Great American Insurance Co. Ltd. v. Dina Nath .
Concise Analytical Summary of the Opinion
Factual and Procedural Background
This is an appeal by the Great American Insurance Company Limited against an order of the lower Court under Section 20 of the Arbitration Act directing the parties to nominate their arbitrators. The original S. 20 application was filed by Dina Nath Suri. He alleged that under a policy in force from 6 March 1947 to 6 March 1948 he had insured a house at Rawalpindi for Rs. 40,000 and household effects for Rs. 10,000. On account of disturbances he left Rawalpindi on 1 August 1947. He later learned that his household goods had been looted in September 1947. He submitted a claim to the Company, which, after investigation, rejected the claim by letter dated 13 April 1949, said to have been received by him on 17 April 1949. Suri filed his S. 20 application on 16 July 1949 seeking reference to arbitration under Clause 18 of the policy. The Company opposed the application, relying principally on Clauses 13 and 19 of the policy and on the contention that Clause 18 did not cover the dispute. The lower Court decided against the Company and ordered the parties to nominate arbitrators. The Company appealed.
Legal Issues Presented
- Whether the dispute between the insured and the insurer falls within the scope of the arbitration clause (Clause 18) in the policy when the insurer has repudiated liability.
- Whether the three-month forfeiture provision in Clause 13 begins to run from the date of the insurer's repudiation or from the date of dispatch of the repudiatory letter.
- Whether Clause 19 (which limits insurer liability after twelve months unless the claim is the subject of pending action or arbitration) bars the present claim.
- Whether the provisions of the Displaced Persons (Debts Adjustment) Act (notably Sections 18 and 36) apply to negate contractual conditions like Clause 19 for displaced persons and whether those provisions apply to proceedings pending when the Act came into force.
- Whether an application under Section 20 to enforce an arbitration agreement constitutes a "legal proceeding" for the purposes of Section 36 of the Displaced Persons Act.
Arguments of the Parties
Appellant (Great American Insurance Company Ltd.)
- The Company argued that Clause 18 (arbitration clause) does not apply because the Company had totally repudiated liability; in their submission the arbitration clause only applies where the Company admits some loss and the dispute is as to amount.
- The Company relied on Clauses 13 and 19 of the policy to contend that the claim had lapsed: Clause 13 (forfeiture if suit not commenced within three months of rejection) and Clause 19 (no liability after twelve months unless claim is subject of pending action or arbitration).
- The Company relied on precedent (Shaw Wallace and Company v. Gurbuzsing Beshensing) for the proposition that notice periods tied to dispatch may be enforced and, by analogy, to challenge the petitioner’s contention about the date of receipt of the repudiation letter.
- The Company contended that Sections 18 and 36 of the Displaced Persons Act either were not applicable to the present proceedings or did not have the effect of nullifying Clause 19 in this context; the Company further argued that clauses of the kind in Clause 19 had been upheld by Courts on earlier occasions and that parties may agree to rights lapsing by contract.
Respondent / Petitioner (Dina Nath Suri)
- The petitioner asserted that his property had been looted in September 1947 and that he submitted a claim which was repudiated by the Company by letter of 13 April 1949, received on 17 April 1949; he filed the S. 20 application on 16 July 1949, within three months of receipt of repudiation.
- He relied on Clause 18 of the policy to obtain reference to arbitration. He contested the Company's factual denial (that no damage was sustained) and sought arbitration under the policy.
- The petitioner relied on the absence of the Company's production of the registered acknowledgment form (which would show postal receipt date) to support his assertion of the date of receipt of repudiation.
- The respondent (as reflected in the opinion) also relied on statutory provisions (Sections 18 and 36 of the Displaced Persons (Debts Adjustment) Act) as applicable to claims by displaced persons and as nullifying restrictive contractual limitation conditions such as Clause 19.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Shaw Wallace and Company v. Gurbuzsing Beshensing, AIR 1929 Sind 58 | Applied the postal/despatch notice rule in a contractual notice provision; upheld strict operation of a reduced notice period tied to despatch. | The appellant relied on it to argue that notice should be treated as served on despatch. The Court disagreed with that decision's reasoning in the present context and held it was not applicable: the three-month period in Clause 13 must run from actual receipt of repudiation, not despatch. |
| National Fire and General Assurance Co. Ltd. v. Mool Singh Gurdev, AIR 1955 NUC (Punjab) 4988 | Interpreted and applied provisions of Section 18(1) of the Displaced Persons (Debts Adjustment) Act to deny insurer the defence that the claim was not made within agreed time. | The Court treated this decision as authority for applying S.18(1) to deny insurers reliance on contractual notice conditions in cases concerning displaced persons; it supported the view that S.18(1) prevents insurers from avoiding liability on the ground of late claims. |
| Lachmeshwar Prasad v. Keshwar Lal, AIR 1941 FC 5 | Held that a Court of appeal is entitled to take notice of legislative changes affecting parties' rights and give effect to them because an appeal is in the nature of a re-hearing. | The opinion cites this Federal Court authority to justify taking account of the Displaced Persons Act (a legislative change) in the appeal and applying it to the parties' rights. |
| Banke Mal Naranjan Das v. Central Bank of India Ltd., 54 Pun LR 324 : AIR 1952 Punj 400 | Held (with respect to S.17 of the Displaced Persons Act) that the section applied to proceedings before the Tribunal under the Act and not outside those proceedings. | The opinion records the argument based on this case but notes that the view was subsequently overruled by a Division Bench decision (Sulakhan Singh). The Court regarded the restrictive view as having little force in light of the later decision. |
| Sulakhan Singh Seth Mool Chand v. Central Bank of India Ltd., 55 Pun LR 348 : AIR 1954 Punj 66 | Division Bench decision overruling the restrictive view in Banke Mal, indicating broader applicability of the Act's provisions beyond the special Tribunal. | The opinion relies on this decision to displace the narrower view and to support the applicability of statutory provisions (such as S.18 and S.36) beyond the Tribunal procedures; it strengthens the conclusion that S.18(1) and S.36 apply to ordinary court proceedings affecting displaced persons' claims. |
Court's Reasoning and Analysis
The Court proceeded through the contested points as follows:
- Clause 18 (arbitration clause) — The Court set out the clause's language ("If any difference arises as to the amount of any loss or damage, such difference shall, independently of all other questions, be referred to the decision of an arbitrator.") and rejected the Company's argument that a total repudiation of liability removes the dispute from the clause. The Court reasoned that whether the Company says "no damage at all" or "some damage but not as much as claimed," in either event there is a dispute as to the amount of loss or damage. Consequently the dispute falls within the scope of the arbitration clause; no additional authority was needed for that conclusion.
- Clause 13 (three-month forfeiture) — The Court agreed with the lower Court that the three-month period in Clause 13 should be taken to commence from the date on which the repudiation of the claim was actually conveyed to the insured (actual receipt), not from the date of despatch. The lower Court had believed the petitioner's evidence that he received the letter on 17 April 1949, in part because the Company had not produced the registered acknowledgment form. The appellate Court accepted this approach and rejected reliance on the postal/despatch rule as applicable in the Shaw Wallace case for the present contract.
- Clause 19 (twelve months bar) and the effect of the Displaced Persons (Debts Adjustment) Act — The Court examined the effect of S. 18(1) and S. 36 of the Displaced Persons Act (the Act came into force during the pendency of the appeal). The Court noted that S. 18(1) prevents an insurance company from refusing payment on the ground that "the claim was not made to the company within the agreed time" for property in West Pakistan belonging to displaced persons insured before 15 August 1947. The Court also considered S. 36, which, among other things, allows suits or legal proceedings affected by contractual conditions to be instituted within a statutory period following commencement of the Act.
- Applicability of the Act to pending proceedings — The Court reviewed authorities (including National Fire & General Assurance Co. v. Mool Singh Gurdev and the Federal Court authority in Lachmeshwar Prasad) to conclude that an appellate court may take notice of a subsequent legislative change and apply it in the re-hearing by way of appeal. It further rejected the contention that the statutory provisions apply only to the special Tribunal under the Act, relying on the Division Bench decision in Sulakhan Singh (which overruled the narrower view in Banke Mal) to support a broader application of the Act's provisions to proceedings generally.
- Characterization of an S. 20 application as a "legal proceeding" — The Company contended that an application under S. 20 was not a legal proceeding and therefore not covered by S. 36. The Court accepted that an application filed in Court to enforce an arbitration agreement is indeed a legal proceeding and therefore within the scope of the statutory provision.
- Conclusion of analysis — On the combined reasoning the Court held that Clause 19 could not be relied upon to defeat the claim of a displaced person in the circumstances of the present case because the statutory provisions (S. 18(1) and S. 36) operate to nullify such contractual conditions insofar as they are in contravention of the Act. The Court therefore dismissed the appeal.
Holding and Implications
Core Ruling: The appeal by the Great American Insurance Company Limited is APPEAL DISMISSED.
Direct Consequences for the Parties
- The lower Court's order directing the parties to nominate their arbitrators under Clause 18 of the policy remains in force.
- The arbitrability of the dispute was upheld: Clause 18 applies even where the insurer repudiates liability; the existence of a dispute as to the amount of loss or damage falls within the arbitration clause.
- The three-month forfeiture period in Clause 13 is to be computed from the date on which the repudiation letter was actually received by the insured (and not from date of despatch).
- Clause 19 (limitation after twelve months) cannot be used by the insurer to avoid liability in respect of claims by displaced persons in the circumstances described, because Sections 18 and 36 of the Displaced Persons (Debts Adjustment) Act operate to nullify such contractual conditions to the extent they contravene the Act.
- The Court awarded costs to the respondent (Counsel's fee Rs. 50) and granted a certificate that the case is fit for filing a Letters Patent Appeal.
Broader Legal Implications Noted by the Court
The opinion treats the Displaced Persons (Debts Adjustment) Act provisions (S. 18(1) and S. 36) as having the effect of removing the operation of certain contractual time-bar provisions (such as Clause 19) in insurance contracts covering property in West Pakistan owned by displaced persons before 15 August 1947. The Court also accepted the proposition (supported by cited authorities) that an appellate court may take notice of and apply a statutory change that came into force during the pendency of the proceedings.
No section of this summary contains information beyond what is explicitly stated in the provided opinion.
1. This is an appeal by the Great American Insurance Company Limited against the order of the lower Court under Section 20 of the Arbitration Act calling on the parties to nominate their arbitrators. The application was filed under S. 20 by Dina Nath Suri on the allegation that under a policy which remained in force from the 6th of March 1947 to the 6th of March 1948 he had insured his house at Rawalpindi for Rs. 40,000/- and household effects contained therein for Rs. 10,000/-, with the defendant Company and that in consequence of the disturbances he had been forced to leave Rawalpindi and flee to this country on the 1st of August 1947 leaving behind his house and furniture, etc. He had learnt in January 1948 that during the month of September 1947 his household goods had been looted by Muslims.
2. He thereupon preferred a claim to the Company in respect thereof and after a lengthy correspondence the Company by its letter dated the 13th of April 1949 rejected his claim informing him that as a result of a report from Messrs Sinclair Murray and Company and from investigations carried out on behalf of the Company it appeared that the premises were neither looted nor burnt. The petitioner alleged that he had received this letter which came from Calcutta by registered acknowledgment post on the 17th of April 1949 and he filed his application under S. 20 of the Act on the 16th of July 1949 claiming a reference to arbitration in accordance with the terms in Cl. 18 of the policy.
3. The application was opposed by the Company which pleaded that the claim no longer subsisted in view of the terms of Cls. 13 and 19 of the policy and that the dispute between the parties was not covered by the narrow terms of Cl. 18. These points were decided by the lower Court against the Company which has come in appeal.
4. As regards the second of these questions it seems that the only ground on which the Company has repudiated the petitioner's claim under the policy was that in fact no damage had been sustained either to the house or its contents, which is simply a question of fact, and even now the claim is not repudiated on any other ground. The relevant words of Cl. 18 are—
“If any difference arises as to the amount of any loss or damage, such difference shall, independently of all other questions, be referred to the decision of an arbitrator.”
5. The learned counsel for the Company has attempted to argue that the total repudiation of any liability on the part of the Company takes the dispute between the parties out of the scope of these words, which, as far as I could gather from him, will only come into play if the Company admits that some loss or damage has been caused and the dispute is only regarding the extent. I cannot see any force in this argument, since it does not seem to me to make any difference whether the Company says that no damage or loss at all has been caused, or whether it says, that some damage has been caused, but not as much as is claimed by the insured.
6. In either case it is quite obvious that there is a dispute between them as to the amount of loss or damage and it does not seem to me that any authority is necessary for holding that the present dispute between the parties falls within the scope of the arbitration clause in the policy.
7. The other points which arise in the appeal relate to the effect of Cls. 13 and 19. The relevant portion of Cl. 13 reads—
“………… or if the claim be made and rejected and an action or suit be not commenced within three months after such rejection …………… all benefit under this policy shall be forfeited.”
8. Clause 19 reads—
“In no case whatever shall the Company be liable for any loss or damage after the expiration of twelve months from the happening of the loss or damage unless the claim is the subject of pending action or arbitration.”
9. The lower Court decided on the first of these points in favour of the petitioner on the ground that the period of three months mentioned in Cl. 13 must be deemed to commence from the date on which the repudiation of his claim by the Company was actually received by him and his evidence that he received the letter on the 17th of April 1949 was believed mainly on the ground that the Company had not produced the registered acknowledgment due form, which would have shown a different date if the petitioner's allegation was incorrect.
10. The effect of Cl. 19 was surmounted by the lower Court by holding that the Company could not take advantage of the fact that it had taken so long to investigate the petitioner's claim that the repudiation of the claim following a lengthy correspondence itself only came very much more than one year after the loss or damage was sustained.
11. As regards the effect of Cl. 13, I agree with the lower Court that the period of three months should be deemed to start from the date on which the repudiation of the claim was actually conveyed to the petitioner. Reliance was placed by the appellant on the decision of Rupchand A.J.C in — ‘Shaw Wallace and Company v. Gurbuzsing Beshensing’, AIR 1929 Sind 58 (A), in which a clause in the contract between the parties read—
“All letters and notices given to the buyers by the sellers in connection with this contract may be sent by prepaid post letters and addressed to the buyers at Amritsar, which the buyers hereby admit to be their address, and all notices so sent shall be considered to be served on the buyers at the time the same ought to have been delivered in due course of post by the Post Office, etc.”
12. It seems that the notice sent by the Company requiring the respondents to appoint an arbitrator within seven days of the date of notice in accordance with the terms of the contract actually took a fortnight to reach the addresses, and in the meantime the Company had appointed an arbitrator on behalf of the so-called defaulting party in accordance with the same terms.
13. It was held that no sufficient cause had been shown why the provisions of reducing the period of notice to seven days from the date of despatch and agreed to by the parties with open eyes should not be given effect to and that the objection by the defaulting party to the appointment of arbitrator on their behalf by the other party on that ground must fail.
14. I can only say with due respect that I do not agree with that decision and consider that in those circumstances there was ample ground for interference by the Court. In any case there is no such seven days' clause in the contract between the present parties and I consider that the period of three months must be taken to start from the date on which the letter repudiating the claim reached the petitioner.
15. With regard to the effect of Cl. 19, my attention has been drawn by the learned counsel for the respondent to the provisions of Sections 18 and 36 of the Displaced Persons (Debts Adjustment) Act LXX of 1964 which came into force during the pendency of the present appeal. The relevant portion of S. 18(1) reads—
“18(1) Where any property in West Pakistan belonging to a displaced person was insured with any insurance company before the 15th day of August, 1947, against any risk arising out of fire or theft or not and civil commotion and there has been a loss in respect of such property arising out of any such risk at a time when the contract of insurance was in force, such company shall not be entitled to refuse payment of the sum due under any claim in relation thereto on the ground that (a) ……………… (b) the claim was not made to the company within the agreed time ……………… (c) …………… (d) the displaced person has not fulfilled any other condition of the contract which in the opinion of the Central Government is of a technical nature and which the Central Government has, by notification in the Official Gazette, specified as a condition of the contract for the purposes of this section,
16. And any contract to the contrary, to the extent to which it is in contravention of the provisions of this sub-section, shall be deemed to have had no effect.”
17. The relevant portion of S. 36 reads—
“36. Notwithstanding anything contained in the Indian Limitation Act, 1908 (IX of 1908) or in any special or local law or in any agreement,—
(a) ………………………
(b) any suit or other legal proceeding for the enforcement of a claim against an insurance company not falling within the provisions of Cl. (a) in respect whereof the cause of action had arisen, whether wholly or in part, in the territories now situate in West Pakistan and the institution of the suit or other legal proceeding has become barred by reason of a condition in the contract, which, but for the condition would have been governed by the provisions contained in Cl. (a),
18. May be instituted at any time within one year from the commencement of this Act.”
19. The question whether the provisions of this Act can be applied to proceedings which were pending before the Act came into force came up for consideration before Harnam Singh and Dulat, JJ. in — ‘National Fire and General Assurance Co. Ltd. v. Mool Singh Gurdev’, Regular First Appeal No. 1-D of 1952; (AIR 1955 NUC (Punjab) 4988 (B)), which was an appeal by an insurance company against a decree passed in favour of a Rawalpindi firm on the basis of a similar claim.
20. In that case the company had relied on the defence that the claim under the policy could not be enforced because no claim had been filed within 15 days of the loss or damage as required by the terms of the policy. The trial Court had decided this point in the plaintiffs' favour on the finding that the condition in question had been waived by the company by its conduct. The learned Judges held that it was not necessary to go into the question of waiver in view of the provisions of S. 18(1) of Act LXX of 1951 which was cited and Dulat, J., who delivered the judgment went on—
“It is quite plain from the provision of law quoted above, that in a case like the present the insurance company cannot avoid liability by urging that the claim was not made within the agreed time. Mr. Isaacs first contended that this Act was not applicable to the present case as it had been enacted after the present suit had been decided, but he did not press this contention after he had considered the decision of the Federal Court in — ‘Lachmeshwar Prasad v. Keshwar Lal’, AIR 1941 FC 5 (C), which authority laid down that a Court of appeal in India is entitled to take notice of any legislative change governing the rights of the parties and give effect to it because an appeal is in the nature of a re-hearing. He did contend, however, that Section 18 of the sub-s. (1) of the Act, applied only to a case before a Tribunal set up under the Act and the provision had no application to proceedings pending elsewhere.
21. For this contention he depended on the argument advanced in — ‘Banke Mal Naranjan Das v. Central Bank of India Limited’. 54 Pun LR 324 : (AIR 1952 Punj 400) (D), in respect of S. 17 of the same Act, in which case Weston, C.J, was persuaded to hold that section was applicable to proceedings held by the Tribunal appointed under the Act and not applicable outside those proceedings.
22. This view was, however, overruled by a Division Bench of which one of us was a member in ‘Sulakhan Singh Seth Mool Chand v. Central Bank of India Ltd.’, 55 Pun LR 348 : (AIR 1954 Punj 66) (E), and the argument therefore has little force. Mr. Isaacs then pointed out that there was a difference between S. 17 and S. 18 of the Act in so far as S. 17 does not at all mention the Tribunal while S. 18, sub-s. (2), does so.
23. This distinction is of no consequence because what we have to consider is not sub-s. (2) of S. 18 but sub-s. (1), for it is sub-s. (1) that contains the substantive provision of law. The language of this sub-section is plain enough and there is in my opinion little doubt that Parliament here intended to do away with the effect of certain conditions in certain contracts and there seems to me little merit in the argument that such contracts are intended to be read one way by the Tribunal appointed under the Act and in another way by other Tribunals in the country.
24. I am in the circumstances unable to agree with Mr. Isaacs that the provision contained in Section 18 of the sub-s. (1) of this Act would not apply to the present case and that being so it is clear that the insurance company can derive no advantage from the fact that the claim was not made within the agreed time.”
25. This judgment admittedly does not mention any of the provisions of S. 36 of the Act, but it is clearly an authority for applying them if they are applicable in any way to the present case. In any case, S. 36(b) clearly refers “to any suit or other legal proceeding” for the enforcement of a claim against an insurance company and so this section cannot be said to be applicable only to proceedings before a Tribunal set up under the Act. Its effect certainly seems to be to nullify clauses similar to Cl. 19 in the present case in any insurance policies where the claim is brought by a displaced person with regard to a property insured in West Pakistan before the 15th of August 1947.
26. It was contended on behalf of the Company that the provisions of S. 36 were not applicable because the validity of clauses similar to Cl. 19 in the present policy had been upheld by the Courts on many occasions on the ground that although the parties could not by agreement change the law of limitation, they could agree that their rights would lapse after certain period regardless of the law of limitation.
27. No doubt in my mind that the words “or in any agreement”, in the first part of S. 36, and “the institution of the suit or other legal proceeding has become barred by reason of a condition in the contract”, in Cl. (b) were clearly intended by he Legislature to nullify clauses of this nature with regard to claims by displaced persons regarding property insured and left behind in Pakistan. Otherwise the words dc not seem to me to have any meaning at all. Some attempt was made to argue that an application under S. 20 was not a legal proceeding, but in my opinion there can be no doubt whatever that an application filed in Court to enforce an arbitration agreement is a legal proceeding. I accordingly dismiss the appeal with costs. Counsel's fee Rs. 50/-. At the request of the learned counsel for the appellant I grant him a certificate that the case is a fit one for filing a Letters Patent Appeal.
V.R.B
28. Appeal dismissed.