Triveni Engineering Industries Ltd. v. Delhi Jal Board Another

Delhi High Court
Dec 18, 2008
Smart Summary (Beta)

Concise Analytical Summary of the Opinion in WP(C) No.7012/2008

Factual and Procedural Background

The petition challenges actions, orders and communications of Respondent No.1 (Delhi Jal Board, "DJB") rejecting the Petitioner's bid for the "Tender for the 1 MGDWTP for CWG" (the design, construction, supply, installation, testing & commissioning, 1 year Defect Liability Period and 3 years Operation & Maintenance of a 1 MGD Water Treatment Plant for the Commonwealth Games Village near Akshardham Temple). The rejection was notified to the Petitioner by a communication dated 28 August 2008 (the opinion also mentions an impugned communication dated 16 September 2008).

Procedurally, the Petitioner (a company incorporated under the Companies Act, 1956) submitted its bid on 31 July 2008 in response to NIT No.4 (2008-09), which set minimum eligibility criteria including project experience requirements under Clause 2.1.5.1 B.1(i)(a). Three bids were received; one bidder was disqualified on technical grounds leaving two (the Petitioner and Respondent No.2). After technical evaluation and a clarification meeting held on 18 August 2008, DJB by letter dated 28 August 2008 rejected the Petitioner's bid for not meeting eligibility criteria and proceeded to open the remaining bidder's price bid.

The Petitioner filed the present writ petition challenging the rejection. The court confined its inquiry to whether the Petitioner fulfilled the experience requirement under Clause 2.1.5.1 B.1(i)(a). By an order dated 18 December 2008 (signed by Mukul Mudgal and Manmohan, JJ.), the court dismissed the writ petition along with pending applications and disposed of the matter.

Legal Issues Presented

  1. Whether the Petitioner met the minimum eligibility criteria for project experience set out in Clause 2.1.5.1 B.1(i)(a) of the tender (specifically: at least one water treatment plant of minimum capacity 4.5 MLD, producing potable water, having operated for at least one year after DLP as on 30.05.2008, executed in the last seven years, preferably started after 30.05.1998).
  2. Whether DJB's rejection of the Petitioner's technical bid (communicated 28 August 2008) was justified, including whether DJB had given adequate reasons and observed principles of natural justice and fair play.
  3. Whether the Petitioner's contention that DJB improperly relaxed eligibility criteria in favour of the other bidder or acted mala fide had merit.
  4. Whether the Petitioner's price advantage (if any) required DJB to consider or open its price bid despite alleged non-fulfillment of eligibility criteria.

Arguments of the Parties

Petitioner's Arguments

  • The Petitioner asserted that it fulfilled all tender eligibility criteria, had submitted all required annexures and performance certificates, and had satisfactorily clarified queries raised by DJB during the technical evaluation.
  • The Petitioner contended that DJB failed to give any reasoned explanation as to why the Petitioner did not meet the eligibility criteria despite requests and reminders.
  • The Petitioner argued that Respondent No.2 (successful bidder) did not conform to eligibility criteria but was allowed to proceed by relaxing or diluting the conditions, and that rejecting the Petitioner's bid diminished competition and harmed public interest by reducing competitiveness of price bids.
  • The Petitioner relied on certificates and a bank guarantee (including NTPC certificates and a bank guarantee dated 20 February 2004) to show completion and performance of relevant projects (Simhadri/NTPC project, Agra project, etc.).

Respondent's (Delhi Jal Board's) Arguments

  • DJB maintained that the Petitioner's submissions failed to satisfy specific eligibility components: financial submissions were for combined business activities rather than separate construction turnover; experience certificates did not demonstrate completion within the required seven-year window or did not evidence the full scope of work required (design, construction, supply, installation, testing & commissioning).
  • With respect to the Agra 144 MLD project, DJB pointed out the plant was put into operation and handed over in 1997, which fell outside the seven-year period prescribed by the tender.
  • The NTPC (Simhadri) certificate (PG Test of 24 March 2003) indicated pending supply of main equipment and mandatory spares, and thus did not establish successful completion of the full scope required by Clause 2.1.5.1 B.1(i)(a).
  • DJB contended that eligibility conditions were imperative and could not be relaxed; DJB afforded the Petitioner an opportunity to clarify shortcomings but the petitioner failed to satisfy the mandatory experience requirements even after the second chance.
  • DJB argued price comparison was irrelevant because the Petitioner's price bid could only be considered after crossing the eligibility threshold.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Laxmi Sales Corpn. Vs Bolangir Trading Co. & Ors., 2005 (3) SCC 157 Preconditions or qualifications for tenders as stipulated by tender documents are mandatory in character. The court relied on this principle to treat the tender's eligibility criteria (Clause 2.1.5.1 B.1(i)(a)) as imperative. Applying that rule, the court concluded that because the Petitioner failed to meet the mandatory experience requirement, DJB's rejection of the Petitioner's bid was justified.

Court's Reasoning and Analysis

The court limited its examination to whether the Petitioner met the specific experience requirement under Clause 2.1.5.1 B.1(i)(a) of the tender documents and proceeded through the following analytical steps:

  1. Identification of the controlling eligibility clause: the court quoted Clause 2.1.5.1 B.1(i)(a), which required that the bidder should have experience of EPC/Design-Build/Design-Build-Operate contracts including design, construction, supply, installation, testing & commissioning successfully of at least one water treatment plant of minimum capacity 4.5 MLD producing potable water, and that such plant should have been operating for at least one year after DLP as on 30.05.2008; additionally, the relevant works should have been executed in the last seven years, preferably started after 30.05.1998.
  2. Examination of the Petitioner's claimed projects against this clause:
    • Agra 144 MLD project: the UP Jal Nigam certificate showed the plant was put in operation and handed over on 24 May 1997. The court found this fell outside the seven-year window prescribed by the tender, so it did not satisfy the requirement.
    • Lime Softening Plant certificate by L&T: the certificate did not establish that the Petitioner had designed, installed, tested and commissioned the entire plant as required by the tender's experience criterion.
    • Simhadri (NTPC) documents: the PG Test certificate dated 24 March 2003 and the follow-up certificate dated 12 April 2003 did not demonstrate successful completion of the entire water treatment plant in the terms required. Notably, the PG Test noted pending points at site such as supply of main equipment and mandatory spares; the later certificate was issued on request for experience credentials but, according to the court, did not rebut the absence of demonstrable completion of the full scope (design to commissioning) required by Clause 2.1.5.1 B.1(i)(a).
    • Bank guarantee dated 20 February 2004: even if taken into account, it did not establish that the Petitioner had performed all obligations to satisfy the clause's mandatory conditions.
  3. Procedural fairness and opportunity to rectify: the court accepted that DJB, in public interest and in line with natural justice, provided the Petitioner an opportunity to clarify shortcomings because only two bidders remained in the process. Despite that second chance, the Petitioner failed to cure the deficiencies with respect to the mandatory experience requirement.
  4. Application of legal principle: invoking Laxmi Sales Corp. (2005), the court treated the tender preconditions as mandatory and concluded that, since the Petitioner did not meet those preconditions, DJB was justified in rejecting the Petitioner's technical bid.
  5. On complaints regarding the successful bidder and price considerations: the court observed that the Sub-Technical Committee found the successful bidder possessed requisite experience on the relevant components (e.g., Lime Softening Plant). The court also emphasized that price comparisons are immaterial until eligibility conditions are satisfied; hence the Petitioner's argument about a lower price was not legally consequential.

Holding and Implications

Holding: DISMISSED — the court dismissed the writ petition and all pending applications. The opinion states that the Petitioner's bid was rightly rejected by Respondent No.1 for failure to meet the mandatory minimum eligibility criteria under Clause 2.1.5.1 B.1(i)(a) of the tender documents.

Implications:

  • The direct effect is that the Petitioner's challenge to the rejection of its technical bid was unsuccessful and the writ petition was disposed of against the Petitioner.
  • The court applied existing precedent (Laxmi Sales Corpn.) to reaffirm that tender preconditions are mandatory; the judgment does not purport to create a new legal principle beyond applying settled law to the facts. The opinion does not state any broader change to tender law—its practical consequence is confined to upholding the DJB's rejection on the ground of non-fulfillment of the specified eligibility criterion and confirming that eligibility must be satisfied prior to any consideration of price.

Judgment dated: 18 December 2008. Judges: (Mukul Mudgal) J. and (Manmohan) J.

Show all summary ...

1. The present petition arises against the impugned actions, orders and communications of Respondent no.1 including the impugned communications dated 28th August 2008 and 16th September 2008 wherein the Petitioners bid in respect of the tender for the design, construction, supply, installation, testing & commissioning successfully, 1 year Defect Liability Period (DLP) and 3 years Operation and Maintenance (O&M) of 1 Million Gallon per Day (MGD) Water Treatment Plant for Common Wealth Games Village near Akshardham Temple (hereinafter referred to as the

"Tender for the 1 MGDWTP for CWG"
) was rejected.

2. The brief facts of the case which led to the present writ petition as per the petitioner are as follows:-

(a) The Petitioner is a company incorporated under the provisions of the Companies Act, 1956 having its office at 8th Floor, Express Trade Towers 15- 16, Sector 16-A, NOIDA.

(b) The Respondent no.1 Delhi Jal Board issued a brief Press Notification

WP(C) No.7012/2008 page 2 of 24

inviting bid applications from interested bidders for the

"design, construction, supply, installation, testing and commissioning successfully, 1 year Defect Liability Period and 3 year operation and maintenance of 1 Million Gallon per Day Water Treatment Plant for Common Wealth Games Village near Akshardham Temple."
The last date for receipt of the "Bid Document" was 16th July 2008 which was later extended by Respondent No.1 upto 31st July 2008.

(c) As per the detailed Notification Inviting Tender (NIT) being NIT No.4 (2008-09) the work was to be carried out on a design, build and operate (DBO) basis as per conceptual scheme, design parameters, drawing and specifications of tender documents/DJB to be all complete. It was further clarified that the completion period (12+3 months trial run=15 months) indicated was for Civil and E&M construction complete.

(d) The NIT also provided for minimum eligibility criteria in respect of financial parameters and project experience to be fulfilled by the bidders. It was further mentioned in the NIT that complete eligibility criteria, other terms and conditions/ requirements for qualification and bid conditions were WP(C) No.7012/2008 page 3 of 24 mentioned in the

"Bid Document"
.

(e) On 31st July 2008, the Petitioner submitted its bid along with all annexures, including the performance certificates to fulfill the conditions of clause 2.1.5.1 of the Tender Documents.

(f) In response to the NIT, three bids were submitted by three parties, including the Petitioner. The technical proposals were opened in presence of the representatives of the bidders. The bid of one of the bidders was disqualified on technical grounds leaving only two bidders, the Petitioner and Respondent no.2, for opening of the final price bid.

(g) Subsequent to the opening of the technical proposal, on 18th August 2008, the Respondent no.1 called the Petitioner for a meeting. The Petitioner attended the meeting at the office of the Respondent no.1 wherein the Respondent no.1 sought certain clarifications.

3. One of the clarifications sought by Respondent No. 1 was "experience details not clear" and it required the Petitioner to cite specific project references against each of the experience requirement in the said clause WP(C) No.7012/2008 page 4 of 24 B.1(i)(a) to (e) of the Tender Documents. Another query raised by Respondent No. 1 was "details of the project, Water pre-treatment plant for Simhadri Thermal Power Plant not given in certificate" and it required the Petitioner to obtain the required certificate from the client giving all required details like capacity per day treated, water quality produced, start and commissioning date, etc. for testing eligibility of the project.

4. The Petitioner by the letter dated 18.08.2008, provided the clarifications to the said queries raised by Respondent No. 1. By the letter dated 28 th August 2008, sent by fax to the Petitioner, the Respondent no.1 rejected the bid of the Petitioner on the grounds of not meeting the eligibility criteria. The Respondent no.1 opened the price bid of the sole remaining bidder, the Respondent no.2 M/s VA Tech Wabag Ltd. The said letter dated 28th August 2008 rejecting the petitioner's bid reads as follows:-

WP(C) No.7012/2008 page 5 of 24

"Sub.:- Design, Construction, supply Installation, testing and commissioning successfully, 1 year DLP and 3 year O&M of MGD WTP for Commonwealth Games near Akshardham Temple on DBO basis. (NIT No. 4(2008-09)). Sir, With reference to your bid for the above mentioned project, received on 31.07.2008 & subsequent clarification dated 18.08.2008. It is to intimate that your bid has been rejected on the grounds of not meeting the eligibility criteria. This is for your kind information please."

5. The Petitioner was informed that the bid of the Petitioner was rejected as it did not fulfill the minimum experience criteria as mentioned under Clause 2.1.5.1 B.1 (i) (a) of the Tender Documents including the time stipulation as to the work having been executed in the last 7 years and that the work should preferably have started after 30.05.1998. It was further informed to the Petitioner that with respect to the said Clause 2.1.5.1 B.1 (i) (a) the experience of Petitioner for 'Water Treatment Plant of capacity 14.4 MLD commissioned in Sikandra, Agra under World Bank Unit, UP Jal Nigam' was considered and its experience for the Simhadri Project was not considered.

6. The learned Counsel for the Petitioner contended as follows:-

WP(C) No.7012/2008 page 6 of 24

(a) Despite repeated requests and reminders of the Petitioner, no reason,

whatsoever, has been given by Respondent No. 1 as to why and how the Petitioner did not meet the eligibility criteria. The Petitioner not only fulfills all the eligibility criteria of the Tender Documents but after opening of the technical bid it has also satisfactorily clarified all the queries raised by Respondent No. 1 and submitted all relevant documents to the satisfaction of Respondent No. 1, and as such the petitioner was fully qualified to be considered for opening of final price bid.

(b) The Petitioner, immediately after the rejection of its technical bid, made representations to Respondent No. 1 that the bid of the Petitioner was fully in conformity with the eligibility criteria laid down for the work. The petitioner further pointed out that the bid of the sole remaining bidder i.e. Respondent No.2 was not conforming to the eligibility criteria even though Respondent No. 2 was considered as a qualified party by relaxing/diluting the eligibility criteria. The petitioner also pointed out that opening the price bid with only one bidder would neither be in the interest of Respondent No. 1 nor in the WP(C) No.7012/2008 page 7 of 24 larger public interest.

(c) To have a competitive price, the Respondent No. 1 ought to have ensured enough number of bids at the time of opening of price bid. By deliberately rejecting the bid of the Petitioner, Respondent No. 1 had not only acted detrimental to its interest but also in a manner which was detrimental to the larger public interest.

(d) The Petitioner had submitted the bid in accordance with the tender pre- condition alongwith supporting documents, as also further clarifications along with more supporting documents, including the Experience Certificate of the Petitioner regarding its Simhadri Project.

(e) Respondent No. 1 ought to have concluded that the bid of the Petitioner fully satisfied all the minimum eligibility criteria and ought not to have rejected the bid of the Petitioner, ignoring the documents on record.

7. The learned Counsel for the Respondent contended as follows:-

(a) On 18.08.2008, the Petitioner responded to the tender notice and

submitted his bid. The Petitioner in support of the financial parameter

WP(C) No.7012/2008 page 8 of 24

submitted the audited balance sheet for the last five years of the company alongwith net worth certificate of the Chartered Accountant. However, the certificates submitted by the Petitioner were in respect of the combined business activities of the Petitioner instead of the required annual turn over of the company in respect of the construction works undertaken by it.

(b) Furthermore, the Petitioner in respect of the work experience claimed to have executed 144 MLD WD at Agra on behalf of UP Jal Nigam and UP Jal Nigam issued a certificate in favour of the Petitioner indicating that the plant in question was put in operation in the year 1997 and was handed over to the UP Jal Nigam on 24.05.1997. The work experience as stipulated in the bid was not satisfied by the Petitioner as it was beyond the period of seven years as the minimum eligibility criteria clearly laid down that work should have been executed in the last seven years and preferably work should have started after 30.05.1998.

(c) Regarding the work experience in respect of the Waste/Water Lime Softening Plant of 2 MLD the Petitioner submitted a certificate issued in its WP(C) No.7012/2008 page 9 of 24 favour by L&T. This certificate did not say as to whether Petitioner had designed, installed, tested and commissioned successfully the entire lime Softening Plant as per the requirement of the experience criteria.

(d) In light of the above, the Petitioner's application was liable to be rejected for having failed to satisfy the minimum eligibility criteria. However, the Delhi Jal Board offered another chance to the Petitioner to clarify in respect to the shortcomings pointed out above. In the meeting held on 18.8.2008 in the office of the Chief Engineer, the Petitioner was informed of the above shortcomings.

(e) The Petitioner attempted to clarify by way of a letter submitted on 18.08.2008. On the question of separate turnover on construction activities, the Petitioner's letter remained silent. For work experience, Petitioner requested the respondent to consider the project at Shimadri executed for NTPC instead of UP Jal Nigam. In respect of the Lime Softening Plant, Petitioner desired that instead of L&T certificate submitted earlier, certificate issued by Chhatishgarh Steel & Power Ltd. may be considered. The WP(C) No.7012/2008 page 10 of 24 clarification note submitted indeed had the certificate submitted by NTPC, Shimadri and Chhatisgarh Steel and Power Ltd.

(f) The Delhi Jal Board agreed to consider the clarification submitted by the Petitioner. But the Petitioner again failed to satisfy the tender conditions in respect of work experience of Water Treatment Plant of 4.5 MLD and also the certificate issued by the NTPC did not mention that the Petitioner had designed, constructed, supplied, installed, tested and commissioned the Water Treatment Plant in question. The certificate merely established that Petitioner had carried out only PG test in respect of the Water Treatment Plant at Shamidri. In fact the certificate stated as follows:-

"However, this is subject to the completion of the

pending points at site like supply of main

equipment, mandatory spares etc. and to liquidate

all the pending issues at the earliest."

(g) It is evident even from the certificate submitted by the Petitioner that Petitioner was not the one who executed the entire work as per the stipulation of the bid and worse, even the main equipment and mandatory spares were yet WP(C) No.7012/2008 page 11 of 24 to be supplied by the Petitioner. Eligibility conditions were to be adhered to since they were imperative in character. It was not envisaged that they were to be relaxed under any circumstances. Delhi Jal Board keeping in view the magnitude of the contract intended to have a contractor experienced enough who had the occasion of handling similar work by a party having the requisite experience. Since, the Petitioner failed to satisfy the eligibility condition on experience, it was decided that the bid of the Petitioner deserved rejection. It was then the Petitioner and the other bidder namely M/s. Sinomen Envirox JV (who was also rejected) were accordingly informed of the decision rejecting their bids.

(h) That inspite of opportunities granted to the Petitioner, the Petitioner failed to fulfill the minimum eligibility criteria in respect of the work experience. The requirement of the experience criteria was that bidder should have had at least the experience of designing, construction, supply, installation, testing and commissioning of at least one Treatment Plant (Water) executed in the last seven years.

WP(C) No.7012/2008 page 12 of 24

(i) The contention that the price bid of the Petitioner was lower than the

Respondent No. 2 was of no consequence since the price bid of the Petitioner was to be considered only after the eligibility bar was crossed and not otherwise. The alleged difference of the price between the Petitioner and the Respondent No. 2 was, therefore, of no consequence.

8. During the course of the proceeding we had asked the counsel for the Respondent to produce the Govt. file of Delhi Jal Board relating to the tender of 1 MGD WTP at Common Wealth Games Village near Akshardam Temple. The noting in the file clearly specifies that M/s. Triveni Engineering and Industries Ltd. satisfies the eligibility conditions (b) to (e) of clause 2.1.5.1 B.1

(i). However, the firm does not have relevant experience against (a) of clause 2.1.5.1 B.1 (i) and hence, cannot be considered eligible. In view of the above, we are confining our findings as to whether the petitioner fulfilled the minimum experience criteria as mentioned under Clause 2.1.5.1 B.1 (i) (a) of the tender documents or not.

9. The minimum eligibility criteria in respect of project experience to be WP(C) No.7012/2008 page 13 of 24 fulfilled by the applicants, as indicated in Clause 2.1.5.1 B.1 (i) (a) of the tender documents which is the center of controversy in the present petition reads as under :-

"i) The bidder should have experience of Engineering procurement construction (EPC)/ Design- Build/Design-Build-Operate-contact including design, construction, supply, installation, testing & commissioning successfully of:

(a) At least one water treatment plant of minimum capacity 4.5 MLD, producing water for potable use. The water treatment plant should have been operating for at least one year after DLP as on 30.05.2008.

For pts. (a) to (e) above, only experience in the Employer's country will be considered for eligibility. All works as required in points (a) to (e) above should have been executed in the last 7 years. The work should preferably have started after 30.05.1998." (emphasis supplied)

10. The main grievance of the Petitioner is that the Respondent No. 1 failed to give sufficient reasons as to why and how the Petitioner did not meet the eligibility criteria of the tender as it had satisfactorily clarified all the queries raised by Respondent No.1 and submitted all the relevant documents in WP(C) No.7012/2008 page 14 of 24 consonance with the tender conditions. In our view, this contention of the Petitioner cannot be sustained as the facts and circumstances of the case clearly show that the petitioner has failed to fulfill the mandatory requirement in respect of project experience as laid down in the tender conditions to participate further in the bid process.

11. The essential pre condition of the minimum eligibility requirement to participate in the tender was with regard to the nature of the project work experience. The Petitioner claimed to have executed 144 MLD WTP at Agra on behalf of UP Jal Nigam who issued a certificate in favour of the petitioner whereby it was indicated that the plant in question was put in operation in the year 1997 and was handed over to the UP Jal Nigam on 24th May, 1997. The work experience stipulated in the bid clearly stipulated that the bidder was required to have the experience of Engineering Procurement Construction (EPC)/design/design build/design build operate contract including design, construction, supply, installation, testing of the water treatment project executed in the last seven years and wherein work should have preferably WP(C) No.7012/2008 page 15 of 24 started after 30th May, 1998. Thus, the petitioner did not satisfy this eligibility condition in view of the fact that UP Jal Nigam project was beyond the prescribed period of seven years.

12. The Petitioner in respect of the Waste / Water Lime Softening Plant submitted a certificate issued in its favour by Larsen & Toubro (L&T). This certificate did not say that the Petitioner had designed, installed, tested and commissioned successfully the entire lime Softening Plant as per the requirement of the experience criteria.

13. The Petitioner at the initial stage of the bid failed to satisfy the minimum essential eligibility criteria. However, in public interest and in view of the fact that only two bidders were taking part in the bid process, the Respondent No.1 in consonance with the principles of natural justice and fair play offered another chance to the Petitioner to rectify the shortcomings evident in the documents in support of his experience related to work projects. The petitioner attempted to clarify by way of letter dated 19th August, 2008. For work experience in respect of the Water Treatment Plant of 4.5 MLD capacity, WP(C) No.7012/2008 page 16 of 24 the petitioner requested to consider the project at Simhadri executed for NTPC instead of UP Jal Nigam.

14. The petitioner submitted the certificate dated 24th March, 2003 issued by NTPC which is reproduced herein below:-

"Sub.: P.G. Test of Water-treatment Plant-Reg.

Ref.:- (i) LOA No. CS-3250-137-9-SU-LOA

3721 dated 29.01.1999

(ii) LOA No. CS-3250-137-9-ER-LOA

3722 dated 29.01.1999

Dear Sir, This is to inform you that the P.G.

Test conducted for the above package and

subsequent submission of the documents it is found

that there is no short fall in equipment performance

as compared to the guaranteed parameters.

However, this is subject to the completion of the

pending points at site like supply of main

equipment, mandatory spares etc. and to liquidate

all the pending issues at the earliest."

(emphasis supplied)

The above certificate submitted by the petitioner dated 24th March, 2003,

issued by the NTPC in respect of the work experience of the Water Treatment

Plant of 4.5 MLD capacity, in our view, does not establish that the Petitioner

had successfully completed the said Water Treatment Plant as the supply of

WP(C) No.7012/2008 page 17 of 24

main equipment and mandatory spares still remained to be done.

15. The petitioner in support of the certificate of work experience issued by NTPC on 24th March, 2003 submitted another certificate dated 12th April, 2003 which is reproduced as under:-

"This is to confirm that the PG Test Certificate

issued by us on 24.03.2003 is for the complete

Water Treatment Plant as per the following LOAs

awarded to M/s. Triveni Engineering & Industries

Ltd.

i) LOA No. CS-3520-137-9-SU-LOA

3721 Dtd. 29.01.1999.

ii) LOA No. CS-3520-137-9-ER-LOA

3722 Dtd. 29.01.1999

This job involves the following:-

• Main Water Treatment System

(Capacity - 800 M³/Hr.)

• Potable Water Treatment System

(Capacity - 600 M³/Hr.)

• Chlorination System

(Capacity - 5 Kg./Hr.)

This certificate is issued on the request of

M/s. Triveni Engineering & Industries Ltd. for their

experience credentials required for their ongoing

bids' negotiations."

However, the certificate dated 12 April, 2003 does not in any way

WP(C) No.7012/2008 page 18 of 24

prove that the petitioner has fulfilled the mandatory requirement of project

work experience as stipulated in the tender documents. This is also evident

from the fact that as rightly pointed by the Respondent without any effective

rebuttal that even upon further clarification that the certificate submitted by the

petitioner on 12th April, 2003, as issued by the NTPC, Simhadri merely stated

that the petitioner did not satisfy fully the mandatory requirements of the

tender process which were the designing, constructing, supplying, installing,

testing and commissioning the Water Treatment Plant. It is thus evident that

the Petitioner had neither designed the entire plant nor had fully supplied even

the full machinery which does not in any way fulfill the minimum essential

criteria to participate in the next stage of the tender process as stipulated in

Clause 2.1.5.1 B.1 (i) (a) of the tender documents.

16. The petitioner in support of the above certificate issued by the NTPC, Shimadri enclosed a bank guarantee dated 20th February 2004 to strengthen his argument that he had discharged his liability fully with regard to the Water WP(C) No.7012/2008 page 19 of 24 Treatment Plant and the contract was completed fully by the Petitioner. This document was disputed as never having been received by the Respondent. However, even if taking the said document into consideration we do not think that this document establishes that in any way that the petitioner had designed, constructed, supplied, tested, installed and commissioned the Water Treatment Plant as per the essential conditions laid down in the tender documents.

17. The Hon'ble Supreme Court in the case of Laxmi Sales Corpn. Vs Bolangir Trading Co. & Ors. 2005(3)SCC 157 held that preconditions or qualifications for tenders as stipulated by the tender documents are mandatory in character. After a perusal of the facts and circumstances of the case, we are of the view that the Petitioner failed to fulfill the pre-conditions in the tender documents. The eligibility condition of work experience which was a mandatory condition of the tender bid being imperative in character was not fulfilled by the Petitioner initially and even after being given a second chance by the Respondent No. 1. Thus, the bid of the Petitioner was rightly rejected WP(C) No.7012/2008 page 20 of 24 by the Respondent No. 1.

18. The contention of the Petitioner that it was in the interest of DJB and the larger public interest that the prices should be competitive which can only happen if there is enough competition in the final price bid. The Respondent No. 1 in public interest and in consonance with the principles of natural justice had rightly given a second chance to the Petitioner to fulfill the mandatory conditions stipulated in the tender documents. The Petitioner again failed to fulfill the essential eligibility criteria with regard to the work experience leading to the rejection of the bid by Respondent No.1 and the liability of such failure on part of the Petitioner cannot be incurred by the Respondent No.1. The Respondent No.1 had also rejected the bid of the other bidder namely M/s. Sinomen Envirox JV alongwith the Petitioner. In this view of the matter, the conduct of the Respondent No.1 cannot be termed as malafide in any manner.

WP(C) No.7012/2008 page 21 of 24

19. The petitioner through his representation dated 1st September 2008 has also contended that the bid of the sole remaining bidder i.e. respondent No. 2 was not in conformity with the eligibility criteria even though the respondent No. 2 was considered as qualified party by relaxing the eligibility criteria. However, the matter received attention of the Sub-Technical Committee consisting of four Chief Engineers on 3rd September 2008. In our view, it was rightly noticed by the appropriate committee that the complaint of the petitioner on the lack of experience of the respondent No. 2 was meritless since the said respondent had the requisite experience on Lime Softening Plant and therefore, we do not deem it necessary to go into such findings. Further, the plea that the price bid of the petitioner was lower than the respondent No. 2 is of no consequence since the price bid of the petitioner was never opened as it needs to be considered only after the minimum eligibility conditions as laid down in the tender documents are fulfilled and not otherwise. We also do not deem it necessary to go into the plea of the petitioner that the price of the successful bidder should be brought at par with the price of the petitioner, as in WP(C) No.7012/2008 page 22 of 24 our view this plea of the petitioner does not merit any attention with regard to the facts and circumstances of the present case which indicate that the petitioner's bid was not responsive.

20. The petitioner, therefore, in our view failed to fulfill the mandatory minimum eligibility criteria in respect of the work experience which required that the bidder should have had the experience of designing, construction, supply, installation, testing and commissioning of at least one Water Treatment Plant. Consequently, in view of the above findings, we dismiss the writ petition alongwith all pending applications. The writ petition is disposed of accordingly.

(MUKUL MUDGAL) JUDGE (MANMOHAN) JUDGE th 18 December, 2008 WP(C) No.7012/2008 page 23 of 24 dr/s/rkb WP(C) No.7012/2008 page 24 of 24