National Aluminium C... v. M/S. Panda Engineeri...
Factual and Procedural Background
The petitioner (National Aluminium Company — NALCO) challenged an order of the Subordinate Judge, Angul dated 22-12-1990 passed in Arbitration Misc. Case No. 52 of 1990. The dispute arose from a contract for the work of a Raw Water Intake Piping System awarded to Opposite Party No. 1 (Panda Engineering Works Pvt. Ltd.), who did not complete the work. The petitioner encashed a bank guarantee of Rs. 19,60,560/- and Panda Engineering sought a writ (O.J.C No. 3276 of 1988) seeking release of that bank guarantee. The High Court directed both parties to take steps to appoint arbitrators and refer disputes to arbitration within four weeks; the Supreme Court later modified the High Court's order to direct payment of Rs. 10 lakhs to Panda and that Panda furnish a bank guarantee for Rs. 10 lakhs in favor of NALCO (Civil Appeal No. 2439 of 1989; order dated 17-4-1989).
After these higher court directions, Opposite Party No. 1 appointed an arbitrator and filed a claim statement; the petitioner appointed its own arbitrator and filed a counter-claim. The arbitrators framed issues (40 issues on 4-7-1990) and decided to treat some issues as preliminary while refusing to treat others (including issues the petitioner sought to have decided preliminarily) as preliminary. The petitioner then filed an application under Section 33 of the Arbitration Act before the Subordinate Judge, Angul seeking directions that several specified issues (Nos. 33, 34, 35 and 38 — as described in the opinion) be taken up as preliminary and that certain claims be held non-arbitrable or not maintainable.
The Subordinate Judge refused to direct the arbitrators to decide the petitioner's nominated issues as preliminary, holding that there was a valid reference to arbitration inferred from the High Court and Supreme Court orders and that he was not competent under Section 33 to decide maintainability/arbitrability in the circumstances. The petitioner challenged that order by way of this Civil Revision.
Legal Issues Presented
- Whether a court may entertain and decide an application under Section 33 of the Arbitration Act to determine the "effect" (scope) of an arbitration agreement — including deciding arbitrability and maintainability of claims — even after arbitrators have entered upon reference.
- Whether the Subordinate Judge was competent to refuse to decide the arbitrability/maintainability of specified issues as preliminary issues, given prior directions of the High Court and modification by the Supreme Court.
- Whether particular claims raised before the arbitrators are within the scope of the arbitration clause of the contract or are excluded (i.e., whether they are excepted matters or beyond the agreement) — specifically the claims identified by the petitioner (Issues Nos. 33, 34, 35 and issues listed in the petition).
- Whether issues of fact or mixed questions of fact and law ought to be decided as preliminary issues or reserved for merit hearing (with reference to Order 14, Rule 2(2) of the Code of Civil Procedure).
Arguments of the Parties
Petitioner's (National Aluminium Company) Arguments
- The petitioner sought relief under Section 33 of the Arbitration Act to have the arbitrability and maintainability of the claims raised by Opposite Party No. 1 (Panda Engineering) determined by the Court — including direction to the arbitrators to take specified issues (Nos. 33, 34, 35 and 38) as preliminary issues.
- The petitioner contended some of Opposite Party No. 1's claims were not arbitrable because they were excepted matters under the contract (clause 50) or required prior decision by the Engineer, and that those items should not proceed before the arbitrator without the Court first ruling on arbitrability/maintainability.
- The petition included specific grounds of non-arbitrability set out in paragraph 20 of the petition under Section 33 (as referenced by the court), challenging maintainability of individual claim items.
Opposite Party No. 1's (Panda Engineering Works Pvt. Ltd.) Arguments
- There was a valid reference to the arbitrators as a consequence of directions issued by the High Court and confirmed/modified by the Supreme Court; therefore the arbitration proceedings were maintainable and the arbitrators had jurisdiction to decide the disputes.
- The Court had no jurisdiction under Section 33 of the Arbitration Act to entertain the petition and decide the arbitrability and maintainability of claims while arbitration proceedings were on foot.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Heavy Engineering Corporation Ltd. v. S.P. Arya, AIR 1983 Pat 64 | Section 33 empowers a Court to determine whether a particular dispute falls within the scope/effect of an arbitration clause — i.e., whether disputes can be referred to an arbitrator. | The court relied on this authority to support the proposition that Section 33 enables the Court to examine scope of the arbitration clause and determine whether particular disputes are covered, even after a reference has been made. |
| AIR 1978 Cal 444 | Section 33 does not indicate that the Court cannot decide the effect of an arbitration agreement after arbitrators have entered reference; Section 23(2) differs because it bars the Court from dealing with a dispute it has itself referred to arbitration. | The court applied this reasoning to conclude that because the reference in the present matter was not a court-made reference but resulted from party action and higher court directions, the Subordinate Judge retained jurisdiction to decide scope/effect under Section 33. |
| Bijoy Rout Ray v. Madhusudan Panigrahi, AIR 1986 Ori 105 | Order 14, Rule 2(2) permits trying an issue of law preliminarily only when it relates to Court jurisdiction or a statutory bar; issues of fact or mixed questions are not suitable for preliminary trial to avoid piecemeal hearings. | The court used this precedent to stress that the Subordinate Judge should not treat mixed questions of fact and law as preliminary issues and that preliminary adjudication is limited to pure issues of law relating to jurisdiction or legal bars. |
| Hindustan Steel Ltd., Bhilai Steel Project v. Kaushal Construction Co., AIR 1966 Madh Pra 249 | When a party applies under Section 33 during pendency of arbitration, the Court must identify the questions joined and decide which fall within the arbitration agreement; the Court cannot dismiss such an application simply because the arbitration is on foot. | The court invoked this authority to hold that the Subordinate Judge erred in refusing to determine whether particular claims were arbitrable and in failing to exercise the jurisdiction vested in him under Section 33. |
Court's Reasoning and Analysis
The appellate court proceeded in a structured way:
- Identification of the procedural posture and the petitioner's reliefs: the petitioner asked the Subordinate Judge under Section 33 to direct arbitrators to treat certain issues as preliminary and to determine the scope/ambit/effect of contractual clauses (clauses 20 and 10 of the General Conditions of Contract as pleaded) and to hold certain claims non-arbitrable or not maintainable.
- Review of the Subordinate Judge's decision: the Subordinate Judge had held that the High Court and the Supreme Court directions constituted a valid reference to arbitrators and therefore he was not competent under Section 33 to rule on maintainability/arbitrability; he observed the arbitrators had decided that arbitrability points would be decided on merits and refused to direct them to treat the petitioner's nominated issues as preliminary.
- Examination of Section 33 of the Arbitration Act: the appellate court read Section 33 (which allows a party to apply to the Court to challenge existence/validity of an arbitration agreement or to have its effect determined) and emphasized that "effect" means scope/tenor/drift, and that determination whether a dispute is covered by the arbitration agreement is a determination of "effect" under Section 33.
- Reliance on precedents: the court cited Heavy Engineering Corporation Ltd. v. S.P. Arya for the proposition that Section 33 authorizes the Court to decide whether a dispute is within an arbitration clause. It also cited an AIR 1978 Cal decision to explain that Section 33 does not preclude the Court from deciding the effect of an arbitration agreement after arbitrators have entered reference, particularly where the reference is not one made by the Court itself. The court also invoked Bijoy Rout Ray to underscore limits on deciding mixed questions or factual issues preliminarily (Order 14, Rule 2(2) principles) and Hindustan Steel to show the Court's duty to identify and decide which issues fall within arbitration when an application is made under Section 33.
- Application of law to facts: the appellate court found the Subordinate Judge erred in thinking the High Court or Supreme Court had made an effective reference that ousted the Court's jurisdiction under Section 33. The higher courts had only directed the parties to have disputes resolved by arbitration and to appoint arbitrators; they had not made a court reference under Section 20(4). Because parties themselves had later appointed arbitrators, Section 23 (bar on dealing with disputes a court has referred) did not operate to oust jurisdiction. Consequently, the Subordinate Judge should have heard the Section 33 petition and determined if any of the claims were non-arbitrable.
- On preliminary issues vs. merits: the court reiterated that questions of fact or mixed questions of fact and law are ordinarily to be decided on merits alongside other issues, and that Order 14, Rule 2(2) authorizes preliminary hearing only for issues strictly concerning jurisdiction or legal bars — not for mixed questions that would lead to piecemeal trials.
- Conclusion from analysis: the Subordinate Judge wrongly refused to exercise jurisdiction vested in him to decide whether any claims were non-arbitrable, and therefore his order dismissing the Section 33 petition was set aside.
Holding and Implications
Holding: The Civil Revision is allowed; the impugned order of the Subordinate Judge, Angul dated 22-12-1990 (in Arbitration Misc. Case No. 52 of 1990) is set aside. The matter is remitted to the Subordinate Judge, Angul to hear the Section 33 petition and to give a finding whether all or any of the claims preferred by Opposite Party No. 1 are not arbitrable. The Subordinate Judge is requested to dispose of the Section 33 petition by 15-07-1991. There shall be no order as to costs. (Petition allowed.)
Implications:
- Direct effect on the parties: The Subordinate Judge must now hear the petition under Section 33 of the Arbitration Act and determine, after following the procedure envisaged in Section 33, whether any or all of Panda Engineering's claims are non-arbitrable. The arbitration proceedings are to continue subject to the outcome of that determination.
- Scope of precedent/new law: The opinion applies established authorities concerning the scope of Section 33, the limits of preliminary adjudication under Order 14, Rule 2(2), and the Court's duty where a Section 33 application is made during arbitration. The opinion does not purport to create a new legal precedent beyond applying and reconciling the cited authorities.
1. The petitioner has preferred this Civil Revision challenging the order of the Subordinate Judge, Angul dated 22-12-1990 passed in Arbitration Misc. Case No. 52 of 1990.
2. The petitioner had filed a petition under Section 33 of the Arbitration Act before the Subordinate Judge, Angul with a prayer to direct the Opposite Party Nos. 2 and 3, namely, the Arbitrators.
(a) to take up the arbitrability, maintainability of the claims raised by the claimant-Opp. Party No. 1 Panda Engineering Works Private Limited as preliminary hearing and direct Opposite Parties Nos. 2 and 3, the Arbitrators to take up issues Nos. 33, 34, 35 and 38 as preliminary issues.
(b) to decide the scope ambit and effect of clause 20 and clause 10 of the General Conditions of Contract between the petitioner and Opposite Party No. 1,
(c) to hold that the claims raised by the claimant-Opposite Party No. 1 before the learned Arbitrators are not maintainable, arbitrable and not within the scope of the Arbitration Clause, and
(d) to pass any other orders or direction as the Court deems fit and proper.
3. Issues Nos. 33, 34, 35 and 38 are as follows:—
Issue No. 33: Whether the claims are arbitrable and maintainable?
Issue No. 34: Whether the claims are covered under the terms of the Agreement?
Issue No. 35: Whether the claims are covered under excepted matters?
Issue No. 36: Whether the claims are beyond the terms of the Agreement?
A very statement of facts leading to the filing of this petition under Section 33 are stated thus:
The Opposite Party No. 1 was one of the tenderers for the work of Raw Water Intake Piping System for C.P.P Angul. His tender was accepted by the petitioner-company (National Aluminium Company) and the aforesaid work was given to the Opposite Party No. 1 for execution. Opposite Party No. 1 did not complete the work and the petitioner gave a notice to the Opposite Party No. 1 to encash the bank guarantee amounting to Rs. 19,60,560/- kept with the petitioner. The Opposite Party No. 1, however, moved this Court in O.J.C No. 3276 of 1988 praying for issue of a writ to the petitioner directing them to release the bank guarantee of the Opposite Party No. 1 amounting to Rs. 19,60,560.00 and to give a direction to pay the aforesaid sum if encashed during the pendency of the writ application. The Hon'ble High Court after hearing the parties directed “that both parties will take such steps as required under the contract entered into between them to appoint Arbitrator and to refer to the Arbitrator the disputes relating to the award in question within four weeks”. That on the petitioner's (Panda Engineering Private Ltd.) furnishing an undertaking to the Opposite Parties, namely, NALCO and another that it will furnish bank guarantee for the entire sum, the Opp. Party will refund the sum of Rs. 19,60,560.00 admittedly drawn by them on encashing the bank guarantee of the petitioner during pendency of this case and within a week after receipt of the said amount the petitioner will furnish the bank guarantee which will remain valid till the proceeding before the Arbitrator is concluded.
4. The present petitioner being aggrieved by the said order of the Hon'ble Court passed in O.J.C No. 3276 of 1988 preferred the Civil Appeal before the Hon'ble Supreme Court being Civil Appeal No. 2439 of 1989 arising out of S.L.P No. 4007 of 1989 in which the Hon'ble Supreme Court modified the order of the Hon'ble High Court regarding the amount concerning the bank guarantee and directed as follows:—
“….. ….. We direct the appellant No. 1 National Aluminium Co. Ltd. to pay a sum of Rs. 10 lacs (Ten lacs) out of the amount of Rs. 19,60,650/- which is in dispute, to the respondent Panda Engineering Works Pvt. Ltd. within two weeks and direct Panda Engineering Works Pvt. Ltd. to furnish the bank guarantee for Rs. 10 lacs in favour of the Ist appellant within the week thereafter. We make an order accordingly. The order of the High Court is modified to the above extent. This payment is subject to the ultimate award to be passed in the arbitration proceedings. The appeal is disposed of.”
This order was passed by the Hon'ble Supreme Court on 17-4-1989.
5. The Opposite Party No. 1 pursuant to the order of the Court, has appointed his Arbitrator but without giving notice to the petitioner and filed the claim statement before the Arbitrator. After receipt of the order of appointment of the Opposite Party No. 1's Arbitrator, the petitioner appointed his Arbitrator and also filed its counter claim before the Arbitrator. The Arbitrators entered into reference on 3-7-1990 on which day the present petitioner filed an application to take the arbitrability and maintainability of the claims as preliminary issues. On 4-7-1990, 40 issues were framed by the Arbitrators and on 6-7-1990 the Arbitrators held that Issues Nos. 30, 32 and 39 will be taken up as preliminary issues and other issues with the objection of its arbitrability, maintainability and jurisdiction to adjudicate upon them will be decided in due course of law. After this order was passed by the Arbitrators, the petitioner filed a petition under Section 33 of the Arbitration Act before the Subordinate Judge, Angul which is numbered as Arbitration Misc. Case No. 52 of 1990. The final order dated 22-12-1990 was passed by the Subordinate Judge in the said Arbitration Misc. Case is impugned in this Civil Revision.
Before the Subordinate Judge, Opposite Party No. 1 (Panda Engineering) filed a counter to the said application raising the following objections:
(1) In view of the directions given by the Hon'ble High Court confirmed by the Hon'ble Supreme Court, there was a valid reference to the Arbitrators. There is no question of the Arbitrators having no jurisdiction to decide the dispute. The Arbitration proceeding was maintainable and the claims are accordingly arbitrable.
(2) That the Court had no jurisdiction under Section 33 of the Arbitration Act to entertain such a petition and decide the arbitrability and maintainability of the claims before the Arbitrators.
The Subordinate Judge after considering the petition and the objections filed by the Opposite Party No. 1 came to a finding that the judgment of the High Court and the Supreme Court had taken into consideration the claims and counter claims made by the petitioner and the Opposite Parties and thought that there was dispute between the parties which are to be referred to arbitration and accordingly their Lordships directed for reference of the dispute to the Arbitrators. The Subordinate Judge further held that in the present case although the Hon'ble High Court had not referred the matter to the Arbitrators but it gave sufficient directions about the existence of the dispute between the parties. The Court accordingly held that in view of that he held that there was a valid reference to the Arbitrators and in view of the decision of the Hon'ble High Court and the Supreme Court, he was not competent under Section 33 of the Arbitration Act to give any finding as to the maintainability of the reference and if the issues can be heard preliminarily. The Subordinate Judge also found that the decision of the Arbitrators was to the effect that point of arbitrability will be decided on merit. According to the Subordinate Judge, the allegations that some of the items are not arbitrable being excepted matters under clause 50 of the agreement, the decision of the Arbitrators to take up this matter on merits in due course in the Arbitration proceeding was justified. The Subordinate Judge, however, held the following in para 9 of his order.
“There is definitely some claims which are to be decided by the Arbitrators and some claims are not arbitrable.”
But he came to observe that this can only be decided on merit in usual course and could not be decided as preliminary issues. The refusal of the Arbitrators to treat some issues as preliminary issues cannot be questioned before him in application under Section 33 of the Arbitration Act and ultimately held that he did not find any reason to direct the Arbitrators to decide the above issues, namely, Issues Nos. 33, 34, 35 and 38 as preliminary issues.
6. The trial Court while expressing its opinion regarding his jurisdiction to entertain such a petition under Section 33 filed by the petitioner stated in his order that the power of the Court under Section 33 of the Arbitration Act cannot be taken recourse to against refusal of the joint Arbitrators to treat some issues as preliminary issues, the remedy lies elsewhere. If the petitioner would have come before him by filing a suit before referring their disputes to the Arbitrators, the Court could have given any finding on the above issues. But since the petitioner has already appointed his Arbitrator and the disputes have been referred by the petitioner and the Opposite Party to the Arbitrators and they have participated in the arbitration proceeding, such a petition under Section 33 of the Arbitration Act did not lie to his court. Accordingly, the Court held that he had no jurisdiction to entertain such a petition and decide the maintainability and arbitrability on such issues. Regarding the allegation of the petitioner that some of the disputes are based on factual aspects and under clause 50 of the Agreement were required to be decided by the Engineer first.
The Court held that it appeared that some claims of Opposite Party No. 1 were under the excepted matters which are to be decided by the Engineer but the Court is not competent to decide the same when it is not a case of the petitioner that all the disputes are not arbitrable, the question of arbitration in the present case is a mixed question of facts and law which is to be decided on merits by the Arbitrators. The Court accordingly dismissed the said petition holding that the petition under Section 23 of the Arbitration Act filed by the petitioner was devoid of merit and, as such, was not maintainable and directed the joint Arbitrators to proceed with the proceeding in accordance with law.
7. I have heard the learned Counsel appearing for the parties. They have not left any stone unturned and presented all the facts relating to the agreement and the dispute. After hearing them in detail and going through the papers concerning the matters in hand and the impugned order, I am of the view that the learned Subordinate Judge misdirected himself regarding his jurisdiction in entertaining the application under Section 33 of the Arbitration Act which aims at avoiding the delays and requiring the parties to bring their disputes to courts for expeditious decision in form of petitions.
Section 33 of the Arbitration Act reads as follows:
“Section 33: Arbitration agreement or award to be contested by application:—
Any party to an arbitration agreement or of any person claiming under him desiring to challenge the existence or validity of an arbitration agreement or an award or to have the effect of either determined shall apply to the Court and the Court shall decide the question on affidavits:
Provided that where the Court deems it just and expedient, it may set down the application for hearing on other evidence also, and it may pass such orders for discovery and particulars as it may do in a suit.”
The section envisages three kinds of application, e.g petitions (a) challenging the existence of an arbitration agreement of award, (b) challenging their validity, and (c) to have their effect determined.
The word “effect” in Sections 32 and 33 means “scope, tenor and drift”. In fact determination of whether or not a dispute is covered by the arbitration agreement is determination of the effect of the arbitration agreement within the meaning of Section 33. In the case of Heavy Engineering Corporation Ltd. v. S.P Arya, reported in AIR 1983 Pat 64, the Hon'ble Court has held thus (at page 65):
“….. ….. If a party to an arbitration agreement desires to have the effect of the arbitration clause determined by the Court viz., as to whether the disputes can be referred to an arbitrator being covered by the arbitration clause, the Court also has the authority under S. 33 to decide this question, i.e as to whether the particular dispute was within the scope of the arbitration agreement, or not. By doing this the Court would simply examine the scope of the arbitration clause and it would be nothing beyond the determination of the effect of the arbitration agreement…………..”
The Court is competent to decide and to determine the effect of the arbitration agreement after the Arbitrators have entered on reference.
In the case reported in AIR 1978 Cal 444, it was held thus (at page 448):
“…… Section 33 does not give any indication whatsoever that the effect of an arbitration agreement cannot be decided by the Court after the arbitrators have entered upon the reference. Section 23(2) stands on a different footings. After the Court makes a reference of a dispute to arbitration, it shall not deal with the same in the suit so long as the arbitration proceedings will remain pending. The principle behind the provision of Section 23 seems to be that a Court making the reference to arbitration should not ignore such reference and usurp the jurisdiction to decide the dispute itself pending such arbitration. In the instant case, the reference had not been made by the Court, but by the parties themselves and, therefore, there was no impediment for the Court to decide the scope and effect of the arbitration agreement.”
In the present case, the learned Subordinate Judge was having a wrong notion that there was definite dispute of the parties before this Court or before the Supreme Court which the Court decided to be settled by the Arbitrators. The parties were fighting before this Court and the Hon'ble Supreme Court only relating to the release of the bank guarantee and the orders were only passed concerning the same. But since this bank guarantee is initially connected with the liability of the contractor, the Opposite Party No. 1, and claims and counter claims were being raised by the parties against each other and there was an agreement for arbitration of any dispute concerning the agreement, the High Court and the Hon'ble Supreme Court simply desired that the dispute should be settled before the Arbitrators as is required under the contract as immediately as possible. Therefore, a direction was given that they must present the dispute within four months from the date of the order and pending this settlement of dispute they wanted their order regarding the bank guarantee to be operative. This is, therefore, not actually a reference of any dispute by the High Court under S. 20(4) of the Arbitration Act to the Arbitrators. It is more so because admittedly there was no Arbitrator appointed by any party by the time the matter was concluded by the Court. It was only a direction of the High Court that the parties should settle their disputes in arbitration proceeding but that does not mean that anything that will be referred to the Arbitrator would be decided by him. The parties can question the maintainability or arbitrability of each or all the claims before the Arbitrators. So when the matters were referred to the Arbitrators and the petitioner found that some of the claims or all claims, according to him, are not arbitrable as they pertain to disputed question of facts and are required to be decided by the Engineer before the matter could be arbitrated upon and there were other matters which according to the petitioner were not at all arbitrable apart from this, there was nothing wrong for the petitioner-company to approach the Arbitrators with no application to decide those questions as preliminary issues but making an application does not amount to conferring right on the petitioner to force the Arbitrators to decide those as preliminary issue. The Arbitrators are free to take a decision as to which of the issues they can hear as preliminary issues.
8. Law is well settled that Order 14, Rule 2(2) of the Code of Civil Procedure authorises the Court to dispose of an issue of law only by trying that issue first relating to
(a) the jurisdiction of the Court, or
(b) a bar to the suit created by any law for the time being in force, and for that purpose may, if it thinks fit, postpone the settlement of the other issues until after that issue has been determined, and may deal with the suit in accordance with the decision on that issue.
So an issue of fact or mixed question of fact and law is not to be decided on a preliminary issue which should be decided on merits along with other issues in the suit.
In a case of Bijoy Rout Ray v. Madhusudan Panigrahi, reported in AIR 1986 Ori 105, this Court hold that (at page 106):
“….. ….. Court is to pronounce judgment on all issues. Same is the principle envisaged under S. 98 of the Act. Postponement of the settlement of other issues is possible only where the case or any part thereof may be disposed of on an issue of law only if that issue relates to the jurisdiction of the Court or being barred by law. Order 14 was, amended by Act 104 of 1976 to avoid piecemeal trials and where answer to an issue would depend upon consideration of evidence even though it relates to jurisdiction or a bar of suit by any law, the same would be heard along with other issues.”
The Subordinate Judge was not hearing as appeal against the decision of the Arbitrator to hear the issues Nos. 33, 34, 35 and 38 as preliminary issues to be decided with other issues on merits.
The petitioner, however, under Section 33 of the Act has made further prayers out of which the first part of his prayer related to preliminary hearing of certain issues but the rest of the prayers were of very different in nature. The petitioner was questioning the scope, ambit and effect of clauses 30 and 50 of the general conditions of the contract and were challenging the maintainability, arbitrability of the claims of Opposite Party No. 1. As already stated, one of the three prayers that could be made under Section 33 of the Arbitration Act is to require the Court to determine a particular issue in dispute if it is within the ambit of the agreement and within the scope of arbitration under the said agreement.
Sub-section (35) is an independent provision permitting a party to an arbitration proceeding to challenge before the Court, the arbitrability of any of the claims raised before the arbitrator and as I have already stated just because they have entered appearance before the Arbitrator and the Arbitrator is in seisin of the proceedings, the Court is not ousted of this jurisdiction to give a finding upon the arbitrability. The petitioner in his petition under Section 33 of the Act has raised various objections challenging the maintainability of the items of the claims raised by Opposite Party No. 1 and has categorically mentioned in para-20 of his petition under Section 33 of the Arbitration Act the grounds of non-arbitrability of such claims.
In Hindustan Steel Ltd., Bhilai Steel Project v. Kaushal Construction Co. Architects, Engineering Contractors, reported in AIR 1966 Madh Pra 249, the Court held thus (at page 250):
“For the foregoing reasons, it seems to me clear law that where, during the pendency of proceedings before an arbitration, any party to the arbitration agreement applies to the Court under Section 33 of the Act to have the effect of the arbitration agreement determined, the Court is bound to find out the questions on which the parties, have joined issue and then to hold which of such issues fall within the jurisdiction of the agreement. The Court has no power to dismiss an application, not even on the ground that the arbitration agreement is a clause in a contract and the decision may involve a declaration as to the existence or validity of the contract itself.”
In the present case, therefore, the learned Subordinate Judge has failed to exercise the jurisdiction that was vested in it in disposing of the application under Sec. 33 of the Arbitration Act by giving its decision as to if any of the claims made before the Arbitrators was not arbitrable according to the agreement and he having refused to go into that question on the wrong apprehension that the disputes now are referred to the Arbitratior by the High Court and confirmed by the Hon'ble Supreme Court had the sanction of the High Court or the Supreme Court was wrong, and he has clearly failed to exercise the jurisdiction that was vested in him.
9. In view of that, the impugned order of the Subordinate Judge cannot be allowed to stand and is accordingly set aside. The matter is remitted back to the Subordinate Judge, Angul, who shall hear both the parties in accordance with the procedure contemplated under Section 33 of the Arbitration Act and give a finding if all or any of the claims preferred by the Opposite Party No. 1 are not arbitrable. Since the Opposite Party No. 1's money has been held up during the pendency of the arbitration proceeding, it is desirable that the learned Subordinate Judge may dispose of the petition under Sec. 33 of the Arbitration Act filed by the petitioner within 15-7-1991.
10. The Civil Revision is allowed but in the circumstances, there shall be no order as to costs.
Petition allowed.