National Highways Authority Of India v. M/S Uem-Essar (Jv)

Delhi High Court
Oct 30, 2009
Important Paras
Please sign up to view Important Paras.
Smart Summary (Beta)

Structured Summary of the Opinion

Factual and Procedural Background

This is an oral judgment delivered by Hon'ble Mr. Justice Valmiki J. Mehta on October 30, 2009, disposing of appeals filed under Section 37 of the Arbitration and Conciliation Act, 1996. The appeals challenge an Arbitral Tribunal order dated 14.8.2009 which dismissed the appellant's application under Section 17 of the Act. The Section 17 application, filed before the Arbitral Tribunal on 29.5.2009, sought interim injunctive relief restraining the respondent (and its agents) from removing certain equipment, materials and temporary works from sites and from creating hindrance in the appellant's use of that equipment until cancellation of the contract by the petitioner.

The appellant based its claim on clause 63.1 of the contract (reproduced in the opinion), which allows the Employer, after giving notice in specified events of contractor default, to enter the site, complete the works and use or sell the contractor's equipment, temporary works and materials and apply proceeds towards sums due. The appellant contended that clause 63.1 gave it a right to use and even sell the machinery in question.

Key dates recorded in the opinion: notice under clause 63.1 was issued on 11.12.2006; a suit was filed before a Civil Judge in Karnataka in March 2008 which was referred to arbitration under Section 8 of the Arbitration and Conciliation Act, 1996; the interim application before the Arbitral Tribunal was filed on 29.5.2009; the Tribunal dismissed that application on 14.8.2009; the appeals to this Court were disposed on 30.10.2009.

Legal Issues Presented

  1. Whether the appellant was entitled to interim relief under Section 17 of the Arbitration and Conciliation Act, 1996 restraining the respondent from taking over or disposing of machinery in light of clause 63.1 of the contract.
  2. Whether the Arbitral Tribunal erred in dismissing the appellant's Section 17 application on the ground that deciding it would effectively decide the merits of the dispute.
  3. Whether, in the factual matrix of this case, an interim appropriation or sale of the respondent's machinery by the appellant would amount to execution of an anticipated future money decree/award by interim measure (i.e., interim execution), which is not permitted by law.
  4. Whether the appellant's application contained the necessary averments required for grant of attachment before judgment under Order 38 Rule 5 CPC (i.e., that the respondent is disposing of property to defraud creditors or is evading the forum).

Arguments of the Parties

Appellant's Arguments

  • The appellant relied on clause 63.1 of the contract and contended that, by virtue of that clause, the machinery in question became the appellant's property in circumstances contemplated by the clause; accordingly, the appellant was entitled not only to use but also to sell the machinery to satisfy sums due to it.
  • The appellant sought interim injunctive relief restraining the respondent from removing equipment and from interfering with the appellant's use of equipment, materials and temporary works, pending adjudication of rights.

The opinion does not set out detailed arguments advanced by the respondent in opposition to the application.

Table of Precedents Cited

No precedents were cited in the provided opinion.

Court's Reasoning and Analysis

The Court's analysis proceeds by reference to the Arbitral Tribunal's reasoning and the factual matrix documented in the record. The principal points of the Court's reasoning, stated in the opinion, are as follows.

  1. The Arbitral Tribunal refused to hear the interim application because deciding it would require construing clause 63.1 and thereby effectively decide contentious issues which go to the merits of the underlying dispute; as final arguments in the arbitration were ongoing, the Tribunal considered such interim proceedings to be an inappropriate mechanism to decide those merits.
  2. The Tribunal had repeatedly (including in an earlier order dated 19.2.2009) urged the parties to concentrate on final arguments rather than filing successive interim applications which consume time. The Tribunal's reiteration of that approach was quoted by the Court and accepted as a reasonable exercise of discretion.
  3. The Court emphasized delay and the stage of proceedings: the cancellation notice was issued on 11.12.2006, the suit was filed in March 2008 and referred to arbitration, and the interim application was filed on 29.5.2009. Considerable time had elapsed and final arguments were then pending before the Tribunal. In that context, an interim application for appropriation of machinery was not justified.
  4. The Court observed the substantial monetary stakes involved (the contract value was approximately Rs. 250 crores, as stated by counsel), and noted there were no counter-claims by the appellant in the present arbitration. The Court recognized that if the appellant were allowed to appropriate or sell the respondent's machinery as an interim measure, that would operate as an execution of an anticipated future monetary award — effectively an interim execution — which the Court held is not known to law.
  5. The Court further noted that the appellant had not provided copies of the respondent's claims in the arbitration, leaving the Court unable to state the exact amount claimed by the respondent. The absence of such particulars contributed to the conclusion that interim appropriation would be inappropriate.
  6. The Court examined whether the appellant's application could be treated as an application under Order 38 Rule 5 CPC for attachment before judgment. The opinion records that the necessary averments required by Order 38 Rule 5 CPC (that the respondent is disposing of property to defraud creditors or is evading jurisdiction) were absent. Therefore, even if the application were treated as one under Order 38 Rule 5 CPC, it would still be liable to fail.
  7. On these combined factual and legal grounds — the Tribunal's rational reluctance to decide merits by interim application, the stage of proceedings and delay, the risk of interim execution of expected monetary claims, and the absence of required averments for attachment before judgment — the Court found no reason to interfere with the Arbitral Tribunal's order under Section 37.

Holding and Implications

Holding: The Court affirmed the Arbitral Tribunal's decision and refused to interfere with the dismissal of the appellant's Section 17 application. The appeals were dismissed. The core ruling is emphasized below.

APPEALS DISMISSED

Direct consequences and orders imposed by the Court:

  • The appeals were dismissed with costs quantified at Rs. 50,000/- in each appeal.
  • Costs are to be deposited with the Delhi High Court Legal Services Authority within two weeks from the date of the judgment; failing which the costs will carry interest at 18% per annum.
  • The opinion records that the respondent had not appeared before the Court.

Implications: The decision leaves intact the Arbitral Tribunal's discretion to refuse interim relief where adjudication of such relief would effectively determine merits of the dispute while final arguments are pending. The Court also indicated that interim appropriation or sale of another party's property, in the absence of required averments under Order 38 Rule 5 CPC and where such appropriation would amount to interim execution of an anticipated money award, is not permissible. The opinion contains no pronouncement that establishes a new precedent beyond applying those principles to the case facts.

Disposition: The appeals were disposed of by Hon'ble Mr. Justice Valmiki J. Mehta on October 30, 2009.

Show all summary ...

JUDGMENT (ORAL)

1. These appeals have been filed under Section 37 of the Arbitration and Conciliation Act,1996 against the order dated 14.8.2009 passed by the Arbitral Tribunal dismissing the appellant's application under Section 17 of the Act. The application was filed by the appellant seeking to restrain the respondent from taking over the machinery which belonged to the respondent and which was used by the respondent in performance of its work till the cancellation of the contract by the petitioner. The exact prayer clauses of the application filed before the Arbitration Tribunal are as under:-

“a. Permanent injunction restraining the defendants, their respective officials, agents, servants or any other person or persons claiming on behalf of the defendants from filing the equipments, material

HON'BLE MR. JUSTICE VALMIKI J. MEHTA

and temporary works from the sites as prescribed in the schedule.

b. Permanent injunction restraining the defendants, their respective officials, agents, servants or any other person or persons claiming on behalf of the defendants from creating any hindrance in usage of the equipments, material and temporary work as prescribed in the schedule, for execution of balance work by NHAI, its officials, agents, contractors or any other person or persons appointed by NHAI.”

2. The appellant claims his right in terms of clause 63.1 of the Contract and which is reproduced below :

“Remedies

Default of Contractor 63.1 “If the Contractor is deemed

by law unable to pay his debts as they fall due, or enters into voluntary or involuntary bankruptcy, liquidation or dissolution (other than a voluntary liquidation for the purposes of amalgamation or reconstruction with the prior permission of the Employer), or becomes insolvent, or makes an arrangement with, or assignment in favour of, his creditors or agrees to carry out the Contract under a committee of inspection of his creditors, or if a receiver administrator, trustee or liquidator is appointed over any substantial part of his assets, or if, under any law or regulation relating to reorganization, arrangement or readjustment of debts, proceedings are commenced against the Contractor or resolutions passed in connection with dissolution or liquidation or if any steps are taken to enforce any security interest over a substantial part of the assets of the Contractor, or if any act is done or event occurs with respect to the contractor of his assets which, under any applicable law has a substantially

similar effect to any of the foregoing acts or events, or if the Contractor has contravened Sub Clause 3.1, or has an execution levied on his goods, or if the Engineer certifies to the Employer, with a copy of the Contractor, that, in his opinion, the Contractor:

(a) has repudiated the Contract,

(b) without reasonable excuse has failed

(i) to commence the Works 28 days of the Date of Commencement in accordance with Sub-Clause 41.1, or

(ii) to proceed with the Works, or any Section thereof, within 28 days after receiving notice pursuant to Sub-Clause 46.1

(c) has failed to comply with a notice issued pursuant to Sub-Clause 37.4 or instruction issued pursuant to Sub-Clause 39.1 within 28 days after having received it.

(d) despite previous warning from the Engineer, in writing, is otherwise persistently or flagrantly neglecting to comply with any of his obligation under the Contract, or

(e) has contravened Sub-Clause 4.1

(f) has substantially suspended the Works for a period of fourteen days without authority from the Engineer and has failed to proceed with the Works within 28 days of receipt of a Notice from the Engineer; or

(g) has failed to supply sufficient or suitable constructional plant temporary works, key personnel, labour materials as proposed in the programme for the execution of

Work furnished under Sub-Clause

14.1; or

(h) has failed to comply with the requirements applicable to Joint Ventures as per the Contract.

then the Employer may, after giving fourteen days notice to the Contractor, enter upon the Site and expel the Contractor therefrom without thereby voiding the Contract, or releasing the Contractor from any

of his obligations or liabilities under the Contract, or affecting the rights and powers conferred on the Employer or the Engineer by the Contract, and may himself complete the Works or may employ any other contractor to compete the Works. The Employer or such other contractor may use for such completion so much of the Contractor's Equipment, Plant, Temporary Works and materials which have been deemed to be reserved exclusively for the execution

of the Works, under the provisions of the Contract, as he or they may think proper, and the Employer may, at any time, sell any of the said Contractor's Equipment, temporary Works and unused Plant and materials and apply the proceeds of sale in or towards the satisfactory of any sums due or which may become due to him from the Contractor under the Contract.”

(Emphasis added)

3. On the basis of the aforesaid clause, it is contended by the learned senior counsel for the appellant that the machinery in question becomes of the appellant and which it is in fact not only entitled to use but also sell at any point of time.

4. The impugned order which has been passed by the Tribunal, (and which could have been worded better) in fact says that by deciding on the application the arbitrators will effectively be deciding on the merits of the controversy, by interpreting the vexed clause 63.1 of the contract and for proceedings which are presently pending before it and final arguments are going on. Since the issue would indeed be a highly contentious one amounting to deciding highly disputed issues by an interim application, the arbitrators in effect have said that the pronouncement in one way or the other would be to effectively pronounce on the merits of the case and which are pending before the Arbitral Tribunal and which the Arbitral Tribunal would seek/prefer not to do. I do not think that this is such an unreasonable finding for which this Court need interfere under Section 37.

5. At this stage, it would be appropriate to refer to the second last para of the impugned order which reads as under:-

“We reiterate what we had stated in the concluding part of our order dated 19.2.2009 while dismissing the application filed by the claimants under Section 23(3) of the Act and once again advise the parties to concentrate on merits of the case rather than filing one application after another, which consumes a lot of time of the arbitral tribunal as well as the parties. The parties would be well advised to conclude their arguments on the merits in an expeditious and speedy manner.”

(Emphasis added)

It is quite clear that the arbitrators have emphasized to the parties that instead of filing interim applications, it would be better if the parties

concentrate on their arguments and complete the final arguments which are presently going on.

6. Considering that an interim application is for an urgent relief which is asked for as necessary to preserve the final relief is prayed in particular/specific type of cases, I may note that the notice under Clause

63.1 which has been issued in this case for cancellation of the contract is way back on 11.12.2006 The suit before the Civil Judge in Karnataka was filed in March, 2008 and which suit was on the application of the respondent herein under Section 8 of the Arbitration and Conciliation Act, 1996 was referred to arbitration because the contract in question had an arbitration clause. Consequently, this application which has been decided by the impugned order was filed before the Arbitrators on 29.5.2009 Obviously, therefore, considerable time has elapsed since the cancellation of the contract, issuing of the cancellation notice, filing of the suit in Karnataka and any issue of interim relief, therefore, would not arise more so because the final arguments are going on before the Arbitral Tribunal and the Tribunal has expressed its annoyance that the parties are concentrating more on filing of interim applications and not on the final arguments.

7. Though the appellant has failed to answer the query of this court it is quite clear that claims of the respondent in the present case, would obviously be in the regime of crores of rupees in as much as the original contract is of Rs. 250 crores approximately. In these arbitration proceedings there are no claims of the appellant, though I am informed that it has claims for which other arbitration proceedings are going on. On query from the

court, the counsel for the appellant states that he does not have and has not filed the copies of the claims of the respondent no. 1. The court is, therefore, handicapped in not being able to state the exact amount of the claims of the respondent no. 1. I may, however, note that the total value of the contract in question was more than Rs 250 crores as per the statement of the counsel for the appellant. I have already noted that there are no counter-claims of the appellant in the present arbitration proceedings. In a case where there are monetary claims of the appellant, the effect of taking over the machinery in terms of the agreed contractual clause in such a case is in fact a relief not only of attachment before judgment but the same would amount to execution of a future decree for money claims which the present appellant may have (of course it is not that it is bound to succeed in getting a money decree/award) and for which it seeks to appropriate the value of the machinery towards such claims in terms of the last para of clause 63.1 reproduced above. I may again note that the appellant claims to have not only the right to use the machinery but it claims under clause 63.1 the right to sell plant and machinery towards satisfaction of sums which it claims would be held to be due to it in other arbitration proceedings. Obviously, if therefore, the plant and machinery is sold, the present appellant would have to account for the monies which are received by it with respect to the sale of the plant and machinery since the machinery does not belong to the appellant and in fact which belongs to the respondent. Even if, there were in a case final monetary claims, any interim appropriation would effectively amount to execution of the final money claims through an interim measure amounting to interim execution of an expected money decree/award and

which is not known to law. Further and more so, because the validity of a claim itself under the subject contractual clause in question is very much in issue and has yet to be pronounced and adjudicated upon by the arbitrators. Therefore, prima facie, I find at this stage, in view of the facts of the present case and the law as applicable that appellant is not entitled to appropriate the machinery, prayed for at the present stage. At the cost of repetition, it may be said that this would in fact amount to appropriation towards final money claims by an interim order when there are vexed issues and strenuous contest before the arbitrators.

8. To the observations already made above I would seek to add herein the aspect that a reference to the appeal filed before this court as also the application for interim relief which was filed before the Tribunal shows that there are no required and necessary averments therein which are called for in an application under Order 38 Rule 5 of the CPC viz of the respondent/claimant is seeking to dispose of its properties to defraud its creditors or is running away from the jurisdiction of the arbitration Tribunal. Therefore, even if, the subject application of the appellant be treated as under Order 38 Rule 5 CPC for attachment of the machinery admittedly belonging to the respondent, the same is/was liable to fail as even the necessary averments for claiming the drastic relief of attachment before judgment are not found in the application which has been dismissed by the Arbitral Tribunal.

9. Therefore, at the time of dismissal of the appeals, I may reiterate what the Tribunal has observed that the parties are well advised to concentrate

on final arguments and not on the filing of interim applications at the time of final arguments. With these observations, these appeals are dismissed with costs quantified at Rs. 50,000/- in each of the appeals, to be deposited with the Delhi High Court Legal Services Authority since the respondent has not appeared. The costs be deposited within two weeks from today and failing which it will carry further interest of 18% per annum. The appeals are accordingly disposed of.

OCTOBER 30, 2009 VALMIKI J. MEHTA, J ib