Pt. Munshi Ram & Associates (P) Ltd. v. Delhi Development Authority .
Factual and Procedural Background
The petitioner contractor was awarded a contract for the construction of 590 dwelling units under the SFS Scheme of the Delhi Development Authority (DDA) in Sector C Pocket V, Vasant Kunj, New Delhi, pursuant to Agreement No. 7.EE/SWD-6/87-88. Disputes arose between the parties regarding the execution of the work under this agreement. In accordance with Clause 25 of the General Conditions of Contract, the Engineer Member of the DDA appointed Mr. C. Rama Rao as the Sole Arbitrator by letter dated 13.4.1993 to adjudicate the disputes. The Sole Arbitrator made and published an award dated 30.9.1995, which the respondent DDA challenged by filing objections. This opinion addresses the objections to the arbitral award under Sections 30 and 33 of the Arbitration Act, 1940.
Legal Issues Presented
- Whether the Arbitrator exceeded jurisdiction or committed legal misconduct by awarding amounts beyond the methodology prescribed under Clause 10(CC) of the contract for escalation of costs during the extended period.
- Whether the award relating to Claim No. 7 concerning the final bill, particularly the item for cutting and straightening of reinforcement steel bars, is sustainable in light of precedent and contractual terms.
- Whether the rate of interest awarded by the Arbitrator at 15% per annum should be modified.
Arguments of the Parties
Respondent's Arguments
- The Court does not have jurisdiction under Sections 30 and 33 of the Arbitration Act, 1940 to reappraise facts and evidence as an appellate forum.
- The Arbitrator should have applied the escalation formula strictly as prescribed under Clause 10(CC) of the contract and not awarded amounts beyond it.
- Reliance on Division Bench judgments (Delhi Development Authority v. K.C Goyal & Co. and Delhi Development Authority v. U. Kashyap) and Supreme Court precedent (Associated Engineering Company v. Govt. of A.P.) to argue that deviation from agreed contractual formula amounts to legal misconduct.
- Objection to the award of payment for cutting and straightening of reinforcement steel bars under Claim No. 7, citing precedent that such items are not payable unless notice was given during the contract period.
- Submission that the Arbitrator’s award lacks sufficient disclosure of reasoning and is contrary to contract terms.
Petitioner's Arguments
- Claim No. 1 relates to extra work done during an extended contract period caused by delays attributable to the respondent, including late site clearance, delayed supply of materials, and other hindrances.
- The petitioner put the respondent on notice that work beyond the stipulated period would be done only at increased rates, supported by correspondence dated 22.6.1989.
- The extension of time was unilateral and without petitioner’s consent, and Clause 10(CC) is not automatically applicable without a valid extension under Clause 5 of the contract.
- Reliance on Division Bench judgments (Delhi Development Authority v. Hindustan Construction Corporation Engineers & Contractors, Delhi Development Authority v. S.S Jetley, and M.L Mahajan v. Delhi Development Authority) to argue that claims for escalation and damages due to prolongation can be awarded beyond Clause 10(CC) under certain conditions.
- Regarding Claim No. 7, the petitioner contended that the work was done as claimed and the dispute was factual, supported by measurements and evidence considered by the Arbitrator.
- Petitioner argued that the rate of interest should be maintained as awarded by the Arbitrator.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Sudarsan Trading Company v. Government of Kerala, (1989) 2 SCC 38 | Arbitral awards should not be interfered with unless perverse; appellate reappraisal of facts not permitted. | Supported the principle that the Court cannot interfere merely because it might have taken a different view if the Arbitrator’s conclusion is plausible. |
| Delhi Development Authority v. K.C Goyal & Co., 2001 II AD (Delhi) 116 | Once a contract provides a formula for escalation, Arbitrator must apply it; deviation amounts to legal misconduct. | Applied to hold that the Arbitrator erred in awarding escalation beyond Clause 10(CC) formula. |
| Associated Engineering Company v. Govt. of A.P., 1991 (2) Arb LR 180 | Parties bound by agreed contractual formula for claims; Arbitrator cannot adopt alternate methodology. | Reinforced the binding nature of contractual formula and guided the Court's decision to set aside excess award. |
| Delhi Development Authority v. U. Kashyap, 1998 VII AD (Delhi) 300 | Similar principle as K.C Goyal & Co. regarding adherence to contractually agreed formulas. | Used to support the position that Clause 10(CC) must be followed for escalation claims. |
| Delhi Development Authority v. Hindustan Construction Corporation Engineers & Contractors, 2002 (1) Arb. LR 98 | Clause 10(CC) applies only where contract is validly extended; absent valid extension, other principles (Section 70 Contract Act) apply. | Distinguished on facts; in present case contract was extended and Clause 10(CC) applicable. |
| Delhi Development Authority v. S.S Jetley, 2001 (1) Arb. LR 289 | Claims for damages under Sections 73 and 74 of Contract Act can be upheld for prolongation beyond Clause 10(CC) claims. | Referenced to distinguish claims for prolongation damages from escalation claims under Clause 10(CC). |
| M.L Mahajan v. Delhi Development Authority, 2002 (3) Arb. LR 376 | Contract without Clause 10(CC) but with Clause 10(C); different escalation provisions. | Noted as different contractual context; no direct application to present case. |
| Ch. Ramalinga Reddy v. Superintending Engineer, 1999 (Suppl.) Arb. LR 440 | Award contrary to contract terms or plainly barred can be set aside. | Supported the Court’s power to set aside award parts that exceed contract terms. |
| Jajodia (Overseas) (P) Ltd. v. Industrial Development Corporation of Orissa Ltd., 1993 (1) Arb. LR 334 | Legal misconduct by Arbitrator in exceeding contract terms. | Referred to justify setting aside excess award. |
| Wee Aar Constructive Builders v. Delhi Development Authority, 2001 IV AD (Delhi) 65 | Work not payable if contrary to contract terms; cutting and straightening of steel bars not payable without notice. | Applied to reject award for cutting and straightening of reinforcement steel bars where no notice was given. |
| Narain Dass R. Israni v. Delhi Development Authority, 2005 VIII AD (Delhi) 556 | Definition of reinforcement is illustrative; certain items not payable unless notice given. | Used to hold that award for cutting and straightening steel bars cannot be sustained without notice. |
| Bedi Construction Co. v. DDA, CS (OS) No. 2822/1994, decided 10.11.2005 | Once Clause 10(CC) formula is agreed, no other methodology should be adopted for escalation claims. | Supported the conclusion that the Arbitrator erred in awarding escalation beyond Clause 10(CC). |
Court's Reasoning and Analysis
The Court recognized the limited scope of judicial interference under Sections 30 and 33 of the Arbitration Act, 1940, emphasizing that the Court cannot act as an appellate authority to reappraise facts or evidence unless the Arbitrator’s conclusion is perverse. The Court analyzed the claims in dispute, focusing particularly on Claim No. 1 (escalation for extra work during extended contract period), Claim No. 7 (final bill including cutting and straightening of reinforcement steel bars), and the rate of interest awarded.
Regarding Claim No. 1, the Court noted that Clause 10(CC) of the contract prescribed a specific formula for calculating escalation during an extended contract period. The Court found that the Arbitrator had awarded an amount exceeding that formula without valid grounds, amounting to legal misconduct. It distinguished the present case from prior judgments where Clause 10(CC) was not applicable due to lack of valid extension. Here, the contract was validly extended and executed with payments made under Clause 10(CC). Therefore, the Court held that escalation claims must be confined to the formula in Clause 10(CC), setting aside the excess award.
For Claim No. 7, the Court examined the factual dispute over whether certain extra items of work were executed. While the Arbitrator found that most claimed works were done and awarded amounts accordingly, the Court held that the award related to cutting and straightening of reinforcement steel bars (Item No. 7) could not be sustained. Precedents establish that such work is not payable unless the contractor had given notice during the contract period, which was not shown here. Hence, this part of the award was set aside.
On the rate of interest, the Court concluded that the Arbitrator’s award of 15% per annum was excessive. The Court modified the interest rate to 12% per annum for the awarded claims during the pre-suit and pendente lite period, to be simple interest and not compounded. For future interest post-decree, the Court fixed a rate of 9% simple interest, with a provision exempting the respondent from future interest if payment is made within 60 days.
Holding and Implications
The Court issued the following rulings:
- The award in respect of Claim No. 1 (escalation for extra work) is set aside to the extent it exceeds the contractual formula under Clause 10(CC).
- The award for Item No. 7 under Claim No. 7 concerning cutting and straightening of reinforcement steel bars is set aside.
- The interest awarded is modified to 12% simple interest per annum for the awarded claims during the relevant periods, and 9% simple interest per annum for future interest, with conditions for exemption if paid timely.
- The award of the Sole Arbitrator dated 30.9.1995 is made rule of the Court with these modifications.
The direct effect of this decision is to limit the petitioner’s recovery strictly to amounts calculated under the agreed contractual escalation formula and to exclude certain disputed items not supported by contractual notice requirements. No broader precedent is set beyond reaffirming established principles regarding the binding nature of contract terms in arbitration awards and the limited scope of judicial interference.
IA No. 1919/1996 (Under Sections 30 and 33 of the Arbitration Act, 1940)
Sanjay Kishan Kaul, J.—The petitioner contractor was awarded the work of construction of 590 dwelling units under the SFS Scheme of DDA in Sector C Pocket V, Vasant Kunj, New Delhi in pursuance to Agreement No. 7.EE/SWD-6/87-88. Some disputes arose between the parties in respect of execution of the work under the agreement and in terms of Clause 25 of the General Conditions of Contract, the Engineer Member of the DDA vide letter dated 13.4.1993 appointed Mr. C. Rama Rao as the Sole Arbitrator to adjudicate upon the disputes between the parties. The Sole Arbitrator entered upon reference and made and published the award dated 30.9.1995 The respondent DDA aggrieved by the same has filed these objections.
2. Learned Counsel for the respondent initially sought to argue the various grounds in the objections but could not seriously dispute the proposition that it is not within the jurisdiction of this Court under Sections 30 and 33 of the Arbitration Act, 1940 (hereinafter referred to as ‘the said Act’) to sit as a Court of appeal to appraise the facts and evidence on record. It has been repeatedly held by the apex Court and by this Court that unless the conclusion arrived at by the Arbitrator is perverse, the same ought not to be interfered with. The mere possibility of this Court arriving at a different conclusion from that arrived at by the Arbitrator cannot be a ground of interference if the view taken by the Arbitrator is plausible. In this behalf, reference may be made to the judgment of the Apex Court in Sudarsan Trading Company v. Government of Kerala, (1989) 2 SCC 38 : AIR 1989 SC 890 and of the Division Bench of this Court in DDA v. Bhagat Construction Co. (P) Ltd., 2004 (3) Arb LR 481.
3. In view of the aforesaid position, learned Counsel for the respondent has confined the submissions in respect of claim No. 1, claim No. 7 and the rate of interest.
Claim No. 1:
4. This claim relates to extra work stated to have been done during the extended period of contract. The claim arises on account of the petitioner's contention that though the work was originally scheduled to be completed within 12 months, the same was prolonged to 30.5 months' time for reasons not attributable to the petitioner. The blame was put on the respondent that the respondent failed to clear the site; there was delay in supply of material; drawings and designs were provided late. There was delay in execution of work by other agencies and decisions were not taken in time; payments were delayed and there was general hindrance of the work. In this behalf, the petitioner relied on various communications. This position was disputed by the respondent who in turn blamed the petitioner. The relevant aspect, however, is that the respondent has stated that Clause 10(CC) of the contract provides for increase in cost of material and that alone can be the formula of grant of the amount.
5. The Arbitrator found that though the agreement provided for Clause 10(CC), it does not compensate to the same extent as the increase had taken place and thus awarded a higher amount than provided under Clause 10(CC). An amount of Rs. 7,36,597/- was awarded against the claim of the petitioner for Rs. 30 lakh. Clause 10(CC) provides for the methodology to calculate for increase in labour and material rates including for the validly extended period of contract.
6. Learned Counsel for the respondent submitted that it was not open to the Arbitrator to apply any formula other than as prescribed under Clause 10(CC) in view of the parties having agreed to the same. In this behalf, learned Counsel relied upon the Division Bench judgment of this Court in Delhi Development Authority v. K.C Goyal & Co., 2001 II AD (Delhi) 116. The Division Bench held, relying upon the judgment of the Supreme Court in Associated Engineering Company v. Govt. of A.P, 1991 (2) Arb LR 180, that once a particular formula is provided in the contract, it is not open to the Arbitrator to award the claim by some other methodology and the same would amount to legal misconduct. The parties were held bound by the methodology of Clause 10(CC) which the Arbitrator ought to have followed.
7. Learned Counsel also relied upon the judgment of the Division Bench of this Court in Delhi Development Authority v. U. Kashyap., 1998 VII AD (Delhi) 300 which is to the same effect and has in fact been referred to in the aforesaid judgment of the Division Bench in K.C Goyal & Co. case (supra).
8. Learned Counsel for the petitioner, on the other hand, relied upon the Division Bench judgment of this Court in Delhi Development Authority. v. Hindustan Construction Corporation Engineers & Contractors., 2002 (1) Arb. LR 98 to contend that Clause 10(CC) would be applicable during the validly extended period of the contract. In the said case, it was held that Clause 10(CC) would not automatically apply and the necessary ground for application must be laid before the Arbitrator. This is so since the clause is not applicable without there being a valid extension as per Clause 5. No such plea was raised before the Arbitrator and the contractor had pleaded to the contrary. The DDA had chosen not to appear before the Arbitrator. Thus, it was held that the principles of Section 70 of the Contract Act would apply for a period after the expiry of the period of the contract or the period for which the contract is validly extended under the provisions of Clause 5.
9. In view of the aforesaid legal position, learned Counsel for the petitioner contended that the petitioner had put the respondent to notice that it was willing to continue the work beyond the stipulated date in case the Department agreed to pay 40% extra over and above the quoted rates. Learned Counsel referred to the letter dated 22.6.1989 (C-64) of the petitioner to this effect addressed to the respondent. It was thus submitted that the extension of time was unilaterally and without the consent of the petitioner and the same was granted ex post facto. It is not, however, disputed that the petitioner remained at site and executed the work but that is sought to be explained away by contending that if the petitioner had failed to carry on the work, action would have been taken under the terms and conditions of the contract against the petitioner for refusing to execute the work. The petitioner claims not to have given up the right based on the delay in the execution of the work.
10. Learned Counsel for the petitioner also referred to ground U of the objections where it has been pleaded that the extension of time was granted under Clause 5 of the agreement at the desire of the contractor. In reply to the said ground U, it has been stated that the extension of time was granted by the respondent without levy of penalty and this was so done as the respondent accepted that the delay was caused due to their omission and commission. The reply goes on to state that the legal position is well settled that the extension of time is not a substitute for loss and damages and it has been specifically denied that the work continued with the mutual consent of the parties. The Counsel sought to contend that Clause 10(CC) does not take into consideration the increase in prices of building material and takes into consideration increase in price of consumables. This is the reason why CPWD had issued Office Memorandum dated 6.2.2003 in which recommendations have been made to take into consideration the price index for construction material rather than any other price index. A further submission advanced is that in U. Kashyap's case (supra), the demand of contractor for enhanced rates was denied whereas there is no such denial in the present case.
11. Learned Counsel for the petitioner has relied upon the judgment of the Division Bench of this Court in Delhi Development Authority… v. S.S Jetley…., 2001 (1) Arb. LR 289. The claim for damages under Sections 73 and 74 of the Contract Act was upheld on account of prolongation of contract. It may, however, be noticed that the Division Bench came to the conclusion that the relevant claim dealt with the issue of idle labour, staff, machinery, etc. on account of prolongation of the contract which was different from the claim under Clause 10(CC). The claim under Clause 10(CC) was separately sought and had been awarded in terms of the formula of Clause 10(CC).
12. A reference was also made to the judgment of the Division Bench of this Court in M.L Mahajan v. Delhi Development Authority, 2002 (3) Arb. LR 376. It may, however, be noticed that the said judgment dealt with the contract where Clause 10(CC) was not incorporated in the standard form of contract and Clause 10(C) used to exist at that time.
13. Learned Counsel for the respondent in the end emphasised that though an award is not liable to be interfered with easily, once the award is contrary to the terms of the contract or is plainly barred, the Court would not hesitate to set aside the claim. In this behalf, the observations made in Ch. Ramalinga Reddy v. Superintending Engineer, 1999 (Suppl.) Arb. LR 440 which in turn relied upon the judgment of the Apex Court in Jajodia (Overseas) (P) Ltd. v. Industrial Development Corporation of Orissa Ltd., 1993 (1) Arb. LR 334, were referred to.
14. In my considered view, the law is quite well settled on the issue of the mode and manner of calculation of such escalation or increase in cost. The position was little different earlier under Clause 10(C) where no proper provision was made and that is why Clause 10(CC) was incorporated to take care of the position where the contract was not completed within the stipulated time and there was an extension granted. The escalations during the extended period of contract have to be calculated in terms of Clause 10(CC). There is also no doubt about the proposition that the extension should be in terms of Clause 5 of the General Conditions of Contract.
15. In the present case, learned Counsel for the petitioner does not even dispute the position in law but relies on the fact that the extension granted was one sided or that the petitioner had to put the respondent to notice as per C-64 that it wanted an increased rate. Increased rates have been given but the stand is that it should be as per Clause 10(CC). The petitioner continued to execute the contract and it has been stated that the petitioner had even received payment under Clause 10(CC) for the entire period up to the date of completion.
16. The judgment in Hindustan Construction Corporation Engineers & Contractors case (supra) arose in the peculiar facts where the DDA had failed to even appear before the Arbitrator and thus failed to lay down the ground for application of Clause 10(CC). Thus, nothing had been pleaded to show that the contract was validly extended and it was in those circumstances that the award was upheld. This is not so in the present case. The contract has been extended and performed and payment made in terms of Clause 10(CC). Thus, the principles laid down in K.C Goyal & Co. case (supra) and U. Kashyap's case (supra) would squarely apply to the facts of the present case. This aspect has also been analysed in the judgment before this Court in CS (OS) No. 2822/1994 in Bedi Construction Co. v. DDA, decided on 10.11.2005 where it has been held that once the formula of Clause 10(CC) forms part of the contract and which is agreed upon, no other methodology should be adopted for the said purpose.
17. I am thus of the considered view that there is a legal misconduct of the Arbitrator in going beyond the purview of the terms and conditions of the contract whereby Clause 10(CC) was specifically provided for and the respondent was entitled to the claim only in terms of Clause 10(CC). The award for this claim is thus set aside.
18. It may be clarified that in case any amount is due as per calculation under Clause 10(CC), the same would be payable but any amount over and above the same cannot be awarded to the petitioner.
Claim No. 7:
19. This claim deals with the outstanding amount of the final bill. The petitioner claims that the work was completed on 4.8.1990 and despite all requests, no action was taken and the final bill Ex. C-83 is stated to be prepared. On the other hand, the respondents have stated that they have prepared the final bill which worked out to minus figure of Rs. 7,815/-. The basis of the final bill prepared by the petitioner is disputed.
20. The principal contention of the learned Counsel for the respondent is that no reasons have been given for holding that the amounts are payable under the various descriptions. It is thus submitted that though there may not be detailed reasoning, at least there should be some disclosure about the mind of the Arbitrator. A specific plea has been raised that in item No. 7 under this claim, cutting and straightening of reinforcement steel bars has been permitted contrary to the judgment of this Court in Wee Aar Constructive Builders v. Delhi Development Authority, 2001 IV AD (Delhi) 65 and Narain Dass R. Israni v. Delhi Development Authority, 2005 VIII AD (Delhi) 556. In this respect, a plea has also been raised by the respondent that the said amount was not payable under the terms of the agreement.
21. Learned Counsel for the petitioner, on the other hand, submitted that there was no dispute about the figures and the only issue was whether they were payable or not based on the fact whether the work was or was not actually done. In this behalf, grounds ZF onwards have been referred to, to substantiate the plea based on the stand of the respondent. The various categories of amounts awarded relate to the extra and substituted items and thus the controversy is whether such work was or was not done. The respondent had taken the stand that the work was not done and that is the nature of the objections in the grounds.
22. A perusal of the aforesaid grounds shows that the respondent has objected to the same on the ground that the relevant work was not done at site. As an example of the same is ornamental grills where in the Grounds it has been stated that such grills were not provided. The respondent has stated that these claims are afterthoughts.
23. A perusal of the eight items awarded would show that the same relate to extra and substituted items. There is no doubt that no detailed reasoning has been given. However, it must be kept in mind that award of an Arbitrator is not like a judgment and it is not to be decided on the said parameters. I find force in the submission of the learned Counsel for the petitioner that the real dispute was whether the particular work was or was not done. Measurements have also been taken as recorded in the award. The stand of the respondent was that these works have not been done. However, the Arbitrator found that the work had actually been done at site and thus the dispute was not about the rates.
24. The Arbitrator found that ornamental grills had been provided, but there was concealed stop cocks of Kingston make, grooves in plaster had been done. Wax polishing and marble chip floor and skirting was also completed. The claim for providing centering and shuttering for balconies at fourth floor level was found sustainable on the ground that the said work had been done. Same is the position in respect of the claim for finishing walls of rough surface with water proof cement paint, cutting and straightening of reinforcement steel bars and cement slurry for sponge plaster. The quantities, rate and amount had been mentioned for each of the claims
25. However, different position would arise in respect of Item No. 7 dealing with cutting and straightening of reinforcement steel bars. It has been held in Narain Dass R. Israni case (supra) that the definition of reinforcement for RCC work is illustrative and not exhaustive. Thus, the mere fact that cutting and straightening was not mentioned while defining reinforcement for RCC work to include bending, binding and placing in position, would be of no assistance to the petitioner. However, it was also observed that in case the contractor puts the DDA to notice during the currency of the contract and DDA does not raise any objection, then amounts can be recovered on this account.
26. In the present case, it has not been disclosed that any such notice was given to DDA.
27. Thus, in my considered view, this award for item No. 7 cannot be sustained and is liable to be set aside.
28. The last issue raised is about the rate of interest. The Arbitrator has awarded interest at the rate of 15% per annum till date of payment or date of decree, whichever is earlier.
29. In my considered view, the prevalent rate of interest at the relevant period of time should be taken as 12% per annum and this has been the approach of this Court in numerous other cases where the Counsel have in fact been even conceding to the same. The interest should be on the actual awarded amount for each specific claim and should not be compounded.
30. I am thus of the considered view that the award in respect of interest needs to be modified and the petitioner is entitled to interest at the rate of 12% per annum on the awarded claims for idle staff, idle TNP and shuttering, final bill and refund of bank guarantee for the pre-suit and pendente lite period.
31. The application is accordingly disposed of.
32. The objections having been disposed of, the award of the sole Arbitrator Shri C. Rama Rao dated 30.9.1995 is made rule of the Court with the modifications whereby the award in respect of the claim for escalation, being claim No. 1 is set aside and part of the amount towards the final bill dealing with cutting and straightening of reinforcement steel bars is also set aside and the interest is awarded on the awarded amounts at simple rate of interest of 12% per annum for past and pendente lite period. The petitioner shall also be entitled to future interest at the rate of 9% simple interest from the date of decree till date of realisation. However, if the respondent pays the decretal amount within 60 days from today, the respondent would be exempted from payment of future interest. Parties are left to bear their own costs. Decree sheet be drawn up accordingly.
Application disposed of.