Anikad Grama Panchayath v. M.D Baiju
Structured Summary of the Opinion
Factual and Procedural Background
The matter involves two writ petitions: the "former" petition by the highest bidder seeking implementation of a Government order and the "latter" petition by the Panchayat challenging the Government order dated 2-12-2003 (Ext.P6). The bidder contended that, because of orders passed by the Deputy Director and by this Court, he was unable to fully collect sand during the licence period and thereby suffered substantial loss. The bidder claimed compensation for 81 days; the Deputy Director awarded compensation for 50 days. The Panchayat took the matter to the Government, which affirmed the Deputy Director's view by issuing the impugned order. The Panchayat challenged the Government's computation and the process followed, asserting that the Government could not have computed the amounts as it did and that, under section 191 of the Kerala Panchayat Raj Act, the Government's proper role was limited (according to the Panchayat) to directing the Panchayat to reconsider. Other contentions recorded include that the bidder had undertaken to remit dues, that any loss should be computed only after proper adjudication, and that the person who heard the matter had not passed the order.
Legal Issues Presented
- Whether the Government's orders (Ext.P4 in the former petition and Ext.P6 in the latter petition) were made in accordance with the procedural requirements of section 191 of the Kerala Panchayat Raj Act, as amended.
- Whether the Government could compute compensation amounts or make the impugned determinations without following the reference/consideration procedure under section 191(2) (including referral to the Ombudsman or the Tribunal and giving the Panchayat an opportunity to be heard).
- Whether, in exercise of powers under section 191, the Government's action is limited to directing the Panchayat to reconsider a resolution (as contended by the Panchayat) rather than cancelling/modifying and computing amounts directly.
Arguments of the Parties
Bidder's Arguments
- The bidder could not fully enjoy the benefit of sand collection during the licence period due to orders of the Deputy Director and this Court, resulting in substantial loss.
- The bidder claimed compensation for loss for 81 days.
- The bidder sought implementation of the Government order affirming the Deputy Director's decision; the Deputy Director had fixed compensation for 50 days (less than claimed).
Panchayat's Arguments
- The Deputy Director and the Government could not properly compute the compensation amounts as done in the impugned orders.
- Even if the Government considered a Panchayat resolution required cancellation, modification or variation, under section 191 the Government could only direct the Panchayat to reconsider the issue (per the Panchayat's contention).
- Other contentions included that the bidder had undertaken to remit dues, any loss (if at all) must be computed after proper adjudication, and that the person who heard the matter had not passed the order.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The Court examined section 191 of the Kerala Panchayat Raj Act (as amended effective 24-03-1999), which provides that the Government may cancel or vary a Panchayat resolution in specified circumstances but, before doing so, may refer the matter to the Ombudsman or the Tribunal for consideration; the Ombudsman or Tribunal must give the Panchayat an opportunity of being heard and send a report with conclusions to the Government, on the basis of which the Government may cancel, amend or confirm the resolution or decision.
The Court found that the Government's impugned orders were not made in accordance with this procedure. Specifically, there was no evidence of a reference to the Ombudsman or the Tribunal, no record of the required consideration with notice to the Panchayat, and no report as mandated by section 191(2). Because the mandatory procedural steps under section 191(2) were not followed, the Government's orders could not stand.
On that basis, the Court quashed the Government orders (noted as Ext.P4 in the former petition and Ext.P6 in the latter petition) and directed the Government to pass appropriate orders in accordance with law in the appeal filed by the petitioner in WPC No. 2835/2004. The Court fixed a timeline of four months from the date of production of a copy of the judgment for the Government to act.
Holding and Implications
The Government orders (Ext.P4 and Ext.P6) are quashed.
Direct consequences:
- The Government is directed to pass appropriate orders in accordance with law in the appeal filed by the petitioner in WPC No. 2835/2004 within four months from the date of production of a copy of this judgment.
- The writ petition is disposed of as above.
Broader implications: The opinion is limited to setting aside the specific Government orders for failure to follow the procedure mandated by section 191(2). The text does not set out any broader precedent beyond requiring adherence to the statutory referral and hearing procedure under section 191.
1. The Panchayat has filed the latter writ petition challenging the order dated 2-12-2003 (Ext.P6) and the highest bidder in auction for collection of sand has filed the former writ petition for implementing the said order. According to the bidder, owing to the orders passed by the Deputy Director and this court he could not fully enjoy the benefit of collection of sand during the period of licence and hence he suffered huge loss. He approached the Deputy Director. The Deputy Director held that the petitioner should be compensated for the loss for 50 days instead of 81 days as claimed by him. The Panchayat took up the matter before the Government and the Government passed the impugned order affirming the stand of the Deputy Director. According to the Panchayat, the Deputy Director and the Government could not have computed the amounts as done in the impugned orders. Even if the Government was of the view that a resolution by the Grams Panchayat requires cancellation, modification or variation, in exercise of the power under section 191 of the Kerala Panchayat Raj Act the Government could only direct the Panchayat to reconsider the issue. There are also other contentions (1) the bidder himself had undertaken to remit the dues, (2) if at all there is any loss it is to be computed on a proper adjudication, (3) the person who heard the matter has not passed the order etc.
2. Section 191 of the Act was amended with effect from 24-03-1999. To the extent relevant the section reads as follows:—
“191. Power of cancellation and suspension of resolutions etc.- (1) Government may either suo motu or on a reference by President, Secretary or a member, or on a petition received from a citizen, cancel or vary a resolution passed or decision taken by the Panchayat if in their opinion such decision or resolution - (a) is not legally passed or taken or (b) is in excess of the powers conferred by this Act or any other law or its abuse or (c) is likely to endanger human life, health, public safety, communal harmony or may lead to riot or quarrel or (d) is in violation of the directions or provisions of grant issued by Government in the matter of implementing the plans, schemes, or programmes. (2) Before cancelling or amending a resolution or decision as per sub section (1), the Government may refer the matter for consideration either of the Ombudsman constituted under section 271G or the Tribunal constituted under section 271 and the Ombudsman or the Tribunal as the case may Be, after giving the Panchayat an opportunity of being heard: send a report to the Government with its conclusions and the Government may, on its basis cancel, amend or confirm the resolutions or decision.”
3. Evidently, the order passed by the Governments and impugned by the Panchayat is not one passed as per the procedure. There is no reference and the required consideration with notice to the Panchayat and the report under Section 191 (2) of the Act. Hence I quash the Government order (Ext.P4 in the former and Ext.P6 in the latter). There will be a direction to the Government to pass appropriate orders in accordance with law in the appeal filed by the petitioner in WPC No. 2835/2004. This shall be done within a period of four months from the date of production of a copy of this judgment.
4. The writ petition is disposed of as above.