Dilbagh Singh v. The Collector, Land Acquisition, Industries, Department, Punjab And Others.

Punjab & Haryana High Court
Mar 15, 2002
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Factual and Procedural Background

The appeal challenges an order dated 5.9.2000 by the learned Single Judge, which dismissed both the application for condonation of delay and the Regular First Appeal (R.F.A.) filed against the award of the District Judge, Kapurthala. The State of Punjab, by notification dated 24.9.1985 under Section 4 of the Land Acquisition Act, 1894, acquired 1100 acres of land across eight villages, including the appellant's land in village Rawal Bechirag, District Kapurthala. Compensation was awarded by the Land Acquisition Collector at specified rates. The appellant's application under Section 18 for enhancement of compensation was dismissed along with similar applications by the District Judge on 3.4.1996.

After a delay of approximately two years and five months, the appellant filed the R.F.A. under Section 54 of the Act, accompanied by an application under Section 5 of the Limitation Act seeking condonation of a 793-day delay. The appellant explained the delay citing a bona fide mistaken belief that all references arising from the acquisition notification would be decided simultaneously, and that the appellant’s brother was managing the case. The respondent contested these claims, asserting the appellant himself was aware and negligent in not filing within the prescribed period. The Single Judge dismissed the application and appeal, finding the delay inexcusable.

Legal Issues Presented

  1. Whether the delay of 793 days in filing the Regular First Appeal could be condoned under Section 5 of the Limitation Act.
  2. Whether the appellant's explanation for delay, based on a bona fide mistaken belief and the pendency of other similar appeals, constituted sufficient cause for condonation of delay.
  3. Whether the learned Single Judge erred in dismissing the application for condonation of delay and the appeal on grounds of negligence and lack of vigilance by the appellant.

Arguments of the Parties

Appellant's Arguments

  • The appellant was unaware of the passing of the award and only came to know through other landowners and after inquiries in 1998.
  • The bona fide mistaken belief that all references related to the acquisition would be decided together caused the delay.
  • The appellant’s brother was managing the case, and the appellant could not contact counsel earlier.
  • The pendency of numerous other appeals arising from the same acquisition notification should be considered sufficient cause for condonation of delay.
  • The Court should adopt a liberal approach in condoning delay, especially considering the appellant's rural background and the impact on livelihood.

Respondent's Arguments

  • The appellant himself was aware of the case, having appeared as a witness, and thus was negligent in not filing the appeal within the limitation period.
  • The explanation that the appellant's brother was managing the case is incorrect and a figment of imagination.
  • The appellant failed to show sufficient cause for condoning the inordinate delay of 793 days.
  • The appeal should be dismissed as not maintainable.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Collector, Land Acquisition, Anantnag and Anr. v. Mst. Katiji and Ors., A.I.R. 1987 S.C. 1353 Liberal approach in condonation of delay under Section 5 of the Limitation Act; courts should prioritize substantial justice over technicalities. The court adopted the precedent to hold that delay should be condoned liberally, especially for litigants from rural areas, rejecting the narrow and pedantic view of the Single Judge.
Ram Kishan and Anr. v. U.P. State Roadways Transport Corporation and Anr., (1994 Supp. (2) S.C.C. 507) Delay in filing can be condoned despite unconvincing explanation if substantial justice requires it. The precedent was cited to support the principle that delay should not automatically bar a litigant from pursuing a meritorious claim.
M.K Prasad v. P. Arumugam., (2001) 6 S.C.C. 176 Discretion under Section 5 of the Limitation Act must be exercised to advance substantial justice; delay condonation should not be denied solely due to lack of vigilance. The court relied on this precedent to emphasize that the appellant's failure to be vigilant should not oust him from litigation concerning valuable property.

Court's Reasoning and Analysis

The court analyzed the appellant's explanation and found that the delay was caused by a bona fide mistaken belief by the appellant's brother, who was managing the case, that all references arising from the acquisition would be decided together. The court rejected the respondent’s argument that the appellant’s personal appearance as a witness implied awareness and vigilance sufficient to bar condonation. Recognizing the rural context and the appellant’s limited legal knowledge, the court emphasized the necessity of a liberal approach in condoning delay, particularly when the case involves deprivation of livelihood.

Relying on the Supreme Court’s decision in Collector, Land Acquisition, Anantnag v. Mst. Katji, the court highlighted the elastic and justice-oriented nature of the term "sufficient cause" under Section 5 of the Limitation Act. The court noted that strict technical rules should not defeat substantial justice, especially when delay is not deliberate or due to culpable negligence. The pendency of several appeals arising from the same acquisition was also considered a valid ground for condonation.

Consequently, the court concluded that the learned Single Judge erred in dismissing the application for condonation of delay and the appeal.

Holding and Implications

The appeal is allowed. The order of the learned Single Judge dismissing the application for condonation of delay and the Regular First Appeal is set aside. The delay of 793 days in filing the R.F.A. is condoned. The R.F.A. is to be listed for hearing alongside other similar appeals.

The decision directly benefits the appellant by permitting the appeal to proceed despite the delay. It reinforces the principle that courts must adopt a liberal and justice-oriented approach in condoning delay, especially for litigants from rural backgrounds and in matters affecting livelihood. No new precedent is established; rather, the court applies and affirms existing Supreme Court authorities.

Show all summary ...

1. This appeal is directed against order dated 5.9.2000 vide which the learned Single Judge dismissed the application for condonation of delay as well as the Regular First Appeal filed by the appellant against the award of the District Judge, Kapurthala.

2. The facts necessary for deciding the appeal are that vide notification dated 24.9.1985 issued under Section 4 of the Land Acquisition Act, 1894 (for short, the Act), the State of Punjab acquired 1100 acres of land situated in eight different villages including the land of the appellant situated in village Rawal Bechirag, District Kapurthala. The Land Acquisition Collector awarded compensation at the following rates:-

Chahi - Rs 22691/- per acre Barani - Rs.13731/- per acre Gair Mumkin - Rs.12483/- per acre Application filed by the appellant under Section 18 of the Act for enhancement of compensation was dismissed by the District Judge, Kapurthala alongwith similar applications vide award dated 3.4.1996.

3. After 2 years and almost 5 months, the appellant filed R.F.A. under Section 54 of the Act alongwith an application under Section 5 of the Limitation Act for condonation of 793 days delay. The same were registered as RFA No.3024 of 1998 and C.M. No. 3596-Cl of 1998. In support of his prayer for condonation of delay, the appellant made the following averments:-

"2. That the State of Punjab vide notification dated 24.9.1985 had acquired 1100 acres of land situated in 8 villages including the village of the appellant. The Collector has announced the award on 22.1.1986 vide order No.3. The award regarding compensation of other villages was also announced on the same date. The land owners had sought references and the reference was sent in 1989. The reference sought by the appellants was registered as reference No. 25 of 22.9.1989. Another reference sought by appellant was registered as reference number 24 of 1989. The reference sought by land owners of village Manga Bodha was registered as reference No.29 of 1989. The appellants came to know about the judgment dated 4.5.1998 in the first week of June, 1998. The appellants made enquiries and came to know that the reference regarding their land has been decided on 3.4,1996. the appellants applied for the copy on 5.6.1998 and the copy was received on 6.6.1998. The High Court was closed for summer vacation and therefore the appeal was filed on 29.6.1998.

3. That the appellants could not file the appeal because the references arising out of the same notification were pending and the appellants were under the impression that all the cases were being decided together. The appeal could not be filed earlier because of the bona fide mistake that all the references would be decided together and could not contact the counsel as appellants brother was looking after the case.

4. That there were two cases regarding the land of the appellants' family. Besides the reference No.25 concerning the appellants there was another reference No. 24 of 1989 which was concerning the appellant as well as his brothers Jasbir Singh, Raghubans Singh, Satnam Singh and Gurcharan Singh. Raghubans Singh was looking after both the cases. Raghubans Singh was under the bona fide belief that all the references would be decided together. On learning that other references had been decided in May, 1998, Raghubans Singh enquired about reference Nos.24 and 25 and came to know that the same had already been decided on 3.4.1996. The delay, it is submitted, has occurred because of a bona fide mistaken belief of Raghubans Sjngh and is inadvertent."

4. On being noticed by the Court, respondent No. 2 filed reply to contest the application for condonation of delay by making the following averments:-

"3 & 4. That all the averments made in these paras are mis-statements are not based on true facts and circumstances of the cases. The reason given that the brother of the appellant/claimant was looking after the case is totally wrong and figment of imagination. It is the appellant/claimant himself who has stepped in the witness box and has made statement, which is the only evidence on record. This clearly shows that appellant/claimant was himself aware of the case and was therefore grossly negligent in not filing the appeal within the prescribed limitation period.

5. That appellant/claimant has been grossly negligent and has miserably failed to show any sufficient cause for condonation of inordinate delay of 793 days.

5. After hearing counsel for the parties, the learned Single Judge dismissed the application for condonation of delay as well as the main appeal by recording the following observations:-

"After hearing the learned counsel for the parties this Court is of the considered opinion that delay of 793 days in filing the present appeal cannot be condoned from any angle of vision or on any parameter.

It Was submitted on behalf of the appellant that a huge area of 1100 acres was acquired by single Notification. The appellant was not aware about the passing of the award by the Court. He came to know about the passing of the award only through other land-owners. The law helps the vigilant and not to the person who wants to sleep over his rights. The petitioner was represented before the Court through his lawyer. He should have contacted his lawyer from time to time about the passing of the award.

It was also submitted by the learned counsel for the appellant that against this very notification several appeals are pending in the High Court. This is not a precedent to the present appeal. Every case is to be considered on it s own merit. The appeal has not been filed within limitation and sufficient cause has not been explained under Section 5 of the Limitation Act. The consequences are very fatal."

6. Sh. Sarjit Singh argued that the view taken by the learned Single Judge on the issue of condonation of delay is too narrow and pedantic and is contrary to the law laid down by the Supreme Court in Collector, Land Acquisition, Anantnag and Anr. v. Mst. Katiji and Ors., A.I.R. 1987 S.C. 1353, and therefore, the impugned order may be set aside. He stated that a large number of R.F.As. filed against the awards passed by the District Judge in relation to the acquisition in question are pending for hearing and this, by itself, should have been treated as sufficient cause for condonation of delay in filing the R.F.A.

7. Sh. Puneet Jindal supported the order under challenge and argued that even though the recent decisions of the Supreme Court suggest that the Court should adopt a liberal approach in the matter of condonation of delay, the appellant should not be given any relief because the explanation given by him for delay in filing of the R.F.A. was wholly unsatisfactory. Learned counsel submitted the appellant's plea of ignorance about the proceedings was rightly not entertained by the learned single Judge because he had appeared as a witness in support of his claim. He, however, conceded that a number of R.F.As. arising out of the awards passed by the District Judge, Kapurthala in relation to the same acquisition are pending in this Court. Sh, Jindal gave out number of one of such R.F.A. as 3259 of 1998.

8. Mrs. S.K. Bhatia, learned Deputy Advocate General, Punjab supported the arguments of Sh. Jindal and submitted that the L.P.A. may be dismissed as not maintainable.

9. We have given serious thought to the respective arguments. In our opinion, learned counsel for the appellant is correct in his submission that the view taken by the learned Single Judge on the issue of condonation of delay is contrary to the liberal approach reflected in the recent decisions of the Supreme Court and, therefore, the impugned order deserves to be set aside. The solitary reason assigned by the learned Single Judge for declining the appellant's prayer for condonation of delay appears to be that he had not contacted his lawyers from time to time. In this context, it is important to bear in mind that majority of people living in the rural areas of the country are illiterate and ignorant of their rights. They are also not aware of this intricacies of law and proceedings in the Courts and Tribunals. Most of the time, they are busy in earning their livelihood and suffer injustice at the hands of all and sundry including the State. Therefore, while considering the plea for condonation of delay raised by a peasant or litigant coming from rural area, the Court has to adopt an extremely liberal approach, more-so when the case involves depriving the applicant of his source of livelihood. If the old and antiquated rule that each day's delay should be satisfactorily explained is applied in such cases, then grave injustice would be done to a majority of population living in rural India and persons like the appellant would be deprived of their legitimate right to seek justice.

10. In Collector, Land Acquisition, Anantnag v. Mst. Katji (supra) the Supreme Court made a departure from the old school of thought on the interpretation of the expression sufficient cause appearing in Section 5 of the Limitation Act and held that the courts should adopt liberal approach in condoning the delay. This is clearly reflected in the following portions of the judgment:

"The legislature has conferred the power to condone delay by enacting Section 5 of the Indian Limitation Act of 1963 in order to enable the courts to do substantial justice to parties by disposing of matters on merits. The expression "sufficient cause" employed by the legislature is adequately elastic to enable the courts to apply the law in a meaningful manner which subserves the ends of justice that being the life-purpose for the existence of the institution of courts. It is common knowledge that this court has been making a justifiably liberal approach in matters instituted in this Court. But the message does not appear to have percolated down to all the other courts in the hierarchy. And such a liberal approach is adopted on principle as it is realised that:

1. Ordinarily a litigant does not stand to benefit by lodging an appeal late.

2. Refusing to condone delay can result in a meritorious matter being thrown out at the very threshold and cause of justice being defeated. As against this when delay is condoned the highest that can happen is that a cause would be decided on merits after hearing the parties.

3. "Every day's delay must be explained" does not mean that a pedantic approach should be made. Why not every hour's delay, every second's delay ? The doctrine must be applied in a rational common sense pragmatic manner.

4. When substantial justice and technical considerations are pitted against each other, cause of substantial justice deserves to be preferred for the other side cannot claim to have vested right in injustice being done because of a non-deliberate delay.

5. There is no presumption that delay is occasined deliberately, or on account of culpable negligence, or on account of male fides. A litigant does not stand to benefit by resorting to delay. In fact he runs a serious risk.

6. It must be grasped that judiciary is respected not on account of its power to legalze injustice on technical grounds but because it is capable of removing injustice and is expected to do so.

Making a justice-oriented approach from this perspective, there was sufficient cause for condoning the delay in the institution of the appeal."

11. In Ram Kishan and Anr. v. U.P. State Roadways Transport Corporation and Anr.,'2- 1994 Supp. (2) S.C.C. 507, their Lordships condoned the delay in filing the application for compensation before the Motor Accident Claims Tribunal and remanded the case despite the fact that the story put forward by the appellants was not found convincing.

12. In M.K Prasad v. P. Arumugam., (2001)6 S.C.C., 176), their Lordships of the Supreme Court reiterated the liberal approach in condonation of delay by recording the following observations:

"In construing Section 5 of the Limitation Act, the court has to keep in mind that discretion in the section has to be exercised to advance substantial justice. The court has a discretion to condone or refuse to condone the delay as is evident from the words "may be admitted" used in the section.

XX XX XX XX XX XX XX XX XX Even though the appellant appears not to be as vigilant as he ought to have been, yet his conduct does not, on the whole, warrant to castigating him as an irresponsible litigant. He should have been more vigilant but his failure to adopt such extra-vigilance should not have been made a ground for ousting him from the litigation with respect to the property, concededly to be valuable. While deciding the application for setting aside the ex pane decree, the court should have kept in mind the judgment impugned, the extent of the property involved and the stake of the parties."

13. We may now revert to the case in hand. A perusal of the averments contained in the application for condonation of delay in filing the R.F.A. shows that the case of the appellant was being pursued by his brother Raghubans Singh, who remained under a mistaken impression that all the references arising out of the acquisition of 1100 acres of land would be decided simultaneously. Therefore, he did not try to enquire about the decision of the references filed by the appellant and his family members. The averments contained in the application were supported by the affidavit of Raghubans Singh. In the reply filed on behalf of respondent No. 2, an attempt has been made to discredit the version of the appellant by saying that he had himself appeared in the witness box. In our opinion, the appearance of the appellant as a witness cannot lead to an inference that he was himself pursuing the matter before the District Judge. That apart, he and his brother cannot be accused of lack of vigilance because the latter remained under a bona fide impression that all the references arising out of the same acquisition would be decided by open award.

14. We are further of the view that the pendency of appeals arising out of the awards passed by the District Judge in other cases relating to the same acquisition constituted a valid ground for condonation of delay in filing of the R.F.A. by the appellant and the learned Single Judge erred in declining his prayer.

15. Hence, the appeal is allowed. The order of the learned Single Judge is set aside. The delay in filing of the R.F.A. is condoned. The R.F.A. may now be listed for hearing before the learned Single Judge along with other similar appeals.