- Bookmark
- Share
- CaseIQ
K. Abdul Rahiman And Others v. Divisional Forest Officer And Another
Factual and Procedural Background
Two confessed defaulters filed writ petitions under Article 226 of the Constitution challenging the recovery of loss caused to the Government due to their default in a timber auction conducted by the Divisional Forest Officer, Palghat. The petitioner participated in a public auction on 26-12-1979 after depositing earnest money and signing the sale notice accepting all conditions. He was the highest bidder with a bid of Rs. 3,31,000 and paid part of the amount on the sale date. However, on 8-1-1980, he withdrew his offer through a lawyer's notice and requested a refund, which was declined. The sale was confirmed on 4-2-1980. The petitioner failed to pay further instalments or execute the agreement, leading to resale of the timber rights at a lower price on 7-5-1980, causing a loss of Rs. 96,250.33. The Government issued a demand notice seeking recovery of this loss under the Revenue Recovery Act. The petitioner challenged this recovery proceeding by filing the writ petition on 9-2-1988.
Legal Issues Presented
- Whether the petitioner was entitled to withdraw from the auction after being declared the highest bidder and before the sale confirmation.
- Whether a valid contract existed between the petitioner and the Government in the absence of a written agreement executed under Article 299 of the Constitution.
- Whether the Government could be its own arbiter in assessing damages for breach of contract.
- Whether the loss caused by resale due to the petitioner's default could be recovered as a statutory liability under Section 79 of the Kerala Forest Act and the Revenue Recovery Act.
- Whether recovery of damages under the Revenue Recovery Act is permissible despite the absence of a contract complying with Article 299.
Arguments of the Parties
Petitioner’s Arguments
- After withdrawing his offer and before confirmation of sale, no contract existed with the Government, hence no breach occurred.
- Assuming a contract existed, no agreement was executed as required under Article 299 of the Constitution, rendering any claim for breach invalid.
- The Government cannot act as its own arbiter to assess damages, and the claim for damages is unsustainable in law.
Government’s Arguments
- The liability enforced is statutory, not contractual, relying on Section 79 of the Forest Act and Section 68 of the Revenue Recovery Act.
- The petitioner was bound by the auction conditions and could not withdraw after being declared highest bidder.
- The claim is for liquidated damages specified in the auction notice, negating the need for an enquiry to fix quantum.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| State of Karnataka v. Rameshwar Rice Mills, AIR 1987 SC 1359 | State cannot be its own arbiter in breach disputes; assessment of damages by State is binding only if breach is admitted or undisputed. | Confirmed that where breach is admitted, Government can assess damages and recover them without external adjudication. |
| K.P Chowdhry v. State of M.P, AIR 1967 SC 203 | Article 299 prohibits implied contracts between Government and others; contracts must comply with constitutional requirements. | Held no contract existed between petitioner and Government as required by Article 299; no implied contract arises from auction participation. |
| A. Damodaran v. State of Kerala, AIR 1976 SC 1533 | Statutory contracts outside Article 299 rigour; statutory liabilities enforceable even without formal contract. | Supported view that statutory status and liabilities arise under statute and are enforceable despite absence of formal contract. |
| State of Haryana v. Lal Chand, AIR 1984 SC 1326 | Statutory contracts under Excise Act enforceable without Article 299 compliance; statutory liabilities recoverable under law. | Applied principle that statutory liabilities arising from auction bids can be enforced notwithstanding lack of formal contract. |
| Chellappan v. Executive Engineer, 1979 Ker LT 53 | Distinction between liquidated and unliquidated damages is not recognized; quantum of damages may require court determination. | Referenced but distinguished, noting Supreme Court decisions supersede its wide statement on liquidated damages. |
| Ponnappan v. D.F.O, 1984 Ker LJ 853 | Liquidated damages may be scrutinized for reasonableness; penalty clauses may be unenforceable. | Noted but court preferred Supreme Court authority limiting such scrutiny in cases of admitted breach and liquidated damages. |
| State of Kerala v. Universal M. Agencies, 1980 Ker LT 187 (AIR 1980 Ker 158) | Government’s power to adjudicate breach and damages under contract provisions. | Overruled by later Supreme Court ruling; adjudication of breach by one party to contract opposed to public policy. |
| Bhaskaran Nair v. State of Kerala, 1980 Ker LT 462 | Section 79 of Kerala Forest Act allows recovery of money payable under auction notices as arrears of land revenue. | Supported Government’s right to recover amounts under statutory liability enforceable as arrears of land revenue. |
| Kunjukrishnan v. State, AIR 1983 Ker 73 | Affirmed recovery under Section 79 of Kerala Forest Act for money payable under auction conditions. | Followed Bhaskaran Nair’s decision, reinforcing statutory recovery mechanism. |
| State of Kerala v. Aly, 1985 Ker LT 249 | Clarified distinction between contracts under Article 299 and statutory liabilities under auction notices. | Confirmed that liabilities arising under auction notices are recoverable under Section 79 as statutory dues. |
| State of Kerala v. Joy, 1985 Ker LT 1030 | Money payable under auction notice recoverable under Section 79 even if no contract under Article 299 exists. | Reiterated statutory liability enforceability under Section 79 of Kerala Forest Act. |
| Spl. Dy. Tahsildar v. Kunju Moideen, 1980 Ker LT 850 | Held Section 79 inapplicable where liability was not related to timber or forest produce under contract or auction notice. | Distinguished present case; no conflict with other decisions enforcing Section 79. |
| State of Kerala v. Kerala Flour Mills, 1980 Ker LT 966 | Revenue recovery not permissible for liabilities arising under void contracts not conforming to Article 299. | Distinguished as not involving enforcement of statutory liability; not applicable to present case. |
Court's Reasoning and Analysis
The Court analyzed the auction conditions and statutory provisions governing the sale and recovery of dues. It held that the petitioner, having complied with auction conditions by depositing earnest money and signing the sale notice, was bound by those conditions and could not withdraw his offer after being declared highest bidder. The auction conditions explicitly provided that failure to pay instalments would result in cancellation and resale at the bidder’s risk and loss, with liability to compensate any loss sustained by the Government.
The Court distinguished between contractual and statutory liabilities, emphasizing that no valid contract existed under Article 299 due to absence of a written agreement executed in conformity with constitutional requirements. However, a statutory liability arose under Section 79 of the Kerala Forest Act for money payable under the terms of the auction notice, enforceable under the Revenue Recovery Act as arrears of land revenue.
The Court addressed the petitioner’s contention that the Government could not be its own arbiter in assessing damages. Relying on the Supreme Court decision in State of Karnataka v. Rameshwar Rice Mills, it held that where breach of contract is admitted or undisputed, the Government’s assessment of damages is binding and does not require external adjudication.
The Court rejected reliance on earlier Kerala High Court decisions suggesting that liquidated damages clauses require court determination of quantum, noting that the Supreme Court’s authoritative ruling supersedes that view. It further clarified that statutory liabilities arising from auction notices are distinct from contracts and enforceable notwithstanding the absence of formal contract execution under Article 299.
Finally, the Court found no conflict between prior Division Bench rulings once the scope of Section 79 and the Revenue Recovery Act was properly understood and applied. It concluded that the Government lawfully initiated recovery proceedings under statutory provisions to recover the loss caused by the petitioner’s default.
Holding and Implications
The writ petitions are dismissed.
The Court held that the Government was entitled to recover the loss sustained due to the petitioner’s default under the statutory provisions of Section 79 of the Kerala Forest Act and the Revenue Recovery Act. The petitioner was bound by the auction conditions and liable for damages measured by the difference between the original and resale auction prices. No prohibition or mandamus could restrain the Government from proceeding with recovery. The decision clarifies that statutory liabilities arising from auction notices are enforceable as arrears of land revenue even in the absence of a contract executed under Article 299. No new precedent was set beyond affirming existing Supreme Court and High Court authority. The direct effect is that the petitioner must pay the amount due, and the Government’s recovery actions are lawful and valid.
Bhaskaran Nambiar, J.:— Two confessed defaulters seek redress under Art. 226 of the Constitution in practically identical circumstances in these two writ petitions. For convenience, therefore, it is sufficient to refer to the petitioner and the facts in one writ petition. O.P No. 3799 of 1981.
2. The Divisional Forest Officer, Palghat, notified on 4th December, 1979 that the right of collection and removal of all timber and firewood except Teak, Rosewood and other enumerated categories of wood, in specified areas will be offered for sale in public auction subject to certain conditions. The auction was held on 26-12-1979 and the petitioner was permitted to bid after he made the earnest money deposit of Rs. 1,000/- and signed a copy of the sale notice in token of having accepted all the conditions. He was the highest bidder with a bid of Rs. 3,31,000.00. He also paid on the sale date Rs. 10,000/- less the earnest money deposit already paid. Within a week thereafter, on 8-1-1980, he however, informed the first respondent, the Divisional Forest Officer, through a lawyer's notice that he was withdrawing his offer, and requesting for refund of the amount paid by him. The first respondent declined his request and the sale was confirmed on 4-2-1980. The petitioner refused to pay the instalments or execute the agreement as per the conditions of auction. Treating him as a defaulter, resale was ordered and the fresh sale was conducted on 7-5-1980 and the highest bid was only Rs. 2,35,000/-, less by Rs. 96,000/- than covered by the first auction. The loss caused Rs. 96,250.33, was sought to be recovered from the petitioner. A demand notice was sent directing the petitioner to remit the amount within fifteen days of the date of receipt of the notice failing which he was warned that revenue recovery steps would be initiated. Faced with the threat of action under the Revenue Recovery Act, which even allowed immediate attachment of movables on mere show of a demand notice, the petitioner rushed to this Court and filed this writ petition on 9-2-1988.
3. Shri, Sugunapalan learned counsel for the petitioner submitted that after the petitioner withdrew his offer, before the sale was confirmed there was no contract with the Government and there could be no breach of that contract. It was also submitted, assuming that there was a contract, the petitioner did not execute any agreement as contemplated under the auction or in conformity with Art. 299 of the Constitution and thus there was no valid contract to sustain a claim for its breach. The Government, it is stated, cannot in any case, be the arbiter regarding the quantum of damages and the claim now made is not sustainable in law.
4. The learned Advocate General, appearing for the State contended that the State was enforcing only a statutory liability and not any contractual obligation and relied on S. 79 of the Forest Act and S. 68 of the Revenue Recovery Act for the purpose. The petitioner was bound by the conditions of auction and he could not be permitted to withdraw after he participated in the bid and was declared the highest bidder. It was again pointed out that the claim was only for liquidated damages specified in the auction notice, and there was no necessity to conduct any enquiry to fix the quantum.
5. The conditions of auction. Ext. R-1(a) provided that before being permitted to bid the intending bidder must make an earnest money deposit. E.M.D for Rs. 1,000/- in cash and also sign a copy of the sale notice in token of having accepted all the conditions therein. There is no dispute that the petitioner complied with these conditions. He therefore bound himself to abide by all the conditions of auction and the questions as to whether he was entitled to withdraw after making the highest bid and whether he was required to make good the loss if any, sustained by the Government consequent on his default, are matters referable to those conditions and the relevant statutory provisions.
6. Under the scheme of auction “no highest bidder will be permitted to withdraw his offer till a final decision is taken by the department on his offer”. Therefore, the petitioner was not entitled to resile from his offer, after he was declared as the highest bidder at the close of the auction on 26-12-1979 and the first respondent rightly rejected his request.
7. After confirmation of the sale, the successful bidder has to remit the balance 1/3rd of the bid amount, pay sales tax for the total sale value, pay into the Government Treasury Savings Bank Account an amount equal to 10% of the total sale value as security, execute an agreement in the prescribed form in stamp paper and remit the balance 2/3rd of the bid amount in two equal instalments, the first within one month of the execution of the agreement and the second within two months or within such extended time as may be ordered. It is also specifically provided:—
“Failure to remit any of the above instalments even during the extended period will entail cancellation of the contract and forfeiture of all monies paid till then and all produce remaining in the coupe. The right thus cancelled will be resold at the risk and loss of the contractor.”
8. The petitioner did not make any payment after the sale was confirmed. He was a defaulter on his own showing. Clause 7 of the conditions of auction was automatically attracted. Clause 7 provides:
“In case of resale or departmental working on account of default by the successful bidder/contractor, the loss, if any, will be made good by the defaulter but he shall not be entitled to the profit the department may derive thereby.”
9. The conditions of the auction, accepted by the petitioner and binding on him authorised the Government, on breach by the terms of the auction, to conduct a fresh auction at the “petitioners risk and loss” and the petitioner agreed to make good the loss, if any, sustained on resale. On the terms of the auction notice, the petitioner, in this case, was liable to pay the loss caused to the department on account of his own default. The loss was measured by the difference between the price obtained in the first auction and what was obtained in the second auction. The expenses incurred for conducting the auction, of course, were part of the loss.
10. The petitioner cannot derive any support from the conditions of auction and cannot deny his liability on the admitted breach of its terms. It is in this context that he raises two legal contentions which we shall presently deal with.
11. It is contended that when the State is one of the contracting parties, and seeks to recover damages for breach of that contract, the State cannot be a Judge in its own cause and cannot be its own arbiter to determine the liability and quantum of damages. This question poses no problem as the matter is settled by several decisions, and the latest decision of the Supreme Court in State of Karnataka v. Rameshwar Rice Mills, Thirthahalli, AIR 1987 SC 1359 concludes the issue against the petitioner. The Supreme Court held thus:—
“The terms of Cl. 13 do not afford scope for a liberal construction being made regarding the powers of the Deputy Commissioner to adjudicate upon a disputed question of breach as well as to assess the damages arising from the breach. The crucial words in Cl. 12 are “and for any breach of conditions set forth hereinbefore, the first party shall be liable to pay damages to the second party as may be assessed by the second party”. On a plain reading of the words it is clear that the right of the second party to assess damages would arise only if the breach of conditions is admitted or if no issue is made of it. If it was the intention of the parties that the officer acting on behalf of the State was also entitled to adjudicate upon a dispute regarding the breach of conditions the wording of Cl. 12 would have been entirely different. It cannot also be argued that a right to adjudicate upon an issue relating to a breach of conditions of the contract would flow from or is inhered in the right conferred to assess the damages arising from a breach of conditions. The power to assess damages, as pointed out by the Full Bench, is a subsidiary and consequential power and not the primary power. Even assuming for arguments sake that the terms of Cl. 12 afford scope for being construed as empowering the officer of the State to decide upon the question of breach as well as assess the quantum of damages, we do not think that adjudication by the Officer regarding the breach of the contract can be sustained under law because a party to the agreement cannot be an arbiter in his own cause. Interests of justice and equity require that where a party to a contract disputes the committing of any breach of conditions the adjudication should be by an independent person or body and not by the other party to the contract. The position will, however, be different where there is no dispute or there is consensus between the contracting parties regarding the breach of conditions. In such a case the officer of the State, even though a party to the contract will be well within his rights in assessing the damages occasioned by the breach in view of the specific terms of Cl. 12.
We are, therefore, in agreement with the view of the Full Bench that the powers of the State under an agreement entered into by it with a private person providing for assessment of damages for breach of conditions and recovery of the damages will stand confined only to those cases where the breach of conditions is admitted or it is not disputed.”
(emphasis supplied).
12. When a contract is broken, the party who suffers by such breach is entitled to receive from the party who has broken the contract, compensation for any loss or damage caused to him thereby. This principle of S. 73 of the Contract Act equally applies where one of the contesting parties is the Government. It is the breach of the contract that gives rise to the cause for damages. The primary duty therefore is to fix the liability for the breach. Assessment of damages is only an incidental or subsidiary function. The liability to pay damages is thus fastened where there is breach of contract. However, when a dispute arises as to whether the contract has been broken or not that dispute cannot be settled by one of the parties to the contract, for, he cannot be an arbiter in his own cause. The dispute may have to be referred to an arbitrator or the matter has to be settled in a Court of law. This principle applies to the Government also as a party to the contract. Where the breach of the contract is admitted, i.e, where there is no dispute that the contract has been broken by one of the parties, the Government as the party entitled to claim compensation for the breach need not Wait for a determination by any outside agency as to whether there was any breach of contract. In that event, the question of damages alone remains to be considered. A sum can be named in the contract as the amount to be paid in case of breach, an amount in liquidation of the claim for compensation. The contract can thus provide for liquidated damages in the event of breach and the Government claiming that amount as compensation for the admitted breach committed by the other party to the contract, need not seek the aid of Court or any outside agency for the fixation of the quantum of damages. Similarly, if the contract itself provides that “that one party shall be liable to pay damages to the second party as may be assessed by the second party”, the assessment by the second party, in case the breach is admitted, is binding on the first party and there is no more any necessity for a further quantification of the damages by any outside agency. The party assessing the damage can straightway seek to recover the amount and if that party is the Government, it can have recourse to the remedy available under the Kerala Revenue Recovery Act.
13. These principles are now well settled and applying them to the facts of the case, it is clear that the petitioner admits that he has broken the contract and that he did hot comply with the terms of the conditions of auction. He was, therefore, bound to compensate for the loss sustained by the Government. His loss is mitigated to a large extent by the Government conducting a resale and the auction conditions stipulate that the Government can only claim the loss, if any, on account of the resale. The auction notice itself fixes the mode and the method of calculation of the damages. The ascertainment of the quantum is, therefore, a simple arithmetical calculation after the resale. The contention that the Government cannot take steps for recovery of this amount under the Kerala Revenue Recovery Act cannot be accepted.
14. But, considerable reliance was placed in a decision of a learned single Judge of this Court in Chellappan v. Executive Engineer, 1979 Ker LT 53, and especially the following observations:—
“It may be that parties may contemplate in the contract the amount of liquidated damages in the event of breach. But there is no subtle distinction in India between liquidated and unliquidated damages, for, even where parties to a contract agree in the contract itself as to the quantum of damages payable by the party in the event of the breach the question as to the amount of damages is still a matter for determination by Court, for, in spite of such agreement whether the amount would be reasonably due and therefore for that reason the covenant for liquidated damages is enforceable is a question which would call for examination. That is the reason why even the stipulation for liquidated damages would not render the defaulting party liable ipso facto by reason of the default to answer for the sum agreed upon as damages. The position, therefore, would be that on the breach only a right to sue for damages may accrue. But so long as the sum due remains undetermined it cannot be said that any amount is due.”
15. This was approved in a Division Bench ruling in Ponnappan v. D.F.O, 1984 Ker LJ 853 thus:—
“As pointed out by this Court in the decision in Chellappan v. Executive Engineer, 1979 Ker LT 53 there is no distinction in this country between liquidated damages and unliquidated damages and therefore even when the parties to a contract agree upon and specify the sum of damages in the event of breach the Court may be called upon to consider the reasonableness of the quantum. If the parties stipulate as damages what may amount to penalty the statute relieves the contracting party from the obligation to pay such penalty. We are only indicating that the determination of quantum of damages is not avoided even in a case of specification of liquidated damages.”
16. We are afraid, with due respect to the learned Judges that the principle has been too widely stated. In fact, in the Supreme Court case referred to above, in State Of Karnataka v. Shree Rameshwara Rice Mills, Thirthahalli, Thirthahalli, AIR 1987 SC 1359 it was also stated thus:—
“To illustrate the position if the agreement provides for a liquidated sum being paid as damages for breach of conditions instead of a sum to be assessed by the Deputy Commissioner, it cannot be said that the specified damages will not be money due under the contract and hence the damages cannot be recovered under the Revenue Recovery Act. What applies to specified damages will likewise apply to damages which are quantified after assessment.”
Admission of the breach of contract by the defaulting party and assimilation of a provision for liquidated damages in the event of breach, dispense with a determination of any dispute by any outside agency and the Government, as the party claiming compensation can proceed to recover the amount due under the Revenue Recovery Act without recourse to a Court of law.
17. It is also necessary to refer to one more decision of a Division Bench consisting of V.P Gopalan Nambiyar, C.J and G. Balagangadharan Nair, J. in State of Kerala v. Universal M. Agencies, 1980 Ker LT 187 : (AIR 1980 Ker 158). In that case, under Cl. 16 of the relevant agreement all sums found due to the lessor could be recovered as arrears of land revenue and Cl. 17 provided thus:—
“If any dispute or question shall arise between the lessee and the lessor touching on or relating to any of the matters or things hereinbefore contained the same will be decided by the lessor and the decisions of the lessor shall be final and conclusive and shall be binding on the lessee.”
These provisions were interpreted by this Court as being wide enough to give the lessor the right to recover all sums found due to the lessor Under or by virtue of the agreement and conferring on the Government “the right of deciding the amount due to the Government”. This Court thus held that the Government had the power under the terms of the agreement to adjudicate regarding the breach of the contract and also about the extent of damage suffered by the State consequent on that breach. We think that this decision can no longer be held as good law in view of the decision of the Supreme Court in State Of Karnataka v. Shree Rameshwara Rice Mills, Thirthahalli, Thirthahalli. AIR 1987 SC 1359. A provision enabling one of the parties to an agreement to be the arbiter to decide whether the contract has been broken or not is opposed to public policy, equity and justice and that adjudication regarding the breach of the contract has to be left to an independent person or body and cannot be made by one of the parties to the contract, intimately interested in the result of the adjudication.
18. The last and most important contention urged is that the terms of the auction, though accepted by the petitioner, are no longer enforceable in the absence of a written agreement signed by the parties and conforming to the constitutional requirements under Art. 299. It is mainly on this question that this case has been referred to a Full Bench. We shall extract the order of reference:—
“As these cases involve an important question of law and as we find that there is apparent conflict between the Division Bench rulings of this court reported in 1980 Ker LT 850 between the Spl. Dy. Tahsildar v. Kunju Moideen and 1985 Ker LT 249 between State Of Kerala v. M.E Aly, we consider it appropriate to refer these cases to a Full Bench for consideration. The petitioner shall produce proper paper books for all the three Judges, with copies to the other side within ten days from this date. The learned Advocate General has agreed to produce the relevant papers pertaining to sale notice etc. It is ordered accordingly.”
Before we attempt to resolve the conflict, if any between the decisions of this Court, it is necessary to note that there are three decisions of the Supreme Court which lay down the law on this aspect and which are sufficient to settle the controversy in this case. We have been taken through these three decisions, K.P Chowdhry v. State of M.P, AIR 1967 SC 203. A. Damodaran v. State of Kerala, AIR 1976 SC 1533 and State of Haryana v. Lal Chand, (1984) 3 SCC 634 : (AIR 1984 SC 1326).
19. Thus, Art. 299 of the Constitution applies to all contracts made in the exercise of the executive power of the Union or a State. The contracts in such cases have to be executed on behalf of the President or Governor by such persons and in such manner as he may direct or authorise. A contract not in compliance with this constitutional requirement is null and void. There can thus be no implied contract and the contract which is void admits of no ratification either. The mandate of Art. 299, therefore, applies only to contracts made in exercise of the executive power. It can have no application to contracts which are statutory in nature: Nor can it have any application for the enforcement of any statutory liability, for, the liability arises not under the contract but under the statute.
20. The decision in K.P Chowdhry v. State of M.P, AIR 1967 SC 203 of a Bench of five Judges is authority for the proposition-that Art. 299 does not countenance implied contracts. There is no implied contract either before the bidding or after the auction. This was a case of a forest auction. It was held thus:—
“The first is that in view of Art. 299(1) there can be no implied contract between the Government and another person, the reason being that if such implied contracts between the Government and another person were allowed, they would in effect make Art. 299(1) useless, for then a person who had a contract with Government which was not executed at all in the manner provided in Art. 299(1) could get away by saying that an implied contract may be inferred on the facts and circumstances of a particular case. This is of course not to say that if there is a valid contract as envisaged by Art. 299(1), there may not be implications arising out of such a contract. The second consequence which follows from these decisions is that if the contract between Government and another person is not in full compliance with Art. 299(1) it would be no contract at all and could not be enforced either by the Government or by the other person as a contract. In the present case it is not in dispute that there never was a contract as required by Art. 299(1) of the Constitution. Nor can the fact that the appellant bid at the auction and signed the bid-sheet at the close thereof or signed the declaration necessary before he could bid at the auction amount to a contract between him and the Government satisfying all the conditions of Art. 299(1). The position therefore is that there was no contract between the appellant and the Government before he bid at the auction, nor was there any contract between him and the Government after the auction was over as required by Art. 299(1) of the Constitution. Further in view of the mandatory terms of Art. 299(1) no implied contract could be spelled out between the Government and the appellant at the stage of bidding for Art. 299 in effect rules out all implied contracts between Government and another person. The view taken by the High Court that S. 155(b) of the Madhya Pradesh Land Revenue Code which provides for recovery of money as arrears of land revenue would therefore ensure (enure?) in favour of the Government and enable it to recover the deficiency cannot be sustained. That clause provides for recovery of all moneys falling due to the State Government under any grant, lease or contract and says that they shall be recoverable in the same manner as arrears of land revenue. The High Court was of the view that the word “contract” in this clause includes an implied contract. But if there can be no implied contract between the Government and another person in view of the mandatory provision of Art. 299(1) of the Constitution there can be no question of recovery of any money under an implied contract under Cl. (b) of S. 155”.
21. The decision in A. Damodaran v. State of Kerala, AIR 1976 SC 1533 illustrates the case of a statutory contract which is outside the pale of the rigour of Art. 299. It was a case arising under the Abkari Act where a “statutory status” was conferred to a “grantee” of a privilege under the Kerala Abkari Act. It was held thus:—
“Section 18A(2) lays down that “no grantee of any privilege under sub-sec. (1) shall exercise the same until he has received a licence in that behalf from the Commissioner”. It will be seen that this provision contemplates the statutory status of a “grantee” even before he becomes entitled as of-right to exercise privileges of a grantee on the receipt of a licence. What is noticeable is that even before he receives his licence he is described as a “grantee”. The successful bidders, in the case before us, had been permitted by the excise authorities, in recognition of their rights to receive and in anticipation of receipt of licences, to exercise the privileges of grantees. They were thus treated as grantees in anticipation of execution, of contracts and grants of licenses. Grantees under S. 28 of the Act are those who have received the privilege and not necessarily only those who have received the written contracts and licenses. The word “grantee” used there seems to us to carry this wider connotation with it”.
“The appellants became entitled to get licenses from the Government which had to perform its duty to execute written agreements and grant licenses as soon as the appellants fulfilled required conditions by paying up the remainder of the amounts due. The Government had performed its part of the bargain and even allowed the appellants to start selling liquor. The appellants also became liable and bound to perform their corresponding obligations under the conditions of the auctions imposed in pursuance of statutory provisions. This reciprocity of obligations, quite apart from its basis in agreement, had thus acquired an operative force resting on statutory sanction and equity”.
22. The decision in State of Haryana v. Lal Chand, (1984) 3 SCC 634 : (AIR 1984 SC 1326) was again an “Excise case” regarding the enforcement of a statutory liability. It was held thus:—
“We are clearly of the opinion that in the case of a statutory contract like the one under the Excise Act, the requirements of Art. 299(1) cannot be invoked. In A. Damodaran v. State of Kerala, (AIR 1976 SC 1533), the Court interpreting S. 28 of the Kerala Abkari Act, 1967 which was in pari materia with S. 60 of the Punjab Excise Act, 1914 held that even if no formal deed had been executed as required under Art. 299(1) still the liability for payment of the balance of the licence amount due could be enforced by taking recourse to S. 28 of the Act. The Kerala High Court rejected the contention of the appellants by holding that the liability to satisfy the dues arising out of a bid was enforceable under S. 28 quite apart from any contractual liability and this view was upheld by this Court on the ground that the word ‘grantee’ in S. 28 has a wide connotation to mean a person who had been granted the privilege by acceptance of his bid. It was further held that the statutory duties and liabilities arising on acceptance of the bid at a public auction of a liquor contract may be enforced in accordance with the statutory provisions and that it was not a condition precedent for the recovery of an amount due under S. 28 of the Act, that the amount due and recoverable should be under a formally drawn up and executed contract. This is in recognition of the principle that the provisions of Art. 299(1) of the Constitution are not attracted to the grant of such a privilege to vend liquor under the Act”.
23. In the present case, no contractual liability can be enforced as there was no contract complying with Art. 299 of the Constitution. There was no statutory contract as the provisions of the Kerala Forest Act and the rules made thereunder do not provide for the creation of any such contract. However, a statutory liability, distinct from a contractual obligation is fastened on the parties under S. 79 of the Forest Act which reads thus:—
“79. Recovery of money due to Government:—
All money, other than fines, payable to the Government under this Act or any rule made thereunder, or on account of timber or forest produce or of expenses incurred in the execution of this Act in respect of timber or forest produce, or under any contract relating to timber or forest produce including any sum recoverable thereunder for the breach thereof or in consequences of its cancellation or under the terms of a notice relating to the sale of timber or forest produce by auction or by invitation of tenders, issued by or under the authority of a Divisional Forest Officer, and all compensation awarded to the Government under this Act may, if not paid when due be recovered under the law for the time being in force, as if it were an arrear of land revenue”.
24. There is corresponding provision in the Revenue Recovery Act in S. 68 providing that all sums declared by any other law for the time being in force, to be recoverable as arrear of public revenue due on land, may be recovered under the provisions of the Revenue Recovery Act.
25. Thus under S. 79, all money payable to the Government under the terms of a notice relating to the sale of timber or forest produce by auction or invitation of tenders issued by or under the authority of a Divisional Forest Officer, if not paid, when due could be recovered under the law for the time being in force as if it were an arrear of land revenue. In the present case, the Government was only chiming an amount under this statutory provision, thus enforcing a statutory liability. There is no constitutional embargo under Art. 299 to enforce this statutory obligation.
26. Now to the decisions of this Court. In Bhaskaran Nair v. State of Kerala, 1980 Ker LT 462, a Division Bench of this Court (Balakrishna Eradi and George Vadakkel, JJ.) held thus:—
“S. 79 of the Kerala Forest Act, 1961 specifically provides that all money payable to the Government on account of timber or forest produce inclusive of any sum recoverable under the terms of a notice relating to sale of timber or forest produce by auction may, if not paid when due, be recovered under the law for the time being in force, as if it were an arrear of land revenue. What sought to be recovered from the appellant under Ext. P6 is an amount said to be recoverable from him under the terms of the notice relating to the sale of forest produce by auction and hence it falls directly within the scope of S. 79. It cannot therefore be said that the respondents have acted without jurisdiction in initiating proceedings against the appellant under the Revenue Recovery Act for recovery of the said sum”.
27. This decision has been followed by a Division Bench consisting of Justice Bhaskaran (as his Lordship then was) and one of us (Sukumaran, J.) in Kunjukrishnan v. State, AIR 1983 Ker 73). The same view has been expressed in a later decision of a Division Bench in State of Kerala v. Aly, 1985 Ker LT 249, consisting of M.P Menon and Radhakrishna Menon, JJ. Their Lordships construing the effect of S. 79 of the Forest Act stated thus:—
“Confining attention to only two of the heads under which money payable to Government is made recoverable under the Section, the first to be noticed is liability arising under a contract relating to timber or forest produce. The second is money payable under the terms of a notice relating to timber or forest produce by auction, when such notice is issued by a Divisional Forest Officer. The term ‘contract’ under the first head can possibly include only formal contracts executed under Art. 299(1), in exercise of the State's executive power. But the second head is obviously designed to cover, something different from such contracts, for otherwise, there was no need to separately provide for it. And what is covered by it is a liability arising from sale notice issued by the D.F.O The mere issuance of a sale notice may not create liability, but when money becomes “payable under the terms” of such a notice, that becomes recoverable. That is, when a person participates in the auction and becomes answerable for money payable under the terms of the auction notice, something recoverable under S. 79 comes into being”.
28. In yet another decision of a Division Bench of this Court in State of Kerala v. Joy, 1985 Ker LT 1030, Justice Balakrishna Menon and one of us (Sukumaran, J.) observed thus:—
“A Division Bench of this Court in State of Kerala v. Aly, 1985 Ker LT 249 : 1985 Ker LJ 1 has held that money payable under the terms of a notice for sale of timber or forest produce by auction issued by a Divisional Forest Officer is recoverable under S. 79 of the Kerala Forest Act. Even though the mere issue of a sale notice may not create any liability, but when money becomes payable under the terms of such a notice, it is held the amount is recoverable under S. 79. Such occasions arise when a person participates in the auction and becomes answerable for money payable under the terms of the auction notice. The liability may not be contractual when tested in the light of Art. 299(1) of the Constitution. But the liability is nevertheless fixed and may be enforceable by the statutory provision contained in S. 79 of the Kerala Forest Act. Whether the plaintiffs are entitled to any reliefs in these suits will depend upon the question whether they are liable for any amounts to the State enforceable under S. 79 of the Forest Act”.
The other decision that is required to be referred by the reference order, is the decision in Spl. Dy. Tahsildar v. Kunju Moideen, 1980 Ker LT 850, disposed of by Balakrishna Eradi, C.J and Balagangadharan Nair, J. Their Lordships were considering the question as to whether the loss sustained by the forest department on account of resale of the right to raise Punam cultivation on certain lands could be recovered under the Revenue Recovery Act, relying on S. 79 of the Forest Act. The learned Judges held that it was not an amount due on account of or in respect of timber or forest produce under any contract relating to timber or forest produce and therefore S. 79 could not be invoked. On the facts of the case, therefore, this case is distinguishable in that it was a case to which S. 79 of the Forest Act did not apply and the question as to whether S. 79 created a statutory liability which could be enforced under the Revenue Recovery Act did not arise. There is thus no conflict between the decision in Special Deputy Tahsildar v. Kunju Moideen, 1980 Ker LT 850 and State Of Kerala v. M.E Aly, 1985 Ker LT 249.
29. The decision in State Of Kerala v. Kerala Flour Mills, 1980 Ker LT. 966 by Gopalan Nambiyar C.J and G. Balagangadharan Nair, J. is also not helpful to the petitioner as revenue recovery proceedings were taken in respect of a liability arising under a void contract not conforming to Art. 299 and there was no enforcement of any statutory liability or statutory contract.
30. We are, therefore, of the view that in this case, the Government was competent and perfectly justified in taking steps under the Revenue Recovery Act, to recover “the amount due under the terms of a notice relating to the sale of timber by auction”, in enforcement of a statutory liability created under S. 79 of the Forest Act. No writ of prohibition or mandamus can issue prohibiting or forbearing the respondents from taking proceedings under the Revenue Recovery Act for recovery of the loss sustained by the Government consequent on the default committed by the petitioner. The demand notice is also not liable to be quashed as it was issued by a competent authority and with jurisdiction. The parties have been able to retain with them the amount payable to the Government all these seven years. They cannot expect anything more. There are no merits in both the Original Petitions and they are dismissed; but, in the circumstances of the case, no costs.
Petitions dismissed.
Alert