Associated Builders v. Dda .

Delhi High Court
Feb 23, 2006
Smart Summary (Beta)

Judgment Summary: IA No. 429/1997 (under Sections 30 and 33, Arbitration Act, 1940)

Factual and Procedural Background

The petitioner was awarded a contract for construction of SFS houses at Sarita Vihar, Sector I, under Agreement No. 14.EE/CPD-5.DDA/84-85. Disputes arose and, relying on Clause 25 (the arbitration clause) of the contract terms, the Engineer Member, DDA, by letter dated 25.11.1991, appointed Sh. M.S. Telang (Chief Engineer (Retd.), CPWD and DDA) as the sole arbitrator. The arbitrator made and published an award dated 6.12.1995. The respondent filed objections to that award under Sections 30 and 33 of the Arbitration Act, 1940. The present proceedings disposed of those objections (recorded as CS(OS) 507A/1996).

Legal Issues Presented

  1. Whether this Court should reappraise evidence or interfere with the arbitral award under the scope of Section 30 of the Arbitration Act, 1940, or whether interference is limited to matters falling within the statutory parameters.
  2. Whether specific awards made by the arbitrator in respect of various claims (notably claims Nos. 6, 7, 8, 10, 25, 26 and 28) are liable to be set aside or sustained.
  3. Whether Clause 25‑B (if applicable) and Clause 10CC of the contract apply to particular claims and, if so, whether their scope limits the arbitrator's award.
  4. Whether the mandatory procedure in Clause 12A for claims arising from substituted/additional items or deviations was followed by the contractor and considered by the arbitrator.
  5. The appropriate rates and scope of interest to be awarded (pendente lite and future interest) and whether interest should be awarded on interest (i.e., compound or on both principal and interest).

Arguments of the Parties

Respondent's (Objector's) Arguments

  • General objection: The respondent's counsel took the Court through the award and arbitral record and sought to argue each objection on merits, challenging various specific claims in the award.
  • Claim No. 7: Argued that Clause 25‑B of the contract conditions would apply to the claim and so the arbitrator's award should be re‑examined on that basis.
  • Claim No. 8: Contended that the award was granted on account of increase in labour and wage rates beyond Clause 10CC and that payments under Clause 10CC had already been given; thus the further award could not be sustained. The respondent also asserted that the petitioner had contractual extensions and any delay attributable to the petitioner should be considered.
  • Claim No. 10: Contended that it was a term of the contract that the petitioner should make himself familiar with the site, implying lack of entitlement where adverse site conditions were foreseeable.
  • Claim No. 26: Contended that Clause 12A prescribes a mandatory procedure to be followed for claims arising from substituted/additional items or deviations and the arbitrator should have examined whether that procedure was complied with (e.g., cut-off date for notice).
  • Interest: Implicitly challenged the arbitrator's award of interest on both principal and interest and the rates awarded.

Petitioner's Arguments

  • Claim No. 8: Petitioner contended the claim was made on multiple accounts and not only for increase in material and labour rates; thus the award should encompass the broader heads claimed (damages due to prolongation etc.).
  • Claim No. 26: Relied on Document C‑41 dated 18.2.1996 to show respondent had been notified about the deviation in question (i.e., that the requisite notice/procedure had been given).
  • Interest: After some hearing, the petitioner limited its claim to pendente lite interest at 12% per annum on the principal amount alone (abandoning any claim for interest on interest or higher future interest).

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
DDA v. Bhagat Construction Co. Pvt. Ltd., 2004 (3) Arb.LR 481 (and 2004 (3) Arb.LR 548) Authority for the proposition that the court does not sit as an appellate fact‑finding body to re‑examine evidence and that an arbitrator (as a technical expert) is not required to write a judgement in the form of a judge. The Court relied on this Division Bench authority to limit its interference with the arbitration award and to accept that the arbitrator's form of reasoning and technical conclusions did not require the same form of judicial judgment-writing.
Sudarsan Trading Co. v. Govt. of Kerala, (1989) 2 SCC 38 : AIR 1989 SC 890 Support for the limited scope of judicial interference with arbitral awards (i.e., court should not re‑weigh evidence where the arbitrator's conclusion is plausible). Used by the Court to reinforce the principle that so long as the arbitrator's conclusion is a plausible one, the court should not interfere under Section 30.
State of UP v. Allied Constructions, (2003) 7 SCC 396 Establishes that interference by the court is circumscribed by the parameters of Section 30; unless an objection falls within those parameters the court need not scrutinize the award. The Court relied on this authority to require the respondent to indicate specific claims falling within Section 30's parameters before allowing broader scrutiny.
DDA v. K.C. Goel and Company, 2001 AD Delhi 116 Held that where Clause 10CC provides a formula for compensation for increases in labour/materials, no other claim on that account is permissible outside that formula. The Court applied this principle to the facts concerning Claim No. 8 and treated the arbitral approach to additional heads beyond Clause 10CC as susceptible to being set aside.
Bedi Constructions v. DDA, CS(OS)2822/94 (decided 10.11.2005) Followed the reasoning of the Division Bench in K.C. Goel: once the Clause 10CC formula is provided and relied upon, that formula alone should be applied and other amounts outside it cannot be granted. The Court noted that this subsequent decision followed K.C. Goel and used the same logic to justify setting aside awards that granted amounts beyond the Clause 10CC formula.
Narain Das R. Israni v. DDA, 2005 VIII AD 556 Holds that claims under Clause 10CC (for increases in material/labour) are distinct from claims for overhead expenses or loss of profit. The Court used this distinction to uphold the award of overhead expenses (Claim No. 25) while treating Clause 10CC claims as covering a different category.
DDA v. Jagan Nath Ashok Kumar, 89 (2001) DLT 668 Holds that the procedure prescribed in Clause 12A (for substituted/additional items and deviations) is mandatory. The Court cited this authority (and noted its following in Narain Das Israni) when considering respondent's challenge to Claim No. 26 and concluded that the required procedure had been followed in the present case.

Court's Reasoning and Analysis

The Court's analysis proceeded in two broad strands: (A) a threshold jurisdictional limitation and (B) claim‑by‑claim examination within those limitations.

A. Threshold Jurisdictional Limitation

  • The Court invoked precedents (including Sudarsan Trading Co. and DDA v. Bhagat Construction) to emphasize that it does not act as an appellate fact‑finding body re‑weighing evidence. The court's power under Section 30 is limited and it will not interfere merely because it might have reached a different conclusion on the same evidence.
  • Relying on State of UP v. Allied Constructions, the Court required the respondent to point to specific claims that fall within the parameters of Section 30 before undertaking scrutiny; absent an objection falling within those parameters, the Court would not re‑examine the arbitrator's factual findings.
  • The Court also observed that a technical arbitrator is not required to write a judgment in the style of a judge; the award and record need only show due consideration of the material (as reinforced by Division Bench authority in DDA v. Bhagat Construction Co.).

B. Claim‑by‑Claim Application of Law to Facts (as stated in the opinion)

  • Claim No. 6: The arbitrator awarded Rs. 1,080 on consideration of Conditions 10 and 11 of the agreement. The Court found the arbitrator's construction plausible and declined interference.
  • Claim No. 7: The arbitrator found Clause 25‑B was scored out of the contract, and therefore inapplicable. Because the clause was scored out, the Court accepted the arbitrator's conclusion and would not interfere.
  • Claim No. 8: The arbitrator allowed a much smaller sum (Rs. 1,75,940) out of the claimed Rs. 19,25,521, expressly assessing the award "towards the claimants' inputs on construction materials and labour rates alone." The Court observed that the arbitrator's award was confined to the Clause 10CC category. However, applying Division Bench precedent in DDA v. K.C. Goel (and subsequent followings such as Bedi Constructions), the Court held that where Clause 10CC provides a formula and is relied upon, "that formula alone" should be applied and amounts beyond it are impermissible. Consequently, in the final disposition the award under Claim No. 8 was disallowed (see final order modification).
  • Claim No. 10: The claim related to execution under foul conditions (flooding by sewage) and was largely disallowed except for Rs. 32,702 awarded by the arbitrator. The Court concluded that even if the contract required contractors to familiarise themselves with the site, that could not be a defence to sewage flooding conditions which were not part of the contractual assumptions; the arbitrator considered the material and the limited award did not call for interference.
  • Claim No. 25 (overhead expenses): The arbitrator awarded overheads because the respondent was found to be at fault for the delay. The Court upheld that award, citing Narain Das R. Israni v. DDA for the proposition that Clause 10CC is distinct from claims for overheads or loss of profit.
  • Claim No. 26 (abnormal reduction in quantities): The respondent argued Clause 12A's mandatory procedure was not followed. The Court examined the record, noted Document C‑41 (18.2.1996) which showed the respondent was notified, and cited DDA v. Jagan Nath Ashok Kumar holding that Clause 12A's procedure is mandatory. The Court concluded that in this case the procedure could not be said not to have been followed and did not interfere with the arbitrator's conclusion.
  • Claim No. 28 (interest): The arbitrator had granted pendente lite interest at 12% and future interest at 16% on both principal and interest. After hearing, the petitioner confined its claim to pendente lite interest at 12% on the principal alone. Applying commercial realities and precedent, the Court modified the interest award: pendente lite simple interest at 12% on principal; future simple interest from date of decree till realization at 9% (and expressly clarified that interest would be on principal amounts awarded only, not on any pendente lite interest component).

Holding and Implications

Core Ruling: The objections to the arbitrator's award were disposed of and the award of the sole arbitrator Mr. M.S. Telang dated 6.12.1995 was made rule of the Court with specified modifications.

Specific operative modifications and consequences:

  • The award under Claim No. 8 stands disallowed (the Court set aside that portion of the award in light of Clause 10CC and relevant Division Bench precedent).
  • The petitioner is entitled to simple pendente lite interest at the rate of 12% per annum on the principal amounts of the claims awarded (for the pendente lite period and until the date of decree).
  • The Court clarified that the 12% pendente lite interest is to be awarded only on the principal amounts and not on any pendente lite interest component (i.e., no interest on interest for the pendente lite award).
  • For future interest (from date of decree till realization), the petitioner is entitled to simple interest at 9% per annum on the decretal principal amounts. If the respondent pays within 60 days, respondent will not be liable for future interest.
  • Parties are directed to bear their own costs, and the decree sheet is to be drawn accordingly.

The opinion does not purport to lay down any new legal precedent beyond applying and following existing authorities. The Court's decision primarily has direct, case‑specific effects on the parties: it makes the arbitrator's award rule of court subject to the stated disallowance of Claim No. 8 and the modified interest directions.

Objections disposed of.
Show all summary ...

IA No. 429/1997 (under Sections 30 and 33 of the Arbitration Act, 1940)

Sanjay Kishan Kaul, J.—The petitioner was awarded the contract for construction of SFS houses at Sarita Vihar, Sector I, in pursuance to the agreement No. 14.EE/CPD-5.DDA/84-85. Disputes arose between the parties and in view of Clause 25 being the arbitration clause of the terms and conditions of the contract, the Engineer Member DDA vide letter dated 25.11.1991 appointed Sh. M.S Telang, Chief Engineer (Retd.) of CPWD and DDA as the sole arbitrator. The arbitrator made and published his award dated 6.12.1995 The respondent aggrieved by the same has filed the objections under Sections 30 and 33 of the Arbitration Act, 1940 (hereinafter referred to as ‘the said Act’).

2. Learned Counsel for the respondent has taken me through the award and the arbitral record. Learned Counsel seeks to argue each of the objections on merits, but in my considered view, this is not the jurisdiction of this Court. The Court does not sit as a Court of appeal to scrutinize evidence and facts on record. It is not the jurisdiction of this Court to interfere with an award because on the same set of facts and evidence on record, this Court may come to a different conclusion. So long as the conclusion arrived at by the arbitrator is a plausible one, it is not for this Court to interfere with the award. It is not the jurisdiction of this Court to scrutinize each claim in this behalf. A reference may be made in this behalf to the Division Bench judgment of this Court in DDA v. Bhagat Constructon Co. Pvt. Ltd., 2004 (3) Arb.LR 481 and of the Apex Court in Sudarsan Trading Co. v. Govt. of Kerala; (1989) 2 SCC 38 : AIR 1989 SC 890. It is in view thereof that learned Counsel for the respondent was asked to point out the specific claims in respect of which scrutiny would be permissible within the parameters of Section 30 of the said Act since until and unless an objection falls within the said parameters, this Court is not required to scrutinize the same, as held by the Apex Court in State of UP v. Allied Constructions, (2003) 7 SCC 396.

3. Learned Counsel for the respondent referred to claim No. 6. The said claim has been awarded to the petitioner on consideration of the two conditions being Conditions 10 and 11 of the agreement. The arbitrator has construed the two conditions and come to the conclusion of awarding the amount of Rs. 1080 which does not call for interference.

4. Learned Counsel for the respondent also referred to claim No. 7 and its various clauses to contend that Clause 25-B of the conditions of the contract would apply. The arbitrator has found that the said clause was scored out. Since the clause is scored out, it has no application to the contract in question and thus the award would not call for any interference.

5. Learned Counsel for the respondent forcefully contends that the award under claim No. 8 cannot be sustained for the reason that the award is on account of increase in labour and wages rates beyond Clause 10CC. It is not disputed that the payments under Clause 10CC for increase in labour and material have already been given to the petitioner. The petitioner, however, wanted a higher rate especially as there was considerable delay in the contract though the contractual period was extended by the respondent. Such delay is attributable to the respondent.

6. Learned Counsel for the petitioner, on the other hand, contends that this claim was made on various accounts and not only for increase in material and labour rates.

7. A perusal of the award shows that the claim was made for Rs. 19,25,521/- on account of damges due to prolongation of the contract. The claim has been allowed only to the extent of Rs. 1,75,940/-. Insofar as this claim is concerned, the arbitrator awards it as ‘I assess the net damages towards the claimants’ inputs on construction materials and labour rates alone at Rs. 1,75,940/-.”

8. Thus it is abundantly clear that what has been awarded is only the said category of award which is covered by-Clause 10CC.

9. The Division Bench of this Court in DDA v. K.C Goel and Company, 2001 AD Delhi 116 has held that in view of clause 10CC no other claim on this account would be permissible. This judgment of the Division Bench has been recently followed by this Court in CS(OS)2822/94 titled Bedi Constructions v. DDA, decided on 10.11.2005 while discussing the aforesaid judgments and other judgments it has been held that once the formula of Clause 10CC is provided for and is relied upon by the petitioner, it is that formula alone which should have been applied and no amount other than that formula could have been granted. Award to that extent is, thus, set aside.

10. Learned Counsel for the respondent next referred to Claim 10 on account of execution of work under foul conditions. The award is only 32,702/- against the claim of 6,05,348/-. This claim has been awarded on account of the fact that the execution of the work took place in conditions when the area used to be flooded by sewerage as a result of breach in the adjoining canal tributary carrying sewage. The petitioner through various communications brought that to notice of the respondent. Learned Counsel for the respondent urges that it was term of the contract that the petitioner should make himself familiar with the site. In my considered view, that would be no defence since it is certainly not part of the terms and conditions that the area would be flooded with sewerage water. The working condition of the petitioner was affected by such sewerage and the arbitrator on consideration of the material has made the award which does not call for any interference.

11. Learned Counsel for the respondent also referred to claim No. 25 which is on account of overhead expenses. The claim has been awarded since the respondent has been found to be at fault for the delay. That being the position, it can hardly be disputed that the petitioner would be entitled to the amounts on account of such overhead expenses. The claim under clause 10CC is distinct from the claim for such overhead expenses or loss of profit as held in Narain Das R. Israni v. DDA, 2005 VIII AD 556. Thus the contention of the respondent cannot be accepted.

12. Learned Counsel for the respondent referred to claim No. 26 on account of damages due to abnormal reduction in the quantities of the agreement. Learned Counsel for the respondent contends that clause 12A sets forth the procedure required to be followed in case of such claim. The said clause is as under:

“Clause 12A.—In the case of contract substituted items or additional items which result in exceeding the limits laid down in Sub-clause (vi) of Clause 12 except the items relating to foundation work, which the contractor is required to do under Clause 12 above, the contractor shall, within 7 days from the receipt of order, claim revision of the rates supported by proper analysis in respect of such items for quantities in excess of the deviation limit, notwithstanding the fact that the rates for such items exist in the tender for the main work or can be derived in accordance with the provisions of Sub-clause (ii) of Clause 12 and the Engineer-in-Charge may receive their rates, having regard to the prevailing market rates and the contractor shall be paid in accordance with the rates so fixed. The Engineer-in-Charge shall, however, be at liberty to cancel his order to carry out such increased quantities of work by giving notice in writing to the contractor and arrange to carry it out in such a manner as he may consider advisable, but under no circumstances the contractor shall suspend the work on the plea of non settlement of rates of items falling under this clause. All the provisions of the preceding paragraph shall equally apply to the decrease in the rates of items or quantities in excess of the deviation limit, not-withstanding the fact that the rates for such item exist in the tender for the main work or can be derived in accordance with the provisions of Sub-clause (ii) of the preceding Clause 12, and the Engineer in Charge may revise such rates having regard to the prevailing market rates.”

13. The Division Bench of this Court in DDA v. Jagan Nath Ashok Kumar, 89 (2001) DLT 668 held that the procedure prescribed therein was mandatory and this judgment has been followed in Narain Das Israni's case (supra).

14. Learned Counsel for the petitioner has referred to the Document C-41 dated 18.2.1996 which shows that the respondent was notified about the deviation in question. Learned Counsel for the respondent submits that the arbitrator ought to have gone into the issue to determine as to what would be the cut off date for the notice.

15. The arbitrator in the present case is a technical person who is well conversant with the nature of the trade. Such an arbitrator is not required to write a judgment in the form as written by a Judge. The award and the documents on record show consideration of this material. This view is re-inforced by the judgment of the Division Bench in DDA v. Bhagat Construction Co. (P) Ltd., 2004 (3) Arb.LR 548.

16. In view of the aforesaid, it cannot be said that the procedure under Clause 12A has not been followed.

17. The last issue raised by learned Counsel for the respondent is in respect of claim No. 28 on account of interest. The arbitrator has granted pendente lite interest at the rate of 12 per cent, future interest from the date of the award till date of the decree or date of payment at the rate of 16 per cent per annum and that too on both the principal and the interest amount. After some hearing, learned Counsel for the petitioner confines his claim of interest to interest @ 12 per cent on the principal amount alone. This is also the rate of interest which has been awarded by this Court for the relevant period of time keeping in mind the then prevailing commercial rates of interest.

18. The objections stand disposed of.

CS(OS) 507A/1996

19. In view of the objections having been disposed of, the award of the sole arbitrator Mr. M.S Telang dated 25.11.1991 is made rule of the Court with the modification that the award under the claim 8 stands disallowed and the petitioner is held entitled to simple interest at 12 per cent per annum for pendente lite period as well as till date of decree. It is thus clarified that the interest awarded would only be on the principal amounts of the claims awarded and not on the pendente lite interest component. The petitioner shall also be entitled to future interest from date of decree till date of realisation at 9 per cent simple interest. In case the respondent makes the payment of the decretal amount within 60 days, the respondent shall not be liable to pay future interest.

20. Parties are left to bear their own costs.

21. Decree sheet be drawn up accordingly.

Objections disposed of.