C.E.S.C Ltd. & Ors. v. Karan Cafe & Ors.
Structured Summary of the Opinion
Factual and Procedural Background
These appeals arise from an order of a learned Single Judge directing restoration of electric supply without any conditions requiring deposit of any sum against demands made by the appellant (the licencee/CESC). The appeals, presenting identical questions, were heard together and are disposed of by this common judgment.
The proceedings concern multiple writ petitions in which the licencee alleged theft/pilferage of electricity and raised demands covering the period of one year prior to the date of alleged detection. In addition to estimated pilfered electricity, demands included government duty, fuel surcharge and an additional security amount.
The learned Trial Judge (order dated 28th June 1999, quoted in the opinion) observed absence of evidence about notice or disconnection in the petitioner’s presence and directed restoration of the electrical connection within 48 hours subject to payment of Rs. 40 as re-connection charges and with the question of a 50% deposit to be heard on affidavits on a returnable date.
Legal Issues Presented
- Whether restoration of electricity supply should be made conditional upon payment of fifty percent (50%) of the amount claimed by the licencee for alleged pilferage (i.e., whether fifty percent of the demand must be deposited before restoration).
- Whether there should be consistency and uniformity in the exercise of judicial discretion in cases involving theft/pilferage of electricity, so that similar matters receive similar treatment (and whether the learned Single Judge erred in not imposing a 50% deposit condition).
Arguments of the Parties
Appellant's Arguments (as stated in the opinion)
- Mr. Anindya Mitra, senior counsel for the appellant, argued for the need for consistency and uniformity in judicial discretion in theft/pilferage cases so that similar matters receive similar treatment and to avoid grievances of discriminatory treatment.
- It was urged that, in light of consistent earlier decisions directing restoration of electricity supply subject to payment of 50% of the demand, the learned Single Judge ought to have directed restoration subject to deposit of 50% of the demand in the instant cases.
Respondents' / Writ Petitioners' Contentions (as stated in the opinion)
- The respondents contended that neither at the time of inspection nor while removing meters was a fair and reasonable procedure adopted by the appellant/licencee.
- They argued the demands raised (for one year prior to alleged detection) were unreasonable and unsupported by any basis, including charges for government duty, fuel surcharge and additional security amount; they described these demands as arbitrary and without jurisdiction.
- It was contended that in the absence of relevant material establishing pilferage, a prima facie conclusion of theft could not be reached, and it would be improper for the court to uphold a demand or condition based on such a presumption.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Vishnu Traders v. State of Haryana, 1995 Suppl. (1) SCC 461 | Observation that in interlocutory matters the principle of binding precedent does not strictly apply, while emphasizing the need for consistency and uniformity in judicial discretion. | The court accepted the dual proposition: interlocutory orders are not strictly bound by precedent, but consistency in approach is desirable; this informed consideration of earlier single-judge orders directing deposit conditions. |
| Hanuman Steel Rolling Mills, AIR 1996 Cal. 449 | Interim order directing restoration on deposit (noted: deposit of Rs. 1,50,000/- in paragraph cited); decision that disconnection on ground of pilferage requires compliance with principles of natural justice in absence of rules. | The court noted this as one of the decisions where restoration was ordered subject to deposit; cited as part of the body of decisions showing a pattern, and as authority for the proposition that natural justice may be required before disconnection in absence of regulatory provisions. |
| Siva Steel Rolling Mills Ltd., 1998 (1) CLT 424 | Direction for restoration of supply on payment of Rs. 30 lacs within 72 hours; preservation of old meters and reference to Chief Electrical Inspector. | Used as an example of a single-judge decision directing restoration subject to payment and referring disputes to the Electrical Inspector. |
| P.K. Mukherjee v. CESC Ltd., 1999 (1) CHN 107 | Final disposal directing restoration on payment of 50% of amount claimed within 72 hours; preservation of meters and reference to Electrical Inspector. | Referred to as another decision where restoration was made conditional on payment of 50% and referral to the Electrical Inspector. |
| Nishi Kanto Banik v. CESC, 1996 (2) CHN 534 | Disposal directing payment of 50% of amount claimed and restoration within 48 hours; disputes referred to Electrical Inspector. | Cited as authority distinguishing fact situations and as a decision in which deposit of 50% was directed; also used to illustrate limitations on CESC's power to withhold supply without legal authority. |
| Unreported Division Bench in Meena Agarwal (FMAT No. 364-367 of 1999, dated 15-2-1999) | Directed deposit of 50% by way of interim order (unreported). | Noted as part of the practice of directing 50% deposits in interim orders. |
| W.B. State Electricity Board v. Fakir Chand Rice Mills, 1996 (8) SCC 647 | Statutory principle that in money claims normally at least half of the amount should be directed to be deposited. | The court acknowledged this Supreme Court principle as relevant to the question of directing deposits in interim orders. |
| M.P. Electricity Board v. Harish (Harsh) Wood Products, 1996 (4) Supreme 630 | Held that when electricity authorities detect malpractice (including tampering), they may disconnect forthwith and call for payment; a consumer is not entitled to prior notice under section 24 where pilferage is detected; proceedings were drawn in presence of consumer's representative and meters found tampered. | The court relied on this decision as the principal Supreme Court authority allowing disconnection without prior notice where prima facie tampering is established; it distinguished that the Harish Wood facts included inspection in presence of consumer and a prima facie finding, which the instant cases lacked. |
| Hyderabad Vanaspati Ltd. v. A.P. State Electricity Board, AIR 1998 SC 1715 | Held that regulations under section 49 of Electricity (Supply) Act, 1948 empowering provisional assessment of unmetered consumption (Clause 39) were within the Board's powers and not ultra vires the cited Acts; elaborated procedure for provisional and final assessment with hearing. | Referred to for the proposition that where Regulations exist they can empower provisional assessment; contrasted with the West Bengal position where such regulations had not been framed. |
| M.P. State Electricity Board v. Smt. Basanti Bai, AIR 1988 SC 71 | Held that fraud by tampering with the meter or breaking seals is outside the ambit of section 26(6) and an Electrical Inspector has no jurisdiction to decide such cases of fraud; Electrical Inspector may decide disputes about meter correctness or inherent defect. | Relied upon to clarify the limits of the Electrical Inspector's jurisdiction and to explain which disputes fall within the Inspector's purview. |
| State of West Bengal v. Rupa Ice Factory, 1997 (2) CHN 254 | Division Bench held that in absence of rules/regulations or agreement authorising the licencee to determine amount payable for pilferage the matter should be decided by the Electrical Inspector; clause 6(iii) of the Schedule to the Indian Electricity Act construed to permit reference. | Used to support the position that where licencee lacks express statutory/regulatory power the dispute should be referred to the Electrical Inspector. |
| Ganges Manufacturing Co. Ltd. v. West Bengal State Electricity Board, 1993 (2) CLJ 210 | Authority for referring disputes relating to tampering of meters to the Electrical Inspector. | Cited as part of the preponderant judicial opinion of this High Court that disputes about tampering should be determined by the Electrical Inspector. |
| Shiva (Siva) Steel Rolling Mill Ltd. v. CESC Ltd., 1998 (1) Calcutta Law Times 424 | Case considering the power of the Board/licencee to assess unmetered consumption; cited among relevant decisions. | Referred to as one of the decisions addressing licencee power to raise bills for unmetered consumption. |
| Isha Marbles v. Bihar State Electricity Board, 1995 (2) JT 626 | Observation that dishonest consumers cannot be allowed to prey on public property, but inadequacy of law cannot justify over-zealousness. | Quoted to balance the need to prevent dishonest consumers and the need to avoid excessive or improper action by the licencee. |
Court's Reasoning and Analysis
The court's analysis proceeds from two intersecting considerations: (a) the need for consistency and uniformity in judicial exercise of discretion in theft/pilferage cases (as urged by the appellant), and (b) the sufficiency of material to reach a prima facie conclusion of pilferage in the instant cases.
The court recognized the authority of the Supreme Court decisions (notably the Harish Wood Products case) that allow a Board/licencee to disconnect supply and call for compensation where prima facie tampering is established, and that prior notice under section 24 need not apply in such cases. The court also acknowledged decisions and practice in which single judges have directed restoration subject to deposits (often 50%), and the Supreme Court's statement that in money claims normally half the amount should be directed to be deposited.
However, the court emphasized that those precedents often turned on factual matrices where inspection proceedings were drawn up in the presence of the consumer (or representative), seals were found tampered and a prima facie conclusion of pilferage could be reached. By contrast, the instant cases lacked such material to justify a prima facie conclusion. The court found deficiencies in the procedure adopted by CESC:
- Bills produced by CESC were not prepared on any explained principle; how amounts were calculated was "not known to this court".
- The demands covered a lengthy period (one year) and included additional items (fuel surcharge, government duties, additional security) leading the court to view the overall procedure as not satisfying a test of reasonableness.
- In absence of materials from which the court could arrive at a prima facie conclusion of tampering, it was not appropriate to withhold supply or to require 50% deposits by way of interim condition, on the facts before the court.
Given that there are no appropriate State regulations in West Bengal like those considered in Hyderabad Vanaspati's case, and in light of existing High Court authority, the court concluded that the suitable course was to refer the disputes for adjudication before the Chief Electrical Inspector as a "Special Referee". The Inspector, being an expert statutory authority, could examine the facts, hear parties, assess damages (if any), and determine whether allegations of tampering/pilferage are established.
The court also reaffirmed that (i) the writ petitioners must continue to pay charges for consumption recorded in the meter and any admitted charges; (ii) if such admitted charges or bills based on meter consumption are not paid, the licencee may resort to section 24 of the Indian Electricity Act for recovery; and (iii) the interim order of the learned Trial Judge (restoration subject to the modest re-connection charge and further consideration of 50% deposit) would remain subject to any final order after proper adjudication.
Holding and Implications
Holding: The appeals were disposed of with directions that:
- The matters be relegated to adjudication before the Chief Electrical Inspector as Special Referee.
- The interim order passed by the learned Trial Judge (restoring electricity subject to payment of re-connection charges and further hearing on any deposit) shall remain in effect but is subject to any final order that may be passed following the reference and adjudication.
- The writ petitioners must continue to pay charges for consumption as recorded in the meter and any admitted charges; failure to pay such admitted charges may permit the appellant to invoke section 24 of the Indian Electricity Act for recovery.
The court expressly held that, on the facts before it, the appellant/CESC was not entitled to the same relief as in Harish Wood Products (i.e., an automatic direction for payment of 50% of the demand before restoration) because the procedure adopted by CESC did not satisfy the test of reasonableness and there was insufficient material to reach a prima facie conclusion of pilferage.
Implications:
- Direct effect on the parties: the restoration order of the learned Trial Judge is upheld for the interim and the disputes are to be referred to the Electrical Inspector for full adjudication; consumers remain liable to pay charges recorded by the meter; the licencee may seek statutory remedies for unpaid admitted charges.
- Procedural guidance: the court emphasized that CESC (and similar licencees) must adopt fair and reasonable procedures (including drawing up inspection proceedings in the presence of the consumer or representative and basing demands on reasonable grounds such as previous consumption) before asking courts to direct restoration on the basis of deposits; where such fair procedure and prima facie evidence exist, higher orders (including deposit directions) may be appropriate.
- Precedential stance: the court did not purport to lay down a new general rule overriding prior decisions; rather it distinguished Harish Wood Products and similar decisions on facts and remitted matters for proper fact-finding. The decision clarifies that deposit conditions (like a 50% interim deposit) depend upon the factual sufficiency of the licencee's procedural steps and evidence, and in absence of such sufficiency the licencee cannot claim identical relief as in cases where prima facie tampering was established.
Appeals disposed of
R.B.
By Court: All these appeals are against the order of a learned Single Judge whereby directions were issued for restoration of electric supply without any conditions as to depositing any sum on account of the demand made by the appellant.
2. As identical question arises for consideration, the appeals were heard analogously and are being disposed of by this common Judgment.
3. Mr. Anindya Mitra, learned senior counsel on behalf of the appellant submitted that in cases involving theft/pilferage of electricity there is need for a consistency of approach and uniformity in the exercise of judicial discretion respecting similar causes and desirability to eliminate occasions for grievances of discriminatory treatment requires that all similar matters should receive similar treatment except where factual differences require a different treatment so that there is assurance of consistency, uniformity, predictability and certainty of judicial approach.
4. The said submission of Mr. Mitra is supported by the Judgment of the Supreme Court in Vishnu Traders v. State of Haryana, reported in 1995 Suppl. (1) SCC 461 wherein observations to the above effect had been made by the Supreme Court after having stated that in the matters of interlocutory orders, principle of binding precedents cannot be said to apply. There can be no dispute with the aforesaid proposition that although in the matters of interlocutory orders principle of binding proceeding can not be said to apply, the need for consistency in approach and uniformity in the exercise of judicial discretion in similar matters needs no emphasis. In the light of the above it was submitted by Mr. Mitra that in the below mentioned cases, all judgments of learned Single Judges, the court had taken a consistent view while directing restoration of electricity supply.
“(a) AIR 1996 Calcutta 449 (Hanuman Steel Rolling Mills)—interim order was passed directing restoration on deposit of Rs. 1,50,000/- (Paragraph 11) at the final hearing. Upon completion of affidavits the writ petition was disposed of by directing CESC to give a post decisional hearing.
(b) 1998 (1) CLT 424 (Siva Steel Rolling Mills Ltd.)—Direction was for restoration of supply on payment of Rs. 30 lacs within 72 hours from deposit and direction was given for preservation of the old meters and reference to the Chief Electrical Inspector (Paragraph 24).
(c) 1999 (1) CHN 107 (P.K Mukherjee v. CESC Ltd.)—Final disposal of the writ petition by directing CESC Ltd. to restore electricity on payment of 50% of the amount claimed within 72 hours of last payment. Direction was given for preservation of the meters and reference to the Electrical Inspector (Para 62).
(d) 1996 (2) CHN 534 (Nishi Kanto Banik v. CESC—Disposal of the Writ petition by directing payment of 50% of the amount claimed to CESC and restoration within 48 hours thereafter, disputes referred to Electrical Inspector (Para 25).
All the aforesaid judgments are in respect of cases involving allegations of theft/pilferage of electricity.
(e) Unreported judgment of the Division Bench in Meena Agarwal's case in FMAT No. 364-367 of 1999 dated 15th February, 1999—directing deposit of 50% by way of interim order.
(f) Interim order of the Hon'ble Supreme Court directing deposit of 50% reported in 1996 (8) SCC 647—subject to determination of controversy in the suit.
5. It was the submission of Mr. Mitra that the learned Single Judge in the instant cases ought not to have taken a different view and directed restoration of electricity supply without imposing a condition as to payment of 50% of the demand.
6. In M.P Electricity Board v. Harish Wood Products reported in 1996 (4) Supreme 630, the Supreme Court held that the Electricity Board, when it detects that any consumer had committed any malpractice with reference to his use of electrical energy, may disconnect the supply of electricity forthwith and may call upon consumer to make payment for compensation of unauthorised use of electricity i.e theft of electricity. The Supreme Court rejected the contention that a consumer is entitled to a prior notice as contemplated in section 24 of the Indian Electricity Act, 1910, before disconnection as that section would have no application to a demand in respect of detection of pilferage. The relevant portion of the said judgment of the Supreme Court is extracted herein below:
“A reading thereof clearly indicates that the appellant-Board, when it detects that any consumer had committed any mal practice with reference to his use of electrical energy including unauthorised alternations to installations, unauthorised extension and use of devices to commit theft of electrical energy, may, without prejudice to its other rights, disconnect the supply of electricity forthwith and may call upon the consumer to make payment for compensation of the unauthorised use of electricity which is now stated to be a theft of electricity. It is not in dispute that an FIR had already been lodged for theft of electrical energy. It is seen that the proceedings have been drawn in the presence of the representative of the respondent-Industry and the meters were found to have been tampered with. In furtherance thereof, a prima facie conclusion of pilferage has been reached that the meters were tampered with and respondents were called upon to pay the difference of the rate for electricity said to have been consumed during the stated period of the detection. It would appear that the said assessment was based upon the previous consumption. It is seen that since the proceedings are pending, it would not be desirable to record any finding in this behalf.”
7. A few relevant facts of the above case, as extracted, in the said judgment need to be stated. They are; that during the course of inspection one Mr. Dilip was present as representative of M/s. Harsh Wood Products and proceedings were drawn up with respect to the irregularities noticed which were to the effect that no seal found on meter terminal cover. Body seals of the Meter found tampered. Meter Body seals on other meters found broken and tampered. Consumer was called upon to pay the difference of rate based upon previous consumption.
8. It will be seen that the proceedings in that case had been drawn up in the presence of the representative of the consumer wherein the meters were found tampered with. It is in pursuance thereof a prima facie conclusion of pilferage had been reached. The demands raised on account of alleged pilferage was based upon the previous consumption.
9. It is the contention of the respondents/writ petitioners that neither at the time of inspection nor while removing the meters a fair and reasonable procedure has been adopted by the Appellant The demands raised in all the cases are for a period of one year prior to the date of alleged detection of pilferage.
10. In addition to the estimate of electricity pilfered government duty payable in relation thereof, fuel surcharge calculated on that basis and additional security amount has been demanded.
11. The respondents contend that the said demand, apart from being highly unreasonable is not supported by any basis. Even before the case of pilferage is prima facie established, the consumer is required to pay an abnormal sum including towards Government Duty, Fuel Charge and Additional Security Amount. This, it was contended is arbitrary, wholly without jurisdiction and contrary to any accepted norms.
12. No doubt, a statutory principle has been laid down by the Supreme Court in W.B State Electricity Board v. Fakir Chand Rice Mills, reported in 1996 (8) SCC 647 wherein it was held, that normally, in matter of money claim, at least half of the amount should be directed to be deposited.
13. The question, therefore, that arises is whether whatever amount i.e demanded by the Appellant/CESC fifty percent thereof needs to be paid before restoration of electricity can be ordered, that is the only question in the instant cases.
14. Before we consider the said question, it may be useful to refer to some of the judgments dealing with the power of the Board/Licencee to assess amount of unmetered consumption.
15. In Hyderabad Vanaspati Ltd. v. A.P State Electricity Board, reported in AIR 1998 SC 1715, the Supreme Court was considering the question whether A.P State Electricity Board had the power to assess amount of unmetered consumption and whether the regulation framed with respect to the terms and conditions of supply of electricity are contrary to the provisions of Electricity (Supply) Act, 1948 and the Indian Electricity Act. It was noticed, in that case, that under section 49 of the Electricity Supply Act, 1948 Regulations had been framed with respect to the terms and conditions of supply of electricity. Clause 39 of the said terms and conditions lay down elaborate procedure empowering the Board to make provisional assessment of the amount towards unmetered consumption in case of pilferage and thereafter to make final assessment after hearing the consumer. The said Clause 39 was the subject matter of challenge, inter alia, on the ground that the same is ultra-vires section 24, 26(6) and Clause 6(iii) of the Schedule to the Indian Electricity Act, 1910 as also section 44 of the Electricity (Supply) Act, 1948 and that it was arbitrary besides being violative of section 49 of the Indian Electricity Act.
16. The Supreme Court held the said regulation to be statutory and that the same was within the power of the Board to frame such conditions and regulations under section 49 of the Act. It was further held that the said regulations did not contravene the provisions of sections 21 and 26 of the Indian Electricity Act, 1910, nor it is violative of section 49 of the Electricity (Supply) Act, 1948. The Supreme Court repelled the contentions of the appellants before it that the aforesaid conditions of supply are contrary to the provisions of the Indian Electricity Act specially sections 21(4) and 26(6)(b) of the Act.
17. After referring to and relying upon the judgement in M.P State Electricity Board v. Smt. Basanti Bai, reported in AIR 1988 SC 71, the Supreme Court held that a dispute regarding commission of fraud that is by tampering of the meter and breaking the body seal is one outside the ambit of sections 21 and 26 of the Indian Electricity Act and an Electrical Inspector has no jurisdiction to decide such case of fraud. sections 21 and 26 of the Indian Electricity Act, it was held, provided for different situations. A relevant portion of the said judgement of the Supreme Court in Smt. Basanti Bai's case needs to be extracted and is accordingly extracted hereunder;
“…………… If there is an allegation of fraud committed by the consumer in tampering with the meter or manipulating the supply line or breaking the body seal of the meter resulting in not registering the amount of energy supplied to the consumer or the electrical quantity contained in the supply, such a dispute does not fall within the purview of sub-section (6) of section 26 such a dispute regarding the commission of fraud in tampering with the meter and breaking the body seal is outside the ambit of section 26(6) of the said Act. An Electrical Inspector has, therefore, no jurisdiction to decide such cases of fraud. It is only the dispute as to whether the meter is/is not correct or it is inherently defective or faulty not recording correctly the electricity consumed, can be decided by the Electrical Inspector under the provisions of the said Act.”
18. In so far as the State of West Bengal is concerned, concerned, no such regulation has been framed as was under consideration before the Supreme Court in Hyderabad Vanaspati's case.
19. In Hanuman Steel Rolling Mills (AIR 1996 Cal. 449) one of us upon consideration of various decisions has held that in absence of any rule disconnection of electrical energy on the ground of pilferage or otherwise cannot be made without compliance of the principle of natural justice. The said decision has been followed recently in Pankaj Kumar Mukherjee v. Cesc Limited & Anr. reported in 1999 (1) CHN 107.
20. Furthermore, in State of West Bengal v. Rupa Ice Factory, reported in 1997 (2) CHN 254, a Division Bench of this High Court held that in the absence of any rules and regulations or conditions of supply or agreement between the parties authorising the licencee (CESC) to determine the amount payable on account of pilferage the matter should be decided by Electrical Inspector. In coming to the said conclusion reliance was placed upon clause 6(iii) of the Schedule to the Indian Electricity Act, 1910 which provides, inter alia, reference of any dispute to the Electrical Inspector as to the improper use of energy and the said expression was construed to mean use of energy in an unauthorised manner.
21. Admittedly, there is no provision in the Indian Electricity Act, 1910 which authorises the licencee (CESC) to determine any such amount towords unmetered consumption.
22. This aspect of the matter has also been considered in Shiva Steel Rolling Mill Ltd. v. CESC Ltd. reported in 1998 (1) Calcutta Law Times 424.
23. The preponderance of judicial opinion of this High Court has been that in absence of any provisions in the Act or Regulations in that behalf or agreement, empowering the Board/Licencee to raise bills towards unmetered consumption on the ground of tampering of the meter, the course left open to the Board/Licencee was to realise such amount by establishing the claim by reference of the dispute to the Electrical Inspector. However, it was held that disputes relating to tampering of meter can be referred to and determined by the Electrical Inspector. See Ganges Manufacturing Company Ltd. v. West Bengal State Electricity Board, 1993 (2) CLJ 210, Hanuman Steel Rolling Mills v. CESC 1996 (1) CHN 469 also the cases cited in the earlier part of this judgement.
24. Harsh Wood Products case, cited supra, has been distingushed in Nisi Kanta Banik v. CESC Ltd. reported in 1996 (2) CHN 534 in the following terms:—
“As the Act of default itself is disputed, it would not be appropriate to withhold the supply of electricity to the petitioner merely on the calculations as made by C.E.S.C Besides there is no provision in law or in the conditions of supply which eanbles CESC to withhold the connection unless payment is made as demanded by CESC. The most important distinction between this case and the Harsh Wood Product's case (supra) is the absence of any provision in the case before me entitling CESC to withhold the supply of electricity after disconnection on the ground of pilferage without the payment of the alleged claim on account of improper dues. In the case before the Supreme Court, the power was expressly provided for.”
25. As indicated hereinbefore, such a view has been taken by this court in other decisions as well. In the aforementioned cases it has been held that Clause (vi) of the schedule appended to the Indian Electricity Act shall apply although there cannot be any doubt that section 26(6) thereof would not. In any event, the appellant herein in a large number of cases before us had agreed that reference to the Chief Electrical Inspector be made as special referee.
26. Reference to an independent statutory authority would sub-serve the interest of justice inasmuch as he would be in a position to hear both the parties examine the extent of damages to which the licencee may be entitled to as also the fact as to whether the assertions of the licencee to the effect that the writ petitioners are guilty of pilferage and/or theft of electrical energy is correct or not. It is not possible for this court to enter into such a question and the Chief Electrical Inspector is an expert in the field and as such his opinion would be valued by both the licencee and the consumer.
27. It is only the dispute as to whether the meter is/is not correct or it is faulty not recording correctly the electricity consumed, can be decided by Electrical Inspector under the provisions of the said Act. Also, in such cases a consumer is not entitled to a prior notice as contemplated under section 24 of the Indian Electricity Act, before disconnection as section 24 has no application to a demand in respect of detection of pilferage. The Board/Licencee without prejudice to its rights can disconnect the supply of electricity forthwith and may call upon the consumer to make payment by way of compensation towards theft of electricity.
28. The above position of law will undoubtedly operate where the disconnection is based upon at least prima facie proof of fraud committed by the consumer. There must be material placed before court based upon which at least a prima facie conclusion can be arrived at as regards the ‘fraud’ committed by the consumer in tampering with the meter and/or the seals. Unless, a conclusion can be arrived at that there has been tampering with the meter and/or the seals, we do not think any prima facie conclusion of pilferage of electricity can be reached justifying the disconnection of electricity or of the demand raised on that assumption.
29. Let us now examine whether the procedure adopted by CESC in the instant cases can be adjudged to be fair.
30. We must bear in mind that only a prima facie view can be expressed on this aspect as we do not, in this proceeding, wish to decide finally the matters between the parties as that would be a matter based on which the validity of the demand raised by CESC is to be considered and decided.
31. In Nisi Kanta Banik's case (supra), the precautions to be taken by the CESC have been referred to and more particularly, it has been observed that ipsi dixit of CESC is not final at the highest, it is a presumption which may be drawn.
32. Harsh Wood Product's case (supra) proceeded on a different fact situation. That was also a case where the allegations of theft of electricity was founded on the ground that the seals were found tampered. The electricity authorities in that case conducted the inspection and drew up proceedings in the presence of the consumer and/or his representative who was also a signatory to such proceedings.
33. In that view of the matter, a prima facie conclusion could be arrived at and was in fact, arrived at with regard to theft of electricity.
34. The estimate of such theft of electricity was made on the basis of previous consumption for the similar period and not on an assumption of load factor for the entire period of one year proceeding the detection as in the instant case.
35. Before us various Bills prepared by CESC Limited had been produced. Such Bills had not been prepared on any principle. Even in cases where the consumer has paid electricity charges on the basis of the consumption of electrical energy recorded in the meter upto a certain period, even if alleged pilferage has been detected in the next month the consumer has been asked to pay a huge amount. How and on what basis such Bills have been prepared, are not known to this court. Reasonableness or otherwise of the claim as a result whereof; the consumer can be directed to deposit a portion of the Billed amount and/or furnish security amount, thus, depend upon facts and circumstances of each case.
36. Prima facie, therefore, we are of the view that the procedure adopted by the appellant does not satisfy the test of reasonableness in the instant case.
37. We are, therefore, of the view that apellant/CESC is not entitled to get similar relief as in Harsh Wood Product's case (supra), wherein directions were issued for payment of 50% of the demand raised before restoration of electricity. We must emphasise here that appellant/CESC being a State though only for the purpose of Article 226 of the Constitution of India, nevertheless it has a duty to act in a fair, just and a reasonable manner. Electricity is an essential requirement and a vital raw material for the Industry. The very existence of an Industry or a Commercial establishment depends upon the supply of electricity. Vast powers have been conferred by the Act, Rules and Regulations upon the CESC regulating supply of Electricity including Power to disconnect the same apart from measures provided for recovery of the outstanding.
38. The licencee in terms of the conditions of licence as also under the Indian Electricity Act can discontinue supply of electrical energy only in terms of law. In none of the aforementioned cases despite the decision of this court in Hanuman Steel Rolling Mill (supra) an opportunity of hearing had been granted. Whether the exceptional case has been made out for giving a post decisional hearing would, thus, also depend upon the facts and circumstances of each case.
39. It has been held that principles of natural justice have to be complied with before disconnection, The same view has been taken by a Division Bench of Patna High Court in 1999 (2) PLJR 665.
40. It is not disputed that there are no Rules, Regulations providing for guidelines in the matter of assessment of damages on account of theft of electricity. Mere absence of such Regulations cannot confer unbridled power upon CESC to resort to the extreme step of disconnecting electric supply. The consumer has to be protected from the vagaries and arbitrariness of licencee. Actions of the Licencee/CESC have to conform to the standard as expected of an authority within the meaning of Article 12 of the Constitution of India.
41. At the same time, as observed by the Supreme Court in Isha Marbles v. Bihar State Electricity Board, reported in 1995 (2) JT 626, dishonest consumers cannot be allowed to pay tyrant with the public property but inadequacy of the law can hardly be a substitute for over zealousnes.
42. At this stage, it must be noticed that the learned Trial Judge by his order dated 28th June, 1999 observed as under;
“There is no evidence before this court as to the notice, if any or such disconnection is made in the presence of the petitioner or any independent person. Therefore, if today this court holds that there is pilferage this will be a presumption and on the basis of such presumption to hold as such without any material will be an interference with the right of the petitioner in its essential service. Therefore, the respondent authorities are directed to restore the electrical connection in the factory premises of the petitioner within 48 hours from date. Re-connection charges, if any, for a sum of Rs. 40/- will be paid by the petitioner without prejudice to its rights and conditions. The demand of the respondents, if any, on account of deposit of 50% of the amount claimed will be heard and considered on the basis of affidavits to be filed by the parties on the returnable date.”
43. We are prima facie of the view that on the facts and circumstances of the case, the learned Trial Judge was justified in making the observations as he did so for want of any relevant material based on which a prima facie conclusion could have been arrived at with regard to the theft of electricity.
44. Mr. Mitra, however, submitted that the question of fact such as whether there has been pilferage of electricity by the consumer or not is a matter which cannot be adjudicated in writ proceedings. True, the writ court normally does not adjudicate disputed questions of fact. On that ground, however, it cannot be said that a writ application under Article 226 of the Constitution of India is not maintainable by an aggrieved consumer of electricity. Scope of writ petition as also the jurisdiction of a writ court are circumscribed only by the parameters of well settled principles of judicial review. It is, however, not helpless to issue appropriate directions where the procedure adopted by a statutory authority does not meet the test of fairness, as in the instant case.
45. Normally, such writ applications as the instant cases are being disposed of with directions relegating the parties to refer the dispute to the Electrical Inspector as “Special referee” for adjudication and pending disposal of such dispute, directions are issued for restoration of electric supply upon payment of reasonable amount based upon the demand raised by the statutory authority. As already noticed in the cases referred to supra, directions had been issued in those reported cases by the learned single Judges of this court directing restoration of electricity on payment of 50% of the demand raised.
46. As a question has now been raised with respect to the consistency in passing interim orders, we are of the considered opinion that the CESC should follow a fair and reasonable procedure both with regard to drawing up of proceedings in the presence of the consumer and/or his representative so that a prime facie conclusion can be arrived at that there has been pilferage of electricity. The CESC is also required to raise the demand on account of alleged pilferage based upon some reasoned or reasonable basis. The previous consumption by the consumer for a similar period which is not in dispute can be said to be reasonable basis.
47. In the instant cases, with a view to expedite the disposal of the disputes and in the view that we have taken in the matter consistant with the judgments of this court, the parties are to be relegated to the adjudication of the disputes before the Electrical Inspector as Special Referee. Also, keeping in view the fact that the demands raised by the appellant-CESC in the instant cases pertain to the period of one year prior to the date of alleged detection of pilferage and also keeping in view the fact that apart from the electricity pilferred, demand has been raised with respect to fuel sur-charge, Government duties and additional security amount, it would serve the ends of justice if without interfering with the orders under appeal we remit the matter back with a view to give an opportunity to the CESC authorities to satisfy the learned trial Judge as regard imposition of conditions for passing of an interim order.
48. There cannot be any doubt whatsoever that the writ petitioners-respondents shall go on paying the charges for consumption of electrical energy as recorded in the meter. The writ petitioners-respondents, there cannot further be any doubt, would also be bound to pay the admitted charges. In any case, such admitted charges and/or any Bill raised on the basis of the consumption of electrical energy as recorded in the meter and/or other charges payable to the appellant in terms of the provisions of Indian Electricity Act and/or condition of supply is not paid, it would be open to the appellant herein to take recourse to the provisions of section 24 of the Indian Electricity Act.
We may further make it clear that the interim order passed by the learned trial Judge shall be subject to any final order that may be passed in the matter.
These appeals are disposed of with the aforementioned directions any order as to costs.
Appeals disposed of