Factual and Procedural Background

The matter is a Public Interest Litigation filed by a petitioner who identifies himself as a social worker and environment activist. The petitioner sought a writ of mandamus restraining the respondents (Metro Railway authorities or their agents) from extending a Metro Rail project through the river bed of Adi Ganga and prayed for the recall and rescission of the extension project. The petitioner alleged that a prior order by the Court's Green Bench had directed cleaning and improvement of Adi Ganga, and that despite that, the Metro extension from Tollygunge to Garia would place pillars in the middle of the river along a stretch described as approximately six kilometres. The petitioner asserted that the State had spent Rs. 35.51 crores on cleaning, dredging and removing encroachments from Adi Ganga, and that constructing pillars in the river would obstruct free flow of water and harm a river of cultural and religious significance.

The Metro Railway filed an affidavit-in-opposition. It stated that construction of the extension began only after obtaining permission from the State Government; the extension, sanctioned in 1999–2000 at Rs. 696 crores, is an elevated structure running along Tolly Nala for 8.45 km with six stations; the project would be beneficial to the public by improving access and reducing pressure on existing suburban rail sections; technical measures had been taken to avoid silting and permit future dredging; Metro agreed to extra-widening and lining proposals by the Irrigation Department; Metro engaged M/s M.N. Dastur & Company Ltd. for an environmental impact assessment (EIA); and Metro's Chief Engineer clarified that construction would not disturb thickly populated residential areas on either side of the nullah.

The Court heard counsel for the parties and disposed of the writ petition after considering statutory provisions, administrative steps already taken by Metro, and relevant precedent.

Legal Issues Presented

  1. Whether the Court should exercise writ jurisdiction to restrain or recall the Metro Rail extension project that involves placing pillars in the river bed of Adi Ganga.
  2. Whether statutory environmental controls (including the Environment (Protection) Act, 1986 and associated rules/notifications) require environmental clearance for railway projects such as the Metro extension.
  3. Whether Section 11 of the Railways Act, 1989 — particularly its non-obstante clause and powers to construct in or across rivers and to alter watercourses — overrides environmental legislation and thereby precludes judicial interference in the railway construction project.

Arguments of the Parties

Petitioner's Arguments

  • The Metro extension will place pillars in the middle of Adi Ganga along a substantial stretch (allegedly about 6 km), obstructing free flow and harming the river's environment and cultural/religious significance.
  • The State had already invested in cleaning, dredging and de-encroachment works for Adi Ganga, and the Metro's permanent structures would undermine those efforts.
  • Invoked principles of sustainable development (referencing the Stockholm Declaration and "Our Common Future"), including intergenerational equity, conservation of natural resources, precautionary principle and polluter-pays, to argue that the project should not tamper with the river's free flow.

Respondent Metro Railway's Arguments

  • The Metro commenced construction activities only after obtaining permission from the State Government.
  • The extension is an elevated structure designed to benefit the public by improving connectivity (linking Eastern Railway at Garia, bringing South 24-Parganas closer to the Central Business District) and easing pressure on existing rail sections.
  • The project was sanctioned at Rs. 696 crores and runs along Tolly Nala for 8.45 km with six stations.
  • Technical measures have been addressed to prevent silting and to preserve feasibility of future dredging; Metro agreed to extra-widening and lining proposed by the Irrigation Department.
  • Metro appointed M/s M.N. Dastur & Company Ltd. to prepare an environmental impact assessment and the Chief Engineer clarified that heavily populated residential areas would not be disturbed.
  • Metro contended that the Environment (Protection) Act's provisions are not applicable to construction of the railway project (as a matter of statutory position asserted in their affidavit).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Goa Foundation v. Konkan Railway Corporation, AIR 1992 Bombay 471 (Bombay High Court) Consideration of Section 11 of the Railways Act vis-à-vis environmental and forest conservation statutes; whether writ jurisdiction should be exercised to restrain railway construction. The Division Bench declined to exercise writ jurisdiction over the Konkan Railway construction. The present Court relied on that approach to support non-interference in a railway construction project under similar statutory considerations.
Special Leave Petition in relation to Goa Foundation v. Konkan Railway — Order dated 7.12.89 (Supreme Court) Supreme Court's treatment of the Bombay High Court decision (affirming the judgment while setting aside costs and certain remarks). The Court noted that the Apex Court affirmed the Bombay High Court's judgment (subject to costs/remarks being set aside), and treated this affirmation as further support for the conclusion that writ interference was not appropriate in the present case.

Court's Reasoning and Analysis

The Court examined the statutory framework and administrative facts and concluded that it could not interfere in the present Public Interest Litigation. The reasoning followed these main steps:

  1. The Court reproduced and analysed Section 11 of the Railways Act, 1989. Section 11 contains a non-obstante clause ("Notwithstanding anything contained in any other law for the time being in force") and grants wide powers to a railway administration to construct works "in or upon, across, under or over" rivers and to alter or divert the course of rivers or streams for purposes of railway construction and maintenance.
  2. Because Section 11 starts with a non-obstante clause and the Railways Act, 1989 is a subsequent enactment (i.e., later in time) compared to the Environment (Protection) Act, 1986, the Court concluded that the later statute (Railways Act, 1989) has overriding effect over inconsistent provisions of the earlier Environment Act. The Court explained the legislative purpose and normal operation of non-obstante clauses as a device to grant overriding effect to later enactments.
  3. The Court considered the Environment (Protection) Rules, 1986 notification (issued under the Environment (Protection) Act) which requires environmental clearance for projects listed in Schedule I. The Court noted that Schedule I does not include railway projects, and therefore the specific statutory notification did not require central environmental clearance for the Metro project.
  4. The Court recorded administrative steps: the State Pollution Control Board had extended permission for cutting trees (dated 10-05-2000) on the recommendation of the Forest Department; no overall No Objection Certificate had been issued by the West Bengal Pollution Control Board for the entire project because the project had not submitted an EIA study; concurrently, the Metro had engaged M/s M.N. Dastur & Company Ltd. to undertake an environmental impact assessment.
  5. The Court drew on precedent — a Bombay High Court decision in Goa Foundation v. Konkan Railway and the subsequent Supreme Court action in that matter — where the Division Bench declined to exercise writ jurisdiction in a broadly similar context. The Supreme Court affirmed the judgment (though set aside certain costs and remarks), and the present Court treated that outcome as persuasive in concluding that judicial interference was not appropriate here.
  6. Although the Court concluded there was no statutory bar to the project and thus no ground to issue the requested writ, it emphasised that this did not license a complete disregard for environmental concerns. The Court noted the Metro had appointed an expert firm to assess environmental impact and expressed the expectation that Metro Railway authorities would abide by the expert recommendations and attempt to minimise environmental harm while carrying out a public-interest developmental project.

Holding and Implications

Holding: The Court declined to grant the relief sought by the petitioner and therefore did not restrain or recall the Metro Rail extension project. The writ petition was disposed of.

DISPOSED OF

Implications:

  • The immediate, direct effect is that the petitioner's request for judicial intervention to stop or rescind the Metro extension through Adi Ganga was refused and the Metro project may proceed subject to applicable statutory and administrative provisions.
  • The Court relied principally on the statutory position under Section 11 of the Railways Act, 1989 (including its non-obstante clause) and on precedent declining writ interference in a comparable railway project; the opinion therefore does not create a novel judicial rule contrary to those statutes or precedents described in the judgment.
  • The Court expressed a clear expectation that the Metro authorities will follow the EIA recommendations made by the expert firm they engaged; beyond that admonition, the judgment records no additional supervisory or remedial orders directed at the respondents.

Disposition recorded in the opinion: "The writ petition is accordingly disposed of with the above observations." (G.C. Gupta, J. agreed.)

Show all summary ...

A.K Mathur, C.J:— This is a Public Interest Litigation whereby the Petitioner has prayed that by a writ of Mandamus the Respondents or their agents should be restrained from extending the project of Metro Rail through the river bed of Adi Ganga in any manner and to recall and rescind the project of extension of Metro Rail. Petitioner alleged that he is a Social Worker and environment activist. Therefore he has filed this petition for protection of the environment. It is alleged that the Green Bench of this Court has already passed an order of cleaning of Adi Ganga and also directed to implement the Scheme for Improvement of the river Adi Ganga. It is alleged that Petitioner has come to know that the extension project of Metro Railway from Tollygunge to Garla has now started and substantial part of Metro Rail will be laid on Adi Ganga by constructing pillars at the middle of the river. It is alleged that on account of construction of pillars in the river bed the entire stretching from Tollygung to Garia about 6 Kilometre will be covered by pillars. It is alleged that on the one hand the State Government has already implemented a Scheme for cleaning, dredging and removing the encroachments from Adi Ganga by spending Rs. 35.51 Crores and on the other hand a permanent construction are being created by the Central Government Agency that is Metro Rail Authority by constructing pillars at the middle of the river for the entire stretching from Tollygunge to Garla. It is alleged that the construction of these pillars will be highly detrimental to the free flow of the water in this river. Therefore being inspired by the bonafide intention to maintain the environment and not to interfere with the free flow of water in river Adi Ganga the petitioner has filed this petition. It is also submitted that Adi Ganga carries a high degree of cultural and religious heritage of Calcutta/West Bengal/Hinduism. Therefore it is a sacred duty of all citizens to save this from being polluted.

2. In the written submission also the petitioner has repeated more or less what he has said in the writ petition and he has tried to highlight that in this new millennium it is the duty of all the citizens of the World to maintain ecology. It is submitted that the concept of sustainable development has been come to be known for the first time in the Stockholm Declaration of 1972 and thereafter this concept has been given a definite shape by World Commission on Environment and Development in its Report called “Our Common Future”. It is pointed out that the salient principles of “Sustainable Development” are the Inter Generational Equity, use and Conservation of Natural Resources, Environmental Protection, the Precautionary Principle, Polluter Pays Principle, Obligation to assist and Cooperate, Eradication of Poverty and Financial Assistance to the developing countries. It is also pointed out that the environmental measures mean that the State Government and the statutory authorities must anticipate, prevent and attack the causes of environmental degradation. Therefore the whole attempt of the petitioner with reference to the various National and International documents is to show that the Metro Rail should be prevented from tampering with the free flow of the water in sacred and religious river Adi Ganga. An affidavit-in-opposition was filed by the Respondent Metro Railway and they have pointed out that the Metro Railway started the construction activities relating to extension project along the Central line of the Tolly Nala only after obtaining permission from the State Government. It is submitted that this extension of the Metro Railway will be highly beneficial to the people of Calcutta. It will also connect Eastern Railway at Garia and will bring South 24-Parganas closer to Calcutta Central Business District. This will also reduce enormous pressure of Sealdah South Subarban Section. It is also pointed out that this extension was sanctioned at a cost of Rs. 696 Crores in the year 1999–2000. The section will be on the elevated structure and the alignment will run along the Tolly Nala to the extent of 8.45 K.M with six stations. The full project will be most useful project for the benefit of the public at large. It is also pointed out that all technical redressal had been addressed to avoid silting of the nullah as well as to ensure feasibility of future dredging. It is also pointed out that the Metro Railway has agreed to the proposal of extra-widening and lining of the nullah as proposed by the Irrigation Department. It is also pointed out that the Metro Railway has engaged M/s M.N Dastur and Company Ltd. for carrying out environment Impact Assessment in connection with the extension. It is also pointed out that the Chief Engineer, Metro Railways has issued a clarification that they will not disturb a huge thickly populated residential area on either side of the Tolly nullah and the proposal to run the train through the Tolly's nullah has been accepted. It is also pointed out that the provisions of the Environment Act is not applicable to the construction of the Railway Project.

3. We have heard learned counsel for the parties at length. After going through the matter we are of the opinion that in the present state of legal position which we shall advert to herein-after it would not be possible to Interfere in this Public Interest Litigation. In this connection our attention was invited to section 11 of the Railways Act, 1989. Section 11 of the Railways Act reads thus:

“11. Notwithstanding anything contained in any other law for the time being in force, but for subject to the provisions of this Act and the provisions of any law for the acquisition of land for a public purpose or for companies, and subject also, in the case of a non-Government railway and the Central Government, a railway administration may, for the purposes of constructing or maintaining a railway—

(a) Make or construct in or upon, across, under or over any lands, or any streets, hills, valleys, roads, railway, tramways, or any rivers, canals, brooks, streams or others waters, or any drains, water-pipes, gas-pipes, oil-pipes, swears, electric supply lines, or telegraph lines, such temporary or permanent inclined-planes, bridges, tunnels, lines of railways, passages, conduits, drains, piers, cuttings and fences, in-take wells, tube wells, dams, river training and protection works as it thinks proper;

(b) alter the course of any rivers, brooks, streams or other water courses, for the purpose of constructing and maintaining tunnels, bridges, passages or other works over or under them and divert or later either temporarily or permanently, the course of any rivers, brooks, streams or other water courses or any roads, streets or ways, or raise, or sink the level thereof, in order to carry them more conveniently over or under or by the side of the railway:

(c) make drains or conduits into, through or under any lands adjoining the railway for the purpose of conveying water from or to the railways:

(d) erect and construct such houses, warehouses, offices and other buildings, and such yards, stations, wharves, engines, machinery apparatus and other works and conveniences as the railway administration thinks proper;

(e) alter, repair or discontinue such buildings, works and conveniences as aforesaid or any of them and substitute others in their stead;

(f) erect, operate, maintain or repair any telegraph and telephone lines in connection with the working of the railway;

(g) erect, operate, maintain or repair any electric traction equipment, power supply and distribution installation in connection with the working of the railway; and

(h) do all other acts necessary for making, maintaining, altering or repairing and using the railway.”

4. Section 11 starts with the non-obstante Clause “Notwithstanding anything contained in any other law for the time being in force” thereby the provisions of any other enactment will not come in the way of the construction undertaken by the railways, be it on any line or any streets, hills, valleys, roads, rivers, canals, brooks, streams or other waters and drains. It further says that It can alter the course of rivers, brooks, streams or other water courses for the purpose of constructing and maintaining tunnels, bridges, passages or any other works over or under them and divert or alter either temporarily or permanently, the course of any rivers, brooks, streams or other water courses.

5. Therefore, in view of the overriding provisions of this Act all other provisions stand superseded by virtue of this non-obstante Clause. In this connection it may also be relevant to mention that (The) Environment (Protection) Act, 1986 is an earlier legislation than that of the Indian Railways Act, 1989 (hereinafter referred to Act of 1989). Therefore the Indian Railways Act, 1989 will supersede the Environment (Protection) Act, 1986 (hereinafter referred to Act of 1986). That section 24 of the Act of 1986 which has also a non-obstante clause which also says that any Act or Rules or Orders made shall not have any effect notwithstanding anything contained inconsistent with the provisions of this Act. These two non-obstante Clauses appear in two different enactments. But the Railways Act is a subsequent Act than that of the Environment Act. In case of two non-obstante Clauses appearing in two different enactments, when the subsequent enactment says that notwithstanding anything contained in any law for the time being in force it supersedes all the enactments prior to coming into force of this enactment. The non-obstante Clause is normally used as a legislative device to modify the ambit of provisions of the existing law and to have the overriding effect. Therefore in view of this statutory provision no effect can be given to the Environment Act. In this connection our attention was invited to a Notification issued under the Environment (Protection) Rules, 1986. This Notification had been issued in exercise of the power conferred under sub-section (1) and Clause 1 of sub-section (2) of section 3 of the Environment (Protection) Act, 1986 read with Clause (d) of sub-rule 3 of Rule 5 of the Environment Protection Rules 1986 thereby the Central Government has directed that on and from the date of publication of this Notification in the Official Gazette, expansion or modernization of any activity if pollution load is to exceed the existing one or new project listed in Schedule I to this notification, shall not be undertaken in any part of India unless it has been accorded environmental clearance by the Central Government in accordance with the procedure laid down in this Notification. However the Schedule-I appended to this Notification does not include the Railway Projects. Central Government has laid down that for projects mentioned in Schedule I for which an environment clearance has to be taken from Central Government. In that there is no mention of the railway projects. State Pollution Board has also informed the Court that the Board also issued an Order extending permission to the Metro Railway Authorities for cutting of trees for the project on 10-05-2000 as per the recommendation of the Forest Department, Government of West Bengal. It is also pointed out that “No Objection Certificate” has not been issued at present by the West Bengal Pollution Control Board for the entire project as the project did not submit “Environment Impact Assessment” study. In this background so far as the railway projects are concerned, there is no requirement of the environment clearance under the statutory provisions and the Railways Act, 1989 has the overriding effect. However by this we do not mean to suggest that there should be complete go by to the environment impact. The Railway Administration, the Metro Railway themselves have already appointed a Firm M/s. M.N Dastur and Company to assess the environmental impact of the construction of this Railway. Though no direction can be given so far as the Project is concerned as there is no statutory bar, however the Metro Railway Authorities has already appointed an expert body to undertake the environmental impact and we hope and trust that the Metro Railway Authorities will abide by the recommendation made by the expert body appointed by them. It is true that the construction of the Metro Railway Project is also a public project for the welfare and benefit of the public. However such developmental work should also work harmoniously with the environment causing as far as possible less harm to environment.

6. Our attention was also invited to a decision of the Bombay High Court in the case of The Goa Foundation v. The Konkan Railway Corporation, reported in AIR 1992 Bombay at page 471. There a somewhat identical problem was faced by the Railway Administration for construction of the Konkan Project and in that connection the Division Bench of that Court came to consider the impact of section 11 of the Railways Act, vis-a-vis the Environment and Protection Act and the Forest Conservation Act of 1980. The Division Bench after considering the matter declined to exercise writ Jurisdiction over the construction of the aforesaid Railway Project. The matter was taken up before the apex Court by way of Special Leave Petition and their Lordship affirmed the aforesaid judgment by Their Order dated 7.12.89 However Hon'ble Supreme Court only set aside the cost awarded by the Bombay High Court and certain remarks made in that Judgment. Thus in view of these statutory provisions it is not possible to interfere in this Public Interest Litigation. However as mentioned above, we hope that the Railway Administration will certainly abide by the advice given by M/s. M.N Dastur & Company on their Study and Assessment of the Environmental Impact of this Project.

The writ petition is accordingly disposed of with the above observations.

G.C Gupta, J.:— I agree.

Petition disposed of