The United Oxygen Co. (Pvt.) Ltd. Bangalore v. Karnataka Electricity Board, Bangalore And Another
Structured Summary of the Opinion
Factual and Procedural Background
The petitioner is United Oxygen Company (Private) Limited, an industrial electricity consumer with a factory producing oxygen and an installation in a Bangalore suburb. The petitioner paid bills as demanded based on meter readings taken by officials of the 1st respondent, Karnataka Electricity Board (the Board). Subsequently the Board issued a notice of a short claim amounting to Rs. 1,09,459.75 (letter dated 25 July 1977 at Annexure-C), and after correspondence and meetings a demand of Rs. 99,211.09 was made as arrears for the period 16-11-1974 to 8-11-1976, on the basis that the meter was not functioning properly and a new H.T. meter was installed on 8-11-1976 and 12 months of that consumption was taken as the basis for the short claim.
Aggrieved, the petitioner filed a petition seeking (a) quashing of the demand (Exhibit 'H' and related letters) and (b) a mandamus/prohibition restraining the Board from charging more than meter-recorded amounts without complying with law. A rule nisi issued on 20-4-1978 and stay of the final demand (Exhibit-K) was granted. The Board appeared and filed a statement of objections on 11-3-1980, admitting that L.T. single-phase meters were used because H.T. metering cubicles were not available, that those meters were faulty at times, and that after H.T. metering cubicle installation the recorded consumption rose significantly (to 53,320 units), leading the Board to treat earlier L.T. recordings as patently erroneous and compute a back-billing short claim under its regulations and a Board order dated 20-2-1975.
The matter proceeded before this Court for determination whether the Board's demand was authorised by the Board's Regulations and applicable law.
Legal Issues Presented
- Whether the demand for alleged short claim (approx. Rs. 99,211–1,09,459), computed after installation of an H.T. meter, is without authority of law and should be quashed.
- Whether the circumstances of faulty or inappropriate meters at the petitioner's installation fall within Regulation 28(a)(ii), 28(a)(i) or 28(a)(iii) of the Electricity (Supply) Regulations (made under s.79(j) of the Electricity (Supply) Act, 1948), thereby validating the Board's back-billing method.
- Whether the supply and billing ought to have been treated as a "direct connection" for the purposes of Regulation 29 (and its note) and, if so, whether the Board followed the billing methods prescribed in Regulation 29 when making the demand.
- Whether the Board may be permitted to re-determine and recover any legally recoverable dues after applying the correct regulatory method of back-billing, and whether the Court should reserve liberty to the Board to do so.
Arguments of the Parties
Petitioner (United Oxygen Company)
- The demand (Exhibit 'H' and related letters) is without authority of law and liable to be quashed.
- The Board must not be permitted to charge amounts higher than what meters have recorded without complying with the provisions of law; relief sought included writs of certiorari, mandamus or prohibition to restrain enforcement of the impugned demand and to prevent future similar action without legal compliance.
Respondent (Karnataka Electricity Board)
- The Board admitted L.T. single-phase meters were used because H.T. metering cubicles were not available; these L.T. meters were faulty at times and under-recorded consumption compared to the sanctioned 400 KVA supply and the subsequent H.T. meter readings.
- After installation of the H.T. metering cubicle and a large rise in recorded consumption (to 53,320 units), the Board treated earlier L.T. recordings as patently erroneous and, relying on Regulation 28 and Board Order No. A6/2621/71-72 dated 20-2-1975, billed the installation on a direct connection basis to compute the short claim (Rs. 1,09,459.75) for Jan. 1975 to Dec. 1976.
- The Board contended it has a statutory obligation to collect lawful charges and not permit consumers to escape liability; it therefore prayed for dismissal of the petition.
Additional Counsel Argument
- Counsel (Mr. K.N. Gupta) contended that despite defective meters having been installed, the supply must be deemed to have been on the basis of direct connection and therefore the Board's back-billing should be sustained.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The Court's analysis proceeded primarily by reference to the Board's Regulations (promulgated under s.79(j) of the Electricity (Supply) Act, 1948), especially Regulation 28 (Faulty Meters) and Regulation 29 (Charges for Supply), and by comparing the factual admissions in the Board's statement of objections with the specific language and scope of those Regulations.
Step-by-step reasoning as stated in the opinion:
- The Court recited the text and structure of Regulation 28, noting sub-clause (a) provides three contingencies for permissible back-billing and sub-clause (b) addresses meters belonging to the consumer. The Court observed Regulation 28 addresses meters that turn out to be faulty and under-record supply; it noted there is no corresponding provision addressing a faulty meter that records more than it should (an observation relevant to interpretation disputes raised).
- The Court examined whether the facts fit Regulation 28(a)(ii), which applies when a meter goes out of order on the day it is installed or any day before the first meter reading date after installation/service. Sub-clause (ii) prescribes billing on a direct connection basis for the unrecorded period, subject to later regulation by averaging one year of consumption after a working meter is installed.
- The Court found that Regulation 28(a)(ii) did not apply because: (a) the Board admitted it installed L.T. meters temporarily due to lack of H.T. metering cubicles; (b) those L.T. arrangements were repeatedly found to be faulty but the Board did not stop metering or supply at any point and continued to allow supply until finally an H.T. meter was installed; therefore the meter did not cease recording on the day of installation or before the first reading in the narrow sense contemplated by sub-clause (ii).
- The Court held the facts were instead only potentially covered by Regulation 28(a)(i) or 28(a)(iii) (both concern back-billing based on averages of highest consumption months up to a maximum of six months or such period as deemed appropriate), but not by 28(a)(ii).
- The Court then considered Regulation 29 and its note, which governs charges for supply when meters are not available and direct connections are given: bills are to be prepared on the basis of burning hours/working hours with later revision based on average consumption ascertained for a period of one year subsequent to meter installation. The Regulations set out specific methods for H.T. and L.T. supply quantification under direct connections.
- Comparing the Board's conduct with Regulation 29, the Court found that none of the methods enumerated in Regulation 29 (note and tariff provisions) had been followed in making the demand. Thus the demand was not computed according to any method provided for high-tension installations under Regulation 29.
- The Court rejected the broader technical argument that any supply must be deemed a "direct connection" (because energy physically flows through conductors) as a reason to nullify the regulatory framework; it emphasized the Board had specifically made Regulations to deal with non-availability of meters (Regn. 29), and the Board had not availed itself of the procedural and substantive requirements of that Regulation.
- Because the demand was not shown to have been computed in accordance with the applicable regulatory provisions, the Court concluded the petitioner should succeed and be entitled to a mandamus restraining enforcement of the impugned demand.
- The Court declined to reserve liberty to the Board to determine afresh in the Court's order because the Court was not in a position, on the material before it, to decide whether the facts fell under Regulation 28(a)(i) or 28(a)(iii) — it was not apprised of the difference between energy meter reading and maximum demand meter readings necessary to make that determination. The Court therefore left it open for the Board to act on its own initiative (subject to the petitioner having remedies if a revised demand is issued).
- The Court recorded that Annexure-E (energy consumed as metered at various times culminating in 52,000 units per mensem when a proper meter was installed) had not been disputed in accuracy, and Annexure-F's accuracy was not contested.
Holding and Implications
Holding: THE PETITION IS DISPOSED OF.
The Court's direct orders and their practical consequences, as stated in the opinion, are:
- The petitioner is entitled to a mandamus restraining the Board from enforcing the impugned demand (the demand set out in Exhibit-K and related letters); the demand is quashed to the extent challenged in the petition.
- Any amount paid by the petitioner to the Board pursuant to the impugned demand and on the direction of the Court is liable to be refunded or adjusted against future dues of the petitioner; a direction to that effect shall issue.
- The Court did not make any order as to costs ("there will be no order as to costs").
- The Court did not itself re-compute or substitute a fresh lawful demand; it indicated the Board may, on its own initiative and in accordance with the applicable regulation, determine afresh whether any amount is recoverable (but the Court did not expressly reserve or grant liberty to do so in the terms of the Court making that determination). If the Board issues any revised demand, the petitioner may resort to available remedies.
Broader implications: The decision's immediate effect is limited to the parties: the impugned demand was quashed and sums paid under that demand must be refunded or adjusted. The opinion does not purport to establish a new binding precedent beyond applying the Board's Regulations to the facts of this case.
Note: This summary is based exclusively on the content of the provided opinion. No external material or precedent beyond that opinion has been used or inferred.
1. The petitioner is the United Oxygen Company (Private) Limited, a Company incorporated under the Indian Companies Act, 1956. It has a factory where oxygen is produced. Therefore, it is electricity based industry. It obtained installation to its factory in one of the suburbs of Bangalore. It is alleged by the petitioner that it was paying the bills regularly as and when the demands were served on it according to the reading taken by the officials of the 1st respondent-Karnataka Electricity Board (hereinafter referred to as the Board). However, the petitioner was surprised that it had to pay a sum of Rs. 1,09,459-75 being the short claim detailed in the letter dt. 25th July, 1977 issued by the Asstt. Engineer, Electrical, ESD-3, Bangalore-1. A true copy of that letter is produced at Annexure-C to the petition. Thereafter, there appears to have been meetings between the representatives of the Company and those of the Board and much correspondence. Finally, a demand was made at Rs. 99,211-09 being the arrears of energy consumption charges for the period between 16-11-1974 and 8-11-1976 when the meter was not functioning properly or recording the consumption of energy accurately. It is asserted by the Board, in the correspondence, as averred by the petitioner, that a new meter meant for H.T consumption was installed on 8-11-1976 and energy of 12 months thereof has been taken to be the basis for making the demand, in respect of what is contended to be the short claim. Aggrieved by the ultimate demand, the petitioner-company has approached this Court inter alia contending that the demand is without the authority of law and therefore is liable to be quashed. The prayers (a) and (b) in the petition are as follows:—
“(a) to quash by the issue of a writ of certiorari or any other appropriate writ, order or direction as the case may be the demand as made in Exhibit ‘H’ (letter No. ESD.3.F/10278/83 dt. 22nd Jan., 1978 and letter No. AAO/ESD.3/462-67 dt. 17th April, 1978 as per Exhibit-K.
(b) By issue of a writ of mandamus or writ of prohibition or any other appropriate writ, order or direction as the case may be to prohibit the respondent-Board from asking any higher charges than what their meters had recorded without complying with the provisions of law if at all the Board should ask for any difference on the alleged grounds of faulty reading of meters.”
2. Rule nisi was issued in this case on 20-4-1978 and stay of Exhibit-K, the final demand, was stayed. For reasons beyond the control of this Court, the matter was not disposed of. In the meanwhile, the Board has entered appearnace and filed its statement of objections on 11-3-1980. It is stated in the return that the contentions raised in the petition have been carefully considered by the Board. It is further stated that to an extent of 400 KVA electricity supply was sanctioned to the petitioner-company and the same was to be availed by the petitioner-company from 1-1-1974, but the petitioner took service on 16-11-1974. It is admitted that due to non-availability of H.T metering cubicles, the petitioner's installation was metered on L.T side by fixing three single phase meters. They were found to be faulty from time to time and the bills prepared on the basis of the consumption recorded by those meters was far less than the allotment. Even though the meters were replaced, the erroneous and faulty recording of the meters continued till they were replaced by H.T metering cubicle. It is further stated by the Board that the H.T meteringin cubicle was installed and the bills were prepared by the Board and paid by the petitioner on the basis of the consumption recorded by H.T meter. After the H.T metering cubicle was fixed, the consumption went up to 53320 units i.e, more than 50 per cent rise. Therefore, the consumption recorded by L.T metering was patently erroneous and in accordance with para 28 of the Electricity Supply Regulations and the subsequent Boards's order No. A6/2621/71-72 dt. 20-2-1975, the installation was billed on direct connection basis and therefore from Jan., 1975 to Dec., 1976 when the H.T metering in cubicles was operative, the short claim worked out to be Rs. 1,09,459-75 and the same was intimated to the petitioner-company.
3. The other averments do not require to be noticed except the one in para 10 which states that the L.T meters fixed to the petitioner's installation were changed twice. Once on 18-2-1975 and again on 6-4-1976 but they were still recording erroneously.
4. In that circumstance, the Board contends that what it has done is correct. As a statutory Board, it has an obligation to collect charges from every consumer in accordance with law and not allow any consumer to escape liability to pay charges. Therefore it is prayed that the petition may be dismissed.
5. In the light of these rival stands, this Court has to examine the correct position emanating from the Regulations formulated by the Board in terms of S. 79(j) of the Electricity (Supply) Act, 1948. The Regulations provide for definitions, the manner in which the application will be made for supply, the mode of servicing an installation, shifting of services, classification apparatus as L.T and H.T for purpose of consumer classification, approval of installations, among many other things. We may confine ourselves to a detailed reference to Regn. 28 of the Electricity (Supply) Regulations (hereinafter referred to as the Regulations) and Regn. 29 of the Regulations which is referred to as paragraphs by the Board in its statement of objections. Regn. 28 of the Regulation is as follows:
“28. Faulty Meters:
(a)(i) In the event of the energy meter of an installation being out of order for any reason (other than tampering by a human agency) the installation may be back-billed for a maximum period of six months or for such period as may be in the circumstances of the case deemed appropriate, on the basis of the average of the highest consumption recorded during any three months of the year in which the fall in consumption is noticed and in cases where that is not possible, then on the basis of the average of the highest consumption recorded during any three months of the preceding year. The faulty meter will be replaced by another one in good working order immediately or the same will be repaired and reinstalled as expeditiously as possible.
(ii) In the event of the meter going out of order on the very day on which it is installed and serviced or any other day before the first meter reading date after the installation is Serviced, the installation shall be billed on direct connection basis for the period during which the consumption is not recorded subject to the consumption for that period being subsequently regulated taking into account the average of one year consumption after a working meter is installed.
(iii) In the event of the maximum demand meter of an installation being out of order for any reason (other than tampering by a human agency) the installation may be back billed for a maximum period of six months or for such period as may in circumstances of the case be deemed appropriate on the basis of the highest consumtion recorded during any three months of the year in which the maximum demand meter is found to have become out of order and in cases where that is not possible then on the basis of the average of the highest consumption recorded during any three months of the preceding year. The faulty meter will be replaced by another one in good working order immediately or the same will be repaired and reinstalled as expeditiously as possible.
Exception: (i) Whenever meters of I.P installations are found recording incorrectly or not recording, the consumer shall be billed on the basis of average consumption of preceeding 12 months (or any lesser number of months the installations are in service).
Exception: (ii) Whenever, for want of metering equipments the KVA recording meters are not installed or where trivector meters installed are faulty and not replaced, for billing purposes the standard power factor, O. 9 will be adopted for converation of KW to KVA.
(b) In case the meter belongs to the consumer, the consumer should get his meter repaired and tested if possible, by the Board by paying the standard charges or by any other approved agency. Till that period the Board will instal its own meters to record the consumption for “which the consumer shall have to pay the fixing and removing charges of Rs. 3 only.”
As the marginal heading indicates, it deals with faulty meters. That is, a meter installed which turns out to be faulty and thereby fails to record the actual consumption of electrical energy supplied to the consumer thereby causing loss to the Board. If one may observe, no provision corresponding to Regulation 28 of the Regulations is made if a faulty meter records more than what it ought to, when the consumer becomes liable to pay excessive charges. That is only an observation in the light of the untenable construction that was sought to be put by the learned Counsel on the scope of application of Regn. 28 of the Regulations.
6. As is apparent from the arrangement of Regn. 28 of the Regulations, it has two sub-cls. namely, (a) and (b). Sub-cl. (a) of Regn. 28 of the Regulations provides three contingencies for back-billing as permissible in accordance with the mode and manner provided therein. However, two exceptions are created. In respect of irrigation Pump installation with which we may not concern ourselves in this case. But, nevertheless, a look at the second exception which provides that for want of metering equipments the KVA recording meters are not installed or where trivector meters installed are faulty and not replaced for billing purposes the standard power factor, O. 9 will be adopted for conversion of KW to KVA. It is nobody's case that this second exception provided to cl. (a) of Regn. 28 of the Regulations has been adopted by the Board. Cl. (b) of Regn. 28 of the Regulations provides that where the meter belongs to the consumer, the consumer should get his meter repaired and tested if possible, by the Board by paying the standard charges or by any other approved agency. Till that period the Board will instal its own meters to record the consumption for which the consumer shall have to pay the fixing and removing charges of Rs. 3/- only.
7. Cl. (a) of Regn. 28 of the Regulations has no application to the facts of this case which are not in dispute and which have been stated earlier. The question is, is it a case which falls under sub-cl. (ii) of Cl. (a) of Regn. 28 of the Regulations? Sub-cl. (ii) of Cl. (a) of Regn. 28 of the Regulations comes into operation when the meter goes out of order on the very day on which the installation is made and serviced or any other day before the first meter reading date after the installation is serviced, and not otherwise. In such an event, the installation is required to be billed on direct connection basis for the period during which the consumption is not recorded. However, subject to the consumption for that period being subsequently regulated taking into account the average of one year consumption after a working meter is installed. Therefore, the need for billing for a back claim in accordance with sub-cl. (ii) of Cl. (a) of Regn. 28 of the Regulation will arise only when the meter has stopped recording either on the day on which it was serviced or when it was discovered not to be recording on the first meter reading day after installation and service and not otherwise. In the instant case, we have indisputable evidence supported by the admission of the Board itself that a proper type of meter for H.T installation was not available and therefore they made other arrangements by installing a L.T meter with certain alterations which it expected to work properly and record the consumption. They discovered more than once the substitution they had made was not recording properly. But the Board or its officers did not choose to, stop metering the energy consumed by the petitioner at any point of time. But continued to allow the petitioner to get the supply through the meter till finally a replacement was made by a meter meant for H.T supply. It is then that they have decided to back-bill.
8. Therefore, in the opinion of this Court, the matter is likely to be covered only by the method provided for in Regn. 28(a)(i) or Regn. 28(a)(iii) of the Regulations and definitely not under sub-cl. (ii) of Cl. (al of Regn. 28 of the Regulations.
9. However, Mr. K.N Gupta contended that in any event this Court should consider that despite the defective meter having been installed, the supply of energy must be deemed to have been on the basis of direct connection and therefore the back billing done must be sustained.
10. The argument may be technically correct, in the sense that it is common knowledge that electrical energy is transmitted only if the flow of the energy is continuous through the conductors. In that sense every connection is a direct connection. That would absolve the liability of the Board to instal meters and frame regulations to settle the accounts between themselves and the consumers. That argument, however, must be rejected for the reason that the Board while making regulations were aware of the situation, that may crop up on account of non-availability of meters. Therefore, a special regulation has been made to cover the said situation and that Regn. is 29. Regn. 29 provides as follows:—
“29. Charges for supply:
(a) The price and methods of charging for energy supply shall be those as fixed by the Board from time to time.
Note:— When meter are not available and direct connections are given, bills will be prepared on the basis of burning hours/working hours indicated herein subject to revision based on average consumption ascertained for a period of one year subsequent to the installations of the meter.
CHARGES FOR H.T SUPPLY: 1. Cases coming under Tariff H.T I(A) H.T.I (B), H.T.I (D) and H.T.I (E). i) Demand charges on 75% of the contract demand plus energy charges at 25% load factor (i.e six hours full load for a eight hours shift). ii) Demand charges on 75% of the contract demand plus energy charges at 50% load factor (i.e twelve hours full load for a sixteen hours shift). iii) Demand charges on 75% of the contract demand plus energy charges at 66-2/3% load factor (i.e sixteen hours full load for a twentyfour hours shift). 2. Cases coming under tariff H.T.I (C) (I.P Sets) Demand charges on 75% of the contract demand plus energy charges at 20% load factor (or five hours basis per day). 3. Cases coming under tariff H.T 3. Same as corresponding installation under L.T supply. 4. Cases coming under tariff H.T 4. Temporary supply-Demand charges on the entire contract demand plus energy charges at 50% load factor and working hours at 12 hours per day. CHARGES FOR L.T SUPPLY: Classes of service (Low Tension) Burning Hours per day i) Domestic lighting: Two and a half ii) Domestic lighting heating and power: Five iii) Commercial lighting, heating and power: Eight iv) Industrial power: Six for eight hours shift, twelve for sixteen hours shift eighteen for twenty-four hours shift. (v) Cinema: Six hours for two shows per day nine hours for three shows per day. (iv) I.P Sets: Monthly minimum charges equal to 1/12th of the amount of the annual minimum charges for H.P per month.
Monthly minimum charges shall be collected even when the annual minimum charges are waived for reasons of drought etc., subject to revision based on energy consumption ascertained for a period of one year subsequent to the installation of the meter.
Before serving the installations, both H.T and L.T installations, on direct connection basis, the officers of the Board should obtain a separate agreement from the consumers in the form prescribed hereunder.”
11. From the note to cl. (a) of Regn. 29, it is clear that when meters are not available and direct connections are given bills will be prepared on the basis of burning hours or working hours indicated therein. Now, from the statement of objections filed, it is clear that none of the methods enumerated in Regn. 29 has been followed in making the demand. Therefore, the demand which is resisted by the petition is not a demand computed in any one of the methods provided for high tension installations under Regn. 29. Therefore, it is too late in the day to contend that this Court must deem it as a direct connection when by their own acts of omissions and commissions, the Board has failed to get the advantage, if any, that was available under Regn. 29.
12. In that view of the matter, the petitioner must succeed and will be entitled to a mandamus restraining the Board from enforcing its impugned demand.
13. Mr. N.K Gupta nevertheless-contended that liberty should be reserved to the Board to determine afresh in accordance with the regulation which is applicable to back-billing and recover the dues so that the public exchequer will not lose. It is true this Court has only decided that on the facts of the case, the petitioner's case was not covered by sub-cl. (ii) of cl. (a) of Regn. 28. But the court is not in a position to determine whether it falls under sub-cl. (i) or sub-cl. (iii) not being apprised of the difference between the energy meter reading and the maximum demand meter referred to in the sub-clauses under Regn. 28(a). Therefore, this Court is not in a position to reserve the liberty. Any action, the Board proposes to take must be on its own initiative subject to the petitioner resorting to any remedy available if revised demand is issued to him.
14. I must also place on record in this behalf that Annexure-E to the petition speaks of the energy consumed as metered by the meter installed at various points of time finally resulting in 52,000 units per mensem being recorded when proper meter was installed and that accuracy of Annexure-F has never been disputed.
15. With the above observations, the petition is disposed of. Any amount paid by the petitioner on the direction of this Court against the demand impugned is liable to be refunded or adjusted against future dues of the petitioner. A direction to that effect shall issue.
16. In the circumstances of the case, there will be no order as to costs.
Order accordingly.