Ms Bhagwati Contractors v. Union Of India & Anr
Structured Summary of the Opinion (Rajiv Sahai Endlaw, J., 22 Dec 2009)
Factual and Procedural Background
This petition was filed under Section 34 of the Arbitration and Conciliation Act, 1996 challenging an arbitral award dated 13 May 2009 which rejected certain claims of the petitioner. The petitioner principally challenged the arbitrator's findings on Claims No. 1, 2, 3, 4 and 7 and sought issuance of notice. The arbitrator had, in the award, addressed matters including damage to work caused by heavy rains and floods, assessment of losses, approval of quarry samples and notices or certificates given by the petitioner. After considering the parties' submissions and the award, the court concluded that no grounds were made out to set aside the award and dismissed the petition. The recorded order also notes IA No. 8484/2009 as "Allowed subject to just exceptions."
Legal Issues Presented
- Whether the arbitrator's rejection of Claim No. 1 (restoration work after heavy rains/floods) — despite findings that (a) heavy rains and flooding occurred, (b) design provided by respondent was faulty and required rectification, and (c) losses had been assessed and sent to higher authorities — amounted to a ground for interference under Section 34 (including public policy) because of an alleged internal inconsistency in the award.
- Whether Claim No. 2 (compensation for extra lead of 75 KM for GSB materials) could be sustained given the arbitrator's finding that petitioner did not submit samples from any nearer quarry and in the absence of any contractual provision for extra payment for distance.
- Whether Claim No. 3 (unproductive expenses) could be set aside given arbitrator's findings that (a) petitioner had not given notice for such claim and (b) petitioner had furnished a certificate and undertaking of having not suffered revenue loss on account of delay.
- Whether Claim No. 4 (payment for an extra item of work allegedly executed) could be set aside because the arbitrator found no written instructions from the respondent and no timely notice of the extra item, despite petitioner relying on a specific letter/exhibit.
- Whether Claim No. 7 (challenged on grounds of being contrary to or ignorant of documents on record) amounted to a ground for interference under Section 34.
- More broadly: whether alleged factual errors or internal inconsistencies in the arbitrator's findings amount to illegitimacy of the arbitral process or contravention of public policy permitting annulment under Section 34.
Arguments of the Parties
Petitioner's Arguments
- Claim No.1: The petitioner argued the arbitrator recorded that heavy rains and flooding (not anticipated by respondent) damaged the work and that the respondent's earlier design was faulty and had to be rectified; the award itself records losses were assessed during a joint inspection on 5 August 2003 and forwarded to higher authorities (letter dated 20 October 2003). Thus, the petitioner contended it was inconsistent for the arbitrator to reject the claim on the ground that the petitioner proceeded without assessing the damages.
- Claim No.1 (additional): The petitioner also pointed to an entry at internal page 7 recording that the Executive Engineer replied that damages of Rs. 16,86,000/- had accrued at site; petitioner relied on this as further inconsistency in the award.
- Claim No.2: The petitioner contended that a letter dated 24 November 2002 (and other documents) notifying the respondent of the long distance of the approved quarry was served on the same person to whom other letters had been submitted and that the arbitrator wrongly treated the letter as not served or not diarized. Those documents, the petitioner argued, had important bearing on the claim for extra lead.
- Claim No.3: The petitioner argued that the arbitrator's finding that no notice was given was contrary to record (the petition lists particulars of a letter alleged to have been given). As to the certificate/undertaking that purportedly waived claims for delay, the petitioner argued that such certificates were given under pressure and that the certificate was given while work continued.
- Claim No.4: The petitioner stated it had raised the claim during the currency of the contract by a letter dated 18 April 2005 (Exhibit-29), contending that the arbitrator overlooked documents on the record.
- Claims generally: The petitioner submitted that the cumulative effect amounted to an injustice warranting interference under Section 34 and that the petitioner had suffered heavy losses due to unprecedented rains.
Respondent's Arguments
The opinion does not contain a detailed account of the respondent's legal arguments in the same structured manner as the petitioner's contentions. The record does, however, reflect certain respondent positions referred to by the court (for example, reliance on condition No.5 of the agreement in relation to Claim No.1 and internal communications concerning assessment of damages), but a full argument list attributable to the respondent is not set out in the provided opinion.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| O.N.G.C. Ltd v. Saw Pipes Ltd, AIR 2003 SC 2629 | Interpreting Section 34 and the phrase "public policy of India" broadly — award may be set aside if contrary to fundamental policy of Indian law, interest of India, justice or morality, or if it is patently illegal; illegality must go to the root; award so unfair as to "shock the conscience" may be set aside. | The court acknowledged Saw Pipes' wider meaning of "public policy" but held that the present facts did not warrant interference on that basis. The court emphasized that in absence of documentary proof before the arbitrator (e.g., assessment of damages), the arbitrator's finding could not be characterized as contrary to law; thus Saw Pipes did not mandate setting aside the award here. |
Court's Reasoning and Analysis
The court proceeded by examining each challenged claim in light of the arbitral findings and the limited scope of Section 34. The court's analysis can be summarized in the following steps:
- On the nature and scope of Section 34: The court explained that Section 34 provides a remedy of annulment which is concerned with the legitimacy of the decision-making process rather than the substantive correctness of the award. It emphasized that Section 34 is not an appeal and that annulment may void an award in whole or in part but does not permit modification as an appeal would.
- On Claim No.1 (damages after rains/floods): The arbitrator had recorded facts favourable to the petitioner (heavy rains, damage, faulty design) and also recorded that "losses were assessed during joint inspection on 5th August, 2003 and sent to higher authorities." Nevertheless, the arbitrator rejected the claim on the ground that the petitioner proceeded without assessing actual damages or getting them assessed by the respondent. The court found that because there was no documentary evidence before the arbitrator recording the assessment, the arbitrator's finding that the petitioner had not got the losses assessed could not be treated as contrary to law. The court emphasized the evidentiary principle that the party making a claim must prove it and that absence of a document before the tribunal cannot be remedied via Section 34.
- On alleged internal inconsistency: The court held that the presence of two findings that might appear at surface-level inconsistent does not automatically render the award contrary to law. Where there is no supporting document before the arbitrator, the court would not characterize the arbitrator's finding as illegitimate or as a ground for annulment.
- On Claim No.2 (extra lead for quarry at 75 KM): The arbitrator found the petitioner had not submitted samples from any nearer quarry and there was no contractual provision entitling extra payment because of distance. The court noted the petitioner did not dispute that no other samples had been submitted and that there was no clause entitling extra payment. In those circumstances, the court found no ground under Section 34 to set aside the arbitrator's conclusion.
- On Claim No.3 (unproductive expenses): The arbitrator rejected this claim because petitioner had not given notice, and because petitioner had furnished certificates/undertakings denying revenue loss and not withdrawn them even after extensions were granted. The court observed that appraisal of evidence is within the arbitrator's domain and that alleged erroneous appraisal does not make the award contrary to law. The petitioner did not show a contemporaneous protest letter; the arbitrator also rejected duress claims as unbelievable. The court found no fault with this reasoning.
- On Claim No.4 (extra item of work): The arbitrator found petitioner was required to take written instructions for extra work and to give notice within seven days; no such written instructions or timely notice were found. Although petitioner pointed to a letter (Exhibit-29) raising the claim during the contract, the court held that merely showing one of several reasons to be contrary to material on record does not render the whole award contrary to public policy or justify annulment under Section 34.
- On Claim No.7 and other challenges: The court treated these similarly — missing or contrary documentary support for the petitioner's contentions did not convert factual appraisal or isolated errors into grounds for annulment.
- On policy and systemic considerations: The court expanded on the legislative purpose behind the 1996 Act — to make arbitration faster and final, to remove scope for courts to treat Section 34 as an appeal, and to limit grounds for interference to issues affecting the legitimacy of the arbitral process. The court warned against using Section 34 to "complete or develop an argument" that a party could and should have made during arbitration.
Holding and Implications
Holding: The court concluded that no grounds were made out to set aside the arbitral award and the petition under Section 34 is dismissed. The court specifically recorded: "No grounds are found to set aside the award. No case for issuance of notice is made out. The petition is dismissed."
Implications:
- Direct effect: The arbitral award dated 13 May 2009 stands; the petitioner's challenges to Claims Nos. 1, 2, 3, 4 and 7 did not meet the narrow standards for annulment under Section 34 and therefore were not allowed.
- On the law of arbitration: The opinion emphasizes and reinforces the principle that Section 34 is confined to examining the legitimacy of the arbitral process rather than substituting the court's view for the tribunal's factual appraisal or legal interpretation. Mere erroneous findings of fact, or isolated inconsistencies in reasoning, do not automatically amount to a ground for annulment.
- On public policy & precedent: While the court acknowledged the broader test articulated in Saw Pipes (O.N.G.C. Ltd v. Saw Pipes Ltd) regarding "public policy", it applied that doctrine narrowly on these facts — holding that the absence of documentary proof before the arbitrator precluded labeling the award as contrary to public policy. The court cautioned against courts reverting to appeal-like review and undermining the finality intended by the amended arbitration statute.
- Procedural note in record: IA No. 8484/2009 is recorded as "Allowed subject to just exceptions" in the order, but the primary petition under Section 34 was dismissed.
This summary is drawn exclusively from the provided opinion. No additional facts, arguments or precedents have been added beyond those appearing in the text.
1. The petition under Section 34 of the Arbitration Act, 1996 has been preferred with respect to the arbitral award dated 13th May, 2009 rejecting certain claims of the petitioner. The counsel for the petitioner for the purposes of issuance of notice has made submissions particularly with respect to the findings of the arbitrator under Claims No. 1, 2, 3, 4 & 7.
2. The claim No. 1 of the petitioner before the arbitrator was on account of work done to restore the work damaged due to heavy rains and flood. The counsel for the petitioner has contended that the arbitrator, in spite of finding (i) that there were heavy rains and flooding not anticipated by the respondent; (ii) that the same did damage the work already carried out by the petitioner; (iii) that in fact the design earlier given by the respondent to the petitioner was faulty and had to be rectified pursuant to the said rains and (iv) while further rejecting the plea of the respondent of the said claim being not payable owing to condition No. 5 of the Agreement, has still rejected the said claim holding that the petitioner proceeded with the work in the damaged portion without assessing the actual damages themselves or getting the damage assessed by the respondents. It is contended that the said finding of the arbitrator is contrary to the finding recorded on internal page 5 of the award (second line) wherein it is recorded "Thereafter losses were assessed during joint inspection on 5th August, 2003 and sent to higher authorities by respondent E.E for taking final decision vide letter dated 20th October, 2003 (C-
16)". The learned counsel for the petitioner has contended that thus the reason given for rejecting the claim is inconsistent with the finding aforesaid of the arbitrator inasmuch as the arbitrator having held that the losses were assessed and sent to higher authorities, the claim could not have been rejected for the reason of the petitioner having proceeded with the work in the damaged portion without assessment of the actual damage.
3. I have put it to the counsel for the petitioner whether there was any document on record where the assessment of the said losses was recorded. The counsel for the petitioner has contended that the same would be contained in the measurement book and/or documents in the possession of the respondent only and as per the practice and procedure followed is always retained with the respondent and the question of the same being with the petitioner does not arise.
4. In my view, the interpretation in O.N.G.C. Ltd Vs Saw Pipes Ltd. AIR 2003 SC 2629 of the provisions in Section 34 of the Act, of interference with the award for the reason of the same being contrary to the public policy, would not admit interference in the aforesaid facts. In the absence of there being any document before the arbitrator, where the assessment of damages was recorded, it cannot be said that the finding of the arbitrator of the petitioner having not got the losses assessed is contrary to law. It is the party making the claim which has to prove the claim and even if the document containing the assessment of damages was with the department, law provides for the procedure to be followed for production thereof and in the absence of there being any document before the arbitrator of assessment of damages, the ordinary principle of the party failing to prove its case doing so at its own peril has to be followed and no fault can be found with the approach of the arbitrator in this regard. It can also not be said that the two findings are inconsistent with each other or for that reason a ground for interference under Section 34 of the Act is made out. A Section 34 proceeding, which in essence is the remedy of annulment, cannot be used by one party to complete or develop an argument which it could have and should have made during the arbitral proceedings or help that party retrospectively to fill gaps in its arguments.
5. The counsel for the petitioner has pointed out that in fact the award records that the petitioner had given its own assessment of damages and has also pointed out to para 3 on internal page 7 of the award where it is recorded that the Executive Engineer of the respondent had replied to the Superintending Engineer of the respondent vide letter dated 17th October, 2003 that damages to the tune of Rs. 16,86,000/- had accrued at site and has contended that owing to this also, reasoning given by the arbitrator is inconsistent with the findings elsewhere in the award. The counsel for the petitioner has contended that the interference under Section 34 is permissible when the courts find injustice to have been committed and in the present case, it stands established that substantial work done by the petitioner was damaged owing to the unprecedented rains and the petitioner has suffered heavy losses on this account.
6. In my view the finding aforesaid at internal page 7 of the award cannot also be said to be inconsistent with the reasoning given. Moreover in my view, mere wrong finding of fact by the arbitrator or even a wrong interpretation of the various documents is non-interfereable under Section 34 of the Act and if such interference is done by the court, the same will set at naught the whole purpose of amendment to the law.
7. Arbitration is intended to be a faster and less expensive alternative to the courts. If this is one's motivation and expectation, then the finality of the arbitral award is very important. The remedy provided in Section 34 against an award is in no sense an appeal. The legislative intent in Section 34 was to make the result of the annulment procedure prescribed therein potentially different from that in an appeal. In appeal, the decision under review not only may be confirmed, but may also be modified. In annulment, on the other hand the decision under review only may be invalidated in whole or in part or be left to stand if the plea for annulment is rejected. Annulment operates to negate a decision, in whole or in part, thereby depriving the portion negated of legal force and returning the parties, as to that portion, to their original litigating positions. Annulment can void, while appeal can modify. Section 34 is found to provide for annulment only on the grounds affecting legitimacy of the process of decision as distinct from substantive correctness of the contents of the decision. A remedy of appeal focuses upon both legitimacy of the process of decision and the substantive correctness of the decision. Annulment, in the case of arbitration focuses not on the correctness of decision but rather more narrowly considers whether, regardless of errors in application of law or determination of facts, the decision resulted from a legitimate process.
8. In the case of arbitration, the parties through their agreement create an entirely different situation because regardless of how complex or simple a dispute resolution mechanism they create, they almost always agree that the resultant award will be final and binding upon them. In other words, regardless of whether there are errors of application of law or ascertainment of fact, the parties agree that the award will be regarded as substantively correct. Yet, although the content of the award is thus final, parties may still challenge the legitimacy of the decision- making process leading to the award. In essence, parties are always free to argue that they are not bound by a given "award" because what was labeled an award is the result of an illegitimate process of decision.
9. This is the core of the notion of annulment in arbitration. In a sense, annulment is all that doctrinally survives the parties' agreement to regard the award as final and binding. Given the agreement of the parties, annulment requires a challenge to the legitimacy of the process of decision, rather than the substantive correctness of the award.
10. Joseph Raz in his paper "The Politics of the Rule of Law" has opined that the function of the rule of law is to facilitate the integration of a particular piece of legislation with the underlying doctrines of the legal system; the authority of the courts to harness legislation to legal doctrine arises neither from their superior wisdom nor from any superior law of which they are the custodians; it arises out of the need to bring legislation in line with doctrine. The courts ensure coherence of purpose of law, ensuring that its different parts do not fight each other. The learned author has further observed that a law which is incoherent in purpose serves none of its inconsistent purposes very well. Purposes conflict if due to contingencies of life serving one will in some cases retard the other. The second basis for the authority of the courts to integrate legislation with doctrine is the need to mix the fruits of long established traditions with the urgencies of short term exigencies. In ensuring the coherence of law, the courts are expected to ensure the effectiveness of the democratic rule. In giving weight to the preservation of long established doctrines i.e., the traditions, they protect the long term interest of the people from being swamped by the short term. I have taken the liberty to quote from the aforesaid paper since the courts are being repeatedly called upon to adjudicate on the various provisions of the re-enacted arbitration law. From the various pronouncements in the last about 12 years since re-enactment, it appears that the danger of interpreting the new Act in a manner doing away with the whole object/purpose of re-enactment is imminent. The courts continue to be inundated till date, in spite of repeal of the old Act 12 years ago, with cases thereunder also, particularly of challenge to the arbitral award. Provisions of the old and the new Act relating to inference with the arbitral award are vastly different. However, when the courts in the same day are wresting with a matter concerning arbitral award under the old Act and with that under the new Act, the chances of culling out the huge difference between the two are minimal. It is not to be forgotten that the courts deal with and rule on disputes where monies and properties of real persons are at stake. The courts do not decide in abstract. Thus, when in one case the courts interfere with the award for the reason of the same not rendering to the litigant what the courts would have granted to him, the courts find it difficult in the very next case, though under the new Act to apply different parameters.
11. Arbitration under the 1940 Act could not achieve the savings in time and money for which it is renowned and had merely become a first step in lengthy litigation. It was to get over the said malady that the law was sought to be overhauled. While under the old Act, the award was unenforceable till made rule of the court and for which it had to pass various tests as laid down therein and general power/authority was vested in the court to modify the award, all this was removed in the new Act. The new Act not only made the award executable as a decree after the time for preferring objection with respect thereto had expired and without requiring it to be necessarily made rule of the court but also did away with condonation of delay in filing the said objections. The reason/purpose being expediency. The grounds on which the objections could be filed are also such which if made out, the only consequence thereof could be setting aside of the award. It is for this reason that under new Act there is no power to the court to modify the award or to remit the award etc. as under the old Act. A perusal of the various grounds enunciated in Section 34 will show that the same are procedural in nature i.e., concerning legitimacy of the process of decision. While doing so, the ground of the award being in conflict with Public Policy of India was also incorporated. However the juxtaposition of Section 34(2)(ii) shows that the reference to Public Policy was also in relation to fraud or corruption in the making of the award. The new Act was being understood so till the Supreme Court in Saw Pipes Ltd (supra) held that the phrase Public Policy of India is required to be given wider meaning and if the award on the face of it is patently in violation of statutory provisions, it cannot be said to be in public interest and such award/judgment/decision is likely to adversely affect the administration of justice. In para 37 of the judgment it was held that award could be set aside if it is contrary to fundamental policy of Indian Law or the interest of India or justice or morality or if it is patently illegal. A rider was however put that illegality must go to the root of the matter and if the illegality is of trivial nature it cannot be held that the award is against the public policy. Yet another test laid down is of the award being so unfair and unreasonable that it shakes the conscience of the court.
12. The courts have thereafter been inundated with challenges to the award. The objections to the award are drafted like appeals to the courts; grounds are urged to show each and every finding of the arbitrator to be either contrary to the record or to the law and thus pleaded to be against the Public Policy of India. As aforesaid, the courts are vested with a difficult task of simultaneously dealing with such objections under two diverse provisions and which has led to the courts in some instances dealing with awards under the new Act on the parameters under the old Act.
13. The result is that the goal of re-enactment has been missed.
14. The re-enactment was not only to achieve savings in time and prevent arbitration from merely becoming the first step in lengthy litigation but also in consensus with the international treaties and commitments of this country thereto. Since the enactment of the 1940 Act, the international barriers had disappeared and the volume of international trade had grown phenomenally. The new Act was modeled on the model law of international commercial arbitration of the United Nations Commission on International Trade. It was enacted to make it more responsive to contemporary requirements. The process of economic liberalization had brought huge foreign investment in India. Such foreign investment was hesitant, owing to there being no effective mode of settlement of domestic and international disputes. It was with such lofty ideals and with a view to attract foreign investment that the re-enactment was done. If the courts are to, notwithstanding such re-enactment, deal with the arbitration matters as under the old Act it would be a breach of the commitment made under the treaties on international trade.
15. As far as the submission of the counsel for the petitioner in the present case of injustice having been done, the same is a subjective perception and the courts on their own notion of justice and injustice cannot undo what was sought to be done by the legislature by amending the arbitration law. All that can be said is that no case of the judicial conscience of this court having been shocked exists.
16. The counsel for the petitioner with respect to Claim No. 2 on account of extra lead of 75 Km of GSB materials not provided in agreement has contended that the finding of the arbitrator with respect to non-service of letter dated 24th November, 2002 on the respondent is contrary to the record. It is stated that the said letter was delivered to the same person to whom other letters on record had been submitted and the logic given by the arbitrator of the letter having not been diarized is also erroneous. It is contended that the said letter has important bearing on the matter. It is further contended that other documents forming the basis of the said claim and on the record of the arbitral tribunal have also not been considered or discussed by the arbitrator.
17. The arbitrator has while rejecting the said claim reasoned that the petitioner had not submitted for approval the samples from any other quarry than the quarry situated 75 KM away from the site of work and also failed to establish if other authorized quarry was available at lesser distance and hence no compensation was payable to the petitioner for the sample approved of a quarry at a long distance of 75 KM.
18. It is not disputed by the counsel for the petitioner that the samples from no other quarry had been submitted. The counsel for the petitioner has however contended that it was the respondent who had approved the quarry and the petitioner had vide letter dated 24th November, 2002 and other documents ignored by the arbitrator notified the respondent that owing to the quarry being at a long distance claims would be preferred.
19. I have enquired from the counsel for the petitioner whether there was any provision/clause in the agreement that if the quarry is beyond a particular distance, extra payment will be made for the same. The answer is in the negative. In the absence of any such provision and further the petitioner having failed to submit the samples of any other nearby quarry (which are argued to be within a distance of about 1 or 2 KM), again, no ground for interference under Section 34 of the Act is made out.
20. The Claim No.3 for Rs. 4,80,000/- on account of unproductive expenses is related to Claim No. 1 aforesaid. The said claim has been rejected by the arbitrator for the reason of the petitioner having not given any notice to the respondent for claiming such damages and for the reason of, claimant having furnished, certificate to the respondent of having not suffered any revenue loss on account of late completion of work and an undertaking not to claim any damages for delay. The objection of the learned counsel for the petitioner is that the first finding of not giving any notice is contrary to the record. In the petition in ground F-1 particulars of the letter stated to have been given are stated. With respect to the second reasoning it is contended that if the said certificate had not been given by the petitioner as demanded by the respondent, the respondent would have levied other penalties on the petitioner as the work was continuing.
21. The appraisal of evidence is within the domain of the arbitrator and a wrong appraisal of evidence by the arbitrator would not amount to the award being contrary to law. As far as the reason for giving certificate and undertaking is concerned, I have enquired whether any protest letter was given by the petitioner immediately after the certificate and/or undertaking had been obtained. It is stated that no such protest letter was given as the works were continuing. The arbitrator has also held that the plea of the petitioner of the certificates having been given under duress is not believable inasmuch as the petitioner had at no time withdrawn the said certificate, even after grant of extension of time.
22. Again no fault can be found with the said reasoning and the objection in this regard, is also not found tenable.
23. Claim No.4 was for extra item of work executed. The arbitrator rejected the claim holding that the petitioner was supposed to take written instructions for the same from the respondents and no such instructions were obtained and the claim was not raised during the currency of work. The challenge before this court is that the said finding is in ignorance of documents on record; the petitioner had raised the claim during currency of contract vide letter dated 18th April, 2005 proved as Exhibit-29. The question which arises is whether the award can be said to be against the public policy for this reason. It is significant that there is no challenge to the finding of arbitrator of no written instruction from respondents having been obtained or to notice of extra item being required to be given within seven days of execution of extra work. Merely because one of the several reasons given is shown to be contrary to the material on record, it will not make the award contrary to public policy or be a reason for annulment of the award.
24. Lastly, with respect to the Claim No. 7, the objection is that the same is again in ignorance of documents on record and/or contrary to documents. For the reasons given above, the same does not fall within the domain of Section 34 of the Act.
No grounds are found to set aside the award. No case for issuance of notice is made out. The petition is dismissed.
IA No. 8484/2009 Allowed subject to just exceptions.
RAJIV SAHAI ENDLAW, J December 22, 2009 rb