Hem Narain Jhunjhunwala v. State Of Bihar And Another

Patna High Court
Nov 8, 1989
Smart Summary (Beta)

Structured Summary of the Opinion

Factual and Procedural Background

The petitioner sought quashing of two impugned instruments: the order recorded as Annexure‑1 and a notice recorded as Annexure‑6. Together they prohibited the petitioner from continuing construction of a building in Patna City and held that the building plan sanction granted to the petitioner on 21‑1‑1977 had lapsed for failure to obtain revalidation as required by S. 43 of the Bihar Regional Development Authority Act, 1974 ("the Act").

Facts as set out in the opinion: the petitioner procured land, prepared a map and building plan, and obtained necessary municipal and regional development authority sanctions (the development authority sanction under S. 37(1) of the Act was given on 21‑1‑1977). Construction proceeded but stalled at the ground floor due to financial difficulty. The petitioner applied for revalidation of the map and plan on 20‑1‑1980 as required by S. 43. The second respondent directed payment of the revalidation fee on 10‑11‑1981, which the petitioner deposited that same day. No revalidation order was communicated to the petitioner. On 26‑2‑1988, the petitioner was served with a notice (Annexure‑6) under S. 39(1) directing him to stop construction and produce the sanctioned map. The second respondent maintained that because no revalidation order had been made within the three‑year period prescribed by S. 43, the original sanction had lapsed and the petitioner must apply for a fresh sanction.

The petitioner filed the present petition to quash the impugned order and notice. Respondent No. 2 filed a return disputing the petitioner's position and asserting that the sanction had lapsed on 21‑1‑1980 and that, in any event, a further three‑year period had elapsed before Annexure‑6 was issued.

Legal Issues Presented

  1. Whether S. 43 of the Bihar Regional Development Authority Act, 1974 is ultra vires Articles 14 and 13 of the Constitution of India, as initially contended by the petitioner.
  2. How S. 43 should be interpreted: whether the statutory requirements (submission of a completion certificate within three years and requirement of revalidation) are mandatory (failure leading to automatic invalidation of the sanction) or regulatory (breaches to be assessed in context, not necessarily automatically fatal).
  3. What is the meaning of the phrase "revalidation shall be subject to the Rules and Regulations then in force": whether "then in force" refers to the rules in force at the time of the original sanction or to rules in force at the time of application for revalidation (after expiry of three years).
  4. Whether the second respondent's order (Annexure‑1) and the notice (Annexure‑6) were lawful and within jurisdiction, given the factual history of application and fee payment for revalidation and the respondents' conduct prior to 1988.

Arguments of the Parties

Petitioner's Arguments

  • Initially challenged S. 43 as being ultra vires Articles 14 and 13 of the Constitution (as pleaded by learned counsel), but later refined the challenge to a constructional argument.
  • Argued that S. 43 should be read such that the requirement that the sanction remain valid up to three years — during which a completion certificate must be submitted or revalidation sought — is regulatory rather than mandatory. In other words, failure to meet the three‑year formalities does not automatically render the original sanction invalid.
  • Contended that the phrase "then in force" in S. 43 must refer to the rules and regulations in force on the date the original sanction was granted (i.e., at the time of the 1977 sanction), not rules in force at the time of any later revalidation application.
  • Pointed to procedural conduct by respondents: he applied for revalidation on 20‑1‑1980, paid the revalidation fee when directed on 10‑11‑1981, and respondents did not communicate any revalidation denial until they issued the stop‑work notice in 1988.
  • Asserted that delays in completing construction were due to financial constraints and that there was no allegation of fraud or material suppression in obtaining the original sanction or seeking revalidation.

Respondent No. 2's Arguments

  • Maintained that the original sanction dated 21‑1‑1977 lapsed on 21‑1‑1980 for failure to comply with S. 43.
  • Asserted that even if there was any default by the Patna Regional Development Authority, a further period of three years counted from the petitioner's claim for revalidation had also elapsed before Annexure‑6 was issued in 1988.
  • Argued that the revalidation requirements under S. 43 are intended to ensure adherence to town planning rules and regulations, which are revised periodically to meet planning needs, and therefore must be enforced to ensure compliance with current rules.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The court's analysis proceeded in a stepwise manner and is summarized from the opinion as follows.

  1. Assessment of factual conduct: The court found no allegation or evidence of material suppression or fraudulent representation by the petitioner in obtaining the original sanction or in seeking revalidation. The respondents accepted the petitioner's revalidation application and collected the fee on 10‑11‑1981, and did not treat the application as invalid at that time. The respondents' own conduct suggested they regarded S. 43 as a formality until February 1988.
  2. Characterisation of S. 43: The court examined the statutory language that permits submission of a completion certificate within three years or otherwise requires revalidation. The court concluded that this provision is regulatory rather than mandatory in the sense that non‑compliance does not automatically nullify the prior sanction in every circumstance. The court emphasized that while regulatory provisions must be observed, courts may consider whether non‑observance was intentional; if not intentional, the court may decline to invalidate the act done.
  3. Interpretation of "then in force": The court rejected the interpretation that the phrase "then in force" refers to rules in force at the time of a later revalidation application after expiry of three years. The court reasoned that to give "then in force" the meaning suggested by the respondents would allow retrospective application of changed rules to sanctioned plans, potentially causing serious hardship to persons who had partially performed and invested in construction. The court held that "then in force" must be read as referring to the rules in force when the original sanction was granted.
  4. Workability and justice as interpretive aids: The court invoked principles that statutes should be given workable meanings that promote justice rather than interpretations that would scuttle fair expectations. Applying that approach, the court found it difficult to interpret S. 43 as imposing a strict three‑year limit beyond which revalidation could never operate; revalidation could, in practical terms, continue beyond three years depending on circumstances and conduct of the authority.
  5. Conclusion on jurisdictional error: Because the respondents had not earlier insisted the petitioner revalidate within successive three‑year periods, had accepted the revalidation fee, and had not communicated a revalidation denial, the court found that the second respondent committed an error of jurisdiction and law in issuing Annexure‑1 and related directions in Annexure‑6.

The court also observed that the respondents remain entitled to take action if the petitioner deviates from the original sanctioned plan dated 21‑1‑1977.

Holding and Implications

Holding: The order contained in Annexure‑1 is quashed and set aside for want of jurisdiction and error of law.

Direct consequences and implications:

  • The petitioner is entitled to continue construction of the building in accordance with the plan sanctioned on 21‑1‑1977.
  • The respondents are at liberty to take appropriate action if the petitioner deviates from the sanction granted on 21‑1‑1977; the court did not grant immunity for any actual deviation from the sanctioned plan.
  • On the facts of the case, there is no order as to costs.
  • The opinion does not claim to lay down any new general precedent; it resolves the petition on the particular facts, the statutory construction of S. 43 in that context, and the respondents' conduct in accepting the application and fee without earlier enforcement. The court emphasised a contextual and workable interpretation rather than mechanically applying a strict forfeiture rule.
Order accordingly.
Show all summary ...

1. Petitioner herein has moved this Court for quashing the order as contained in Annexure 1 and the notice as contained in Annexure-6 which, together, forbid the petitioner from proceeding with the construction of a building in the town of Patna (City area) and hold that the sanction accorded to the building plan of the petitioner on 27-1-1988 lapsed because no revalidation was granted as required under S. 43 of the Bihar Regional Development Authority Act, 1974 (hereinafter referred to as ‘the Act’).

2. The petitioner herein, it is not disputed, has alleged that noticing that Patna city was important for tourists, pilgrims and businessmen, visitors needed proper accommodation but there was no posh hotel, managed to have sufficient land, got a map and a building plan prepared by an architect and as required under the provisions of the Patna Municipal corporation Act and the Bihar Regional Development Authority Act, applied to the Corporation and the Patna Regional Development Authority for necessary sanction. Necessary sanctions were accorded to the map and the plan by the competent authorities in the Patna Municipal Corporation and the Town Planning Officer of the Patna Regional Development Authority. Requisite sanction by the development authority, thus, was given to the petitioner under S. 37(1) of the Act on 21-1-1977. The petitioner proceeded accordingly to construct the hotel. In the meanwhile, according to the petitioner, the Government of India introduced a scheme of Janta hotels. The petitioner applied to the concerned department of the Central Government for sanctioning conversion of the petitioner's hotel project into a Janta hotel project. He was by an order dated 15-6-1979 informed by the Director, Hotels, Ministry of Tourism and Civil Aviation (Department of Tourism) that the petitioner's hotels project was approved for domestic and budget minded foreign tourists on the condition that “in the event of your making any changes in the plans of the project as submitted now or in its location the approval of this Department will have to be applied for afresh for the project”. The project, which was for a four storied building, however, got stuck for want of finance (after construction upto ground, floor). The petitioner, as required under S. 43 of the Act, applied for revalidation of the map and the plan on 20-1-1980. The second respondent, however, directed the petitioner to deposit the revalidation fee by his order dated 10-11-1981. On that very day the petitioner deposited the revalidation fee. No communication, however, was made to the petitioner revalidating the sanction accorded for the building construction until he was noticed to appear before the Vice Chairman-second respondent and show cause. The notice (Annexure-6) dated 26-2-1988 purportedly issued under S. 39(1) of the Act asked the petitioner to stop construction of the said building and called upon him to produce the sanctioned map. The petitioner appeared before the second respondent and stated that he had a sanctioned plan on which he had proceed to make construction of the hotel building, that his project was approved by the department of Tourism, Government of India, that he had applied for revalidation on 20-1-1980, that when asked for, he had deposited the revalidation fee on 10-11-1981 and that he was proceeding with the construction rather slowly because he was facing financial problems, yet he had substantially completed the building construction. The second respondent, however, held that S. 43 of the Act required revalidation within a period of three years of the original sanction, that any application for revalidation was required to be made along with the prescribed fee therefor and that revalidation had to be ordered, subject to the Rules and Reglations then in force. According to respondent No. 2, since no revalidation order was made on the application of the petitioner within the prescribed period of three years, the petitioner could not proceed with the construction of the building and revalidation being out of question, the petitioner was required to apply for a fresh sanction which could be granted only when the petitioner was found complying with the Rules and Regulations for construction of a building on the date of the application for a fresh sanction.

3. Learned counsel for the petitioner initially contended that S. 43 of the Act is ultra vires Arts. 14 and 13 of the Constitution of India but modulated his argument to submit that the correct meaning to the language in S. 43 of the Act will lead to the inference that the prescription that the sanction once accorded shall remain valid upto three years during which period a completion certificate from the registered Architect/Engineer/or a person approved by the Vice Chairman in the form prescribed in the building regulation shall be submitted, is not a mandatory provision and that the words that revalidation shall be subject to the Rules and Regulations then in force, for the purpose of revalidation of the sanction, must mean rules and regulations in force on the day the original sanction was ordered.

4. In the return, filed on behalf of respondent No. 2, it has been alleged that the original sanction accorded on 21-1-1977 lapsed on 21-1-1980 and even if it is assumed that there was any default on the part of the Patna Regional Development Authority, a further period of three years counted from the claim of revalidation of the petitioner had also lapsed before the notice as contained in Annexure-6 dated 26-2-1988 was issued.

5. Contentions raised on behalf of the petitioner have been contested by the statements that the requirements under S. 43 for a revalidation are intended to ensure a town planning and development by adherence to the rules and regulations in force which are revised from time to time to meet the needs of planning and development of the city.

6. It is evidently not a case of any material suppression or fradulent representation made by the petitioner for either obtaining the original sanction or claiming revalidation. It is also not a case where any action was taken to cancel the sanction accorded to the petitioner. The respondents received the application of the petitioner dated 20-1-1980 for revalidation and accepted the renewal fee on 10-11-1981. Their conduct gives sufficient support to the fact that they never, until February, 1988, thought that S. 43 had to be enforced. Respondent No. 2 in his order dated 8-4-88, for the first time found that S. 43 had not been observed. Untill then they treated the requirements of S. 43 of the Act as a formality. They never treated petitioner's action of applying for revalidation without requisite fee enough to hold that there was no valid application made for revalidation. That is why they accepted the required fee on 10-11-1981.

7. The condition that in case the complection certificate in the prescribed forms was not submitted, ‘the permit shall have to be revalidated before the expiration of this period’ indicates that it is required to ensure that the Patna Regional Development Authority is informed about the progress of the building construction. This cannot transform the requirements of revalidation into a mandatory decree by law that if not done the permit (sanction) would be rendered invalid. I am inclined, for the said reason, to agree with the interpretation given by the learned counsel for the petitioner that requirements of S. 43 of the Act that completion certificate should be presented within three years of the original sanction and if not done revalidation before the expiration of this period should be asked for, has to be read as a regulatory provision and not as a mandatory provision. I may, however, add that even regulatory provisions are required to be observed. Non-observance of regulatory provisions also sometimes render actions to the contrary invalid, yet in a given case the court may examine, whether omission to observe a regulatory provision was intentional or not. If non-observance is found to be not intentional the court may not for non-observance hold that the act done is invalid.

8. Revalidation shall be subject to the Rules and Regulations then in force can receive to other meaning than one that will make the original sanction valid even after the expiry of the period of three years, in accordance with the Rules and Regulations then in force. Any variation or change in the rules and regulations if introduced in the map and the plan already sanctioned, may cause serious hardship to a person who proceeded to complete the work and could not complete because he either suffered on account of one or the other disability. Then in force must mean in force when the original sanction was granted. Rules for interpretation of statute require that a workable meaning should be given to a statute. A meaning which shall promote the interest of justice is the real meaning and not one which may be used to scotch or scuttle the ends of justice.

9. In the instant case, in my view, no further discussion on the subject is necessary except stating that the words ‘then in force’ cannot mean that the rules and regulations in force at the time of making the revalidation application, that is to say, the time after the expiry of three years from the original sanction will be applied.

10. Had the respondents made their intention known that the petitioner was required to receive revalidation on expiry of each three years period from the original sanction or revalidation or that except one revalidation no further revalidation was permissible, the petitioner who had applied on 20-1-1980 could have applied once again, after the expiry of further three years period for revalidation or could have applied for a fresh sanction. The respondents, however, in my view, could not ask the petitioner to complete the construction of the building within the period of three years from the date of sanction or even within a further period of three years counted from the date of revalidation. A person who invested a substantial amount of money in obtaining the sanction and making substantial construction, must have been under serious constraints of one or the other kind, otherwise no person would attempt delaying construction of a building. Delays occur because of constraints. The petitioner has alleged that he suffered financial constraints. There is no reason to discredit his assertion. Had revalidation been communicated on the application of the petitioner dated 21-1-1980, the petitioner could reckon that a further period of three years began from the date of the revalidation. No such revalidation order was communicated to him. It is difficult to read in the language of S. 43 that revalidation shall be only for a further period of three years. Revalidation may continue even after the expiry of three years. Still, as I have said earlier, respondent No. 2 never insisted that the petitioner should approach for a further revalidation or that the period of revalidation was to survive for three years and not more.

11. Having found as above, I have no hesitation in holding that the second respondent has committed error of jurisdiction and error of law in issuing the order as contained in Annexure-1; the same is accordingly quashed. The petitioner shall be entitled to continue construction of the building in accordance with the plan sanctioned on 21-1-1977. The respondents, however, shall be at liberty to take suitable action against the petitioner if he deviated from the sanction accorded on 21-1-1977. However, on the facts and in the circumstances of the case there will be no order as to costs.

Order accordingly.