Surat (Hazira) Kamdar Karmachari Union And Others v. State Of Gujarat And Others
Factual and Procedural Background
Four Special Civil Applications were filed concerning contract labour at Essar Steel Ltd.: Special Civil Application Nos. 7027, 7037 and 7431 of 1997 were filed by the Surat (Hazira) Kamdar Karmachari Union; Special Civil Application No. 3647 of 1997 was filed by the Surat Labour Union. The State of Gujarat and the Commissioner of Labour are Respondent Nos. 1 and 2 in all petitions. Essar Steel Ltd. is the principal employer; certain contractors and government officers are additional respondents.
The petitions principally seek abolition of the contract labour system at Essar Steel Ltd. and a direction to the State to refer the matter to the State Advisory Contract Labour Board under the Contract Labour (Regulation & Abolition) Act, 1970. The petitions concern approximately 1,300 workers in total (breakdown in the opinion).
When the matters were initially filed, the court granted interim protection restraining Essar Steel Ltd. and the contractors from terminating the services of the listed employees. Those interim orders were passed between September and October 1997. Replies were subsequently filed by the principal employer and contractors.
On February 11, 1998, the State of Gujarat made a reference to the Advisory Board regarding 38 trades to determine whether the contract labour system applied by the principal employer in those trades ought to be abolished. The Board’s report was awaited at the time of the opinion.
Legal Issues Presented
- Whether the employees concerned can be terminated during the pendency of the State Government's reference to the Advisory Contract Labour Board.
- Whether interim protection (restraining terminations and certain transfers) previously granted should continue during the interregnum while the Board's reference is pending.
- What interim arrangements and conditions (if any) should govern disciplinary action, transfers, discontinuance of contractors, and preservation of employees' rights (including lien and eventual absorption) during the pendency of the reference.
- What directions (including a time frame) should be issued to the Advisory Board for disposal of the reference.
Arguments of the Parties
Petitioners' Arguments (Union representatives)
- Seeking abolition of the contract labour system and protection for employees during the pendency of the Board reference.
- Relied on Supreme Court authority (Canteen Mazdoor Sabha) to show that principal employer can and should require that successive contractors retain existing employees.
- Argued that interim protection should continue because otherwise employees would be left without protection while the substantive reference is pending; noted the principal employer's affidavit indicating an inclination to insist that contractors retain old employees.
Principal Employer's Arguments (Essar Steel Ltd.)
- Mr. Nanavati submitted that normally the principal employer would retain employees during the interregnum, but there may be legitimate reasons to discontinue particular contractors or particular employees based on complaints.
- Relied on a Division Bench decision (A.P. Dairy Development Co-op. Federation v. K. Ramulu) to suggest that writ jurisdiction should not be used to direct employers to impose conditions on successive contractors.
- Also relied upon The State Of Orissa v. Madan Gopal Rungta to highlight limitations on Art. 226 concerning interim relief as the sole/final remedy.
Contractors' Arguments
- Representatives of contractors argued they should not be restrained from terminating contracts if dissatisfied with their contractual relationship with the principal employer.
- Contractors also contended they should be permitted to transfer employees to other contracts where the employees could be useful, and that their right to take disciplinary action against their employees should be protected.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Air India Statutory Corporation v. United Labour Union, (1997-I-LLJ-1113) (SC) | Abolition of contract labour system ensures the workmen's right to regularisation/absorption as employees of the establishment; High Courts have power under Art. 226 to enforce such rights and give appropriate directions (paras 58 and 59 quoted). | The court relied on this authority to recognise that if the contract system is ultimately abolished the employees will have a right of absorption; it used the judgment to justify continuation of interim protection during the interregnum and to treat interim relief as ancillary to the main relief. |
| Canteen Mazdoor Sabha v. Delhi Administration, 1986 (1) SCALE 181 | Where an erstwhile contractor ceases, the principal employer, when awarding a fresh contract, should incorporate a term that the contractor employ the existing employees and continue to employ them during the contract period. | The petitioners relied on this decision to support the proposition that the principal employer can and should insist that contractors retain old employees; the court considered this as support for continuation of the interim protection. |
| A.P. Dairy Development Co-op. Federation v. K. Ramulu, (1989-II-LLJ-312) (AP-DB) | Held that writ jurisdiction cannot be used to direct employers to impose conditions on successive contractors. | Cited by the principal employer to argue against the grant of interim relief directing conditions on contractors; the court noted this decision but observed the contrary Supreme Court precedent (Air India) warranted extension of the principle in the interest of justice. |
| The State Of Orissa v. Madan Gopal Rungta, AIR 1952 SC 12 | Article 226 cannot be used for giving interim relief as the only and final relief; interim relief is to be ancillary and in aid of the main relief. | The respondents relied on this principle to argue against interim relief being treated as sole relief. The court acknowledged the principle but held the interim protection granted in the present case was ancillary to the main relief (abolition reference) and thus appropriate. |
| Bijli Mazdoor Panchayat v. State of Gujarat, (1996-III-LLJ(Suppl)-277) (Guj) | A similar interim direction was previously granted and the Board was directed to dispose of the reference within eight weeks (as per the single Judge decision cited). | The court noted this precedent but observed that, in practice, the Board took longer (about six months) in that case. Having considered procedural realities, the court directed disposal within six months in the present matters and required stagewise statements to be filed by the Board. |
Court's Reasoning and Analysis
The court framed the principal question as whether the employees could be terminated during the pendency of the State Government's reference to the Advisory Board (the "interregnum"). The court proceeded through the following reasoning steps, as reflected in the opinion:
- Recognised that the State had referred 38 trades to the Advisory Board on February 11, 1998, and that the Board's report was awaited. Given that a reference had been made, the substantive purpose of the petitions (abolition reference) was served to that extent, but the interregnum required attention.
- Relied on the Supreme Court's holding in Air India that abolition of contract labour gives workmen the right to regularisation (absorption) and that High Courts have a constitutional duty under Art. 226 to enforce rights arising from statutory prohibition of contract labour. This made clear the likely end-result if the reference succeeded.
- Considered the competing submissions: the principal employer's and contractors' concerns about legitimate discontinuance of contractors, transfers, and discipline; and the petitioners' concern that without interim protection employees would be vulnerable to termination and loss of livelihood.
- Noted that interim orders had been in operation for about a year without any complaint of breach by the Union, and that Essar Steel's own affidavit indicated a practice or willingness to insist that contractors retain existing employees (while also disclaiming that such a clause would itself create a right to regularisation).
-
Balanced the interests by continuing interim protection but carving out limited and structured exceptions:
- Contractors retain primary control to take disciplinary action for misconduct, subject to subsequent review by appropriate authorities and the eventual outcome of any industrial dispute.
- Transfers are permitted in cases of absolute necessity, but any written transfer order must state that the employee will have a lien under the principal employer and that, if the reference is ultimately decided in favour of the employees, they will have a right to absorption. A copy of such transfer orders must be given to the petitioner-union, the principal employer and filed before the Advisory Board and this Court.
- If a contractor is discontinued, employees under that contract will be continued under the principal employer, albeit possibly under another contractor; if the entire activity is discontinued, employees will continue to have a lien on their position under the principal employer.
- Analysed procedural aspects of the Advisory Board process (nine stages identified in the Board's procedure) and found delay in providing requested particulars by the principal employer. To ensure timely disposal, the court directed the Board to complete the reference within six months from receipt of the writ and to file a statement in this Court upon completion of each stage.
- Applied the principles from cited authorities: while recognising limits on Art. 226 (per The State Of Orissa case) and contrary High Court authority relied upon by respondents, the court gave weight to the Supreme Court's Air India decision and to the Canteen Mazdoor Sabha decision in fashioning interim protections that are ancillary to the main relief.
- Dealt with a specific Civil Application (No. 7863 of 1998) challenging transfer of five workmen: found the respondent's justification absent and disposed of the application, directing those employees to continue under the principal employer unless absolute necessity for transfer arises and then subject to the earlier stated conditions.
Holding and Implications
Holding:
Rule is made absolute to the extent of continuing interim protection (restraining termination and subject to specified conditions) and the petitions are disposed of vis-à-vis the prayer for abolition of contract labour with directions to the Advisory Board to dispose of the reference within six months and to report stagewise to this Court.
Direct consequences and implications for the parties (as expressed in the opinion):
- The interim protection against termination and transfer granted earlier will continue, subject to the modifications set out in the opinion (disciplinary action by contractors allowed subject to later review; transfers only in absolute necessity with written orders preserving a lien and right of absorption; arrangements where contractors are discontinued or activities cease as described).
- The Advisory Board is directed to complete the reference within six months from receipt of the writ and to file statements in this Court on completion of each of the nine procedural stages identified in the opinion; the Union will be permitted to represent employees before the Board.
- The interim protection will continue until completion of the Board's proceedings and for two months thereafter, with the parties required to cooperate and not to seek unnecessary adjournments.
- Civil Application No. 7863 of 1998 (challenging transfers of five workmen) was disposed of; those employees will continue to work under the principal employer unless an absolute necessity for transfer arises, in which case the conditions previously stated must be followed.
- Other submissions and prayers raised in the petitions were left open: petitioners may seek other remedies or file separate petitions; rights in that respect are reserved. There is no order as to costs.
The opinion does not purport to set a generalized new legal precedent beyond the orders and directions issued in these specific matters; the Court fashioned interim relief in light of existing Supreme Court and High Court authorities and the particular facts and procedural posture before it.
1. Rule. Service of Rule is waived for the Respondents in all the matters.
2. Special Civil Application Nos. 7027, 7037 and 7431 of 1997 are filed by the Surat (Hazira) Kamdar Karmachari Union. Special Civil Application No. 3647 of 1997 is filed by the Surat Labour Union. The State of Gujarat and the Commissioner of Labour are Respondent Nos. 1 & 2 in all these petitions. Essar Steel Ltd., is one of the other respondents in these petitions. Apart from these three principal respondents, certain other Government officers are also joined as respondents in these petitions and some of the companies/firms which are engaged as labour contractors by the aforesaid Essar Steel Ltd., are also joined as respondents in these petitions. Prayers in all these petitions principally seek abolition of contract labour system under Essar Steel Ltd., and for that they seek a direction against the State of Gujarat for a reference to the State Advisory Contract Labour Board constituted in that behalf under the provisions of Contract Labour (Regulation & Abolition) Act, 1970. The total number of employees covered under these petitions is approximately as follows :
------------------------------------------------------------------------ Spl. C. A. No. of Workmen ------------------------------------------------------------------------ S.C.A. 7027 of 1997 670 S.C.A. 7037 of 1997 140 S.C.A. 3647 of 1997 450 S.C.A. 7431 of 1997 40 ------------------------------------------------------------------------ 1,300 ------------------------------------------------------------------------
3. Mr. P. C. Master appears for the petitioners in all these petitions. Mr. Hasurkar along with Ms. S. B. Trivedi appears for the State of Gujarat and the Commissioner of Labour. Mr. K. S. Nanavati with Mr. Chudgar appear for Essar Steel Ltd., the principal employer. Mr. R. D. Dave with Mr. Upadhyay appear for Respondent Nos. 5, 6 & 7 in Special Civil Application No. 7027 of 1997. They are the labour contractors concerned in that matter. Mr. K. M. Patel appears for respondent No. 5 in Special Civil Application No. 3647 of 1997. Respondent No. 5 is the concerned contractor in that matter. In Special Civil Application No. 7431 of 1997, Mr. H. C. Rawal appears for respondent No. 6 who is the contractor concerned in that matter.
4. When these matters first came to me, it was apprehended that, because of the efforts taken by the petitioner-Union to organise the employees, the workmen concerned would be terminated from their services. Hence, while issuing notices to the respondents, interim protection was granted to the workmen concerned whose lists are annexed to all these petitions and thereby Essar Steel Ltd., who is the principal employer, and the contractors were restrained from terminating the services of the employees concerned until further orders. Such an order was passed in Special Civil Application No. 7027 of 1997 on October 25, 1997; in Special Civil Application No. 7037 of 1997 on September 25, 1997; in Special Civil Application No. 3647 of 1997 on October 21, 1997 and in Special Civil Application No. 7431 of 1997 on October 9, 1997. Subsequently, replies were filed by the principal employer as well as by the contractors concerned.
5. During the period when the aforesaid matters were pending, the State of Gujarat made a reference to the above-referred Board on February 11, 1998 seeking its advice with respect to 38 trades as to whether the contract labour system employed by the principal employer in these trades deserves to be abolished. In view of this reference, the substantial purpose of filing of the petition had come to be served and the report of the Advisory Board is awaited. The Hon'ble Supreme Court in the case of Air India Statutory Corporation v. United Labour Union, reported in (1997-I-LLJ-1113) (SC) in terms held that, in the event the contract system is abolished, the employees concerned have a right of being absorbed. Thus, in paragraph 58 of the said judgment, the Hon'ble Supreme Court has observed :
"Abolition of contract labour system ensures right to the workmen for regularisation of them as employees in the establishment in which they were hitherto working as contract labour through the contractor. The contractor stands removed from the regulation under the Act and direct relationship of employer and employee is created between the principal employer and workmen."
Thus, the end-result of the efforts taken by the petitioners if they succeed in the reference, is also known. The question, therefore, which now arises is only with respect to the interregnum, namely, whether the employees concerned can be terminated during the pendency of the reference which has been made by the State Government and that is the protection which is sought by the petitioners.
6. As against this submission, Mr. Nanavati, learned Counsel for the principal employer submitted that, during this interregnum, normally, the principal employer would retain all the employees and contractors though there could be some cases for discontinuing the contract of some of the contractors or discontinuing the employees under him due to the complaints by the principal employer vis-a-vis some of the employees working with the contractors. It was submitted by Mr. Dave that there is some dispute between his clients and the principal employer with respect to the terms of the contract and, if his clients are not satisfied, they would like to terminate their relationship with the principal employer and that they should not be restrained from doing so. Mr. Patel submitted that some of the employees could be useful in some other contracts and the contractor should be permitted to transfer their employees in such an eventuality. He also submitted that the right of the contractors to take disciplinary actions against their employees may also have to be protected.
7. As stated above, the orders protecting the workmen concerned have been passed by me way back in September and October, 1997. The Union has not made any grievance that there is any breach of that order. Not only that, but Mr. Master has pointed out that in the affidavit-in-reply filed by the principal employer Essar Steel Ltd., in Special Civil Application No. 7037 of 1997, it is stated in paragraph 33 as follows :
"At the cost of repetition, I state that it is true that with the passage of time and purely with a view to safeguard the interests of workers, many principal employers while renewing the contracts have been insisting that the contractor or the new contractor retains the old employees. In fact, such a condition is incorporated in the contract itself. However, such a clause in the contract which is benevolently inserted in the contract to protect the continuance of the source of livelihood of the contract labour cannot by itself give rise to a right to regularisation in the employment of the principal employer."
In the said affidavit-in-reply in para 33 it has been earlier stated as follows :
"However, respondent No. 4 as a principal employer would certainly insist that the contractor or the new contractor retains the old employees."
Mr. Master has also drawn my attention in this behalf to the judgment of the Hon'ble Supreme Court rendered in the case of Canteen Mazdoor Sabha v. Delhi Administration reported in 1986 (1) SCALE 181 wherein in the event of an erstwhile contractor going out and where the employees under that contractor were likely to lose their jobs, the Hon'ble Supreme Court directed that the principal employer while negotiating or giving a fresh contract for running the canteen, shall incorporate a term in the contract that the contractor shall employ the employees concerned in the canteen and continue to employ them during the contract period. In that view of the matter, Mr. Master submits that the principal employer having continued and having offered to continue the same employees (for which there is a precedent in the aforesaid order of the Supreme Court), there is no reason to imagine difficulties. Besides, the interim orders passed by this Court have been operating for about an year or so by now.
8. Mr. Nanavati made a number of other submissions, including that such an interim protection is not called for. He referred to a judgment of a Division Bench of the Andhra Pradesh High Court reported in (1989-II-LLJ-312) (AP-DB), in the case of A.P. Dairy Development Co-op. Federation v. K. Ramulu, wherein it has been held that the writ Jurisdiction cannot be used to direct employers to impose conditions on successive contractors to engage the employees. As stated above we have seen a contrary precedent of the Supreme Court. No doubt, that was a case concerning contract employees in Delhi High Court canteen but, at the same time, in the light of the judgment of the Supreme Court in the case of Air India Statutory Corporation (supra), it is necessary to extend the principle in that judgment to this intervening period in the interest of justice. Mr. Nanavati also referred to and relied upon a judgment of the Supreme Court in the case of The State Of Orissa v. Madan Gopal Rungta., reported in AIR 1952 SC 12 wherein it has been held that Art. 226 of the Constitution of India cannot be used for the purpose of giving interim relief as the only and final relief. In the present case, the principal relief sought is to direct the State Government to refer the dispute for abolition of contract labour system. The principal relief here is not to seek any injunction or any interim relief during disposal of the matter. In fact, the principal relief is abolition of contract labour system. Therefore, it cannot be said that the principal relief in this matter is only seeking this interim relief. It is, however, material to note that the aforesaid Supreme Court judgment also states :
"An interim relief can be granted only in aid of and as ancillary to the main relief which may be available to the party on final determination of his rights in suit or proceeding."In my view, the interim relief in the nature in which it is granted herein is just and necessary and will have to continue. The observations of the Hon'ble Supreme Court in para 59 of the Air India case (supra) are very apt in this behalf :
"The founding fathers placed no limitation or fetters on the power of the High Court under Art. 226 of the Constitution except self-imposed limitations. The arm of the Court is long enough to reach injustice wherever it is found. The Court as sentinel in the qui vive is to mete out justice in given facts. On finding that either the workmen were engaged in violation of the provisions of the Act or were continued as contract labour, despite prohibition of the contract labour under Section 10(1), the High Court has, by judicial review as the basic structure, constitutional duty to enforce the law by appropriate directions."
The submission of Mr. Master with respect to continuation of the interim protection will have to be accepted. Non-acceptance of it will render the employees without any protection and that would be unjust.
9. At the same time, some arrangements will have to be made during the interregnum, particularly for the situations where a misconduct takes place or where there is an absolute necessity to transfer any employee, the event of a misconduct being committed by any employee as of now, the principal control is that of the contractor and therefore, he cannot be prevented from taking any action against the employee concerned. That will, of course, be subject to whatever orders are passed thereafter by the appropriate authorities in case any industrial dispute is raised and, in the event the action of the employer being vitiated, the employee will be entitled to come back in the position wherein he wanted to be under the principal employer if the contract system is abolished in the meanwhile. Similarly, in the event of absolute necessity to transfer any employee, the contractor cannot be prevented from transferring his employee but, during this interregnum, when the employee is seeking a permanent position under the principal employer, his interests also will have to be protected. It is, therefore, directed that, in such an eventuality, the contractor will incorporate in the order of transfer that the employee will have a lien under the principal employer and in the event the reference is decided finally in favour of the employees, he will have the right of absorption. A written order of transfer containing such a protection will be given to the employee concerned and a copy thereof will be given to the petitioner-union, and the principal employer and will be filed before the Advisory Board as well as in this Court.
10. As stated above, in the event any contractor is discontinued, the employees under that contract will be continued under the principal employer though under another contractor. There is, however, one more eventuality. In the event, the entire activity is not required by the principal employer, then the employees will continue to have a lien on their position under the principal employer. In Civil Application No. 11403 of 1997 in Special Civil Application No. 7431 of 1997, some such workmen were discontinued and the amounts due to them have been deposited in this Court. They will have a liberty to withdraw those amounts. Mr. Master states that the work which has been discontinued has been given to another contractor who has engaged other employees. It will be open to the applicant-Union or the employees to make necessary application and to place it on record before the Board and, in the event the Board is satisfied with respect to that finally, in its report the Board will make necessary recommendations.
11. Then comes the question as to what directions would be appropriate. Mr. Master drew my attention to the judgment of a single Judge of this Court in the case of Bijli Mazdoor Panchayat v. State of Gujarat, reported in (1996-III-LLJ(Suppl)-277) (Guj), wherein similar interim direction was granted and a direction to dispose of the proceeding before the Advisory Board was also issued directing the Board to dispose of the reference within eight weeks. Mr. Master informs that the reference was, however, disposed of after about six months. In that view of the matter, on a query to Mr. Hasurkar, he has informed that there are in all 38 trades which are under consideration for abolition in these matters and there are 46 contractors/sub-contractors. He has also pointed out that, after receiving the reference, the procedure followed by the Board is in all in nine stages. They are as follows :
"1. Notices served to submit the information in respect of contractors, contractors, workers, No. of workers employed by the company, wages paid etc.
2. Statement of claims are to be submitted to the Board by the Union or workers.
3. The management files reply to the statements of claim.
4. Both the parties are heard at length.
5. Committee formed, to collect data and information with regard to the contractors' labourers.
6. In case if there is no necessity of Committee to visit, the report is prepared from the submissions of facts and arguments.
7. Proforma opinions distributed to the members for filling, whether to be abolished (YES), or not to be abolished (NO).
8. Report prepared depending upon above facts and opinions of members and recommendations to be made to Government.
9. Report is to be forwarded to Government, thereafter."
12. A notice has already been issued to the principal employer to inform with respect to the work-force under various contractors. That notice had been served on the principal employer way back in March, 1998 and the employer has not given any particulars in the meanwhile. The employer has sought three months' time and the same is granted and yet those particulars are not given though more than three months are over. In the circumstances, this is not a situation for which employees alone are responsible. They are interested in early decision and for that matter the principal employer as also the contractors are also interested in early disposal. In the circumstances, looking to the facts of this case, it would be proper if the Board is directed to dispose of the reference within six months from the date of receipt of the writ. The Advisory Board will file a statement in this Court at the completion of each stage out of the nine stages mentioned in the proceeding. Mr. Master states that the Union would like to represent the employees before the Board. That will be so permitted. Mr. Hasurkar stares that, when a notice is issued to them, they may also file reply. He further states that after receipt of the final report, normally the appropriate order of abolition is issued within one month and so it will be in the present case. The interim protection against termination and transfer granted herein will, therefore, continue with the modifications mentioned in paras 9 & 10 above till completion of the proceeding before Advisory Board and for a period of two months thereafter. The principal employer, the contractor as well as the Union of employees will co-operate for early disposal of the proceeding and will not unnecessarily adjourn the matter. All the aforesaid petitions are accordingly disposed of vis-a-vis the prayer with respect to abolition of contract labour system with directions as above. With respect to other submissions and prayers, the petitioners may avail of other remedies or may file separate petitions. Their right is reserved.
13. As far as Civil Application No. 7863 of 1998 is concerned, the same is against transfer of five workmen. By the order dated August 31, 1998, my brother PANDIT J., had directed the respondent to justify the transfers. A reply is filed but without any Justifying material. These transfers, therefore, cannot be permitted as of now. This Civil Application is accordingly disposed of. The employees concerned will continue to work under the principal employer unless there is an absolute necessity for transfer in which case the conditions mentioned earlier will be required to be followed.
14. Rule is made absolute in each petition to the aforesaid extent. All the Civil Applications made therein are disposed of accordingly. There will be no order as to costs.