay in handing over the site. The court concluded that Claim No. 6 could not be sustained because of a specific bar contained in Section 11(C) of the contract agreement. The impugned part of the award was held to be the result of misconduct by the Arbitrator. For the detailed reasons, the court relied on CR No. 3884 of 2001 AKM Construction v. Commander Works Engineer and set aside only the Rs. 61,152 portion of the award while upholding awards under other heads.
Holding and Implications
Revision petition is partly allowed.
Direct effect: The portion of the arbitrator's award awarding Rs. 61,152 to the respondent-contractor for prolongation of the contract is set aside; awards under the other heads are upheld. No broader precedent was announced beyond reliance on the reasoning in CR No. 3884 of 2001 AKM Construction v. Commander Works Engineer.
Vinod K. Sharma, J. (Oral):— This revision petition has been filed against the judgment passed by the learned District Judge, Chandigarh vide which the appeal filed by the Union of India against the judgment of learned Sub Judge First Class, Chandigarh making the award rule of the Court was dismissed.
2. The award passed by the learned Arbitrator was challenged by the Union of India on the ground that Claim Nos. 1, 2, 3, 4, 6 and 7 raised by the contractor-respondent were not sustainable in view of the terms of the contract.
3. The reading of the order shows that the learned lower Appellate Court came to the conclusion that Claim Nos. 1, 2, 3, 4 and 7 awarded to the contractor were admissible under the terms of the agreement and it was not open to the Court to substitute its opinion so as to set aside the award passed by the learned Arbitrator. No error can be found with the findings recorded by the Courts below on this aspect.
4. The only challenge to be considered in this revision petition is qua the amount of Rs. 61,152/- awarded towards the reimbursement of damages suffered on account of breach of contract by the department including delay in issuing of Schedule B stores and delay in handing over site etc. which resulted in prolongation of contract period. The Arbitrator against this claim had awarded a sum of Rs. 61,152/-. The claim of Rs. 61,152/- under Claim No. 6 for prolongation of the contract for non-supply of stores and delay in handing over of site cannot be sustained in view of the specific bar under Section 11(C) of the contract agreement. The impugned part of the award, therefore, is the outcome of the misconduct on the part of the Arbitrator. Therefore, for the detailed reasons given in CR No. 3884 of 2001 AKM Construction v. Commander Works Engineer, this revision petition is partly allowed and claim of Rs. 61,152/- awarded to the respondent-contractor by the Arbitrator for prolongation of the contract is hereby set aside while claim under other heads are upheld.
5. Revision petition is partly allowed.
Petition partly allowed.