State Of West Bengal v. Jiwanmall Babu And Another

Calcutta High Court
Dec 18, 1959
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Structured Summary of Opinion delivered by Renupada Mukherjee, J.

Factual and Procedural Background

The State of West Bengal (appellant) appealed against a Trial Court decree in favour of two respondents (plaintiffs and proprietors/kartas of Mahabir Rice Mill). The respondents sued in their personal capacities and as Kartas of a joint Hindu family for recovery of Rs. 6,535/8/6 pies as damages arising from a contract for purchase of paddy and supply of rice entered into between the Government and Mahabir Rice Mill on 17-5-1948. Clause 7 of the agreement provided for an allowance of up to 3% refraction (dust and foreign matter) and entitlement to compensation if refraction exceeded that percentage.

The respondents alleged that milling tests showed refraction in excess of 3% for large quantities of paddy and presented challans claiming Rs. 6,535/8/6 pies; the Trial Court, after examining evidence and certain government procurement reports (exhibits E series), awarded the plaintiffs Rs. 5,901/6 as damages. The State contested the suit primarily on three grounds: (1) the Section 80 notice served on the Government was invalid; (2) the suit was barred by limitation; and (3) the claim was excessive. The Trial Court overruled the legal objections and granted the partial decree; the State appealed.

Legal Issues Presented

  1. Whether the notice served under Section 80 of the Code of Civil Procedure (CPC) was legally valid or whether it was invalid because the date of accrual of cause of action given in the notice pre-dated the date of accrual as pleaded in the plaint.
  2. Whether the plaintiffs' claim was barred by limitation given the dates asserted in the notice and the plaint.
  3. Whether the Trial Court correctly assessed the amount of damages for excess refraction (the appellant also contended the amount claimed was excessive, although the appeal did not seriously dispute the Trial Court's computed figure).

Arguments of the Parties

Appellant's Arguments (State of West Bengal) — as presented by Mr. Chakravarti, Government Pleader

  • The notice under Section 80 CPC was not legal or valid because it stated the cause of action as arising on 20-7-1948 while the plaint gave the date of accrual as 29-11-1951; a notice given before the accrual date (as per the plaint) is premature and invalid.
  • Section 80, as interpreted in cited authorities, effectively requires an advance copy of the plaint and the notice should not contradict the plaint; the disparity of dates rendered the notice illegal.
  • The claim was barred by limitation because, if the starting point is taken as 20-7-1948 (the date in the notice when challans were submitted), the suit was instituted more than three years later.
  • An additional contention was that the amount claimed was excessive (no detailed numerical challenge to the Trial Court’s figure was pressed before the Bench).

Respondents' Arguments (Mahabir Rice Mill) — as presented by Mr. Chandra

  • A notice under Section 80 only needs to state the cause of action in substance; it is not necessary to state precisely the date on which the cause of action arose.
  • The substance of the claim in the notice (paragraphs 2 and 3) was identical to the material portions of the plaint (including reproduction of the three challans and the schedule), so the notice adequately conveyed the cause of action.
  • The date specified in the notice (20-7-1948) was wrong insofar as saying the cause of action accrued on that precise day; the cause of action arose when Government refused to pay the claimed amount — i.e., it arose after Government's examination and eventual refusal to accede to the demand.
  • Limitation should not run from the mere submission of bills; it runs from refusal (express or implied) by Government to pay, and the material correspondence (including a Government letter of 29-11-1950 saying the claim was under examination) showed that refusal occurred later; the suit was instituted within three years of that effective breach.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
State of Seraikella v. Union of India, 1951 SCR 474; AIR 1951 SC 253 Observation (Mahajan, J.) that Section 80 in effect provides that an advance copy of the plaint should be served on the defendant; S.80 is procedural machinery for litigation. The Court considered this observation (as quoted by counsel) but did not allow a pedantic application to invalidate the notice where the substance of the cause of action in the notice and plaint matched. The Court treated S.80 as procedural machinery but applied common-sense scrutiny rather than strict formality.
Jaharlal v. Union of India, AIR 1959 Cal 273 (quoting Mahajan, J.) Used as the source where Mahajan, J.'s observations (re: S.80 as advance copy of plaint) were quoted by Ray, J. The counsel relied on the observations in this report to argue that a notice inconsistent with the plaint is invalid; the Court reviewed the observation but held the notice valid on substance.
Peoples Insurance Co. v. Benoy Bhusan Bhoumik, ILR (1943) 1 Cal 564; AIR 1943 Cal 199 Definition of "cause of action": every fact which it would be necessary for the plaintiff to prove, if traversed, to support his right to judgment. The Court applied this definition to identify the cause of action as the detection of excess refraction, submission of challans, and Government's refusal to pay; this helped determine whether the notice had sufficiently stated the cause of action and when limitation began.
Poyser v. Minors, (1881) 50 LJ Ex. 555 Referred to in connection with the proposition that Section 80 is procedural machinery for obtaining legal rights (supporting the machinery concept). Used as a classical authority cited within the quoted observation; the Court treated it as background authority in assessing the procedural purpose of S.80 rather than as determinative of notice validity in the facts before it.
Dhana Singh Sobha Singh v. Union of India, AIR 1958 SC 274 Authority invoked to support a commonsense, non-pedantic approach to compliance with Section 80 of the CPC. The Court relied on the principle (cited as authority) that S.80 should not be construed in an overly pedantic fashion and that common sense should be applied in assessing the validity of notices under S.80.

Court's Reasoning and Analysis

The Court approached the legal questions in a sequential and fact-sensitive manner.

  1. What the notice under Section 80 must contain: The Court stated that S.80 requires a notice to contain (a) the cause of action; (b) the name, description and residence of the plaintiff; and (c) the relief claimed. It noted the statutory requirement for a plaint (Order VII, Rule 1) to state the facts constituting the cause of action and when it arose.
  2. Examination of the notice and the plaint: The Court compared material portions and found paragraphs 2 and 3 of the Section 80 notice were "exact replica" of the corresponding paragraphs of the plaint and that the schedule of three challans in the plaint reproduced the schedule in the notice. Thus, the substance of the claim was present both in the notice and in the plaint.
  3. Meaning and identification of "cause of action": Using the judicial definition from Peoples Insurance Co. v. Benoy Bhusan Bhoumik (cause of action = every fact necessary to be proved to obtain judgment), the Court identified the cause of action here as: detection of excess refraction, submission of three challans claiming refund, and Government's refusal to pay.
  4. The significance of the date discrepancy: The Court acknowledged a "serious disparity" between dates (notice: 20-7-1948; plaint: 29-11-1951). It held that a notice under S.80 need not necessarily state the exact date of accrual of the cause of action; it is sufficient if the notice states the cause of action in substance. Further, the Court agreed with the respondents' submission that the cause of action could not have arisen merely on submission of bills; it arises upon Government's refusal to pay.
  5. Consideration of contemporaneous Government correspondence: The Court relied on exhibit 3 — a letter dated 29-11-1950 from the Deputy A.R.C.P. Burdwan advising the mill that their claim was under examination and calling them to produce papers on 4-12-1950. The Court interpreted this as evidence that there was not an immediate refusal on 20-7-1948 and that the dispute and claim were continuing up to and beyond 29-11-1950.
  6. Application of authorities and approach to Section 80: The Court considered authorities (including the observation that S.80 operates as procedural machinery akin to advance service of the plaint) but rejected a pedantic approach. It invoked Dhana Singh Sobha Singh to justify applying "common sense" in assessing compliance with S.80. Because the notice conveyed the substance of the claim and because the cause of action continued until Government's refusal or failure to pay, the notice was held neither premature nor illegal.
  7. Limitation analysis: Given the Court's finding that the breach (refusal to pay) occurred after 29-11-1950 (the Government letter shows the claim was still under examination on that date), the Court concluded limitation did not begin on 20-7-1948. The suit was instituted within three years of the relevant date (i.e., within three years of the effective refusal), so the claim was not time-barred.
  8. Evaluation of the damages figure: The Trial Court had computed the value of excess refraction at Rs. 5,901/6 as based on account books and local government officers' reports (exhibit E series). The Bench found that the Trial Court had correctly determined the figure and observed that learned counsel for the State did not seriously challenge that computation.

Holding and Implications

Holding: APPEAL DISMISSED.

More precisely, the Court held:

  • The notice under Section 80 of the CPC served on the Government was not premature or illegal; it did sufficiently state the cause of action in substance despite a discrepancy in the date stated.
  • The plaintiffs' claim was not barred by limitation because the cause of action, as identified, continued until Government's refusal (evidenced by correspondence dated 29-11-1950) and the suit was instituted within three years of that effective breach.
  • The Trial Court's assessment of the excess refraction and the decretal amount of Rs. 5,901/6 as was accepted; the appeal did not succeed on the legal points raised by the State and was dismissed with costs to the respondents.

Direct consequences for the parties:

  • The decree for Rs. 5,901/6 as given by the Trial Court stands and the State (appellant) was ordered to pay the decretal amount to the respondents within two months if not already deposited in the Court below.
  • The appeal was dismissed and respondents were allowed costs.

Broader implications: The Court emphasized that Section 80 should be construed with practical common sense rather than pedantically; however, the opinion does not purport to lay down any novel legal doctrine beyond the application of existing authorities and principles to the facts of the case.


This summary is prepared exclusively from the provided opinion text and does not add or infer facts beyond those appearing in the opinion.

Show all summary ...

The Judgment of the Court was delivered by

Renupada Mukherjee, J.:— The State of West Bengal is appellant in this appeal, and the two respondents are the two plaintiffs of the Trial Court who have sued both in their personal capacity and also as Kartas of a joint Hindu family consisting of themselves and their sons. The suit was instituted by the respondents in the Trial Court for recovery of a sum of Rs. 6535/8/6 pies as damages on a certain contract to which we shall presently refer.

2. The suit was contested by the appellant State on the ground that the notice under Section 80 of the CPC purporting to have been served upon the Government was not a legal and valid notice and the suit was barred by limitation a further plea was taken that the amount claimed by way of damages was excessive. The Trial Court overruled the legal objections taken on behalf of the State and decreed the claim of the plaintiff in part for Rs. 5901/6 as. With corresponding costs. This appeal has been preferred by the State of West Bengal from the above judgment and decree passed by the Trial Court.

3. The genesis of this suit is contained in an agreement for purchase of paddy and supply of rice by a rice mill known as Mahabir Rice Mill of which the respondents are the proprietors. An agreement was entered into between the Government and the said rice mill on 17-5-1948, when rice was a controlled commodity. The gist of the agreement is that the Assistant Regional Controller of procurement would sell paddy to the mill at a certain rate, and the mill would convert the paddy into rice and sell the same to the former according to the terms and conditions laid down in the agreement. In the present suit we are concerned with clause 7 of the agreement which runs in the following terms:

“7. That the mill undertakes to hand over a minimum quantity of Ninteen hundred and twenty-five maunds of rice from the particular lot of paddy purchased. This quantity has been fixed by the A.R.C.P as based on the calculations made in fixing the price of paddy representing an out turn of 38½ seers of rice per 60 seers of amon paddy, subject to the final milling test. The mills also agree that the total weight of paddy purchased by the mills and delivered by Government will be accepted along with 3 p.c of refraction consisting of dust and other foreign matters and any excess retraction is to be refunded by Government or deducted from the total quantity delivered”.

4. From the above mentioned clause in the agreement it would appear that the mill agreed to make an allowance upto three per cent, on account of refraction which means the presence of dust and other foreign matters in the paddy. If there was any refraction in excess of that percentage then the mill was entitled to get the value thereof from Government. Admittedly, large quantities of paddy were delivered by Government to Mahabir Rice Mill, and the mill also delivered back the resultant paddy to Government. It was the case of the plaintiffs in the Trial Court that after conducting milling tests, it was found that the refraction was much higher than three per cent, in respect of a large quantity of paddy. The annexures to the plaint set forth the total quantity of refraction, and in a schedule to the plaint the value of the retraction has been stated to be Rs. 6535/8/6 pies. After a consideration of the oral and documentary evidence adduced by the parties, the Trial Court held that the value of excess refraction to which the plaintiffs are entitled is Rs. 5901/6 as. In the present appeal, Mr. Chakravarti, learned Government Pleader, was not in a position to question the correctness of this figure seriously.

5. The Trial Court examined the question of excess refraction in some detail. It prepared a chart in a tabular form and came to the conclusion that in respect of eight deliveries the total value of excess refraction was Rs. 5901/6 as. This conclusion was arrived at by the Trial Court not only on a consideration of the account books of the mill, but also on a consideration of some reports of local Government officers who were in charge of procurement of paddy. These reports were marked exhibit E series in the Trial Court This being the position, we must say that the value of excess refraction has been correctly determined by the Trial Court, and if the appeal does not succeed on the points of law raised by Mr. Chakravarti, then it would fail.

6. We now turn our attention to the questions of law raised by Mr. Chakravarti on behalf of the appellant State. He contended, in the first place, that the notice served under Section 80 of the CPC upon Government is not legal or valid. The relevant portion of Section 80 of the CPC may be quoted here:

“No suit shall be instituted against the Government or against a public officer in respect of any act purporting to be done by such public officer in his official capacity, until the expiration of two months next after notice in writing has been delivered to, or left at the office of—

…................

and, in the case of a public officer, delivered to him or left at his office, stating the cause of action, the name, description and place of residence of the plaintiff and the relief which he claims; and the plaint shall contain a statement that such notice has been so delivered or left”.

7. a notice under S. 80 of the Code must contain three essential particulars. In the first place, it must state the cause of action; secondly, the name, description and place of residence of the plaintiff must be given; and thirdly, the relief which the plaintiff claims must also be mentioned.

8. In the present case the notice under Section 80 of the CPC was issued on 3-10-1950. The notice was marked exhibit 1 in the Trial Court. The notice contains, among other statements, a statement that the cause of action had arisen on 20-7-1948, when some challans for an amount of Rs. 6535/8/6 pies were submitted to A.R.C.P, Burdwan.

9. Mr. Chakravarti submitted on behalf of the appellant State that the date of the accrual of the cause of action given in the notice is 20-7-1948. In the plaint this date has been given as 29-11-1951, in paragraph 11. Mr. Chakravarti contended that the plaint should be taken at its face value, and if, according to the plaint, the cause of action arose on 29-11-1951, then no valid notice under Section 80-of the CPC could be given before the accrual of the cause of action. In the submission of Mr. Chakravarti, the cart should not have been put before the horse, and the very tact that the requisite notice was given prior to the accrual of the cause of action shows that the notice was an illegal and invalid notice. In this connection Mr. Chakravarti drew our attention to some observations of Mahajan, J. quoted by Ray, J. in a case reported in AIR 1959 Cal 273, Jaharlal v. Union of India. The observations were quoted by Ray, J. at pp. 275 and 276 of the report from the judgment of Mahajan, J. in the case of State of Seraikella v. Union of India, reported in 1951 SCR 474 at p. 513 : AIR 1951 SC 253 at p. 266. The observations are as follows:

“It seems to me that what is enacted in S. 80 is, the first step for litigation between the parties when the cause of action is complete. Section 80 in effect provides that an advance copy of the plaint should be served on the defendant and no suit should be instituted in Court until the expiry of two months after such service. Section 80 does not define the rights of the parties or confer any right on the parries. It only provides a mode of procedure for getting the relief in respect of a cause of action. It is a part of the machinery for obtaining legal rights, i.e, machinery as distinguished from its products. Vide Poyser v. Minors, (1881) 50 LJ Ex. 555”.

10. Mr. Chakravarti submitted before us that, according to Mahajan, J., S. 80 of the Code of Civil Procedure in effect provides that an advance copy of the plaint should be served on the defendant. Mr. Chakravarti further argued that if a notice under S. 80 of the Code be regarded as an advance copy of the plaint, then the present notice should not be regarded as a legal or valid notice because of the disparity between the notice and the plaint regarding the date when the cause of action for the present suit arose. Let us now examine if there is any substance in this contention of Mr. Chakravarti.

11. In the above connection we may refer to paragraphs 2 and 3 of the notice under Section 80 of the CPC which are in the following terms:

“2. That as there were excess refractions above 3 p.c (the maximum percentage allowable according to the terms of the contract) in the paddy sold under the delivery orders mentioned below as tested and sanctioned by your officers we submitted three bills Nos. 741, 742 and 743 dated 20-7-1948, to the A.R.C.P Burdwan for the costs of the excess refractions amounting to Rs. 6535-8-6 p. in all as detailed in the challans and mentioned in the schedule below”.

“3. That in spite of repeated requests and demand the A.R.C.P, Burdwan has not paid the amounts due under the challans and amounting to Rs. 6535-8-6 p. only”.

12. Paragraphs 2 and 3 of the plaint are exact replica of the above mentioned two paragraphs of the notice. The schedule given in the present plaint regarding the three challans is also an exact reproduction of the three challans mentioned in the notice. The entire substance of the claim of the respondents is to be found in the above mentioned paragraphs of the plaint and its schedule. The claim of the plaintiffs is, therefore, given in effect and substance in the notice. There is, no doubt, a serious disparity about the date of the accrual of the cause of action. In the notice under Section 80 of the CPC this date, as we have already mentioned, has been given as 20-7-1948. This was the date when the challans were submitted to the A.R.C.P, Burdwan. We have previously stated that in paragraph 11 of the plaint, it has been stated that the cause of action for this suit arose when the R.C.P of Calcutta was last written to on 29-11-1951, and no reply was received from him. The question, therefore, which falls for our determination is whether this discrepancy between the two dates makes the notice an invalid and illegal notice.

13. The expression “cause of action” has not been defined in the Code of Civil Procedure. The expression has, however, been judicially defined in several cases. We may refer to one such case which is reported in ILR (1943) 1 Cal 564 : (AIR 1943 Cal 199) Peoples Insurance Co. v. Benoy Bhusan Bhoumik, where it has been defined as follows:

“‘Cause of action’ has not been defined in the Code of Civil Procedure, 1908. Cause of Action, however, means every fact which it would be necessary for the plaintiff to prove, if traversed, in order to support his right to the judgment of the Court it does not comprise every piece of evidence which is necessary to prove each fact, but it comprises every fact which is necessary to be proved. Cause of action has no relation to the defence set up in the case”.

14. Regard being had to the above definition of the cause of action, let us now ascertain what was the cause of action for the present suit. According to the plaint case, the cause of action was the detection of excess refraction in the paddy supplied to the respondent mill, the submission of three challans for refund of the price of such excess retraction, and refusal of Government to pay the price. This was also exactly the case made in the notice under Section 80 of the CPC. In the notice, the date of the accrual of the cause of action has been given as 20-7-1948, on which date the challans were submitted to the A.R.C.P

15. Mr. Chandra submitted on behalf of the plaintiffs respondents that a notice under Section 80 of the CPC simply requires, among other things, a statement of the cause of action, and it is not necessary to mention the date of its accrual. Mr. Chandra further submitted that the date of accrual of the cause of action, as given in the notice, was clearly wrong, because no cause of action for the suit could have arisen merely upon the submission of the bills. According to Mr. Chandra, the cause of action would arise after Government had expressed its unwillingness to pay the price of excess refraction. We are in agreement with this contention of Mr. Chandra. In any view of the case, it cannot be said that the cause of action, for the present suit arose on the very date of the submission of the bills because that would be inconsistent with paragraph 3 of the notice where it has been stated that in spite of repeated requests and demands, A.R.C.P, Burdwan, was not paying the amounts due under the challans a notice under Section 80 of the CPC does not require that the date of the accrual of the cause of action should be given. Rule 1 of Order VII of the Code requires, among other things, that the plaint must state the facts constituting the cause of action, and when it arose. In the present case, as we have already indicated, the same cause of action has been stated in the notice under Section 80 of the CPC as in the plaint. We have shown this by a comparison of the material portions of the notice and the plaint. That being the case, it cannot be properly contended that the notice in question is an invalid and inoperative notice.

16. In the above connection Mr. Chakravarti contended on behalf of the appellant State that the maintainability of a suit is to be judged by the statements made in the plaint and not by any other extraneous circumstance. He submitted that according to the statement of the plaintiffs themselves, the cause of action had arisen on 29-11-1951. Mr. Chakravarti, therefore, contended that as the notice under Section 80 of the CPC was given prior to that date, the notice was premature, and such notice should not be held to be a valid notice. This argument of Mr. Chakravarti would have been accepted by us, if we could agree with him that the cause of action for the present suit had not arisen earlier than 29-11-1951. On an examination of the plaint, we must hold that the cause of action had arisen after the date of the submission of the challans, namely, 20-7-1948 and it was continuing thereafter until Government finally refused to accede to the demand of the respondents. In this connection, we may refer to a letter from the Deputy A.R.C.P Burdwan, written to Mahabir Rice Mill on 29-11-1950. This letter was marked exhibit 3 in the Trial Court it is quoted below:

“Office of the Asst. Regional Controller of Procurement Burdwan.

Memo. No. 7926.X-15/50, dated 29th November, 1950.

To Mahabir Rice Mill, Burdwan.

Ref: Your notice under S. 80 of the CPC dated 3rd October, 1950, to State of West Bengal with regard to compensation for refraction of paddy claimed by you. I am directed by the A.R.C.P Burdwan to request you to attend either personally or by an authorised agent with all the papers in support of your claim referred to above on 4-12-1950. You are hereby informed that your claim is under examination.

Illegible

Dy. A.R.C.P, Burdwan.

29-11”.

17. The above letter would show that on receipt of the notice under Section 80 of the CPC, Government was writing to the rice mill to attend the office of A.R.C.P either personally or by an authorised agent with all necessary papers for supporting the claim of the mill. It is then clear that until 29-11-1950, there was no refusal on the part of Government to pay the demand of the mill. La the plaint, the plaintiffs respondents have chosen to show that the cause of action arose on 29-11-1951, when a final letter was written to R.C.P which remained unanswered. In our opinion, it does not mean that the cause of action had arisen on the writing of the letter and not on any previous date. In our opinion, the cause of action had really arisen before the date and it was continuing, and the plaintiffs chose the particular date of 29-11-1951, in the plaint for the purpose of computing the period of limitation. This being our view, we are not prepared to say that the notice in question is defective. It is, no doubt, true that the terms of Section 80 of the CPC are to be strictly complied with, but it does not mean that the terms of the notice should be scrutinised in a pedantic manner, or in a manner completely divorced from common sense a little common sense must be imported in the notice under Section 80 of the CPC. Vide Dhana Singh Sobha Singh v. Union of India, AIR 1958 SC 274.

18. On a consideration of these facts and circumstances, we are of opinion that the notice under Section 80 of the CPC which was served in this case was neither premature nor illegal. The first contention urged on behalf of the appellant, therefore, fails.

19. The other objection urged by Mr. Chakravarti on behalf of the appellant State was that the claim of the plaintiffs respondents is barred by limitation. Mr. Chakravarti contended that according to the admission of the respondents themselves as made in the notice the starting point of limitation would be 20-7-1948. The suit was instituted more than three years after that date. The claim of the respondents would, no doubt, be barred by limitation, if the above mentioned date is taken as the starting point for limitation. But from what we have already stated in the foregoing part of this judgment, it would be clear that limitation could not have run from that date. On that date, the respondents merely represented the bills to the A.R.C.P Until Government declined to pay the amount of the bills, either expressly or by implication, it could not be said that the contract on the basis of which the claim was made had been broken by Government. It our opinion, such a breach of contract must have taken place after 29-11-1950, when the Deputy A.R.C.P wrote to the Rice Mill that the claim of the respondents was under examination. The present suit was instituted within three years of 29-11-1950. The claim is not barred by limitation. The second contention urged on behalf of the appellant therefore, fails.

20. All the contentions urged on behalf of the appellant having failed this appeal is dismissed with costs to the respondents.

21. The decretal amount must be paid by the appellant to the respondents within two months from this date if they have not already been deposited in the Court below.

K.C Sen, J.:— I agree.

FD/D.H.Z

22. Appeal dismissed.