M/S Nihal Singh Motors & Others v. Smt. Shama Malhotra & Another
Judgment Summary — M.M. Kumar, J.
Factual and Procedural Background
This opinion disposes Civil Revision No. 3462 of 2004 and Civil Revision No. 3463 of 2004 filed by the tenant-petitioners under Section 15(5) of the East Punjab Urban Rent Restriction Act, 1949. Both petitions challenge orders dated 14.6.2004. The background facts relevant to the challenges are:
- The landlady respondent instituted an ejectment petition (Civil Suit No. RA 25-A) on 20.3.2003 under Section 13 of the Act seeking ejectment for non-payment of rent for the period 1.6.2002 to 28.2.2003.
- On 31.5.2003 the Rent Controller made a provisional assessment ordering the tenant to pay arrears (quantified) and fixed a date for payment (initially 10.6.2003, later adjourned to 24.7.2003).
- The tenant (a partnership firm M/s S. Nihal Singh Motors) failed to appear or comply with the provisional order; the Rent Controller struck off their defence and on 12.8.2003 passed an ejectment order following the law in Rakesh Wadhawan v. Jagadamba Industrial Corporation.
- The tenants applied to set aside the 12.8.2003 order (described as an application to set aside "ex parte proceedings and ex parte order dated 12.8.2003"); the Rent Controller dismissed that application by order dated 14.6.2004 (holding no ex parte proceeding within the meaning of Order IX and that CPC provisions were not strictly applicable to the Act).
- Separately, the tenants had earlier sought determination of fair rent under Section 4 (R.A. No. 87, instituted 11.6.1997); Rent Controller fixed fair rent on 22.5.2002 (operative dated 22.5.2002) and the Appellate Authority, by order dated 10.9.2003, partially modified the Rent Controller's order but upheld fair rent at Rs. 15,625/- per month and left open enhancement of future rent for determination in accordance with law.
- The tenants appealed against the ejectment order but withdrew the appeal; the Appellate Authority dismissed the appeal as withdrawn on 18.11.2003.
- The landlady moved for execution of the 12.8.2003 ejectment order; executing court dismissed the tenants' objections by order dated 14.6.2004. Tenants challenged both orders (the Rent Controller's and executing court's) by the present civil revisions.
Legal Issues Presented
- Whether the Rent Controller and the executing court correctly dismissed the tenant-petitioners' applications/objections challenging the ejectment order dated 12.8.2003 and the execution proceedings (i.e., whether the orders dated 14.6.2004 were legally sustainable).
- Whether, under Section 13(2)(i) of the Act and the law laid down in Rakesh Wadhawan and subsequent Supreme Court authority, the Rent Controller was obliged to make a provisional assessment, fix a date for payment, and order eviction if the tenant failed to comply with the provisional order.
- Whether applications styled as applications to set aside "ex parte proceedings and ex parte order" (invoking Order IX Rules of CPC, notably Rules 8, 13 and 15) were maintainable where the defence had been struck off for non-compliance rather than where the party had been proceeded against ex parte.
- Whether a subsequent fixation of fair rent by the Appellate Authority (on 10.9.2003) could retrospectively affect the validity of the provisional assessment and the ensuing ejectment when the tenant had not deposited the assessed amount in compliance with the provisional order.
Arguments of the Parties
Tenant-Petitioners' (Appellants') Arguments — as advanced by Shri J.S. Chaudhary
- The provisional assessment order dated 31.5.2003 fixing rent @ Rs. 42,875/- plus house tax, interest and costs became unsustainable after the Appellate Authority fixed the fair rent at Rs. 15,625/- by its order dated 10.9.2003; therefore the provisional order should be deemed modified or a fresh order should have been passed for depositing rent consistent with the Appellate Authority's determination.
- The Act and its provisions should be construed to benefit the tenant; the tenant has a bank draft of Rs. 4,37,000/-, representing the rent according to the Appellate Authority's fair rent, demonstrating readiness to pay under the fair rent determination.
- Reliance placed on Division Bench judgment in Harbilas Rai Bansal v. State of Punjab to support the proposition that provisional orders should not exceed rent fixed under Section 4 and that the tenant's interest must be protected.
Landlady-Respondent's Arguments — as advanced by Shri Rohit Malhotra
- The tenant-petitioners adopted delaying tactics and repeatedly failed to deposit rent in accordance with the provisional assessment dated 31.5.2003 despite indulgence and adjournments (from 10.6.2003 to 24.7.2003).
- Under Rakesh Wadhawan, if a tenant is aggrieved by a provisional assessment the correct course is to deposit the assessed amount and then contest the proceedings; failure to pay requires eviction without further proceedings.
- The provisional assessment merged into the ejectment order of 12.8.2003, which attained finality because the tenants did not successfully challenge it (appeal withdrawn); the application to set aside the 12.8.2003 order was improperly styled and not maintainable.
- The tenants had not paid any amount either pursuant to the provisional assessment or pursuant to the fair rent determined later; their belated readiness to pay in accordance with the later fair rent could not save them from eviction after failure to comply with earlier provisional orders.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Rakesh Wadhawan v. Jagadamba Industrial Corporation (cited multiple times) | The interpretation of Section 13(2)(i) of the East Punjab Urban Rent Restriction Act: Controller must assess arrears, interest and costs, quantify by provisional order the amount tenant must pay, fix a date for payment, and failure to comply leads to eviction; principles for interim deposit, refund or conditional orders on final adjudication. | The court applied and followed these principles as authoritative. It held the Rent Controller followed the Rakesh Wadhawan schedule and therefore the order of ejectment was lawful. |
| Vinod Kumar v. Prem Lata (three-Judge Bench) | Reiteration of the view taken in Rakesh Wadhawan by a larger Bench (confirming the principles in Rakesh Wadhawan). | The court noted the three-Judge Bench reiterated Rakesh Wadhawan and relied on that confirmation in upholding the impugned orders. |
| Rubber House v. Excelsior Needle Industries (P) Ltd. | Earlier contrary view concerning the provisions (contextual to Section 13(2)(i) jurisprudence) which was later held to be contrary. | The court recorded that Rubber House was overruled by subsequent authority (Vinod Kumar) and therefore not applicable. |
| Rajinder Kumar Joshi v. Veena Rani | Earlier contrary authority in the same line which was subsequently overruled. | Noted as overruled by the subsequent Supreme Court authority; therefore not followed. |
| P. Kiran Kumar v. A.S. Khadar and others | Rule on maintainability: after disposal of appeal on any ground other than withdrawal of appeal, an application under Order IX Rule 13 CPC is not maintainable; after withdrawal of appeal, such an application is maintainable. | The Rent Controller referenced this authority in addressing maintainability of applications under Order IX Rule 13; the court recorded that distinction in the context of the tenants' proceedings. |
| Madan Lal v. Sumita Devi | Authority pertaining to Order IX Rule 13 CPC (contextual to maintainability). | The Rent Controller observed this case's law relates to Order IX Rule 13 and found it not relevant to the proposition at hand; the present court recorded that position. |
| Collector, Cuttack-1 v. Indramani Shaoo and another (1996) | Authority that a party cannot challenge the validity of a decree before the executing court. | The Rent Controller relied on this authority to hold that the ejectment order could not be challenged in execution proceedings; the court upheld that approach. |
| Chain Singh v. Mohan Singh (2000) (P&H) | Principle that a court can summarily reject frivolous objections raised with the intention to delay execution proceedings. | The executing court relied on this authority to justify summary dismissal of the tenants' objections; this reasoning was accepted by the court under review. |
| Vasudev Dhanjibhai Modi v. Rajhbhai Abdul Rehman and others (1970) | Principle that the court cannot go behind the decree and must execute it as it stands. | The executing court relied on this case to reject objections and proceed with execution; the present court accepted that reliance. |
| Harbilas Rai Bansal v. State of Punjab and another (1997) | Authority cited by tenant-counsel in support of the proposition that rents fixed under Section 4 should constrain provisional assessments and that Act's provisions should be construed in tenant's favour. | The court observed the Division Bench decision was relied upon by the tenants but held it did not entitle the tenants to violate the provisional assessment and retain possession after failing to comply with provisional orders. |
| 1984 C.I.J (Civil and Criminal) 79; 1981 (2) RCR 614; 1988 (2) RCR 263 | Cases referred to by the Appellate Authority when holding that Section 5 of the Act would not be applicable and parties could litigate enhancement of future rent in accordance with law. | Recorded as authorities cited by the Appellate Authority to justify that parties remain at liberty to get controversy regarding enhancement of future rent determined in accordance with law. |
Court's Reasoning and Analysis
The court's analysis proceeds by examining the sequence of orders and applying the law laid down by the Supreme Court in Rakesh Wadhawan and confirmed in Vinod Kumar.
- The court accepted the legal framework from Rakesh Wadhawan: Section 13(2)(i) imposes on the Controller an obligation to make a provisional assessment (arrears, interest and costs), quantify the amount by an interim order and fix a date after the provisional order for payment; failure by tenant to comply permits immediate eviction without further proceedings.
- Applying those principles to the facts, the Rent Controller passed a provisional assessment on 31.5.2003, fixed dates for payment (10.6.2003, then extended to 24.7.2003), and the tenants failed to appear or deposit the assessed amount. The defence was struck off on 24.7.2003 and ejectment followed on 12.8.2003. The court found the Rent Controller had followed the schedule and principles of Rakesh Wadhawan.
- The court distinguished an ex parte proceeding from a situation where the defence was struck off for non-compliance: applications under provisions of CPC framed for setting aside ex parte orders (Order IX Rules) are not maintainable where the party's defence was struck off for non-compliance rather than where the party was proceeded against ex parte. The Rent Controller's conclusion that CPC provisions are not strictly applicable to the Act and that Order IX Rule 13 was not available in the circumstances was endorsed.
- The court addressed the contention that the later determination of fair rent by the Appellate Authority (10.9.2003) rendered the provisional assessment and subsequent ejectment invalid. It noted the provisional order of 31.5.2003 explicitly took into account the fair rent order passed on 22.5.2002. More importantly, tenants had not tendered the assessed sum or otherwise complied; they withdrew their appeal against the ejectment order and did not successfully challenge the ejectment order. The court stressed that, under para 30(5) of Rakesh Wadhawan, any excess deposit could have been refunded or deficiency addressed by conditional order, but those remedies require compliance with provisional orders at the time.
- Because the tenants did not comply with provisional orders, their later readiness to pay (by bank draft or otherwise) pursuant to the Appellate Authority's later determination could not entitle them to relief from the eviction already validly ordered under the established principles.
- The executing court's dismissal of objections was supported by precedent that executing courts need not go behind decrees and can summarily reject frivolous objections aimed at delay (Chain Singh, Vasudev Modi). The court therefore found both the Rent Controller's and executing court's orders lawful and without illegality.
Holding and Implications
Holding: Both civil revision petitions fail and are dismissed. The orders dated 14.6.2004 passed by the Rent Controller and by the executing court (dismissing the respective tenant applications/objections) are upheld.
Implications:
- Direct effect on the parties: the Rent Controller's order setting aside the tenant application and the executing court's dismissal of the tenant's objections are sustained; the ejectment order of 12.8.2003 stands as having been validly made and executed in accordance with law.
- The court applied and followed existing Supreme Court authority (Rakesh Wadhawan and its reaffirmation in Vinod Kumar) rather than creating new law; no new precedent was announced by this decision beyond the application of settled principles to the facts before it.
Petitions dismissed.
M.M Kumar, J. — This order shall dispose of Civil Revision No. 3462 of 2004 (1st petition) and Civil Revision No. 3463 of 2004 (2nd petition) filed by the tenant-petitioners under Section 15(5) of the East Punjab Urban Rent Restriction Act, 1949 (for brevity ‘the Act’). The challenge in both the petitions is to the two orders dated 14.6.2004
In the 1st petition challenge is to order dated 14.6.2004 passed by the Rent Controller, Ludhiana dismissing an applicant in which prayer was made for setting aside ex parte order dated 12.8.2003 In the second petition, challenge is to order dated 14.6.2004 passed by executing court dismissing the objection of the tenant-petitioner judgment debtor to the execution proceedings taken by the landlady respondent. The landlady respondent had filed an application for execution of order dated 12.8.2003 passed by the Rent Controller for ejectment of the tenant-petitioners from the demised shop.
(1) Brief facts concerning the order of provisional rent and striking of defence.
3. Brief facts necessary for deciding the controversy raised in the instant petitions are that the landlady respondent filed an ejectment petition registered as Civil Suit No. RA 25-A instituted on 20.3.2003 under Section 13 of the Act before the Rent Controller, Ludhiana. The ground for ejectment pleaded in the ejectment petition was non-payment of rent in respect of period from 1.6.2002 to 28.2.2003 Notice of the application was issued to the tenant-petitioners and the case was posted the arguments to pass a provisional order of assessment on 31.5.2003 On 31.5.2003, the Rent Controller after hearing both the sides concluded that the landlady respondent was entitled to recover rent from 1.6.2002 to 28.2.2003 @ Rs. 42,875/- p.m plus house tax of Rs. 6,431.25 plus interest at the rate of 6 percent thereon and costs of Rs. 400/-. An amount of Rs. 20,223A already deposited in excess as per the orders passed by the Appellate Authority was to be adjusted. Thereafter the Rent Controller fixed 10.6.2003 as the next date for payment of rent in accordance with the order dated 31.5.2003 following the law laid down by the Supreme Court in the case of Rakesh Wadhawan v. Jagadamba Industrial Corporation, 2002 (1) RCR (Rent) 514 (SC) : (2000-2) 31 PLR 370. However, on 16.6.2003 the tenant-petitioner failed to appear on the pretext that Surinder Singh, Managing Partner, was unwell. It is appropriate to mention that the tenant-petitioner in this case is a partnership firm under the name and style of M/s. S. Nihal Singh Motors and all the three partners were impleaded as respondents besides the partnership firm. The Rent Controller felt dissatisfied and ordered striking off the defence of the tenant-petitioner. On 12.8.2003, the Rent Controller passed an order of ejectment following the dictum of law laid down in Rakesh Wadhwan's case (supra). The operative part of order dated 12.8.2003 passed by the Rent Controller reads as under :—
“I have pursued the evidence on record and the contention raised by learned counsel for the petitioner. Shri K.D Malhotra has appeared as PW1. He proved on record the power of attorney Ex.P1, lease deed Ex.P2 site plan Ex.P3, order and judgment Ex.P4 and electricity bill Ex.P5 He has proved on record that from April 2000 to March 2003, the respondent is to pay rent of Rs. 4,28,750/- and house tax of Rs. 64,312/-. The interest on this amount is Rs. 17,724/-. Thus, the respondents are liable to pay an amount of Rs. 5,10,786/- to the petitioner. As per the judgment Ex.P4 passed by Shri D.R Arora, learned Appellate Authority, the petitioner has to refund Rs. 20,223/- to the respondents. The respondent has to pay the remaining amount of Rs. 4,90,563,750/- to the petitioner. The respondents have not paid the rent despite order passed by my learned predecessor on 31.5.2003 So, the defence of the respondents has already been struck off by this Court on 24.2.2003 Hon'ble Apex Court of India has held in Rakesh Wadhawan v. Jagdamba Industrial Corporation, (2002-2) 131 PLR (SC) 270 (supra) that on failure of the tenant to pay the arrears of rent, as per the assessment order passed by the Controller nothing remains to be done. An order of eviction of the respondent shall follow. Therefore, the petition for ejectment of the respondents from the demised premises is accepted with costs. The respondents are directed to vacate and deliver the vacant possession of the demised premises within two months from today onwards. Memo of costs be prepared accordingly. File be consigned to the record room.”
4. The tenant-petitioners filed an application for setting aside the order dated 12.8.2003 whereby the defence was struck off by attaching two medical certificates dated 22.2.2003 and 15.8.2003 The application was styled as “for setting aside the ex parte proceedings and ex parte order dated 12.8.2003”. However, it was factually an application for setting aside the order dated 12.8.2003 on the various grounds which by no stretch of imagination was an ex parte order. The Rent Controller noticed that ex parte proceeding against the tenant-petitioner was already set aside on 16.5.2003 subject to payment of costs of Rs. 200/- and thereafter on 31.5.2003 the provisional assessment order of rent plus interest plus costs was passed. The Rent Controller also noticed the other facts to which reference has already been made. It was pointed out that the tenant-petitioner was categorically warned on 10.6.2003 that in case they did not pay the arrears of rent before 24.7.2003 then it was to strike off their defence by passing appropriate order. On 24.7.2003 the tenant-petitioner made “mockery of the order passed on 10.6.2003 and did not come forward for payment of rent as per the order dated 31.5.2003” which led to the passing of the order striking off the defence of the tenant-petitioners on 24.7.2003 Holding that there was no ex parte proceeding, the learned Rent Controller passed the impugned order dated 14.6.2004 the operative part of which reads as under :
“An application under Order 9 Rule 15 CPC for setting aside the ex parte is only maintainable, if in case, the aggrieved party has been proceeded against ex parte, but in the instant case, the defence of the applicants, i.e M/s. Nihal Singh Motors and others has been struck off by this Court for non-complying with the orders passed by it. The applicants have concealed this most relevant material fact from the notice of this Court, especially, only with an intention, to mislead this Court in the instant case. The respondents were not proceeded against ex parte within the meaning of under Order 9 Rule 8 CPC, rather their defence was struck off for non-compliance of order passed by this Court. Moreover, the ejectment petition in the instant case has been filed under Section 13 of the East Punjab Urban Rent Restriction Act, 1949. So, the provisions of CPC are not strictly applicable to the proposition in hand. So far as the maintainability of the present application is concerned, the Hon'ble Apex Court of India has held in P. Kiran Kumar v. A.S Khadar and others, 2003 (1) Apex Court Judgments 100 (S.C), that after disposal of appeal on any ground other than withdrawal of appeal application under Order 9 Rule 13 CPC is not maintainable. So, after withdrawal of appeal the application under Order 9 Rule 13 CPC is maintainable. So, the case of Madan Lal v. Sumita Devi, 2001 (2) RCR (Rent) 212 (P&H) : 2002 (1) CCC 204 (P&H) is not relevant to the case in hand. Moreover, the judgments in these cases have been given pertaining to the matter under Order 9 Rule 13 CPC. As Order 9 Rule 13 CPC is not applicable to the proposition in hand, so the law laid down in these cases is not applicable. The applicants have not alleged that the decree is nullity. So they cannot challenge the validity of the ejectment order dated 12.8.2003, before this executing Court. On this point, the case of Collector, Cuttack-1 v. Indramani Shaoo and another, 1996 (2) CCC 198 (Orissa), is fully applicable to the case in hand. The subject matter in this case is not covered under Order 9 Rule 13 CPC. So, there is no need of framing any issue in this case. Ultimately, I have arrived at the conclusion, that there is no merit in the application. Resultantly, the same is dismissed.”
5. It is pertinent to mention that the tenant-petitioners filed an appeal against the order dated 12.8.2003 before the Appellate Authority on 29.9.2003 However, a prayer was made for dismissal of the appeal as withdrawn. Accordingly on 18.11.2003 the Appellate Authority, Ludhiana passed an order dismissing the appeal as withdrawn.
(II) Facts concerning determining of fair rent at the instance of the tenant-petitioner.
6. The second set of facts which are necessary for deciding the controversy raised in these petitioners are that the tenant-petitioner filed an application under Section 4 of the Act which was registered as R.A No. 87 instituted on 11.6.1997 After detailed examination on 22.5.2002, the Rent Controller, Ludhiana fixed the fair rent of the demised shop. The operative part of the order passed by the Rent Controller reads as under :
“From above discussion on various issues the petition filed by petitioners stands disposed of by fixing fair rent of premises in dispute at Rs. 15,625/- p.m from the date of application and it is to be enhanced as per the terms and conditions mentioned in lease deed Ex.R1.A. There is no order as to costs. Memo of costs be prepared. File be consigned to record room.”
7. The aforementioned order was challenged by the tenants-petitioners before the learned Appellate Authority with a prayer for setting aside the same. However, the learned Appellate Authority partially modified the order by holding that the increase envisaged in the rent note Ex.R1.A was not applicable and the fair rent of the demised shop was Rs. 15,625/-. The observations of learned Appellate Authority in its order dated 10.9.2003 read as under :
“In view of the above said facts, I am constrained to hold that the findings of the Rent Controller on issue No. 6, so far it relates to the enhancement of the rent in future in accordance with the terms and conditions mentioned in the rent note Ex.R1.A is concerned, the same are beyond jurisdiction and unwarranted. Therefore, the same cannot sustain and as such are liable to be set aside. Accordingly, the findings on this issue are modified and the conclusion regarding the fixing of the fair rent of the demised shop as Rs. 15,625/- on the basis of rent note Ex.R1.A is upheld, while the remaining observation is set aside.”
8. It is pertinent to mention that the Appellate Authority allowed the landlady-respondent to get the controversy with regard to the enhancement of future rent determined in accordance with law as is evident from para 14 of the order of the Appellate Authority which reads as under :
“While parting with the judgment, I feel it necessary to mention that since the fair rent in this case has not been fixed by the Rent Controller in accordance with the provisions of Section 4(2)(a) & (b) of the Act and rather it is based upon the case law cited in 1984 C.I.J (Civil and Criminal) 79, 1981 (2) RCR 614 and 1988 (2) RCR 263 (supra), the provisions of Section 5 of the Act will not be applicable and parties will be at liberty to get the controversy, regarding enhancement of future rent, determined in accordance with law”.
9. When the landlady respondent filed an application for execution of the order dated 12.8.2003 for the ejectment of the tenant-petitioners, the tenant-petitioners raised various objections. The objections filed by the tenants-petitioners were rejected by the Rent Controller on 14.6.2004 by recording a separate order. The operative part of the order reads as under :
“On critical examination of contentions raised by the learned counsel for the parties. I have found that my predecessor passed order on 31.5.2003 assessing fair/provisional rent that was to be paid by the applicant. This Court provided due opportunity to the applicants/JDs objectors to comply with said orders and deposit the arrears of rent but they declined to comply with the orders passed by this Court. Ultimately, defence of the JDs was struck off vide order on 24.7.2003 Consequently, ejectment order was passed on 12.8.2003 against the objectors” in light of law laid down by the Apex Court of India in Rakesh Wadhawan v. Jagdamba Industrial Corporation (supra). So there is no point on which issues are to be framed calling for evidence of objectors/DH. The JDs have not paid the rent as per assessment order. Now they have come forward with false and frivolous objections that the execution of the ejectment order dated 12.8.2003 should be stayed. Our own Hon'ble High Court has held in Chain Singh v. Mohan Singh, 2000 (1) CCC 651 (P&H) that the Court can summarily reject the frivolous objections raised with an intention to delay the execution proceedings. This Court cannot go behind the decree, so it is to be executed as it is. On this point, the cases of Vasudev Dhanjibhai Modi v. Rajhbhai Abdul Rehman and others, 1970 RCR (Rent) 427 (SC) : AIR 1970 SC (sic) and 2001 (2) RCR (Civil) 763 are fully applicable. Therefore, I have arrived at the conclusion that the objections have been raised only with an ulterior motive to delay the execution proceedings. Resultantly, objections are dismissed.”
10. Shri J.S Chaudhary, learned Senior Counsel for the petitioners has argued that the order of the Rent Controller dated 31.5.2003 fixing the rate of rent at Rs. 42,875/- plus house tax plus interest and costs has become unsustainable in law after the fair rent was fixed by the learned Appellate Authority in its order dated 10.9.2003 According to the learned counsel, the provisional order of rent dated 31.5.2003 should be deemed to have been appropriately modified or a fresh order should have been passed for depositing the rent in accordance with the order dated 10.9.2003 of the learned Appellate Authority determining the fair rent. The learned counsel has maintained that it is well settled that no order could be passed fixing the rate of rent over and above the rent fixed by the Rent Controller/Appellate Authority in accordance with the provisions of Section 4 of the Act. The learned counsel has maintained that the tenant-petitioner has in its hand even today a bank draft of Rs. 4,37,000/- which is the rent payable to the tenant-petitioner in accordance with the fair rent fixed by the Appellate Authority vide order dated 10.9.2003 In support of his submission, the learned counsel has placed reliance on a Division Bench Judgment of this Court in the case of Harbilas Rai Bansal v. State of Punjab and another, 1997 (1) RCR (Rent) 321 (P&H) : (1997-1) 115 P.L.R 536. The learned counsel has also argued that the provisions of the Act should be construed to the benefit of the tenant rather than the landlord as the basic object of the provisions is to protect the interest of the tenant.
11. Shri Rohit Malhotra, learned counsel for the landlady respondent has argued that the tenant-petitioners have adopted delaying tactics for depositing the rent in accordance with the provisional order of assessment dated 31.5.2003 According to the learned counsel, the Rent Controller has shown indulgence to the tenant-petitioners as 10.6.2003 date fixed for making payment of rent in accordance with the provisional order of assessment of rent dated 31.5.2003 On the request of the tenant-petitioners the case was still adjourned and they were granted about one and half months time to deposit the rent and the case was fixed for 24.7.2003 He has also relied upon the judgment of the Supreme Court in Rakesh Wadhawan's case (supra) to argue that if the tenant-petitioner was aggrieved by the order of provisional assessment of rent dated 31.5.2003 passed by the Rent Controller then the only course open to him was to deposit the rent and then contest the proceedings before the Rent Controller. The learned counsel has emphasized that he could not have defied the order and waited for the decision of his appeal before the Appellate Authority which was eventually decided on 10.9.2003 much after the passing of the provisional order of assessment dated 31.5.2003 The learned counsel has also pointed out that the tenant-petitioner has not paid even a single penny either in accordance with the order dated 31.5.2003 or in accordance with the order dated 11.9.2003 passed by the Appellate Authority fixing the fair rent as per the provisions of Section 4 of the Act. On the contrary the stand of the tenant-petitioners before the Rent Controller was that the managing partner Surinder Singh was unwell and on that account he was unable to attend to the hearing for payment of rent. According to the learned counsel the provisional order of assessment of rent dated 31.5.2003 has already merged in the order dated 12.8.2003 evicting the tenant-petitioners from the demised shop and it has attained finality as it has not been successfully challenged at any forum. The order dated 14.6.203 has been passed by the Rent Controller on the application by the tenant-petitioners on which prayer was made for setting aside the order dated 12.8.2003 which has been styled as an application for “setting aside ex-parte proceedings and ex-parte order dated 12.8.2003”
12. After hearing the learned counsel for the parties at length, I am of the considered view that this petition does not merit admission and is liable to be dismissed. According to Section 13(2)(i) of the Act non-payment of rent is a ground for ejectment of a tenant. The afore-mentioned provision was interpreted by the Supreme Court in Rakesh Wadhawan's case (supra) and it has been held by their Lordships that the Rent Controller is under an obligation to make an assessment of arrears of rent, interest on such arrears and the cost of the application. It has to then quantify by way of an interim order the amount which the tenant must pay or tender. The Rent Controller is further under an obligation to fix a date for payment of arrears after the passing of provisional order determining the arrears of rent. If the tenant fails to comply with the order then nothing more is required to be done and ejectment of the tenant must follow. The Supreme Court in Rakesh Wadhawan's case (supra) after detailed examination of the case law has laid down the following principles :—
“To sum up, our conclusion” are :
(1) In Section 13(2)(i) proviso, the words ‘assessed by the Controller’ qualify not merely the words ‘the cost of application’ but the entire proceeding part of the sentence i.e the arrears of rent and interest at six per cent per annum on such arrears together with the cost of application.
(2) The provision to Section 13(2)(i) of East Punjab Urban Rent Restrictions Act, 1949 casts an obligation on the Controller to make an assessment of : (i) arrears of rent, (ii) the interest on such arrears, and (iii) the cost of application and then quantify by way of an interim or provisional order the amount which the tenant must pay or tender on the first date of hearing after the passing of such order of assessment by the Controller so as to satisfy the requirement of the proviso.
(3) Of necessity, the date of first hearing of the application would mean the date falling after the date of such order by Controller.
(4) On the failure of the tenant to comply, nothing remains to be done and an order for eviction shall follow. If the tenant makes compliance, the inquiry shall continue for finally adjudicating upon the dispute as to the arrears of rent in the light of the contending pleas raised by the landlord and the tenant before the Controller.
(5) If the final adjudication by the Controller be at variance with his interim or provisional order passed under the proviso, one of the following two orders may be made depending on the facts situation of a given case, if the amount deposited by the tenant is found to be in excess, the Controller may direct a refund. If, on the other hand, the amount deposited by the tenant is found to be short or deficient, the Controller may pass a conditional order directing tenant to place the landlord in possession of the premises by giving a reasonable time to the tenant for paying or tendering the deficient amount failing which alone he shall be liable to be evicted. Compliance shall save him from eviction.
(6) While exercising discretion for affording the tenant an opportunity of making good the deficiency, one of the relevant factors to be taken into consideration by the Controller would be, whether the tenant has paid or tendered with substantial regularity the rent failing due month by month during the pendency of the proceedings.
The view of the law so taken by us advances the object sought to be achieved by the legislation, serves best the interests of landlord and tenant both, removes uncertainty in litigation and obscurity in drafting of the provision and also accords with the principles of justice and equity. Even if, it is an innovation, it is in the field of procedural law, without affecting the substantive rights and obligations of the landlord and the tenant and such innovation is permissible on the basis of authority and supported by principles of justice, good sense and reason. We have not touched the substantive rights of landlord and tenant and are feeling satisfied with a do little in the field of procedure so as to effectuate the purpose of enactment.”
13. It is further appropriate to mention that the judgment in Rakesh Wadhawan's case (supra) was reconsidered by a three-Judge Bench in the case of Vinod Kumarpetitioner/ v. Prem Lata., 2003 (2) RCR (Rent) 329 (SC) : 2003 (11) SCC 397 and the view taken by the Supreme Court in Rakesh Wadhawan's case (supra) has been reiterated. The contrary view taken in Rubber House v. Excelsior Needle Industries (P) Ltd.., 1989 (2) RCR (Rent) 530 (SC) : (1989-1) 95 P.L.R 584 and Rajinder Kumar Joshi v. Veena Rani, 1990 (2) RCR (Rent) 573 (SC) : (1990) 4 SCC 526 has been over-ruled.
14. When the facts of the present case are examined in the light of the principles laid down in Rakesh Wadhawan's case (supra) then it becomes evident that the Rent Controller had drawn a provisional order of assessment of rent on 31.5.2003 Thereafter the case was posted for 10.6.2003 for depositing the rent by the tenant-petitioners in accordance with the order dated 31.5.2003 On 10.6.2003, a request was made for grant of further time and the case was posted for depositing the arrears of rent for 24.7.2003 The tenant-petitioners failed to appear before the Rent Controller on that date and then their defence was struck of. As a result the ejectment of the tenant-petitioners was ordered on 12.8.2003 The Rent Controller has minutely followed the schedule and principles laid down by the Supreme Court in Rakesh Wadhawan's case (supra). Infact when the tenant-petitioner has requested for further time on 10.6.2003 there was no necessity to grant any time till 24.7.2003 because the judgment in Rakesh Wadhawan's case in para 30(4) (supra) states that on the failure of the tenant to comply with the provisional order of assessment of rent nothing remains to be done and an order for eviction must follow. The Rent Controller has even granted time by adjourning the case from 10.6.2003 to 24.7.2003 Therefore, there is no illegality committed by the Court below in passing the order dated 12.8.2003
15. In view of the above, the impugned order dated 14.6.2003 passed by the Rent Controller dismissing the application of the tenant-petitioner for setting aside the order dated 12.8.2003 does not suffer from any illegality because firstly no application under Order IX Rule 13 of the Code was maintainable as the tenant-petitioners were not proceeded against ex-parte. Moreover, it has been rightly observed by the Rent Controller that the order dated 12.8.2003 cannot be challenged by the tenant-petitioner before the Executing Court. The view taken by the Rent Controller is absolutely consistent with the principles laid down by the Supreme Court in Rakesh Wadhawan's case (supra) and Vinod Kumar's case (supra).
16. The other order passed by the executing Court also deserves to be upheld as the same has been passed in accordance with the view taken by the Supreme Court in the aforementioned two judgments in the cases of Rakesh Wadhawan and Vinod Kumar (supra).
17. It has been argued by Mr. J.S Chaudhary, the learned counsel for the tenant-petitioner that the order dated 31.5.2003 fixing the rate of rent and the arrears of rent, house tax, interest and costs became illegal because the fair rent under Section 4 of the Act was fixed by the Appellate Authority by partially modifying the order dated 22.5.2002 The afore-mentioned argument cannot be accepted because the order dated 31.5.2003 clearly shows that fair rent order passed by the Rent Controller on 22.5.2002 under Section 4 of the Act was taken into consideration when the order dated 31.5.2003 was passed. It is pertinent to mention that the tenant-petitioner has not tendered any rent before the Rent Controller by contesting the order dated 31.5.2003 Infact he filed an appeal against the order dated 12.8.2003 which was withdrawn on 18.11.2003 Therefore, the tenant-petitioner was under an obligation to comply with the order dated 31.5.2003 and should have contested the claim made by the landlady respondent if after final adjudication any amount in excess deposited by them was at variance with the provisional or interim order then according to the principles laid down in para 30(5) of Rakesh Wadhawan's case (supra), the Rent Controller might have directed the refund of the amount. If the amount deposited by them is found to be short or deficient then the Rent Controller might have passed a conditional order directing then to place the landlord in possession of the premises by giving a reasonable time to the tenant for paying or tendering the deficient amount failing which alone he was liable to be evicted. The compliance of the order would have saved them from eviction. Such being clear position in law subsequent variation in determination of the fair rent by the Appellate Authority on 10.9.2003 would not result into affording another opportunity to the tenant-petitioners for depositing the rent enabling them to save their eviction. The Division Bench of this Court in Harbilas Bansal's case (supra) on which reliance has been placed by the learned counsel does not come to the rescue of the tenant-petitioner because it does not lay down that the provisional order of assessment passed by the Rent Controller could be violated and still the tenant-petitioners could continue to enjoy the possession of a tenanted premises. The readiness and willingness to pay the rent now in accordance with the fair rent determined by the Appellate Authority in its order dated 10.9.2003 can also not be accepted because already two opportunities have been granted by the Rent Controller on 10.6.2003 and 24.7.2003 The tenant-petitioners have failed to deposit the arrears of rent in accordance with the provisional order of assessment dated 31.5.2003 Therefore, there is no merit in the argument raised by the learned counsel for the tenant-petitioners.
18. For the reasons stated above, both these petitions fail and are dismissed.
Petitions dismissed
Alert