Thomas Thomas v. Kottayam Municipality

Kerala High Court
Aug 28, 2008
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Judgment — Structured Summary

Factual and Procedural Background

The petition challenges Ext. P13(a), the order by which the Tribunal for Local Self Government Institutions rejected the petitioners' application (I.A. No. 845/2008) for condonation of a 141-day delay in filing an appeal.

Sequence of events as set out in the opinion:

  • The petitioners applied for a building permit and were issued Exts. P3 and P4 (notices of demolition).
  • An appeal before the Tribunal for Local Self Government Institution set aside Exts. P3 and P4 and directed that fresh orders be passed.
  • Pursuant to that appellate order, Ext. P5 was issued under S. 406(3) of the Municipalities Act; the petitioners filed Ext. P6 (an appeal) against Ext. P5.
  • The Tribunal set aside Ext. P5 but reserved liberty to the respondent to pass fresh orders.
  • Thereafter Ext. P8 notice was issued; the petitioners filed Ext. P9 (objection), but by Ext. P10 the petitioners were ordered to demolish the structure.
  • The petitioners filed Ext. P11 representation seeking recall of Ext. P10; it was not considered, and they filed W.P.(C) No. 23287/2008.
  • On 4.8.2008 the Writ Petition (W.P.(C) No. 23287/2008) was dismissed by Ext. P12 judgment without prejudice to the petitioners' right to file an appeal under the Municipality Act.
  • In pursuance of that judgment, the petitioners filed Ext. P13 appeal dated 11.8.2008 along with I.A. No. 845/2008 seeking condonation of 141 days' delay.
  • The Tribunal considered I.A. No. 845/2008 and dismissed it by Ext. P13(a) dated 11.8.2008 on the ground that the Tribunal's power to condone delay under the Tribunal rule (proviso to R. 8) was limited to one month.
  • The petitioners then filed the present Writ Petition seeking to quash Exts. P10 and P13(a) and to restrain the respondent from initiating proceedings against the structure mentioned in Ext. P10.

Legal Issues Presented

  1. Whether the High Court, exercising its jurisdiction under Article 226 of the Constitution of India, can consider explanations for delay and either quash a demolition order (Ext. P10) or direct condonation of a 141-day delay in filing an appeal when the Tribunal's rules (proviso to R. 8) limit condonation to one month.
  2. Whether a party can invoke extraordinary writ jurisdiction to bypass or render otiose a statutory or rule-based period of limitation that restricts the appellate authority's power to condone delay.

Arguments of the Parties

Petitioners' Arguments

  • The High Court, under Article 226, can examine the explanation for delay and either invalidate Ext. P10 (the demolition order) in the writ petition or direct that the delay in filing the appeal be condoned and the appeal be considered on merits.
  • Reliance was placed on the Apex Court judgment in I.T.C. v. Union of India ((1998) 8 SCC 601) and Singh Enterprises v. Commissioner of Central Excise (2008) 3 SCC 70 to support the contention that condonation beyond the statutory period is permissible in appropriate circumstances.

Respondent / Municipality's Arguments

  • Once the statutory period of limitation has expired, neither the Tribunal nor the High Court (invoking Article 226) can condone the delay in a manner that would render the statutory provision otiose.
  • Counsel relied on judicial authorities including Assistant Commissioner of Central Excise v. Krishna Poduval (2005 (4) KLT 947), Krishnan T. v. State of Kerala (2007 (1) KLT SN 45), and the Apex Court decision in Hatti Gold Mines Company Ltd. v. Vinay Heavy Equipments ((2008) 7 SCC 169) to support the proposition that the High Court cannot resurrect time-barred statutory remedies under Article 226.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
I.T.C. v. Union of India ((1998) 8 SCC 601) The Apex Court in that case permitted filing an appeal beyond the statutory period in the peculiar facts of that case; the direction was issued by the Apex Court invoking power under Article 142 of the Constitution. The court distinguished I.T.C., observing that it arose from peculiar facts and involved Article 142 powers (which the High Court does not possess). The judgment was held not to lay down a general precedent that assists the petitioners.
Singh Enterprises v. Commissioner of Central Excise (2008) 3 SCC 70 Addressed the scope of the I.T.C. decision and declined to follow it; indicated that I.T.C. did not lay down a binding legal principle permitting condonation that would render a statutory limitation otiose. The court relied on Singh Enterprises to show that I.T.C. did not establish a principle favouring condonation beyond statutory limits and that Singh Enterprises declined to follow I.T.C.'s approach.
Assistant Commissioner of Central Excise v. Krishna Poduval (2005 (4) KLT 947) Held that where a statute prescribes a period of limitation and restricts the power to condone delay, the High Court cannot, under Article 226, resurrect time-barred appeals or disregard such statutory limitation. The court treated this decision as authoritative and relied upon it to conclude that once the statutory period expires and appellate authority lacks power to condone beyond the prescribed limit, Article 226 cannot be used to bypass that limit.
Krishnan T. v. State of Kerala (2007 (1) KLT SN 45 : ILR 2007 (1) Ker. 233) Reiterated the principle that Article 226 cannot be invoked to bypass statutory limitations when the statutory authority has no power to condone delay beyond the prescribed period. The Division Bench followed the reasoning in Krishna Poduval and applied the same principle to reject the contention that Article 226 can be used to condone delay beyond the statutory limit.
Hatti Gold Mines Co. Ltd. v. Vinay Heavy Equipments ((2008) 7 SCC 169) Held that when a special statute prescribes a period of limitation and provides for extension up to a specified limit, the special statute prevails and the provisions of the Limitation Act (e.g., S. 5) are excluded by S. 29(2) of the Limitation Act. The court relied on this Apex Court authority to support the view that where a special provision limits condonation (e.g., to one month), the general provisions of the Limitation Act cannot be invoked to extend that period.
Maheswary Fire Work Industries v. Commercial Tax Officer (12 STC 272) (Madras HC) Held (according to the opinion cited) that a limitation on the Appellate Authority's power to condone delay could not be applied to the High Court exercising Article 226 jurisdiction. The court rejected the reasoning in Maheswary Fire Work Industries as unpersuasive and noted that the decision did not contain reasoning sufficient to support departing from the contrary line of authority.
K.K. Pushpakaran v. Union of India (2008 (1) KLT 161) Arising under the Railway Claims Tribunal (Procedure) Rules, 1989 — relevant because Rule R.18 there did not prescribe a fixed maximum condonable period. The court distinguished K.K. Pushpakaran on the basis that R.8 of the Tribunal Rules (in the present case) limits condonation to one month, whereas R.18 in Pushpakaran did not impose such a limit; thus that precedent did not assist the petitioners.

Court's Reasoning and Analysis

The court undertook a step-by-step analysis based upon the authorities and statutory provisions cited in the opinion:

  1. The court noted the petitioners' reliance on I.T.C. and Singh Enterprises. It observed that I.T.C. permitted filing beyond the statutory period only in the peculiar facts of that case and that the Apex Court in I.T.C. acted under Article 142 — a power not available to the High Court. Therefore I.T.C. could not be treated as a general precedent enabling the High Court to condone statutory delay under Article 226.
  2. The court pointed out that Singh Enterprises did not follow I.T.C. on the point and explicitly confined I.T.C. to its facts, reinforcing that I.T.C. did not establish a general rule for condoning statutory delay that would negate a statutory limitation.
  3. The court relied on the Division Bench judgments (Assistant Commissioner of Central Excise v. Krishna Poduval and Krishnan T. v. State of Kerala) which held that where a statute prescribes a period of limitation and does not permit condonation beyond a specific limit, the High Court cannot, by invoking Article 226, resurrect a time-barred remedy or effectively nullify the statutory limitation. The court treated these decisions as directly answering the petitioners' contention.
  4. The court further relied on the Apex Court decision in Hatti Gold Mines Co. Ltd. v. Vinay Heavy Equipments to explain the statutory principle: when a special statute prescribes a limitation period and a defined provision for extension, the special statute prevails and the general provisions of the Limitation Act (for example S.5) are excluded under S.29(2) of the Limitation Act.
  5. The court examined the Tribunal rule (proviso to R.8(3)) and recorded that it authorises the Tribunal to condone delay of only one month if sufficient reason is shown; because the Tribunal's power is thus expressly restricted, the petitioners could not rely on Article 226 to obtain condonation beyond that limit.
  6. The court addressed the petitioners' reliance on K.K. Pushpakaran and distinguished it on facts: R.18 (of those Rules) did not impose a maximum condonable period, whereas R.8 in the present matter did impose a one-month maximum; consequently Pushpakaran did not assist the petitioners.
  7. On balance, the court concluded that the cited line of authority and the statutory/rule-based limits on condonation provide a complete answer to the petitioners' contentions and that Article 226 could not be used to bypass the statutory limitation.

Holding and Implications

Holding: The Writ Petition fails and is dismissed.

Implications and immediate effects:

  • Direct effect on parties: The petitioners' challenge to Ext. P10 (demolition order) and Ext. P13(a) (rejection of condonation application) is unsuccessful; the writ is dismissed.
  • Scope of the decision: The court concluded that where a statutory or rule provision prescribes a specific maximum period for condonation (here, proviso to R.8 allowing condonation up to one month), the High Court in exercise of Article 226 cannot override that restriction to condone delay beyond the prescribed limit. The court relied on earlier Division Bench and Apex Court authorities to support this position.
  • Precedential impact: The opinion treats the cited authorities as controlling for the issue in this case. The court did not state that it was laying down a new principle beyond applying existing jurisprudence; accordingly, the judgment resolves the dispute on the facts and law presented but does not purport to create a novel legal doctrine beyond the line of authority it follows.

This summary is confined to the material contained in the provided opinion and does not add information beyond that text.

Show all summary ...

JUDGMENT

1. The challenge in this Writ Petition is against Ext. P13 (a) order, by which Ext. P13 application filed by the petitioner for condoning 141 days delay in filing an appeal was rejected by the Tribunal for Local Self Government Institutions. Facts of the case are that the petitioners filed an application for a building permit and at that stage they were issued Exts. P3 and P4 notices of demolition. Appeal before the Tribunal for Local Self Government Institution was disposed of setting aside Exts. P3 and P4 and directing that fresh orders be passed. Petitioner submits that in pursuance to the appellate order, Ext. P5 was issued under S. 406(3) of the Municipalities Act and again the petitioners filed Ext. P6 appeal. The Tribunal set aside Ext. P5 reserving liberty to the respondent to pass fresh orders in the matter. Thereafter Ext. P8 notice was issued by the Municipality, in response to which Ext. P9 objection was filed. However, by Ext. P10 petitioners were ordered to demolish the structure.

2. The petitioners submit that they pursued the matter with the Municipality by filing Ext. P11 representation praying for recalling Ext. P10. As their request was not considered, they approached this court by filing W.P(C). No. 23287/2008. When that Writ Petition came up for admission before this court on 4.8.2008, it was disposed of by Ext. P12 judgment, holding that the remedy of the petitioner is to file an appeal before the Tribunal. Accordingly, the Writ Petition was dismissed without prejudice to the right of the petitioner to file appeal as provided under the Municipality Act.

3. Petitioner submits that in pursuance to the said judgment, they filed Ext. P13 appeal dated 11.8.2008, along with I.A No. 845/2008, an application for condonation of delay of 141 days. The Tribunal considered I.A No. 845/2008 and dismissed the same by Ext. P13(a) order dated 11.8.2008 on the ground that the power of the Tribunal to condone the delay in terms of Rule of the Tribunal, R. 8 was limited to one month. Seeking to quash Ext. P10 and P13(a) and to direct the respondent to refrain from initiating proceedings against the structure mentioned in Ext. P10, that this Writ Petition is filed.

4. The counsel for the petitioner submits that, though under the proviso to R. 8 of the Tribunal rules, the power conferred on the Tribunal to condone the delay is confined to a period of one month, it is well within the power of this court under Art. 226 of the Constitution to consider the explanation Offered for the delay and either to the validity of Ext. P10 in the Writ Petition or direct that the delay in filing appeal be condoned and the appeal be considered on merits. For drawing support to this contention of the learned-counsel for the petitioners, the judgment of the Apex Court in the case of I.T.C v. Union of India ((1998) 8 SCC 601) and Singh Enterprises v. Commissioner of Central Excise (2008 (1) KLT SN 62 (C. No. 65) SC : (2008) 3 SCC 70) are relied.

5. Oh the other hand standing counsel for the Municipality submits that once the statutory period of limitation has expired, neither the Tribunal can condone the delay nor can this court, invoking its extraordinary powers under Art. 226 of the Constitution of India, direct that the delay be condoned and thus render the” provision in the statute otiose. In support of this contention, counsel for the Municipality referred to the judgments in Assistant Assistant Commissioner Of Central Excise v. Krishna Poduval (2005 (4) KIT 947), Krishnan T. v. State of Kerala (2007 (1) KLT SN 45 (C. No. 62) : ILR 2007 (1) Ker. 233) and also the Apex Court judgment in Hatti Gold Mines Company Ltd. v. Vinay Heavy Equipments ((2008) 7 SCC 169).

6. I have considered the submissions made by both sides. In the I.T.C case, the Supreme Court has permitted the appellant therein to file an appeal even beyond the period of limitation prescribed in the statute. However, a reading of the judgment shows that it was taking note of the peculiar facts of the case and clarifying that it was to do justice between the parties that the Apex Court had issued such a direction. This evidently is a judgment rendered by the Apex Court invoking the power under Art. 142 of the Constitution, which power is not conferred on the High Court. That apart, in Singh Enterprises v. Commissioner of Central Excises (2008 (1) KLT SN 62 (C. No. 65) SC : (2008) 3 SCC 70) referred to above, the Supreme Court did not follow the I.T.C judgment and para 10 to the extent relevant, reads as under:

“I.T.C case was rendered taking note of the peculiar background facts of the case. In that case there was no law declared by this Court that even though the statute prescribed a particular period of limitation, this Court can direct condonation that would render a specific provision providing for limitation rather otiose. In any event, the causes shown for condonation have no acceptable value. In that view of the matter, the appeal deserves to be dismissed which we direct There will be no order as fo costs.” (emphasis supplied) Therefore, it is obvious that the I.T.C case did not lay down any legal principle to be adopted as a precedent to be followed and therefore this judgment, does not improve the case of the/petitioner in any manner.

7. The judgment in Asst. Assistant Commissioner Of Central Excise v. Krishna Poduval (2005 (4) KLT 947), was a case arising under the Central Excise Act. The statute prescribed the period of limitation and also restricted the power of the appellate authority to condone the delay. As in this case, an appeal was filed belatedly and since the delay sought to be condoned was beyond the permissible period, delay was declined to be condoned and consequently the appeal was rejected. The order was challenged before this court and this court entertained the Writ Petition on merits and examined the validity of the order passed by the departmental authorities and granted relief to the petitioner.

8. Against thejudgment of the learned single Judge, appeal filed by the Department and in paras 7 and 8 of thejudgment, it has been held as follows:

“7.At the outset we may statethat in so far as the respondents have not taken up the original orders imposing penalty in appeals before the Appellate Authority within the maximum period prescribed under S. 85(3) of the Rnance Act, 1994, they cannot get the appeals revived and heard on merits by resorting to the discretionary remedy before this Court under Art. 226 of the Constitution of India. Once the period of limitation has run itself out and the appellate authority does not have power to condone the delay infiling the appeals beond the maximum period presaibed under the Act, there medies of the appellants come to an end just like in the case of a time barred suit and the respondents cannot, by invoking the discretionary remedy under the extraordinary jurisdiction of this court under Art. 226 of the Constitution of India resurrect their unenforceable cause of action and require this court to consider the ircontentions against the original orders on merit That would amount to defeat the very law of limitation which we are not expected to do under Art. 226. If we are to entertain the contentions of the respondents on merits, that would amount to negating the law of limitation which we have no jurisdiction to do under Art. 226 and which may even lead no anomalous results. We are not satisfied that the jurisdiction of this Court under Art. 226 of the Constitution of India is so wideas to resurrecta cause of action which has become unenforceableon account of thelaw of limitation. Further, we are of the firm opinion that the jurisdiction under Art. 226 of the Constitution of India cannot be invoked against express statutory provisions, however harsh the effect of the provisions may be on an assessee or litigant.

9. The learned counsel forthe respondents has cited before us a decision of the Madras High Court in Maheswary Fire Work Industries v. Commercial fax Officer, reported in (12 STC 272), which held that “although”, as far as the Appellate Authority is concerned under the Tamilnadu General Sales Tax Act, 1959, its jurisdiction and powerto condonedelay is limited to a period of 30 days, that limitation cannot be made applicable to the High Court while exercising jurisdiction under Art. 226 of the Constitution of India. With great respect, we are unable to persuade ourselves to agree with the said decision which does not also contain any reasoning for holding so. According to us, all the remedies of the respondents have come to an end when their appeals were dismissed by the Commissioner of Central Excise (Appeals) on the ground of limitation. Even the further appellate authority or this court does not have the jurisdiction to entertain the claim on merits disregarding the limitation or condoning the delay. In any event, the appellants have not pleaded any extraordinary circumstances warranting interference, even if we had the jurisdiction to do so.”

10. This judgment of the Division Bench has been followed by the Division Bench in the case of Krishnan T. v. State of Kerala (2007 (1) KLT SN 45 (C. No. 62) : ILR 2007 (1) Ker. 233), wherein para 7, it has been held as follows:

“Counsel for the appellant however, submitted that though the Government have rejected the appeal on the ground of delay, this court under Art. 226 of the Constitution of India can entertain the Writ Petition in the interests of justice. We have already held in Abel's case that a party cannot invoke the provisions of Art. 226 so as to bypass a statutory remedy, especially when no power is conferred on the statutory authority to condone the delay. This legal position has been approved by this court in Assistant Assistant Commissioner Of Central Excise v. Krishna Poduval where this court held that once the period of limitation has runitself out and the appellate authority does not have the power to condone the delay in filing the appeals beyond the maximum period prescribed under the Act, the remedies come to an end just like in the case of a time barred suit and cannot, by invoking the discretionary remedy under Art. 226 of the Constitution of India, resurrect unenforceable cause of action.”

11. From the aforesaid judgments it is clear that once the statutory period of limitation has expired, the party looses its right of appeal. Thereafter it is not open to him to invoke the power of this court under Art. 226 of the Constitution and bypass the statutory restrictions and get the delay condoned or to have the matter examined by this court. Admittedly proviso to R. 8(3) authorises the Tribunal to condone delay of only one month if it is satisfied that there is sufficient reason for the delay. The power conferred on the Tribunal being restricted, in my view, the above two judgments of this court gives a complete answer to the contentions of the petitioner.

12. As rightly contended by the counsel for the Municipality if a special statute has prescribed a period of limitation, to that extent, the provisions of the Limitation Act will stand excluded as provided in S. 29(2) of the Limitation Act. This contention of the learned counsel for the Municipality is fully supported by the judgment of the Apex Court in ((2008) 7 SCC 169) and para 10 to the extent relevant, reads as under:

“When any special statute prescribes certain period of limitation as well as provision for extension upto specified time limit, on sufficient cause being shown, then the period of limitation prescribed under the special law shall prevail and to that extent the provisions of the Limitation Act shall stand excluded. As the intention of the legislature in enacting sub-s. (3) of S. 34 of the Act is that the application for setting aside the award should be made within three months and the period can be further extended on sufficient cause being shown by another period of 30 days but not thereafter, this Court of the opinion that the provisions of S. 5 of the Limitation Act would not be applicable because the applicability of S. 5 of the Limitation Act stands excluded because of the provisions of S. 29(2) of the Limitation Act

(emphasis supplied)

13. Counsel for the petitioner also relied on the decision reported in K.K Pushpakaran v. Union Of India (2008 (1) KLT 161). That was a case arising under the Railway Claims Tribunal (Procedure) Rules, 1989. However, on going through the Rules, it is seen that unlike R. 8 of the Tribunal Rules, where the maximum condonable period is one month, no such limitation is provided for in R. 18 of the Rules referred to above, which came up for consideration of the Division Bench in the above case. In view of this factual difference this judgment of the Division Bench does not help the petitioner. Therefore the contentions raised by the counsel for the Municipality deserves acceptance and the Writ Petition is only to be dismissed.

14. Writ Petition fails and is dismissed.