Zila Parishad v. Banarsi Dass Kapur

Punjab & Haryana High Court
May 23, 1972
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Structured Summary of the Opinion (Sharma, J.)

Factual and Procedural Background

The plaintiff, an approved contractor, submitted a tender on May 3, 1954 for work (metalling and tarring of Jagadhri-Bilaspur road miles 6 to 8/2260 and supply of burnt bricks, stone-metal etc.) to the District Board Ambala (now Zila Parishad Ambala). The Board accepted the tender and sanctioned it on June 14, 1954. Under the agreement the plaintiff was required to give security for due performance; he opened a Savings Fund Account in respect of Rs. 7,033/- (on 4/5 August 1954) in the Ambala City Post Office and pledged it with the Board. The Chairman of the Board was authorised to withdraw amounts from that account upon certain events showing plaintiff's failure to perform.

The plaintiff claims to have completed the work as per the agreement and was paid the bills submitted. On demanding return of the security deposit after completion, he was informed that the amount had been adjusted as compensation: Rs. 6,076 for alleged delay in supplies of material and Rs. 957 for alleged delay in completion/consolidation, totalling Rs. 7,033/-.

The defendant-Board refused to refund. The parties referred the matter to the Superintending Engineer, Ambala, as sole Arbitrator. The Arbitrator held he had no jurisdiction regarding the Rs. 6,076 item (delay in supplies) but awarded that Rs. 947 of the Rs. 957 be refunded (allowing Rs. 10 as valid compensation). The plaintiff then filed a suit in the Court of Subordinate Judge First Class, Jagadhri (the opinion records the suit as claiming "a sum of Rs. 706/-" in the text).

The defendant filed a written statement denying performance within time, alleging extended but uncomplied deadlines, insufficient and defective material supplied by plaintiff, and asserted that time was the essence and compensation was properly levied. The trial Court framed multiple issues (enumerated in the opinion) and ultimately decided most issues for the plaintiff, awarding a decree for recovery of Rs. 6,076/- with costs. The Board appealed to this Court. The principal ground of challenge before this Court was the question of limitation (Issue No. 10-A).

Legal Issues Presented

  1. Whether the plaintiff supplied the material within the stipulated period or within any period extended by the defendant.
  2. If not, whether the delay in supply of material was caused for no fault of the plaintiff and to what effect.
  3. Whether such delay was caused on account of defendant's fault.
  4. Whether the defendant had waived such delay.
  5. Whether the condition imposing penalty on the plaintiff for delay in supply of material was penal and as such void.
  6. Whether time was not the essence of the contract for supply of material.
  7. Whether the defendant was justified in imposing a penalty of Rs. 6,076/- on the plaintiff for the delay in supply of material; and if not, what should be the correct amount.
  8. Whether the said penalty had been validly imposed by or on behalf of the defendant.
  9. Whether the defendant served a show-cause notice on the plaintiff before imposing the penalty of Rs. 6,076/- and if not, the effect of that omission.
  10. Whether, and if so to what amount, the plaintiff is entitled on account of interest.
  11. Whether the suit is within time (Issue No. 10-A relating to limitation).
  12. Relief (final relief to be granted).

Arguments of the Parties

Plaintiff's Arguments

  • The act of the defendant in levying the compensation was arbitrary, capricious and unilateral.
  • No details of the said compensation had been explained to the plaintiff.
  • The contractual term authorising the defendant to impose compensation was penal and inoperative because time was not the essence; hence no compensation could be imposed.
  • The defendant had waived the terms and was estopped from levying any compensation on that account.
  • The alleged compensation was not imposed by any valid resolution of the District Board but by the Chairman in his individual capacity; the Chairman had no such authority and hence the order was illegal and not binding.
  • The alleged delay in supply of material was not the plaintiff's fault but resulted from the defendant's failure to perform (not constructing roads in time over which material was to be carried).
  • If any compensation were leviable it could be levied only in respect of the part of the contract that was delayed, not the entire contract.

Defendant's (Board's) Arguments as Pleaded at Trial

  • The plaintiff was to supply stone-metal and burnt bricks by January 5, 1955; this date was extended by one month and ten days, but the plaintiff still failed to complete the job and finished supply only on March 28, 1955.
  • The screenings were insufficient — the plaintiff supplied only 2,204 cft against contracted 4,404 cft; material was mixed with earth and contained only one half of screening.
  • Time was the essence of the contract and the plaintiff's delay rendered him liable for compensation which was properly levied.

Contentions Raised on Appeal (Limitation Issue)

  • Appellant's counsel: If the Board refused to return the security, the plaintiff's case is for compensation for breach of contract and thus governed by Article 115 (three years) of the Limitation Act; limitation runs from the breach/performance date.
  • Respondent's counsel: The security deposit remains a deposit in law and the suit is governed by Article 145 (thirty years) of the Limitation Act; alternatively, if Article 145 does not apply, the residuary Article 120 (six years) should apply.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Nagendra Nath Day v. Suresh Chandra Dey, AIR 1932 PC 165 Fixation of limitation periods is somewhat arbitrary; equitable considerations are out of place; "strict grammatical meaning" of words is the safe guide when construing limitation provisions. The Court relied on this principle to interpret competing Articles of the Limitation Act strictly by their language when deciding whether the suit was for compensation or for recovery of a deposit.
Lala Gobind Prasad v. Chairman of Patna Municipality, (1907) 6 Cal LJ 535 Money deposited as security for faithful discharge of duties can be treated as "deposit" within Article 145; movable property in Article 145 includes money. The Court cited this case to support the view that security deposits of money fall within Article 145 and that there is no principled reason to give different limitation periods to similar deposits.
Gannon Dunkerly & Co. Ltd. v. Western India Theatres Ltd., 1961-65 Cal W Notes 504 A deposit made as security for due performance remains a deposit; cause of action for refund is the nature of the deposit, not breach of contract; Article 145 applies (fallback Article 120 if 145 inapplicable). The Court relied on the reasoning that the essence of the plaintiff's cause of action is refund of a deposit, supporting applicability of Article 145 (or Article 120 if not), and quoted the conclusion that Article 145 is applicable.
Ahilyamba Chatram v. R. Subramania Ayyar, AIR 1954 Mad 101 Suit by employee for refund of security deposit for due performance of service falls under Article 145 rather than Article 120. The Court cited this decision to further support that suits for return of security deposits are governed by Article 145.
Datt Singh v. Srihar Singh, AIR 1955 NUC (All) 3551 Observation that deposit money is in the nature of a trust; claim for return of deposit is not within Article 115; Article 145 is the proper Article, or if not, Article 120. The Court referred to the digest of this decision to reinforce that refund claims for deposit money should be treated under Article 145 (or Article 120 as alternative).
Harij Gram Panchayat v. Thakkar Lakhiram Ramil, AIR 1962 Guj 14 Article 120 held applicable for refund-type suits; discussed strict construction of Article 62 and relation to Article 120. The Court noted this decision approving Chagla, C.J.'s observations and observed it supports application of Article 120 where appropriate (though that case did not consider Article 115).
Lingangouda Marigouda v. Lingangouda Fakirgouda, AIR 1953 Bom 79 Observation (by Chagla, C.J.) that Article 62 should be strictly construed; liberal construction would result in many plaintiffs losing on limitation ground; strict construction may lead suits to fall under Article 120. The Court cited this passage approvingly in the context of preferring a construction that allows Article 120 (longer period) to apply rather than a narrower reading that would deprive plaintiffs of remedy.
Jorhat Local Board v. Amtaka Charan Saikia, AIR 1960 Assam 121 Suit for recovery of provident fund from a Local Board governed by Article 120 because no specific Article applied; applicability of Article 115 was considered. The Court relied on this case as supportive authority for treating similar recovery suits under Article 120 when no specific Article governs.
Union of India v. Gangadhar Mimraj, AIR 1962 Pat 372 Division Bench held Article 115 applied where deposits functioned as earnest/part payment and the limitation should run from the happening of the breach/performance event rather than the date of deposit. The Court examined and distinguished this decision, expressing disagreement: it held that a deposit remains a deposit for limitation purposes and that a suit for return of deposit is not necessarily a suit for compensation under Article 115.
State of Andhra Pradesh v. Isukapalli Gangaraju, AIR 1964 Andh Pra 485 Held Article 62 applied to a suit for money illegally collected by the Government; applied fiction that defendant received money for plaintiff's use so Article 62 governs. The Court disagreed with equating a lawfully made security deposit with money illegally collected and rejected extending Article 62 reasoning to security deposits; thus it did not follow this decision.
Thakar Dass Kishan Chand v. State of Pepsu, R.S.A No. 229-P of 1955 (decided 28-9-1959) In a case of illegal levy by government, the Court held Article 62 not applicable and instead Article 120 governed; relied on Privy Council authority (1918 AC 563) treating illegal collections as trust funds. The Court cited this decision to support the proposition that Article 62 is not applicable to all refund suits and that Article 120 (or other deposit-appropriate Articles) may govern; it reinforced the view that refund suits may be treated as trust-based actions outside Article 62.
1918 AC 563 (Privy Council) Passage cited about administration of law and equity in Ceylon and treating actions for money had and received or trusts so as to extend remedies where money collected is not supportable by law. The Court referred to the passage (as relied upon in Thakar Dass) to explain why certain Courts have treated illegal collections as trust funds, but used the broader discussion to differentiate lawful security deposits from illegally collected sums.

Court's Reasoning and Analysis

The Court began by identifying the central legal contest on appeal: which Article of the Limitation Act governs the plaintiff's suit for recovery of the security deposit (Article 115, 120 or 145). The Court set out the text of Articles 115, 120 and 145 from the Limitation Act and noted the periods and triggering events specified by each Article.

Applying the principle from Nagendra Nath Day v. Suresh Chandra Dey (that limitation provisions should be construed by the "strict grammatical meaning" of the words), the Court examined authorities addressing whether a security deposit made for due performance of a contract is properly characterized as a "deposit" (Article 145), a claim for "compensation" for breach (Article 115), or falls under the residuary Article 120.

The Court reviewed multiple precedents that held: (a) money deposited as security for performance is a deposit within the meaning of Article 145 (Lala Gobind Prasad); (b) the cause of action in a suit for refund of such a deposit is the refundable nature of the deposit rather than a contractual claim for damages (Gannon Dunkerly & Co.); and (c) other High Court decisions (Ahilyamba Chatram, Datt Singh) that similarly treated security deposits as governed by Article 145, with Article 120 as an alternative fallback.

The Court considered and distinguished contrary authorities relied upon by the appellant (notably Union of India v. Gangadhar Mimraj and State of Andhra Pradesh v. Isukapalli Gangaraju). In particular, the Court disagreed with the reasoning that a security deposit ceases to be a deposit simply because the depository has a contractual right to deduct sums or because the deposit served as an earnest/part payment; the present Court held that the deposit remains a deposit for limitation purposes and that a suit for its return is not necessarily a suit for compensation under Article 115.

The Court further noted authorities (e.g., Thakar Dass Kishan Chand) that rejected Article 62 for suits of illegal exactions and that Article 120 might govern such recovery suits; but the present Court emphasized the distinction between illegal exactions (where trust/fiduciary principles can be invoked) and lawfully made security deposits under contract.

On balance, the Court concluded that there is "overwhelming judicial opinion in favour of the applicability of Article 145" for suits for return of security deposits. The Court observed that even if one were to assume Article 145 does not apply exclusively, such suits would fall under the residuary Article 120. Since the parties agreed that, if Article 120 applies, the suit is within time, the Court found it was unnecessary to decide definitively between Articles 145 and 120 for the purposes of this appeal.

The Court also reviewed the factual findings of the trial Court — including excessive rainfall causing delay and the appellant's failure to provide reasonable help — and found no serious infirmity in those findings. It noted the contract was not commercial in nature and that, given extensions granted by the appellant itself, time could not be held to be of the essence.

Holding and Implications

Holding: The appeal is dismissed. The Court held that the suit filed by the plaintiff-respondent was not barred by limitation.

Implications:

  • The trial Court's judgment in favour of the plaintiff (granting recovery of the amount withheld) stands as affirmed by this Court on the limitation point and on the other factual findings reviewed.
  • The Court reasoned that suits for the return of security deposits are governed by Article 145 of the Limitation Act in a majority of authorities; if Article 145 is not deemed applicable, Article 120 serves as the residuary Article. Because the parties agreed that Article 120 would make the suit timely, the appeal fails on limitation grounds.
  • No novel legal rule or new precedent was formulated by this Court in the opinion; the Court applied and reconciled existing authorities and concluded the plaintiff's remedy was not barred by limitation and that there was no serious infirmity in the trial Court's other findings.
  • The appeal was dismissed with costs; C.M. 245-C of 1961 was also dismissed. (S.S. Sandhawalia, J. agreed.)

Show all summary ...

Sharma, J.:— This appeal arises out of the following facts.

2. The plaintiff, being an approved contractor, submitted a tender on May 3, 1954, in respect of the work for the metalling and tarring of Jagadihn-Bilaspur road miles 6 to 8/2260 and for the supply of burnt bricks, stone-metal etc. to the District Board Ambala which, has now been substituted by the Zila Parishad Ambala. The District Board (hereinafter called ‘the Board’) accepted the tender and communicated the necessary sanction to the plaintiff vide its letter dated June 14, 1954. In terms of the agreement between the parties, the plaintiff was required to give security for due performance of the contract. He did so by opening a Savings Fund Account in respect of Rs. 7033/- in the Ambala City Post Office on 4/5 August, 1954, and pledged this amount with the Board. The Chairman of the Board was given authority to withdraw any amount from the said Savings Fund Account on the happening of certain events which showed that the plaintiff had failed to perform his part of the contract as stipulated in the agreement deed. The plaintiff claims to have completed the entire work in accordance with the terms of the agreement interj partes. He was made full and final payment of the Mils submitted by him to the Board without any objection. After the completion of the contract, the plaintiff was entitled to receive the amount of security deposit which he had pledged in favour of the Board. When lie made a demand in this behalf, he was informed that this amount had been adjusted towards compensation which had been imposed against the plaintiff as detailed below:—

(a) The amount of compensation levied for the alleged delay in connection with supplies of material Rs. 6076.00 (b) To amount of compensation levied for the alleged delay in the completion of jobs, consolidation etc. Rs. 957.00 Total:— Rs. 7033.00

3. As the defendant-Board refused to refund this amount, the parties referred this matter to the Superintending Engineer. Ambala as the sole Arbitrator. The Arbitrator held that he had no jurisdiction to entertain the dispute about the imposition of Rs. 6076.00 as the compensation claimed against the plaintiff for the alleged delay in completing the work undertaken for the supply of material. Regarding the second item of Rs. 957/-, the Arbitrator gave his award directing the defendant-Board to refund a sum of Rs. 947/-. to the plaintiff after deducting Rs. 10/- only as the valid compensation. The plaintiff filed a suit in the Court of Subordinate Judge First Class. Jagadhri, claiming a sum of Rs. 706/-. The attack levelled against the withholding of Rs. 6076/- as compensation levied for the alleged delay in connection with the sup-lies of materials was based, inter alia, on the following reasons:—

(a) The act of the defendant in levying the compensation in question is arbitrary capricious and unilateral.

(b) No details of the said compensation have been explained to the plaintiff.

(c) The terms of the contract authorising the defendant to impose compensation, being penal and inoperative, again time was not the essence of the contract and no compensation could be imposed.

(d) In any case, the defendant had waived the terms in question and is now estopped from levying any compensation on that account.

(e) The alleged compensation was not imposed by any valid resolution of the defendant-District Board, but by the Chairman of the defendant in his individual capacity. The Chairman of the defendant had no such authority and hence his order imposing the compensation is illegal and not binding upon the plaintiff.

(f) The alleged delay in the supply of the material was made for no fault of the plaintiff and on the other hand, it was the direct result of the failure on the part of the defendant to perform its part of the contract inasmuch as it did not construct the roads in time over which the material was to be carried.

(g) If at all any compensation was leviable, it could be levied only in respect of that part of the contract, the execution of which was delayed, and not on the entire contract.

4. The defendant-Board filed a written statement in which it was alleged that the plaintiff was to supply stone-metal and burnt bricks on the road by January 5, 1955. This date was extended by one month and ten days but the plaintiff failed to complete the job even within the extended time. He finished the supply only on March 28, 1955. The screenings were insufficient the plaintiff supplied only 2204 cft as against the contracted quantity of 4404 cft. The material was largely mixed with earth and contained only one half of screening. It was further alleged that the time was the essence of the contract and the plaintiff rendered himself liable for compensation because he failed to perform his part of the contract within the time fixed and the compensation had been levied properly. The learned trial Court framed the following issues on the pleadings of the parties:—

(1) Whether the plaintiff supplied the material to the defendant within the stipulated period or within the period as extended by the defendant?

(2) If not whether the delay in supply of material was caused for no fault of the plaintiff and to what effect?

(3) Whether such delay was caused on account of defendant's fault?

(4) Whether the defendant had waived such delay?

(5) Whether the condition imposing penalty on the plaintiff for delay in supply of material was penal and as such void?

(6) Whether the time was not the essence of the contract for supply of material?

(7) Whether the defendant was justified in imposing a penalty of Rs. 6076/- on the plaintiff for the delay in supply of material. If not what should be the correct amount?

(8) Whether the said penalty had been validly imposed by or on behalf of the defendant?

(9) Whether the defendant served a show-cause notice on the plaintiff before Imposing the penalty of Rs. 6076/-. If not its effect?

(10) Whether and if so to what amount is the plaintiff entitled on account of interest?

(10-A) Is the suit within time?

(11) Relief.

5. The learned trial Court decided Issues Nos. (1) and (5) against the plaintiff and decided all the other issues in his favour. As a result of this decision, the plaintiff was granted a decree for the recovery of Rs. 6076/- with proportionate costs against the defendant-Board. The defendant Board has come in appeal before this Court. The learned counsel for the appellant has mainly challenged issue No. (10-A) which relates to the question of limitation. According to him, the respondent was required under the contract to supply the materials up to February 13, 1955. Under this contract, he deposited the security for its due performance. If the Board refused to return him the security, then his case would be one for compensation for the breach of a contract and hence governed by Article 115 of the Limitation Act (hereinafter called ‘the Act.’) On the other hand the learned counsel for the respondent has submitted that the security deposit, whether it is in connection with the due performance of a contract or not remains a deposit in the eyes of law and the suit would be governed by a specific Article of the Act on the subject, i.e, Article 145 of the Act. He further added that in case Article 145 was held not to apply, then the suit will be governed by the residuary Article, i.e, Article 120 of the Act. In order to properly appreciate the points in controversy, it becomes necessary to notice the relevant provisions of the statute—

“Description of suit. Period of Limitation. Time from which period begins to run. 115: For compensation for the breach of any contract express or implied not in writing registered and not herein specially provided for. Three years. When the contract is broken or (when there are successive breaches) when the breach in respect of which the suit is instituted occurs, or (where the breach is continuing) when it ceases. 120: Suit for which no period of limitation is provided elsewhere in this schedule. Six years. When the right to sue accrues. 145: Against to depository or pawn to recover moveable property deposited or pawned. Thirty years. The date of the deposit or pawn.

6. After interpreting the provisions of the Act the Courts have enunciated certain salutary principles. In Nagendra Nath Day v. Suresh Chandra Dey. AIR 1932 PC 165, it was held that “the fixation of periods of limitation must always be to some extent arbitrary, and may frequently result in hardship. But in construing such provisions equitable considerations are out of place, and the strict grammatical meaning of the words is the only safe guide. We have to see with reference to the suit filed by the plaintiff-respondent the question of applicability of either of the aforementioned Articles of the Act. If the suit filed by him could be called a suit for compensation or damages, then obviously Article 115 of the Act would apply. But if the suit is one for the return of security deposit, then we cannot invoke this Article which is of in general nature and have to examine the language employed by other Articles of the Act for determining their applicability in the light of the principles enunciated by the Privy Council in Nagenda Nath Dey's case (supra).

7. In Lala Gobind Prasad v. Chairman of Patna Municipality, (1907) 6 Cal LJ 535, the controversy arose on the basis of the following facts. The petitioner in that case was appointed as Naib Buxi in the Patna Municipality and deposited Rs. 100/- as security for the faithful and careful discharge of his duties. The post held by him was abolished and his services were dispensed with. Shortly afterwards, the accounts were examined and it was found that nothing was due from the petitioner. Subsequently, he asked for the refund of the deposit but his application was refused in a suit filed by him for the refund of the security, that Municipality set up the bar of limitation by asserting that his suit was barred under Article 120. Mookeriee, J., after making an elaborate discussion of the points involved in the controversy came to the conclusion that moveable property as mentioned in Artcle 145 of the Act also included money and further observed.—

“It further appears that there is not, in point of principle, any substantial difference between the two cases in one of which a Government security, and in the other, a sum of money, is deposited, for the faithful discharge of the duties undertaken by the depositor, and there is no intelligible reason why two different periods of limitation should be applicable to the two cases in each of which the depositor seeks for the return of his deposit after his service has terminated. If a Government security or a sum of money is delivered to be held as security for the performance of some engagement, and upon the express or implied understanding that the thing deposited is to be restored to the owner as soon as the engagement has been fulfilled, the person with Whom the deposit has been made may rightly be treated as a depository within the meaning of Article 145 of the Second Schedule of the Limitation Act.”

8. In Gannon Dunkerly & Co. Ltd. v. Western India Theatres Ltd., 1961-65 Cal W Notes 504 a building contractor was called upon to deposit a sum of Rs. 7000/- as security with the architects for the due performance of the contract of building. When the work was finished the contractor demanded his security back which was refused. On a suit filed by him the question arose whether Article 115 or 145 of the Act applied to the case. After making an exhaustive analysis of the relevant case law on the point, Bose, J., observed as under:—

“Now a deposit made as security for due performance of a contract is refundable whether it is coupled with a promise or agreement to repay it or not. Even if nothing is agreed as to its repayment at the time the deposit is made, the obligation to repay arises upon the proper performance of the engagement by reason of the very Nature of the transaction of deposit. If an express agreement is entered into for repayment of the deposit, the transaction still remains a deposit and its nature is not thereby altered. The essence of the cause of action for a suit for refund of a deposit is not the breach of the contract to repay it, but the fact that the transaction is a deposit which by its very nature is refundable. The person who holds the deposit and the person on whose behalf or for whose benefit the deposit is held as security are liable to refund it because it is a deposit. They are both in the position of depositories. So my conclusion is that the Article applicable is Article 145 of the Limitation Act and if for any reason this Article cannot be held to be applicable, there is no doubt that Article 120 is applicable to this case.”

9. In Ahilyamba Chatram v. R. Subramania Ayyar. AIR 1954 Mad 101, the question arose whether a suit filed by an employee against his employer for the refund of security deposit made in respect of due performance of the contract of service was governed by Article 120 or 145 of the Act. On a consideration of the earlier cases decided by that Court and some other Courts the learned Judge came to the conclusion that the suit would be governed by Article 145 of the Act This case was later on considered by a learned single Bench of the Allahabad High Court in Datt Singh v. Srihar Singh, AIR 1955 NUC (All) 3551. The commentator has digested the observations made by the learned Judge in the following terms:—

“The claim for a return of the deposit money cannot by any stretch of the language of Article 115 be considered as a suit for compensation for breach of any contract. When an employee makes a deposit for due performance of his duties, the deposit is in the nature of a trust and the proper Article in such a case is Article 145 which provides for a greater period of limitation than Article 120. Even if Article 145 is not applied, there is no escape from the conclusion that the other Article applicable to a case of this type is Article 120.”

10. The question regarding the applicability of the various Articles of the Act in suits for money deposited as security for due performance of the contract came to be considered also in Harij Gram Panchayat v. Thakkar Lakhiram Ramil AIR 1962 Guj 14. The learned Judge noticed with approval the observations made by Chagla, C.J, in Lingangouda Marigouda v. Lingangouda Fakirgouda, AIR 1953 Bom 79, which are to the effect that Article 62 should be more strictly construed because a liberal construction would result in more plaintiff losing in a large number of cases on the ground of limitation, and if this Article was strictly construed, then the suit would fall under Article 120 which gave to the plaintiff a longer period of limitation. Article 120 was held to be applicable for such suits. It may, however, be noticed that the learned Judge did not consider the effect of Article 115 in that case.

11. In Jorhat Local Board v. Amtaka Charan Saikia, AIR 1960 Assam 121, it was held that a suit for recovery of provident fund from a Local Board was governed by Article 120 of the Limitation Act because no specific Article was applicable. The question of applicability of Article 115 was expressly considered in this case.

12. On a perusal of the above mentioned authorities, it becomes abundantly clear that in case of suits for return of security deposits, whether they are made for due performance of a contract of service or of works, the Courts were inclined to hold that Article 145 of the Act applied. This interpretation also appears to be in accord with the principles enunciated by the Privy Council in Nagendra Nath Dey's case AIR 1932 PC 165 (supra).

13. The learned counsel for the appellant, however, relied upon a Division Bench judgment of the Patna High Court in Union of India v. Gangadhar Mimraj, AIR 1962 Pat 372. In that case the plaintiff had entered into a contract with the Railway authorities to supply some goods. In respect of that contract the plaintiff had deposited Rs. 2500/- as security money. This security money was forfeited by the Railway authorities on account of some default alleged to have been committed by the plaintiff. The Court considered the question of applicability Articles 115, 120 and 145 of the Act and came to the conclusion that Article 115 applied. The reasons which influenced the learned Judges to come to this; conclusion can be inferred from the following passage:—

“In these suits, the Railway administration had the authority under the contracts to recover from the plaintiffs any cost which the Railway administration may have to incur for failure to perform the contracts within the stipulated periods from any money due to the plaintiffs by the Railway administration and/or forfeit the security deposits in whole or in part. In fact, in the case of D.D Kapoor, the Railway administration did deduct from the security money the penalty imposed upon him for his failure to execute the contract within the stipulated period. Therefore, in these two cases, the deposits were made, as observed by Fry, L.J for two purposes, first, as an earnest to bind the bargain so entered into and also as a part payment. In such circumstances, the limitation cannot be said to run from the date of the deposits. The limitation will run obviously from the happening of the given contingency that is, performance or non-performance of the contract which must be later than the date of the deposit. The Limitation Act provides for time running only after the cause of action had arisen and on this view alone Article 145 must be held to be Inapplicable in the instant case.”

14. With utmost respect to the learned Judges, who decided this case, we are of the view that the deposit remains a deposit Whether the depository has a right to deduct anything therefrom or not, or whether the cause of action for realising this deposit accrues on a subsequent event. For interpreting the provisions of the Articles of the Act the entries in columns 1 and 2 have to be read together and the words appearing therein have to be given their natural meaning. If this principle is accepted, then it cannot be said that a person who brings in a suit for return of the security deposit or a part thereof actually brings in a suit for compensation for the breach of any contract.

15. The other decision relied upon by the learned counsel for the appellant is State of Andhra Pradesh v. Isukapalli Gangaraju, AIR 1964 Andh Pra 485. In that case the plaintiff had obtained an excise contract from the Government in respect of which he also made a security deposit. This security deposit was forfeited on the basis of the breach of one of the clauses of the licence. The learned Judge observed as follows—

“Therefore. I hold that, to the present case, which is a suit for money illegally collected by the Government from the plaintiff, Article 62 of the First Schedule to the Indian Limitation Act applies. The cases, which are binding on me, have pointed out that when the money was received by the defendant, it need not have been in fact received for the plaintiff's use. When the exaction is illegal the Court applies a fiction that the defendant received the money for the plaintiff's use, because the defendant in justice and equity is bound to refund it to the plaintiff and has no right to retain it”

16. With great respect to the learned Judge, we are of the view that a deposit lawfully made under a contract cannot be equated with money illegally collected. Besides, we find it difficult to import fiction of common law relating to money received by the defendant for the use of the plaintiff. Obviously when security is deposited for due performance of a contract, the depository has a right to take something out of it in accordance with the terms of the contract. In this situation, it cannot be said that the deposit was for the use of the depositor only.

17. In R.S.A No. 229-P of 1955 (Thakar Dass Kishan Chand v. State of Pepsu), decided on 28-9-1959, the Director of Civil Supplies in the former State of Pepsu issued a notification making a levy of one per cent on the ex-mill price of cloth obtained by the dealers for sale in purported exercise of powers under the Pepsu Cloth Distribution Order of 1948. This levy was subsequently found to be illegal. The dealer filed a suit for the realisation of the sum levied against him by the Government and the same was dismissed by the trial Court and the lower appellate Court on the ground that the suit was barred by limitation. Mehar Singh, J., as the learned Chief Justice then was considered the relevant authorities in great detail and came to the conclusion that Article 62 of the limitation Act was not applicable to such a case. It was held that the suit would be governed by Article 120 of the Limitation Act. In coming to this conclusion, his Lordship relied upon the following passage appearing in 1918 AC 563:—

“Under principles which have always obtained in Ceylon, law and equity have been administered by the same Courts as aspects of a single system, and it could never have been difficult to treat an action analogous to that for money had and received as maintainable in all cases where the defendant has received money which ex-aequo et bono he ought to refund.’ If, as in Ceylon, there is no necessity to find an actual contract or to impute the fiction of a contract, inasmuch as every Court can treat the question as one not merely of contract, but of trust fund where necessary, there is no difficulty in extending the remedy to all the cases covered by the words just quoted.”

18. After considering this judgment the learned Judge held that the authorities which took the contrary decision did not take into consideration the above-mentioned judgment of the Privy Council in which it had been emphasised that so far as the Courts situated outside England were concerned it was not necessary to find an actual contract or to impute the fiction of a contract in the case of collections made which were not supportable by law because in such actions the relief could be granted on the ground that the money so collected was a trust fund. The Letters Patent Appeal against this judgment was dismissed in limine. Thus, so far as this Court is concerned, the settled view is that Article 62 of the limitation Act cannot be invoked in such cases.

19. The above-mentioned discussion will show that there is overwhelming judicial opinion in favour of the applicability of Article 145. Even if it may be assumed that the deposit contemplated by Article 145 of the Limitation Act was of the type which was exclusively for the use of the depositor, the suits for recovery of such deposits could not fall under Article 115 of the Act.

20. Such a suit though relating to a deposit would fall under the residuary Article 120 of the Act. For the purposes of this suit it is not necessary to decide the conflicting claims of Articles 145 and 1120. It is agreed by the parties that if, Article 120 applies, then the suit filed by the plaintiff-respondent is within time. In agreement with the decision given by the learned trial Court, we hold that the suit filed by the plaintiff-respondent was not barred by limitation.

21. The other points involved in the controversy were not seriously challenged before us. The learned trial Court came to the conclusion that there was excessive rainfall during the relevant period which caused delay in the performance of the contract. The appellant was also held not have afforded reasonble help to the respondent for doing his job. The contract in dispute was not commercial contract and in view of the extensions granted by the appellant itself, it cannot be held that time was the essence of the contract. No serious infirmity has been brought to our notice regarding these findings arrived at by the learned trial Court.

22. For the reasons mentioned above, this appeal fails and is dismissed with costs. C.M 245-C of 1961 is also dismissed.

S.S Sandhawalia, J.:— I agree.

23. Appeal dismissed.