Beebcon Engineers Pvt. Ltd. v. Bharat Heavy Electricals Ltd.
Structured Summary of the Opinion (Badar Durrez Ahmed, J.)
Factual and Procedural Background
This suit challenges an arbitral award dated 30.01.2000 made by the sole arbitrator. The suit was filed under Sections 14 and 17 of the Arbitration Act, 1940. The respondent (Bharat Heavy Electricals Limited, “BHEL”) filed IA No. 639/2002 objecting to the award under Sections 30, 33, 16, 15 and 17 of the said Act, seeking to set aside the award on grounds that the arbitrator acted contrary to documents on record, exceeded the terms of the contract and Letter of Reference, and misconducted the arbitral proceedings.
The underlying contract arose from a public tender by BHEL for design, engineering, manufacture, testing, supply, erection and commissioning of fuel oil system and miscellaneous tanks for Khaperkheda Thermal Power Station, Maharashtra. The petitioner (a successful tenderer, referenced in the award as "Beebcon") received a Letter of Intent dated 23.03.1987 and a formal Purchase Order dated 20.07.1987. The Purchase Order specified a firm price, delivery milestones (Clause 4.0), and liquidated damages and milestone penalties (Clause 5.0) including a total cap of 10% of the order value for delay/liquidated damages.
The work was completed on 19.01.1993. Disputes were referred to arbitration and the arbitrator issued the award on 30.01.2000. The arbitrator granted certain sums in favour of the petitioner on various heads and granted some amounts to BHEL; the court in this opinion reviews and decides the objections to that award.
Legal Issues Presented
- Whether the arbitral award dated 30.01.2000 should be set aside under Sections 30 and 33 of the Arbitration Act, 1940 on the grounds that the arbitrator acted contrary to contractual documents, went beyond the terms of the contract/Letter of Reference, or misconducted the arbitral proceedings.
- Whether the arbitrator's factual and legal conclusions on the petitioner's five claims (successful completion, extra works, re-rubber lining of DM tanks, loss for non-placement of spare parts, and business loss) and BHEL's counter-claims (liquidated damages, financing cost/sub-vendors, LC/extension charges) are sustainable or require interference.
- Whether the arbitrator had jurisdiction to award interest to the petitioner in view of specific contractual clauses (Clause 6.9.6, Clause 4.7, and Clauses 25.1/25.2) that deal with payment, security deposit, retention and express bars on interest.
- Whether BHEL's claim for liquidated damages should have been allowed where the contract contains a liquidated damages clause.
Arguments of the Parties
Petitioner's Arguments
- The petitioner claimed entitlement to various sums under five heads (successful completion, extra works, re-rubber lining, loss due to non-placement of spares, business loss) and interest as appropriate.
- On the interest point, the petitioner relied on Clause 25 (specifically Clauses 25.1 and 25.2) to contend that clauses barring interest were limited to retention money (security deposits) and did not preclude interest on other sums awarded by the arbitrator.
- The petitioner accepted that Clause 6.9.6 referred to security deposit but argued it did not extend to all other dues — the arbitrator had not awarded interest on security deposit and, therefore, the contractual bar to interest on security deposit could not be used to negate interest on other awarded sums.
Respondent's (BHEL) Arguments
- BHEL objected that the arbitrator had acted contrary to the contract and exceeded his jurisdiction; it urged setting aside of the award under Sections 30 and 33 of the Arbitration Act, 1940.
- On interest, BHEL relied on Clause 6.9.6 and Clause 4.7 (which state that no interest is payable by the purchaser on security deposit or on any money due to the seller) and Clauses 25.1/25.2 (no claim for interest on retained sums) to argue that the arbitrator had no jurisdiction to award interest.
- BHEL contended that where a contract contains a liquidated damages clause, the respondent should not need to prove actual loss and that BHEL’s claim for liquidated damages ought to have been allowed; it relied on authorities (cited in the award) for that proposition.
- In contesting certain petitioner's claims (e.g., re-rubber lining), BHEL pointed to documentary/letter evidence in the record (letters dated 19.10.1989 and 12.12.1989) and expert reports to support positions that the petitioner had accepted liability or that expert opinion was inconclusive.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| D.S.A Engineers (Bombay) v. Housing & Urban Development Corporation (HUDCO), 2004 (2) Arb. LR 33 (Del.) | Holds that if the contract expressly stipulates that no interest is payable, an arbitrator lacks jurisdiction to award interest despite statutory provisions; contractual bar prevails. | The court relied on this decision (and its reasoning) to conclude that where the parties' contract contains express provisions barring interest, the arbitrator could not lawfully award interest; this supported setting aside the interest portion of the award. |
| Secretary, Irrigation Department, Government of Orissa v. G.C. Roy, (1992) 1 SCC 508 | Authority considered in discussion on arbitrator's power to award interest and the effect of contractual bars on interest awards. | Used as precedent supporting the proposition that contractual terms can limit an arbitrator's jurisdiction to award interest; the court treated it as part of the body of authority demonstrating the effect of an express contractual bar. |
| State of Orissa v. B.N. Agarwalla, (1997) 2 SCC 469 | Authority addressing interplay between contractual terms and an arbitrator's power to award interest. | Cited by the court to support the view that an express contractual prohibition on interest precludes the arbitrator from awarding interest; relied upon in interpreting the contract clauses in dispute. |
| Kaushnuma Begum v. New India Assurance Co. Ltd., (2001) 2 SCC 9 | Listed among authorities in the context of interest and related principles. | Referenced by the court in the list of decisions relied upon by the parties regarding interest; the court relied on the collective jurisprudence to construe contractual bars to interest. |
| Bharat Coking Coal Ltd. v. Annapurna Construction, (2003) 8 SCC 154 | Principle that if an arbitrator travels beyond the terms of the contract, the award can be set aside. | The court considered this authority as supporting the respondent's submission that an award granting interest contrary to contract terms could be vitiated; the court applied the principle to determine whether the arbitrator had exceeded the contract in awarding interest. |
| Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705 | Principle that where a contract specifies liquidated damages, actual loss need not be proved for a claim of liquidated damages. | The court acknowledged this authority in assessing BHEL's contention on liquidated damages but ultimately upheld the arbitrator's refusal to award LD because the arbitrator found both parties were responsible for delay; the court held this ground sufficient to sustain the arbitrator's determination. |
Court's Reasoning and Analysis
The court conducted a claim-by-claim analysis of the arbitrator's award and of the objections raised by BHEL. The analysis proceeded as follows:
1. Approach to factual findings and appellate interference
The court repeatedly emphasized deference to the arbitrator's detailed examination of documentary and factual material. Where the arbitrator had considered individual items in detail and reached reasoned conclusions, the court declined to interfere absent a plausible reason to do so.
2. Petitioner's Claim No. 1 (successful completion)
The arbitrator examined nine items and adjustments based on a petitioner letter dated 14.04.1995 and allowed Rs. 5,34,073 after adjusting amounts recoverable by BHEL. The court found the arbitrator's detailed reasoning persuasive, noted that respondent's counsel offered no plausible basis for interference, and therefore declined to disturb this part of the award.
3. Petitioner's Claim No. 2 (extra works and overstay)
The arbitrator split Claim No. 2 into two components: (a) compensation for alleged overstay (about Rs. 30 lakhs claimed) and (b) extra costs (DM water filling, supply of valves, etc.). For overstay, the arbitrator concluded both parties were responsible for delay and that pinpointing sole responsibility was not feasible; he therefore rejected the overstay compensation. For extra costs, the arbitrator allowed Rs. 7,71,821 relating to admitted extra valves and other admittedly extra items. The court accepted the arbitrator's reasoning and declined interference, observing the admitted character of some extra supplies supported the award.
4. Petitioner's Claim No. 3 (re-rubber lining of DM tanks)
The arbitrator considered conflicting expert reports and correspondence. He observed letters from the petitioner indicating a reluctance to contest liability as to the damage but seeking adjustment of recovery method; nonetheless the arbitrator found both parties had contributed to the damage and apportioned liability equally, awarding half of the claimed amount (Rs. 3,10,666). The court held that, given the arbitrator's finding of equal blame, splitting liability was not objectionable and declined to disturb the award.
5. Petitioner's Claim No. 4 (loss due to non-placement of spares)
The arbitrator described the Rs. 10 lakh claim as speculative, lacking evidence, and "shocking" in magnitude; he rejected the substantive claim but nonetheless awarded nominal damages of Rs. 50,000 as "just and equitable." The court agreed that, given the arbitrator's categorical finding of complete lack of evidence, no amount should have been awarded; accordingly, it set aside the arbitrator's nominal award of Rs. 50,000 under this head.
6. Petitioner's Claim No. 5 (business loss)
The arbitrator denied the Rs. 25 lakh business loss claim in full. The respondent did not press any objection in respect of this denial; the court left the arbitrator's rejection undisturbed as recorded.
7. Interest awarded by the arbitrator
The parties contested the arbitrator's award of interest. The court analysed the relevant contractual clauses:
- Clause 6.9.6: "No interest shall be payable by purchaser on security deposit or on any money due to the seller by the purchaser." (plain and categorical wording)
- Clause 4.7: Contains similar prohibition in the context of return of security deposit and expressly states "No interest shall be payable by the purchaser on earnest money/security deposit or on any money due to the contractor by the purchaser."
- Clauses 25.1 and 25.2: Provide that retained sums (lien/withholding) may be kept withheld until adjudication and that the seller shall have no claim for interest or damages in respect of such withholding.
The court rejected the petitioner's narrow reading of Clause 6.9.6 (that it applied only to security deposit) and concluded the clause, read plainly, extends to "any money due to the seller by the purchaser." The court found that Clauses 25.1/25.2 similarly supported a contractual bar to interest on retained sums and on sums due. Applying the line of authority (including D.S.A Engineers, Secretary, Irrigation Department v. G.C. Roy and State of Orissa v. B.N. Agarwalla), the court held that where the contract expressly bars payment of interest, the arbitrator lacks jurisdiction to award interest. Consequently, the court set aside the portion of the award that granted interest to the petitioner.
8. Respondent's claim for liquidated damages
BHEL had claimed liquidated damages (Rs. 26,96,225.60). The arbitrator rejected this claim on the ground that both parties were responsible for delay and it was not possible to ascribe sole responsibility to the petitioner; the court found this conclusion sufficient to sustain the arbitrator's refusal to grant liquidated damages and declined to set aside that part of the award. The court noted the relevance of authorities (e.g., ONGC v. Saw Pipes) on liquidated damages but considered the arbitrator's specific factual finding decisive.
9. Disposition and remedy
After evaluating each disputed item and the parties' submissions, the court upheld the arbitral award in most respects but set aside two elements: (a) the arbitrator's award under Petitioner's Claim No. 4 (the nominal Rs. 50,000) and (b) the arbitrator's award of interest in favour of the petitioner. The court ordered that the award, as so modified, be made a rule of the court and directed that the petitioner shall be entitled to future interest at 9% per annum until payment of the award amount as modified. The objection application and the suit were disposed of accordingly.
Holding and Implications
Holding: The court CONFIRMED the arbitral award dated 30.01.2000 in all material respects except for two modifications: (1) the arbitrator's award on Petitioner's Claim No. 4 (nominal damages of Rs. 50,000) was set aside, and (2) the arbitrator's award of interest in favour of the petitioner was set aside because the contract contains express clauses barring payment of interest.
Implications:
- The award, as modified by the court, was to be made a rule of the court and the petitioner is entitled to future interest at 9% per annum on the modified award amount until payment is made.
- Direct effect: the petitioner receives the amounts awarded by the arbitrator except that the Rs. 50,000 nominal award under Claim No. 4 and the arbitrator's interest award are set aside; the respondent's objection application and the suit are disposed.
- The court applied established authority on the limits of an arbitrator's power where the contract contains express clauses barring interest and on the circumstances in which awards that traverse the contract may be set aside. The opinion does not announce or claim to establish a new legal precedent beyond the application of existing authorities to the contractual clauses and facts before the court.
This summary is limited to the statements and reasoning contained in the provided opinion and does not add information outside the text of that opinion.
Badar Durrez Ahmed, J.:— This suit pertains to the award dated 30.01.2000 made by the sole arbitrator. This suit has been filed under Sections 14 and 17 of the Arbitration Act, 1940 (hereinafter referred to as ‘the said Act’). IA No. 639/2002 has been filed by the respondent objecting under Sections 30, 33, 16, 15 and 17 of the said Act to the said award dated 30.01.2000 passed by the sole arbitrator in the arbitration proceedings between the petitioner and the respondent. By way of this application, the respondent has prayed for the setting aside of the said award dated 30.01.2000 under Sections 30 and 33 of the said Act inasmuch as it is contended that the arbitrator has acted contrary to the documents on record and has gone beyond the terms of contract and Letter of Reference and has misconducted the arbitral proceedings.
2. The respondent [Bharat Heavy Electricals Limited (BHEL)] had invited tenders in respect of the design, engineering, manufacturing, testing, supply, erection, commissioning of fuel oil system and miscellaneous tanks for the Thermal Power Station at Khaperkheda, Maharashtra. The petitioner was one of the tenderers. The bids were opened on 24.06.1986 The petitioner being the successful tenderer was issued the Letter of Intent on 23.03.1987 and the formal Purchase Order on 20.07.1987 The scope of work was setout in Clause 1 of the said Purchase Order. Clause 2.0 pertains to price and it was clearly indicated that the “firm price” for the entire scope of work shall be Rs. 2,69,62,256. Clause 3.0 (Nature of Prices) of the Purchase Order also made it clear that prices shall be firm till the satisfactory execution of the order/contract, in full in all respects. Clauses 4.0 and 5.0 are relevant for deciding the present objections and, therefore, they are reproduced in their entirety:
“4.0 Delivery
The completion of supply, erection and testing, commissioning of with all accessories shall be as under:
(i) DM Storage Tanks to be erected and commissioned by 28.02.1988
(ii) Fuel oil system and other misc. tank by 26.05.1988
5.0 Liquidated Damages
5.1 In case of delays, liquidated damages shall be leviable separately on supply portion as well as on erection and commissioning as follows:
5.1.1 For delay in supplies, liquidated damages leviable shall be @ ½% of supply value per week of delay subject to a maximum of 10% of supply value.
5.1.2 For delay in erection and commissioning, liquidated damages leviable shall be @ ½% per week of erection and commissioning portion subject to a maximum of 10% of the contract value for supply as well as erection and commissioning.
Please note that total liquidated damages on account of delay as above shall be limited to a maximum of 10% of the contract value for supply as well as erection and commissioning.
5.2 Construction Schedule
Please furnish a milestone linked billing schedule. If contractor fails to achieve any milestone indicated in the bar chart, the contractor shall be levied penalty @ ½% per week's delay subject to a maximum of 10% of the milestone value.
However, please note that if overall commissioning schedule is maintained, the amount of penalty deducted if any shall be reimbursed. Total liability towards liquidated damages and milestone penalty shall be limited to 10% of the order value.”
3. The work was ultimately completed on 19.01.1993 Disputes arose between the parties which were referred to arbitration and the sole arbitrator made the impugned award dated 30.01.2000 The petitioner preferred its claim under five heads along with interest and the amounts as awarded by the arbitrator are indicated in the following table:
Sl. No. Description of claim Amount claimed by petitioner (Rs.) Amount awarded by the arbitrator (Rs.) (1) Amount claimed on account of successful completion of the contract 9,42,638.70 5,34,073.00 (2) Claimant on account of extra works 64,25,055.35 7,71,821.00 (3) Re-Rubber lining of DM Tanks 6,21,333.00 3,10,666.00 (4) Amount claimed on account of loss occasioned due to non-placement of the order of the spare parts 10,00,000.00 50,000.00 (5) Business loss 25,00,000.00 Nil (6) Interest claimed @ 18% 12% simple interest over a sum of Rs. 7,71,821.00 from 18.12.1995 to 31.01.2000 plus 12% simple interest on Rs. 15,67,463.00 from the date of award till the whole of the amount is received or till the award is made rule of the court which ever event occur.
4. On other hand, the respondent (BHEL) made the claims under three heads along with interest and the amounts awarded by the arbitrator are as indicated in the following table:
BHEL'S CLAIM
Sl No. Description of claim Amount claimed by BHEL (Rs.) Amount awarded by the arbitrator (Rs.) (1) LD (Liquidated Damages) 26,96,225.60 Nil (2) Financing cost for payment released to sub-vendors of the petitioner 3,50,000.00 50,000.00
(3) Letter of Credit (LC) 53,236.00 Nil Extension Charges 30,99,461-60 50,000.00 (4) Interest Nil
Petitioner's Claim No. 1
5. As would be apparent from the aforesaid table, the petitioner had claimed Rs. 9,42,638.70 from the respondent as being due upon successful completion of the contract. Upon examining the award, I find that this claim has been dealt with in detail by the arbitrator. As many as 9 items under this claim have been examined in the context of the letter dated 14.04.1995 issued by the petitioner in respect of the correspondence exchanged between the petitioner and the respondent on this subject, i.e the final bill amount. After examining all these items in detail, the learned arbitrator has come to the conclusion that the respondent was entitled to deduct a total sum of Rs. 3,87,735.00 from the petitioner on account of overheads against Rs. 6,33,591.00 claimed by them (respondent) under letter dated 14.04.1995 The arbitrator came to the conclusion that in addition to the above, the respondent could also recover a sum of Rs. 20,830.00 from the petitioner towards other claims under the same letter dated 14.04.1995 Therefore, the arbitrator came to the conclusion that the total sum recoverable by BHEL towards their dues, including overheads would be Rs. 4,08,565.00 as against Rs. 8,51,278.24 claimed by them in their letter of 14.04.1995 This being the case, the amount claimed by the petitioner would have to be adjusted by deducting this sum of Rs. 4,08,565.00 therefrom. Accordingly, the arbitrator passed an award with reference to Claim No. 1 of the petitioner in favour of the petitioner in the sum of Rs. 5,34,073.00 after adjusting Rs. 4,08,565.00 from their claim of Rs. 9,42,638.00 under the said Claim No. 1. The balance of the claim was rejected. As I have mentioned above, the arbitrator has, upon a detailed examination of each of the items and sub-items falling under this claim, come to the aforesaid conclusion. The counsel for the respondent was unable to come up with a plausible reason for interfering with the conclusion and reasoning adopted by the arbitrator in respect of the petitioner's Claim No. 1. Therefore, no interference is called for insofar as this claim is concerned.
Petitioners Claim No. 2
6. Under this head, the petitioner has claimed Rs. 64,25,055.35 from the respondent on account of extra work done by them at the site. As indicated by the arbitrator in the award itself, this claim comprises of two components. One relates to compensation for overstay at the site and the other represents the extra cost for filling DM water, damages to transformer, statutory variation, supply of valves, etc. not covered by the contract. The claim in respect of the alleged overstay at the site was to the extent of Rs. 30 lakhs, the balance being for the extra cost for filling DM water, etc. Insofar as the question of overstay at the site was concerned, the arbitrator has rejected the petitioner's claim holding that both the parties were responsible for the delay in the following words:
“Both responsible for the delay.
Given the complexity of the entire case and the innumerable letters exchanged between them in quick succession accusing each other of flagrant violation of the terms of the contract, the veracity of their mutual re-crimination and incrimination cannot be dismissed as entirely baseless and, therefore, irrelevant. They are good enough to disarm the other but no one can be completely decimated. At best they are mutually destructive. This is particularly so when their performance was mutually complimentary. There is overwhelming evidence to prove that both committed breach of contract. In these circumstances, it is quite an uphill task to pinpoint precisely whether it was BHEL or Beebcon who contributed for the ultimate delay.
In the circumstances, I am unable to hold BHEL alone responsible for the alleged overstay by Beebcon at the site. There can, therefore, be no question of compensation on that score.”
7. As regards the extra cost, the arbitrator has, upon a detailed consideration of the various items mentioned in the claim under this head allowed only a sum of Rs. 7,71,821.00 as against a claim of approximately Rs. 3 lakhs. This amount of Rs. 7,71,821.00 has been allowed to the petitioner towards the value of valves and other items supplied by them which were admittedly extra. Therefore, the arbitrator has allowed a sum of only Rs. 7,71,821.00 against the entire claim of Rs. 64,25,055.35 and that too on the basis of value of valves and other items supplied by the petitioner to the respondent which were admittedly extra. In view of the specific admission recorded in the award, the learned counsel for the respondent was unable to controvert this finding and, therefore, I feel that no interference is called for with respect to the finding under the petitioner's Claim No. 2 as contained in the impugned award.
Petitioner's Claim No. 3
8. This claim refers to the re-rubber lining of DM Tanks. Under this claim, the petitioner has claimed a sum of Rs. 6,21,333.00 on the ground that the said amount has been wrongfully recovered by the respondent from their bills on account of damage caused to the rubber lining to the DM Tanks. According to the petitioner, the damage was due to the respondent's negligence. The arbitrator considered the arguments of the petitioner and the respondent as well as the reports of the experts with regard to the rubber lining. He noted that there were two conflicting reports emanating from the technical experts relating to the cause of damage to the rubber lining and, therefore, no conclusive finding could be arrived at on the basis of the opinions of the experts. The learned counsel for the respondent drew my attention to page 945 (internal page 23 of the award) wherein the letters dated 19.10.1989 and 12.12.1989 sent by the petitioner to the respondent are discussed. It appears that the arbitrator came to the conclusion on the basis of these letters that the petitioner had not disputed their liability for damage to the rubber lining. All that they had sought by the said letters was that the adjustment for the same should not be done by the respondent against the pending bills but be set-off against the retention money or the settlement of the insurance claims. In other words, the liability as such for the damage to the rubber lining was more or less accepted by the petitioner and they merely requested for a different mode of adjustment for the cost of the same. The arbitrator also held that these letters were given voluntarily. According to the learned counsel for the respondent, having so held, the arbitrator ought not to have awarded any sum under this claim in favour of the petitioner. The learned counsel for the petitioner, however, pointed out that while the arbitrator found that the petitioner was liable under this head for the damage to the rubber lining of the DM Tanks, the matter did not stop here inasmuch as the arbitrator found that the respondent was also not blameless. It is in this context pointed out that the arbitrator, as would be apparent from internal page 25 of the award, found it difficult to precisely and conclusively conclude as to whether it was the petitioner or the respondent who was wholly responsible for the damage to the rubber lining of the said DM Tanks. He also came to the conclusion that the records unmistakably show that both the parties had contributed to the damages and it is in this context that the arbitrator held that both the parties must share the blame equally and, therefore, instead of allowing the petitioner's claim of Rs. 6,21,333.00, he found that the petitioner would be entitled to receive only ½ of the said amount and accordingly, awarded a sum of Rs. 3,10,666 in favour of the petitioner and against the respondent.
9. Upon a consideration of the facts and circumstances and the arguments advanced by the parties, I find that the arbitrator, upon a detailed examination, has come to the conclusion that both the parties were equally liable for the damage caused to the rubber lining of the DM Tanks. In the wake of such a finding, the arbitrator cannot be faulted in splitting the liability in half insofar as both the parties are concerned. Therefore, the conclusion arrived at by the arbitrator insofar as this claim is concerned, cannot also be faulted.
Petitioner's Claim No. 4
10. The petitioner under this head claimed a sum of Rs. 10 lakhs as loss on account of the respondent's failure to place the order of supply of the spares and maintenance tools. Insofar as this claim is concerned, the learned counsel for the respondent straightway drew my attention to the finding of the arbitrator wherein the arbitrator has recorded as under (at pages 939- 940):
“This submission without anything more to substantiate could hardly be enough to justify and claim of damages to the tune of Rs. 10 lakhs. Such a claim to say the least is shocking. Shocking because Beebcon has failed to lead any evidence much less credible evidence to substantiate their huge claims.”
“The claim of rupees ten lakhs is equal to the value of spare parts not delivered by Beebcon. This figure is apparently based on a pure hypothesis and conjecture. They have no place in the matter of awarding damages.”
“No compensation if loss due to breach not proved.”
“…. The legal position emerging from the analysis being as clear as crystal, the huge and patently exaggerated claim of Rs. 10 lakhs cannot form the basis for award of the damages. This claim simply deserves to be rejected without any hesitation whatsoever.”
11. The learned counsel for the respondent pointed out that despite the clear findings noted above, the arbitrator has awarded nominal damages to the tune of Rs. 50,000 considering the same to be just and equitable. He submitted that in view of the clear and categorical finding whereby the claim of the petitioner was found to be untenable for complete lack of evidence, the said amount of Rs. 50,000 ought not to have been awarded. The learned counsel for the petitioner, however, submitted that the amount of Rs. 50,000 that was awarded by the arbitrator was merely by way of nominal damages which the arbitrator considered to be just and equitable. However, he was unable to explain as to on what basis the sum of Rs. 50,000 was quantified.
12. After considering the arguments advanced by the counsel for the parties, I tend to agree with the submissions made by the learned counsel for the respondent that once the arbitrator had concluded that there was complete lack of evidence, then no amount should have been awarded as damages under this head and, accordingly, the finding of the arbitrator under this head, i.e Claim No. 4 deserves to be set aside.
Petitioner's Claim No. 5
13. The claim of business loss of Rs. 25 lakhs has been denied in toto by the learned arbitrator and, therefore, the respondent has not preferred any objection in respect of this claim.
Interest
14. As regards the award of interest by the arbitrator as indicated in para no. 3 above, the learned counsel for the respondent submitted that no interest at all could be awarded. He based this submission of his on Clause 6.9.6 of the Instructions to Bidders and General Terms and Conditions of the Contract and Clause 4.7 of the General Conditions of the Contract for erection, commissioning of plant/equipment. He relied upon several decisions, namely:
(i) D.S.A Engineers (Bombay) v. Housing & Urban Development Corporation (HUDCO), 2004 (2) Arb. LR 33 (Del.);
(ii) Secretary, Irrigation Department, Government of Orissa v. G.C Roy, (1992) 1 SCC 508 : 1992 (1) Arb. LR 145 (SC);
(iii) State Of Orissa v. B.N Agarwalla, (1997) 2 SCC 469 : JT 1997 (2) SC 51 : 1997 (1) Arb. LR 612 (SC);
(iv) Kaushnuma Begum v. New India Assurance Co. Ltd., (2001) 2 SCC 9;
(v) Bharat Coking Coal Ltd. v. Annapurna Construction., (2003) 8 SCC 154 : 2003 (3) Arb. LR 119 (SC); and
(vi) Oil & Natural Gas Corporation Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705 : 2003 (2) Arb. LR 5 (SC).
15. The aforesaid Clause 6.9.6 reads as under:
“6.9.6 No interest shall be payable by purchaser on security deposit or on any money due to the seller by purchaser.”
16. And the said Clause 4.7 reads as under:
“4.7 Return of security deposit—If the contractor duly performs and completes the contract in all respects to the entire satisfaction of the purchaser and presents an absolute no demand certificate in the prescribed form and returns properties belonging to the purchaser handed over, lent or hired by him for carrying on the said work, half the amount of security deposit will be released to the contractor after deducting all costs of expenses or other amounts that are to be paid to the purchaser under this or other contracts entered into with the contractor. Balance half the amount of security deposit will be released only after satisfactory completion of maintenance period.
No interest shall be payable by the purchaser on earnest money/security deposit or on any money due to the contractor by the purchaser.”
17. On the other hand, the learned counsel for the petitioner stated that the petitioner was clearly entitled to interest as would be clear upon a reading of Clause 25 of the Instructions to Bidders and General Terms and Conditions of the Contract and, in particular, Clauses 25.1 and 25.2 which read as under:
“25.0 Withholding and lien in respect of sum claimed
25.1 Whenever any claim or claims for payment of a sum of money arises out of or under the contract against the seller, the purchaser shall be entitled to withhold and also have a lien to retain such sum or sums in whole or in part from the security, if any, deposited by the seller and for the purpose aforesaid, the purchaser shall be entitled to withhold the said cash security deposit or the security, if any, furnished, as the case may be, and also have a lien over the same pending finalisation or adjudication of any such claim. In the event of the security being insufficient to cover the claimed amount or amounts or if no security has been taken from the seller, the purchaser shall be entitled to withhold and have a lien to retain to the extent of such claimed amount or amounts referred to from any sum or sums found payable or which at any time thereafter may become payable to the seller under the same contract or any other contract with the purchaser or any other person contracting, pending finalisation or adjudication of any such claim.
It is an agreed term of the contract that the sum of money so withheld or retained under the lien referred to above by the purchaser will be kept withheld or retained as such by the purchaser till the claim arising out of or under the contract is determined by the arbitrator (if the contract is governed by the arbitration clause) or by the competent court, prescribed, as the case may be, and that the seller will have no claim for interest or damages whatsoever on any account in respect of such withholding or retention under the lien referred to and duly notified as such to the seller. For the purpose of this clause, where the seller is partnership firm or a limited company, the purchaser shall be entitled to withhold and also have a lien to retain towards such claimed amount or amounts in whole or in part from any sum found payable to any partner/limited company as the case may be, whether in his individual capacity or otherwise.
25.2 It is an agreed term of the contract that the sum of money so withheld or retained under this clause by purchaser will be kept withheld or retained as such by the purchaser or till his claim arising out of in the same contract or any other contract is either mutually settled or determined by the arbitrator (if the contract is governed by arbitration clause) or by the competent court, hereinafter, provided, as the case may be, and that the seller shall have no claim for interest or damages whatsoever on this account or on any other ground in respect of any sum of money withheld or retained under this clause and duly notified as such to the seller.”
18. Reading the said clauses, the learned counsel for the petitioner submitted that it would appear that the petitioner would not be entitled to any interest in respect of retention money, but this did not extend to other money or other liabilities. He submitted that the arbitrator has not awarded any interest in connection with retention money and, therefore, it is clear that the award of interest would not be hit by the aforesaid clause. He further submitted that Clause 6.9.6 pointed out by the learned counsel for the respondent is part of the Clause 6.9.0 which refers to security deposit and, therefore, it clearly implies that the petitioner would not be entitled to interest on the security deposit amount under the said clause. But, as the arbitrator has not awarded any interest on security deposit, the same cannot be negated by reading this clause. He referred to the decision of the Supreme Court in the case of State Of Orissa v. B.N Agarwalla (supra), in support of his proposition that no interest being payable on retention money, did not ipso facto mean that no interest would be payable on the claim. He wanted to refer to a Division Bench decision of this court in the case of Bharat Heavy Electricals Ltd.… v. Globe Hi Fabs Ltd.…., (2005) 116 DLT 1 (DB) : 2004 (3) Arb. LR 636 (Del.) (DB), but the learned counsel for the respondent immediately pointed out that this judgment has been stayed by the Supreme Court in SLP No. 1926/2005.
19. The decision of a learned Single Judge of this court in the case of D.S.A Engineers (supra), clearly holds that if the terms of the contract expressly stipulate that no interest would be payable, then the arbitrator would not get the jurisdiction or right to award interest notwithstanding the provisions of Interest Act. The learned Single Judge further held that power to grant interest by the arbitrator emanates from the statutory provisions, but the same is always subject to the agreement between the parties. This view of the learned Single Judge was based upon a consideration of the decisions of the Supreme Court in the cases of Secretary, Irrigation Department (supra) and State Of Orissa v. B.N Agarwalla (supra). The learned Judge in D.S.A Engineers (supra), was considering the following clause:
“Clause 20.1—No interest shall be payable on any money due to the contractor against the earnest money, security deposit, interim or final bills or any other payments due under this contract.”
20. Interpreting this clause to be a complete bar for the grant of interest, in view of the ratio of the aforesaid decisions of the Supreme Court, the learned Judge set aside the claim of interest awarded by the arbitrator in that case.
21. The decisions of the Supreme Court in Bharat Coking Coal Ltd. (supra) and Oil & Natural Gas Corporation Ltd. (supra), are on the point that if the arbitrator travels beyond the terms of the contract, then the award is liable to be set aside. These decisions were cited by the learned counsel for the respondent to submit that no interest was payable under the terms of the contract and inasmuch as the arbitrator has awarded interest on the claim, he has travelled beyond the contract between the parties and, therefore, to this extent the award is liable to be set aside.
22. After considering the aforesaid decisions and the submissions made by the counsel for the parties, it becomes clear that the crux of the matter is the interpretation that is required to be placed on the clauses referred to by the learned counsel for the parties. The said Clause 6.9.6, although it falls under the head Security Deposit (6.9.0), is quite categorical when it says that no interest shall be payable by purchaser on security deposit or on any money due to the seller by the purchaser. Therefore, the question of no interest being payable is not limited to the security deposit alone but extends to “any money due to the seller by the purchaser”. A plain reading of this clause would mean that if any money is found due and payable from the respondent to the petitioner, the petitioner would not be entitled to any interest thereon. A similar sentiment is expressed in the said Clause 4.7 and, therefore, I feel that there is an express bar in the terms of the contract between the parties for the grant of interest on only money due and payable by the respondent to the petitioner.
23. The argument of the learned counsel for the petitioner that Clause 6.9.6 has a reference only to the security deposit and not other payments or dues is not tenable. The reference to the said Clauses 25.1 and 252 with regard to retention money does not help the petitioner. The said clauses state that when money is so retained, the seller (i.e the petitioner in this case) will have no claim for interest or damages on account of such withholding or retention. These clauses, in fact, support the contention of the learned counsel for the respondent that the petitioner would not be entitled to any interest on any amount due from the respondent to the petitioner and the said point has been expressly extended to retention money withheld also. Therefore, upon a consideration of the aforesaid clauses, it becomes clear that the terms of the contract between the petitioner and the respondent expressly stipulate that no interest would be payable by the respondent to the petitioner. This being the case in view of the aforesaid decisions of the Supreme Court as well as that of the Delhi High Court in D.S.A Engineers (supra), it becomes clear that the arbitrator did not have jurisdiction to award any interest and, therefore, insofar as and to the extent that the arbitrator has awarded interest in favour of the petitioner and against the respondent, the award has to be set aside.
24. The only other aspect which was agitated by the learned counsel for the respondent was that the respondent's claim of liquidated damages to the extent of Rs. 26,96,225.60 has been rejected in its entirety by the arbitrator. It was his contention that when there was a specific clause for liquidated damages which permitted a claim for quantification of the same, the damages ought to have been allowed. The learned counsel for the respondent relied on the decision of the Supreme Court in the case of Oil & Natural Gas Corporation Ltd. (supra), for the proposition that if liquidated damages are mentioned in the agreement, then there is no need to prove actual loss. However, considering the argument of the learned counsel for the petitioner, I find that we need not go into the question of whether liquidated damages ought to be awarded even if actual loss is not proved. This is so because the arbitrator in respect of this claim for liquidated damages has come to the conclusion (as recorded at page 46 of the award) that both the parties were responsible for the delay and that, therefore, it could not be said with certainty as to which party was responsible for the project delay and it is under these circumstances that the arbitrator was unable to hold the petitioner being solely responsible for the alleged delay. It is in this context that he concluded that, therefore, there was no question of any award of liquidated damages in favour of the respondent. Although other considerations have also been taken into account for the refusal to grant the respondent's claim for liquidated damages, I feel that this ground in itself is sufficient to uphold the conclusion arrived at by the learned arbitrator. Therefore, this part of the award inasmuch as the respondents claim for liquidated damages has been negated by the arbitrator cannot be set aside.
25. Accordingly, in view of the aforesaid discussion, the objections filed by the respondent stand disposed of by upholding the award except in respect of the petitioner's Claim No. 4 and the award of interest in favour of the petitioner. The award, therefore, stands confirmed in all other respects. The award as modified be made a rule of the court. The petitioner shall be entitled to future interest @ 9% per annum till the date of payment of the award amount as modified above. The objection application as well as the suit stand disposed of.