Satish Kapur And Another v. State Of Haryana And Another

Punjab & Haryana High Court
Jan 22, 1982
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Structured Summary of the Opinion

Factual and Procedural Background

Two notifications under Ss. 4 and 6 of the Land Acquisition Act (dated Nov. 4, 1977 and Oct. 24, 1980 respectively) were issued by the State Government for the acquisition of 174.46 acres of land, which included the petitioners' land within the revenue estate of Atmadpur, Tahsil Ballabgarh, District Faridabad. The petitioners challenged those notifications in Writ Petitions Nos. 371, 309 and 372 of 1981 primarily on two grounds: (i) non-compliance with S.4(1) (alleged failure to publish the substance of the S.4 notification in the locality simultaneously with its publication in the Gazette), and (ii) absence of bona fide need — asserting the notifications were issued to "peg down" prices and thus were an abuse of the acquiring authority's power.

In response the respondents stated that the substance of the S.4 notification was published in the locality on Nov. 9, 1977, evidenced by an entry in the Rapat Roznamcha No. 104 (dated Nov. 9, 1979) recorded with the Halqa Patwari, that acquisition proceedings were in progress, and that compensation would be paid before taking possession.

Legal Issues Presented

  1. Whether the State complied with S.4(1) of the Land Acquisition Act by publishing the substance of the S.4 notification in the locality simultaneously with its Gazette publication, and whether any unexplained delay between those publications renders the proceedings void.
  2. Whether the issuance of the notifications (including an S.6 notification issued shortly before the statutory three-year expiry) was bona fide, or whether they were issued for a collateral purpose of pegging down the market price of the land — i.e., whether the notifications constituted an arbitrary or abusive exercise of the power of compulsory acquisition.
  3. Whether the long delay and absence of subsequent steps (such as issuing S.9 notice or making an award) deprived the petitioners of reasonable compensation and justified quashing the notifications.
  4. Whether the petitioners are barred by laches from bringing these petitions given the passage of time since the notifications.

Arguments of the Parties

Petitioners' Arguments

  • The substance of the S.4 notification was not published in the locality simultaneously with the Gazette publication; an entry in the Patwari's Roznamcha is alleged to be a mere paper transaction and disputed.
  • The S.6 notification was issued only ten days before the statutory three-year period expired; an earlier S.4 notification dated Oct. 1, 1973 had lapsed without follow-up, and no steps (including S.9 notices or assessment of compensation) have been taken since the present notifications; therefore the notifications were issued to freeze market prices (peg down) rather than for genuine acquisition needs — an abuse of power.
  • Authorities must proceed expeditiously; delays have the effect of freezing compensation to the date of the S.4 notification (per S.23(1)) and ignoring post-notification improvements (per S.24), thereby depriving landowners of reasonable compensation.
  • Even in light of Supreme Court guidance relied upon by respondents, those authorities are not entitled to deliberate delay; the statutory time-limit is an outer limit, not a license to delay without justification.
  • Relied upon precedents (Man Singh; Naval Singh; Ram Krishan Shroff) to support quashing where similar delay or non-action occurred.

Respondents' Arguments

  • The substance of the S.4 notification was published locally on Nov. 9, 1977, as evidenced by the Rapat Roznamcha entry recorded with the Halqa Patwari; acquisition proceedings are in progress and compensation will be paid before possession.
  • Reliance on the Supreme Court decision in Gujarat State Transport Corporation v. Valji Mulji Soneji (AIR 1980 SC 64): where the statutory power is exercised within the prescribed period, the Court cannot examine the question of delay; hence the delay in issuing S.6 (about three years) cannot be impugned if within statutory limits.
  • As a last resort, respondents contended the petitioners be non-suited for laches, citing observations in State of Mysore v. V.K. Kangan (AIR 1975 SC 2190).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Rattan Singh v. State of Punjab (Full Bench), (1976) 78 Pun LR 545 : AIR 1976 Punj and Har 279 Delay between Gazette publication and local publication of substance of S.4 notification renders proceedings void. The Court relied on this Full Bench ruling to support the proposition that unexplained delay between Gazette and local publication vitiates the acquisition proceedings.
Murari Lal Bhargava v. State of Haryana, 1977 Rev LR 337 (Division Bench) A delay of six days between Gazette publication and local publication, without explanation, justified quashing the notifications. Cited as authority showing even a short unexplained delay may lead to quashing; used to reinforce the petitioners' complaint about unexplained delay.
Man Singh v. State of Punjab, ILR (1980) 2 Punj and Har 403 Authoritative support for quashing acquisition notifications where the state's omissions and inaction result in arbitrariness and deprivation of reasonable compensation. The Court treated Man Singh as a supporting precedent for quashing notifications in circumstances involving delay and non-action by authorities.
Naval Singh v. State of Haryana, Civil Writ No. 4230 of 1981 (decided Jan. 11, 1982) Distinguished the facts of Valji Mulji Soneji; where the State itself delays, the ratio in Valji Mulji may not apply; Division Bench quashed Ss.4 and 6 notifications in similar circumstances. The Court relied on the Division Bench observations in Naval Singh to show that Valji Mulji's ratio is fact-specific and to support quashing where the State's inaction caused delay.
Ram Krishan Shroff v. State of Haryana, Civil Writ No. 1028 of 1981 (decided Aug. 24, 1981) Example where the Collector's award under S.11 and the impugned Ss.4 & 6 notifications were quashed for related reasons. Cited to demonstrate prior instances in which awards and notifications were quashed due to similar problems of delay and arbitrary exercise.
Gujarat State Transport Corporation v. Valji Mulji Soneji, AIR 1980 SC 64 Where the statute prescribes time and the authority acts within that period, the Court should not re-examine alleged delay; context-specific Supreme Court observations. Respondents relied on this Supreme Court decision to argue delay could not be impugned if steps fell within statutory time; the Court acknowledged the authority but distinguished its facts and held it did not preclude relief here.
Ambalal Purshottam v. Ahmedabad Municipal Corporation, AIR 1968 SC 1223 Affirms that after issue of Ss.4 and 6 notification, proceedings for determination of compensation should follow without reasonable delay. The Court quoted this passage and relied on it to underscore the statutory expectation of expeditious determination of compensation and to support quashing where authorities allowed matters to drift.
State of Mysore v. V.K. Kangan, AIR 1975 SC 2190 Contains observations on laches (delay) as a consideration in equity and writ jurisdiction. Respondents invoked it to support a laches defence; the Court considered but rejected the laches argument on the facts here.

Court's Reasoning and Analysis

The Court conducted a step-by-step analysis grounded in the record and binding or persuasive precedent cited in the opinion:

  1. Publication under S.4(1): The Court observed that even if it accepted the respondents' contention that the substance of the S.4 notification was published locally (per the Patwari's Roznamcha entry), there was no explanation for the delay between Gazette publication and the alleged local publication. The Court treated an unexplained delay as fatal to the validity of the proceedings, relying upon Full Bench and Division Bench precedents that held similar delays vitiate acquisition notifications.
  2. Timing and purpose of S.6: The Court noted S.6 was issued only ten days before the expiry of the three-year statutory period and that an earlier S.4 notification dated Oct. 1, 1973 had lapsed for want of S.6. Thereafter no material steps (no S.9 notices, no valuation, no award) had been taken to complete acquisition. On these facts the Court accepted the petitioners' submission that the notifications had the practical effect of freezing the market value of the land to the date(s) of S.4 publication (citing S.23(1) and S.24(7th)), thereby depriving owners of reasonable compensation.
  3. Duty to proceed expeditiously: The Court emphasised the scheme and intendment of the Act — notifications under S.6 must be followed by proceedings for determination of compensation without reasonable delay. The Court drew support from Ambalal Purshottam and other authority for this proposition and explained the Land Acquisition Officer's role is essentially to assess market value and pass an award; absent obstruction by landowners, this process should not ordinarily take long.
  4. Distinguishing Valji Mulji: The Court acknowledged the respondents' reliance on Gujarat State Transport v. Valji Mulji Soneji, but considered that decision to be fact-specific. The Court accepted that when the State acts within prescribed statutory time, courts should not re-examine delay; however, where the State itself causes inaction or unexplained delay and the landowners have not contributed to delay, the Valji Mulji ratio is not applicable. The Court referred to the Division Bench in Naval Singh which reached a similar distinction.
  5. Laches: The Court rejected the respondents' plea of laches. It noted that delay in approaching the Court is not automatically fatal; laches is a factor to be weighed (often at the motion stage), and here the petitioners were justified in awaiting the lapse of earlier notifications and in challenging prolonged inaction that worked to their prejudice.
  6. Conclusion from analysis: Given the lack of explanation for delay in local publication and subsequent inaction that froze market values (with no S.9, valuation or award), the Court found the conduct of the acquiring authorities to be arbitrary and a deprivation of reasonable compensation.

Holding and Implications

Holding: The petitions were allowed. The Court quashed the impugned notifications under Ss. 4 and 6 of the Land Acquisition Act insofar as they related to the petitioners' land. The petitioners were awarded costs fixed at Rs. 300 per petition.

Implications:

  • Direct effect on the parties: The impugned notifications are quashed as to the petitioners' land and the petitioners receive costs (Rs. 300 per petition).
  • On broader law: The Court's order applies the principles and precedents it cited (including Supreme Court and Division Bench authorities) to the facts before it; the opinion does not purport to establish a new general precedent beyond applying and distinguishing existing authorities. The decision underscores that acquisition notifications and subsequent procedures must not be used to "freeze" market values by unexplained delay, and that authorities must proceed expeditiously to determine compensation unless delay is caused by the landowners themselves.
Petitions allowed.
Show all summary ...

Two notifications issued by the State Government under Ss. 4 and 6 of the Land Acquisition Act (for short the Act) on Nov. 4, 1977 and Oct. 24, 1980, respectively, for the acquisition of 174.46 acres of land including the land of the petitioners in these Writ Petitions Nos. 371, 309 and 372 of 1981, situated within the revenue estate of Atmadpur, Tahsil Ballabgarh. District Faridabad, are impugned primarily on the grounds that (i) there has been no compliance of the provisions of sub-sec. (1) of S. 4 of the Act in as much as substance of notification has not been published in the locality concerned simultaneously with its publication in the Gazette and (ii) there was no bona fide need for acquiring the property in question and the notifications had been issued for a collateral purpose of pegging down the prices to the date of the notification and thus amounted to abuse of power.

2. On behalf of the respondents, it has been explained in their return that the substance of the notification issued under S. 4 of the Act was published on Nov. 9, 1977 and this fact is evidenced by the Rapat Roznamcha No. 104 dated Nov. 9, 1979, recorded with the Halqa Patwari; acquisition proceedings are in progress and the petitioners would be paid due compensation in accordance with law before taking over the possession from them.

3. After hearing the learned counsel for the parties I find merit in the above noted two contentions raised by the petitioners. Even if the stand of the respondents to the effect that the substance of the notification was published in the locality concerned is accepted as correct - though it is seriously being disputed by the learned counsel for the petitioners with the allegation that the entry in the Roznamcha of the Patwari is only a paper transaction - still I find no explanation whatsoever for the delay that has occurred between the dates of the publication of the notification in the Gazette and the alleged publication of its substance in the locality concerned. In the absence of any such explanation, the proceedings emanating from the impugned notification are obviously rendered void. This has been so ruled by a Full Bench of this Court in Rattan Singh v. State of Punjab, (1976) 78 Pun LR 545 : (AIR 1976 Punj and Har 279). Yet in another Division Bench judgement of this Court in Murari Lal Bhargava v. State of Haryana, 1977 Rev LR 337, the delay of six days between the two dates i.e, the date of publication in the gazette and in the locality concerned, in the absence of any explanation on the part of the acquiring authorities for the same, was found to be enough to quash the impugned notifications.

4. In support of his second contention, the learned counsel relies on the following indisputable facts. The impugned notification under S. 6 was issued just ten days before the expiry of the statutory period of three years from the issuance of the notification under S. 4 of the Act. Earlier to the issuance of the notification under Sec. 4 of the Act on Nov. 4, 1977, a similar notification had been issued on Oct. 1, 1973 but that notiflcation automatically lapsed as it was not followed by a notification under S. 6, within the prescribed period of three years. No further action except the publication of the two notifications has been taken by the authorities concerned to complete the acquisition proceedings either till the filing of these petitions or even till today. So much so, even a notice under S. 9 of the Act has not been issued to the landowner-claimants, what to talk of the assessment of compensation payable to them. It is on the basis of these premises that the learned counsel maintains that the sole purpose of issuing these two impugned notifications was to peg down the prices to the date of notification under S. 4 of the Act for future acquisition of this land. This abuse of power of compulsory acquisition, according to the learned counsel, cannot possibly be allowed. The delay or non-action on the part of the respondent authorities in completing the acquisition proceedings is obviously indicative of the fact that there was no need to acquire the land on the date it was so notified, that is, Nov. 4, 1977. In support of this contention, the learned counsel for the petitioners squarely relies on the following judgements of this Court:—

1. Man Singh v. State of Punjab, ILR (1980) 2 Punj and Har 403.

2. Civil Writ No. 4230 of 1981 (Naval Singh v. State of Haryana) decided on Jan. 11, 1982.*

3. Civil Writ No. 1028 of 1981 (Ram Krishan Shroff v. State of Haryana) decided on Aug. 24, 1981.

5. On behalf of the respondents, however, it is contended in the light of the observations of their Lordships of the Supreme Court in Gujarat State Transport Corporation v. Valji Mulji Soneji, AIR 1980 SC 64 that the delay of about three years that has occurred in the issuance of the notification under Sec. 6 after the publication of the notification under S. 4 of the Act, cannot be taken notice of for the reason that the statute itself confers powers and prescribes time within which this power could be exercised and since the statutory power has been exercised within the prescribed period, the Court cannot examine the question of delay and record a finding that there was unreasonable delay in the exercise of the power by the respondent authorities.

6. Realising the force of the observations of the Supreme Court in the abovenoted judgement, the learned counsel for the petitioners explains that (i) the same are only based on the facts of that case and their Lordships do not lay down as a general rule that the State authorities are entitled to deliberately delay the issuance of the notification under S. 6 of the Act for three years after the publication of the notification under S. 4 of the Act and (ii) the phraseology of the first proviso to sub-sec. (i) of S. 6 of the Act which makes it imperative for the acquiring authorities to publish the declaration under S. 6 within a period of three years from the publication of the notification under S. 4 of the Act, is in the negative form; thereby injuncting the acquiring authorities not to delay the publication for more than three years. This, according to the learned counsel, lays down the outer time limit for the publication of the notification under S. 6 of the Act and it does not mean that the authorities are entitled to delay this publication for that much period without any justification or any basis. The learned counsel maintains that even if an executive authority has the jurisdiction to acquire the land of a landowner, still the power has to be exercised in a manner which does not render it arbitrary. According to him, the respondent authorities are under an obligation to complete the acquisition proceedings within a reasonable time and without any unjustifiable delay so that the landowner gets a reasonable compensation for his land. He points out that the principle of awarding compensation is based on the right of the owner to be indemnified by the community for whose benefit he is being deprived of the property against his will. Compensation would essentially mean a just equivalent of what the owner has been deprived of. In other words, the owner who is deprived of his property should be enabled by the compensation awarded to him to place himself in substantially the same position in which he was before the acquisition. He further asserts that this principle has to be kept in mind by the respondent authorities and this is more so in the present day conditions when the prices of lands around urban areas are witnessing a phenomenal rise and maintain an ever-increasing trend.

7. In support of his first contention, the learned counsel relies on the observations of the Division Bench of this Court in Naval Singh's case (supra). In somewhat similar circumstances, when an argument was raised by the State counsel to the effect that no period of limitation has been prescribed for determining the compensation and giving of an award the learned Judges observed after noticing the above noted judgement of the Supreme Court as follows:—

“However, the facts in that case were entirely different. In that case, the notification under S. 4 of the Act was issued on Oct. 10, 1952, and the following action was taken by the State Government expeditiously within less than a year by issuing a notification under S. 6 on Aug. 14, 1953. The landowners filed a suit challenging the notifications. They lost in different Courts but continued pursuing their remedies and the matter was ultimately decided in the Supreme Court in 1963, whereafter action was taken for determining the compensation. So, it was the landowner who had delayed the proceedings and the State was not at fault. The ratio of this case will not be applicable to the facts of the present case.”

The learned Judges of the Division Bench quashed the impugned notification under Ss. 4 and 6 of the Act on the basis of the earlier judgement in Man Singh's case, (ILR (1980) 2 Punj and Har 403) (supra).

8. After giving thoughtful consideration to the entire matter, I feel that in view of the observations of their Lordships of the Supreme Court in para 16 of the judgement, though hardly any scope has been left - at least before me - to examine the above noted first submission of the learned counsel in any great depth, yet I find that the given facts and circumstances preceding and following the two notifications in the case in hand, do justify the learned counsel's submission to the effect that the omissions and commissions of the respondent authorities have resulted in arbitrariness and deprivation of a reasonable compensation for the acquired land. As has already been pointed out, there is absolutely no explanation for the non-taking of any steps subsequent to the issuance of the impugned notification under S. 6 of the Act. Neither any notice under S. 9 of the Act asking the petitioners to file their claim for compensation payable to them for the land sought to be acquired has been issued nor has any step been taken towards the completion of the acquisition. It is obvious that the impugned notification under S. 4 of the Act was issued four years ago and in the light of the provisions of S. 23(1) of the Act, compensation payable to the petitioners is the ‘market value’ of the land on that date. This too has to be paid only after the passing of the award. It is equally true that the possession is to be taken from the petitioners after the passing of the award and till then they are entitled to reap the benefits from the land, yet it cannot possibly be denied that the issuance of this notification did have the effect of freezing the market price of the land. It resulted in two ways; firstly, the market value of the land to be acquired was to be determined on the date of the notification under S. 4(1) of the Act and secondly, any outlay or improvements on or disposal of the land acquired commenced, made or effected without the sanction of the Collector, after the date of the publication of the notification under S. 4(1) was to be ignored in determining the compensation (see Section 24 seventhly). Not only this the earlier publication of a similar notification under S. 4 of the Act on Oct. 1, 1973, also had a similar effect. Thus it is patent that what is going to be paid to the petitioners ultimately - when it is going to be paid is not as yet certain - would virtually be the price of the land as it existed on October 1, 1973. It cannot be gainsaid that the scheme and intendment of the Act is that the award should be passed as early as possible in the circumstances of the case. It can hardly be denied that over the last several years there has been a substantial rise in the prices of agricultural land, urban vacant sites and immoveable properties. In the case of major towns and cities the increase has been phenomenal. If the land acquisition authorities are allowed to issue a notification under S. 4(1) of the Act and then to wait and ultimately pay compensation as and when they please on the basis of the market price of the land as on the date of the notification under S. 4 of the Act, the said compensation can hardly represent a reasonable and fair compensation. This attitude of the acquiring authorities cannot possibly be countenanced. Procedure under the Act is very simple in nature. Questions of title or disputed claim can neither be considered nor adjudicated upon by the authorities concerned. The Land Acquisition Collector has only to assess the market price of the acquired land and his award ultimately is only in the nature of an offer made by the State. All that the Land Acquisition Officer is required to do under the Act after the publication of the notification under S. 6 of the Act is to prepare a statement of valuation and determine what is the reasonable price payable for the land and then to pass an award on that basis. This should not ordinarily take much of time. It is of course a different matter if the landowners themselves obstruct the proceedings and cause delay by resorting to various remedies in Courts as was the case before the Supreme Court in Valji Mulji Soneji's case, (AIR 1980 SC 64) (supra). In such a case they cannot be heard to complain. But where the landowners have not contributed to the delay in any manner, the Land Acquisition Officer cannot sleep over the matter and take his own time in passing the award. The statutory power conferred on the State by the Act, viz. the power to acquire the land compulsorily should be exercised reasonably and fairly which necessarily means that the award must be passed with reasonable expedition. As has already been pointed out in the cases in hand there is absolutely no explanation on behalf of the respondent authorities for the delay that has taken place in the completion of the acquisition proceedings or the passing of the award. In the absence of any such justifiable reason for the delay that has taken place, the action of the respondent authorities is undoubtedly rendered unreasonable and arbitrary exercise of power. The impugned notifications could not be issued for the purpose of pegging down or freezing the price as the case is found to be and then wait for a convenient and opportune time to pass an award - such a line of thinking and course of conduct is alien to the scheme and intendment of the Land Acquisition Act. This is well supported by the following observations of the Supreme Court in Ambalal Purshottam v. Ahmedabad Municipal Corporation, AIR 1968 SC 1223 (at p. 1227):—

“We are not hereby to be understood as suggesting that after issue of the notification under Ss. 4 and 6 the appropriate Government would be justified in allowing the matters to drift and to take in hand the proceedings for assessment of compensation whenever they think it proper to do. It is intended by the scheme of the Act that the notification under S. 6 of the Land Acquisition Act must be followed by a proceeding for determination of compensation without any reasonable delay…..”

Keeping the above noted principle in view in Ram Kishan Shroff's case (supra). Dhillon, J. even quashed the award given by the Collector under S. 11 of the Act along with the impugned notifications under Ss. 4 and 6.

9. As a last resort, the learned counsel for the respondents urges that the petitioners be non-suited on the ground of laches. He maintains that considerable delay has occurred in the filing of this petition since the publication of the impugned notifications. In support of this contention of his he relies on certain observations of the Supreme Court in State of Mysore v. V.K Kangan, AIR 1975 SC 2190. In view of the facts and circumstances of this case I do not find any merit in this submission. Firstly, it is to be noticed that the delay in approaching the Court is not by itself fatal since there is no law of limitation obliging a person to approach a Court within a particular time. Laches is one of the considerations which deserves to be given weight in exercise of the jurisdiction under Art. 226 of the Constitution of India and this consideration has primarily to be applied at the motion stage, that is, when the petition is admitted to a hearing. Moreover in the type of cases in hand where the acquisition proceedings have been kept pending for a number of years and there being no end in view, the relief is sought to be granted on the ground of inordinate delay on the part of the Land Acquisition Officer in finalising the proceedings. In such a case I am unable to see as to how the respondents can turn round and accuse the petitioners of laches. Furthermore I find that the petitioners were well justified in awaiting the fall or lapsing of the impugned notification under S. 4 of the Act in view of the fact that the respondent authorities had allowed their earlier notification dated Oct. 1, 1973 to exhaust itself with the expiry of three years, from the date of its publication.

10. For the reasons recorded above, I allow these petitions and quash the impugned notifications so far as these relate to the petitioners' land. The petitioners would also be entitled to costs of these petitions which are assessed at the rate of Rs. 300/- per petition.

Petitions allowed.