Darshan Lal v. Delhi Development Authority .

Delhi High Court
Mar 7, 2005
Smart Summary (Beta)

Factual and Procedural Background

This writ petition under Article 226 of the Constitution of India challenges an action of the Delhi Development Authority (DDA) cancelling the petitioner’s perpetual sub-lease of a plot measuring 978 sq. yards. The petitioner had originally been allotted the plot as a member of Mohan Cooperative Estate Ltd., and a perpetual sub-lease in his favour was executed on 17 April 1978. After obtaining permissions, the petitioner constructed on and began using the plot.

On 10 December 2002 the DDA (which had taken over management and leasehold rights) issued a show-cause notice alleging that a site inspection revealed the plot was being used as a “Godown Engineering Tool” in breach of the lease conditions, directing cessation of the alleged misuse and deposit of Rs. 1,039 per sq. metre per annum for the past period together with documentary evidence of commencement and stoppage of use within 15 days.

The petitioner responded to the show-cause notice denying any breach. Despite that, the DDA passed an order on 11 March 2003 cancelling the leasehold rights and directed surrender of possession of the plot and superstructure by 3 April 2003, stating that the petitioner had not shown cause and the alleged misuse had not been remedied. The petitioner made representations (including on 18 March 2003) asserting that he had replied and that the premises were used in accordance with the lease, and later sought conversion to freehold (depositing Rs. 1,40,480 on 2 January 2004), which the DDA declined on the basis that the lease had already been cancelled.

Legal Issues Presented

  1. Whether the DDA’s cancellation/determination of the petitioner’s leasehold rights was legally valid.
  2. Whether the use of part of the industrial plot as a godown/storage amounted to misuse in breach of the lease deed and the Master Plan (i.e., whether storage/godown use was permitted under the Master Plan and lease terms).
  3. Whether the DDA complied with requirements of fair procedure and principles of natural justice (in particular, whether the petitioner was afforded notice and a hearing before cancellation of the lease).
  4. How the “predominant purpose” test (as articulated in the cited Rajandheer decision) should be applied when part of an industrial plot is used for non-manufacturing purposes.

Arguments of the Parties

Petitioner’s Arguments

  • The petitioner contended that part of the premises was used as storage for construction materials (wooden planks, shuttering material, and other construction goods), which is a permitted industrial use under the Master Plan and therefore not a breach of the lease.
  • He relied on the definition of “godown” in the Development Code and on Sub-clause 8(2) of the revised Master Plan to show that storage/godown and warehousing are permitted uses in premises earmarked for manufacturing purposes.
  • The petitioner argued that the show-cause notice itself was incorrect and illegal given the permitted uses, and that the DDA’s cancellation was arbitrary because it proceeded on the basis that no reply was received (where the petitioner says he had replied).
  • It was further asserted that the cancellation order was not preceded by an opportunity of hearing, amounting to a violation of principles of natural justice.

Respondent (DDA) Arguments

  • The DDA maintained that the plot was being misused as a godown for engineering tools, which the DDA said was not permitted by the lease deed.
  • The show-cause notice was based on an inspection report and, according to the DDA, the petitioner did not reply to that show-cause; consequently, the DDA determined the lease in accordance with relevant lease clauses.
  • The DDA’s counsel submitted that even if the Master Plan permits godown use in some zones, that does not automatically entitle the sub-lessee to use the specific plot as a godown where the plot was allotted primarily for manufacturing activity; because the petitioner did not undertake manufacturing, the DDA was entitled to determine the lease.
  • The DDA also asserted that the reply the petitioner relied upon was never received by the Authority.

Table of Precedents Cited

Precedent Rule or Principle Cited For Application by the Court
Rajandheer (India) Pvt. Ltd. v. Delhi Development Authority, 2004 (1) AD (Del) 409 That to determine whether property is put to use contrary to the Master Plan, an inspection and assessment must ascertain the extent of non-manufacturing/non-industrial use; the correct test is the predominant purpose of the use, allowing incidental permitted activities. The Court applied the “predominant purpose” test from Rajandheer, holding that the DDA should have examined total built-up area, the nature and extent of the alleged impermissible use in relation to the whole property, and whether the predominant use remained industrial. Because that exercise was not done and only part of the property was used as a godown, the cancellation could not be sustained.

Court's Reasoning and Analysis

The court's analysis proceeded in the following steps, following the materials cited in the opinion:

  1. Interpretation of the lease deed: The court examined Para 14 of the lease deed which broadly prohibits use of the industrial plot for (a) residence, (b) carrying on any trade or business, and (c) any purpose other than carrying on the manufacturing process or running the industry of the “Item as per Master Plan.” The proviso permits the lessor, in its discretion, to waive or condone breaches on payment of sums and subject to terms the lessor may impose.
  2. Examination of the Master Plan and Development Code: The court reviewed Sub-clause 8(2) (Permission of selected use premises in use zones) and Sub-clause 8(3), and the Annexure definitions. It noted that “Storage, Godown & Warehousing” (S. No. 020) is permitted (P) in manufacturing use zones (M1, M2) and commercial zones, and is not permitted in residential zones. Clause 8(3) lists storage, godown & warehousing among permitted ancillary uses with certain incidental facilities.
  3. Adoption of the Rajandheer “predominant purpose” test: The court relied on the Rajandheer decision which requires inspection and an evaluation of the extent of non-manufacturing use and requires determining the predominant purpose of the plot’s use. The court stated that the facts relevant to this assessment include total area, built-up area, the nature and character of the alleged impermissible use, and the total extent of such use relative to the entire property.
  4. Application to the present facts: The court found that the petitioner had used part of the property as a godown, and there was no allegation that the petitioner had parted with possession or used the premises for expressly prohibited activities like residential or fully commercial use. Given that godown/storage is a permitted use in manufacturing zones under the Master Plan, the court held that the use of only part of the property as a godown should not automatically lead to the drastic consequence of lease determination without the required factual inquiry into predominant use.
  5. Procedural fairness and natural justice: Separately, the court held that the DDA failed to follow fair procedure. The DDA issued a show-cause notice but did not grant an opportunity of hearing before cancelling/determining the lease. The court emphasized that actions affecting valuable property rights and livelihood must be preceded by notice, hearing before an impartial decision-maker, and reasons based on relevant factors. Because these elements of fair procedure were not followed, the cancellation order was unsustainable on procedural grounds.
  6. Relief limited in scope: The court made clear it was not adjudicating the petitioner’s separate claim for conversion of the leasehold to freehold; those contentions and rights were left open for future determination.

Holding and Implications

Holding (Core Ruling): The writ petition was allowed. The court quashed the DDA’s impugned cancellation letter/order and directed that the DDA shall not take any steps to dispossess the petitioner. The court also expressly left open the petitioner’s separate claim for conversion of the property to freehold. No costs were awarded.

Implications and consequences:

  • The immediate direct effect is the quashing of the DDA’s cancellation/determination order and a prohibition on steps to dispossess the petitioner pending further proceedings consistent with this judgment.
  • The court required that any future consideration of alleged misuse must apply the “predominant purpose” test—assessing the extent and character of the use of the entire property—rather than treating a partial incidental use as an automatic breach warranting cancellation.
  • The court emphasized procedural safeguards: before cancelling leasehold rights, the DDA must afford notice, a hearing before an unbiased decision-maker, and record reasons based on relevant factors. The lack of such procedure rendered the impugned order unsustainable.
  • The opinion did not purport to set a new, broader precedent beyond applying the existing Rajandheer framework and procedural fairness principles; the petition was allowed only to the limited extent indicated and the conversion claim was left open.

Writ Petition allowed. The court’s decision is limited to quashing the cancellation and protecting the petitioner from dispossession; it does not decide the separate conversion claim.

Show all summary ...

S. Ravindra Bhat, J.— By this writ petition under Article 226 of the Constitution of India an action of the Delhi Development Authority (DDA) cancelling the perpetual lease deed of the petitioner, dismissing a plot measuring 978 sq. yds. (hereafter ‘the plot’) has been impugned.

2. The petitioner was allotted a plot, as member of Mohan Cooperative Estate Ltd. A perpetual sub-lease was executed in his favour on behalf of the Central Government on the 17th of April, 1978.

3. After securing the necessary permissions the petitioner put up building on the plot and started using it. On 10.12.2002 the DDA (which in the meanwhile had been handed over the management of the Estate and lease hold rights) issued a show-cause notice alleging that during the course of a site inspection it was discovered that the plot was being used for ‘Godown Engineering Tool’ which was in breach of conditions the lease deed. The DDA further directed that the said misuse of the plot be stopped forthwith and that an amount of Rs. 1039/- per sq. mtr. per annum be deposited for the past period, along with documentary evidence about the commencement and stoppage of use within 15 days.

4. It is averred that the petitioner responded to the show cause notice, stating that he had not committed any breach. The DDA proceeded to pass impugned order on 11.3.2003 cancelling the lease hold rights so the petitioner was directed to hand over possession of the plot and superstructure on it on 3.4.2003 The cancellation order also stated that the petitioner have not shown cause to the earlier notice and that the misuse alleged have not been remedied.

5. The petitioner addressed a representation on 18.3.2003 to the DDA stating that he had in fact replied to the show-cause notice and that the premises were being used according to the terms of the lease. This was followed with another representation and a request for conversion of the lease-hold rights, into free-hold. For that purpose, the petitioner deposited an amount of Rs. 1,40,480/- on 2.1.2004 The DDA declined this request for conversion on the ground that the leasehold rights has already been cancelled and, therefore, there was no question of acceding the request for conversion.

6. The petitioner avers that the impugned order was not preceded by any show-cause or opportunity of hearing. The petitioner avers that part of the premises were put to godown/storage of construction material, such as wooden planks, shuttering material and other goods related to construction, which is a permitted industrial use. The basis of the notice, namely, use of the plot contrary to the terms of the lease, has been, therefore, questioned as incorrect and illegal. The petitioner also has averred that as per the Master Plan too, the use of the premises as godown is permissible. The petitioner relied upon a judgment of this Court Rajandheer (India) Pvt. Ltd. v. Delhi Development Authority, 2004 (1) AD (Del) 409. It is also averred that the cancellation was not preceded by opportunity of hearing; therefore, it is vitiated for violation of principles of natural justice.

7. The DDA in its counter affidavit has averred that the plot was being misused for running godown for Engineering Tools, which is not permitted in terms of the lease deed. It is also stated that the show-cause issued in that regard, was based on an inspection report; the petitioner did not reply to the show-cause. Under the circumstances, the lease was determined by the impugned order. It is averred that the impugned order was strictly according to the relevant clauses in the lease deed.

8. Mr. Manish Goel, learned Counsel for the petitioner submits that the relevant clauses in the lease deed required use of the plot for the purposes of ‘manufacturing process or running the industry of or such other manufacturing process or running the industry of item as per Master Plan’.

9. He has relied upon the definition of godown in the schedule of the Development Code in the Master Plan; he has also relied upon the permission to use premises in use zone as per Sub-clause 8(2) of the revised Master Plan. He submits that the activity of storage/godown and warehousing is a permitted use in premises earmarked for manufacturing purposes. It is also submitted that in view of this position, the show-cause notice itself was illegal. It is submitted that in any case, the impugned order is arbitrary since it proceeded to merely confirm the show-cause notice; on the footing that no reply was received. The DDA was in an obligation to grant hearing to the petitioner, which was admittedly not done.

10. Mr. Anil Sapra, learned Counsel appearing for the respondent-DDA submits that merely because the premises are permitted to be used for godown under the Master Plan, there is no automatic assumption that it could be used for godown. The plot was allotted primarily for being used for a manufacturing activity or process. Since admittedly, it was not done, the DDA was well within its right to determine the lease. Its action cannot be faulted because the petitioner did not reply to the show-cause notice. He submits that the reply relied upon by the petitioner was never received by the DDA.

11. The relevant clauses namely, Para 14 of the lease deed in question are extracted below:

“14. The sub-lessee shall not without the written consent of the lessor use or permit to be used the industrial plot or any building thereon for residence or for carrying on any trade or business whatsoever or use the same or permit the same to be used for any purpose than that of carrying on the manufacturing process or running the industry of or such other Item as per Master Plan or such other manufacturing process or industry as may be approved from time-to-time by the Chief Commissioner or do or suffer to be done therein any act or thing whatsoever which in the opinion of the lessor may be a nuisance, annoyance or disturbance to the lessor, lessee and other sub-lessees and persons in the neighbourhood.

Or any unforseen expenditure to be made hereinafter by the lessee on any item of development to be carried out in terms of Clause III of the Agreement or the instructions issued by the Lt. Governor or the directions given by the local bodies in this behalf:

Provided that, notwithstanding anything contained herein to the contrary, the lessor in his absolute discretion, or the lessee with the prior consent in writing of the lessor, may, without prejudice to the right of re-entry as aforesaid, waive or condone breaches, temporarily or other wise, on receipt of such amount by the lessor or by the lessee on behalf of the lessor and on such terms and conditions as may be determined by the lessor and the lessor or the lessee whoever may be entitled may also accept the payment of the said sum or sums or the rent which shall be in arrear as aforesaid together with interest at the rate of six percent per annum. The amounts for waiver or condonation received by the lessee from the sublessee shall be paid forthwith by the lessee to the lessor subject to such deductions as the lessor may, in his absolute discretion, allow to be retained by the lessee.”

12. A reading of the above would show that there is a prohibition for the use of the industrial plot or any building on it for the following purposes—

(a) residence,

(b) carrying on any trade or business,

(c) use or permit the use of the plot for any purpose other than that of manufacturing process or running the industry of “Item as per master plan”.

13. The proviso to this condition enables the lessor to permit a contrary user, or to waive or condone breaches of terms and conditions, by requiring deposit of amounts and imposing further terms and conditions that may be deemed relevant. Significantly, the lease deed does not outline the industrial activity or manufacturing process; it merely refers to what is permitted in the Master Plan. Sub-clause 8(2) of the Master Plan outlines permitted use of select use premises in use zone. Every use has been assigned a serial number, to which the permissible use zones are, in turn, prescribed. Sl. Nos. 36 & 37 deal with light industry plot and extensive industry plot Sl. No. 20 deals with storage, godown and warehousing.

14. The serial number in the Annexure to the development code namely, in Sub-clause 8(2) to show what are the permitted uses for which the different uses/activities permitted in the use premises. Storage, godown and warehousing, described in Sl. No. 20 in respect of storage godown and warehousing, the use zone, as per the chart, permits storage, godown and warehousing activity in manufacturing use zones as well as commercial use zones. However, it is not permitted in residential use zones. Relevant extracts from Sub-clause (8)(2) and the permission of use premises in use zones are reproduced below:

“SUB/CLAUSE 8(2) PERMISSION OF USE PREMISES IN USE ZONES

(as part of approval of layout plan or as a case of special permission from the Authority)

(a)(i) Permission of selected use Premises in Use Zones RD, C1, C2, M1, M2

S. No. Use Premises USE ZONES 016 Convenience Shopping P NA NA NA NA 017 Local Shopping Centre P NA NA NA NA 020 Storage, Godown & Warehousing (i) Non-inflammable NP NP P P P (ii) inflammable (as per regulation regarding explosive material) NP NP P P P

15. Clause 8(3), which deals with uses/use activities permitted in used premises, provides with regard to storage, etc. as follows:

“Storage, Godown & Warehousing—

Storage, Godown & Warehousing, Watch & Ward Residence (Upto 20 sqm), Wholesale Outlet, Administrative & Sales Office.”

16. The development code schedule and its Annexure define different use premises. The relevant clauses are extracted below:

“036. Industrial Plot—Light Industry

A premises for industrial unit as per the list given in annexure III having upto 50 workers with non-hazardous performance.

037. Industrial Plot—Extensive Industry

A premises for industrial unit as per the list given in the annexure III having upto 50 workers in case of new extensive industrial units and 500 workers for existing units.

038 Industrial Premises—Extractive Industry

A premises for carrying out quarrying or extraction of stone and sub-soil material respectively.

039 Industrial Plot—Industry Specific Type

A premises for an industrial unit within a group of such units for manufacturing of specific products like electronic goods etc.”

17. In Rajandeer's case (supra) the Court had held as follows:

“in order to appreciate whether a particular property is being put to use contrary to the Master Plan, an inspection must take place to find out as to the extent of the premises being put to non-manufacturing and non-industrial use, since part of the premises can be put to such use. This has not been done in any of the cases. Really speaking, the test is of the predominant purpose of the use of the plot with permission to carry on the other incidental activities as prescribed in the use zones.”

18. On an application of this test (i.e of predominant use) indicated in the decision, it is apparent that the use that is, otherwise, permitted in the Master Plan, as per the permitted use as per Sub-clause 8(2) has to be examined, in a specific manner. All relevant facts such as the total area the builtup area upon the property, nature and character of the impermissible use, the total extent of such impermissible use, in relation to the total extent of the property have to necessarily be examined. In the absence of such an exercise, the test of determination use, in my view is not satisfied.

19. In the present case, the petitioner has used part of the property as a godown. There is no allegation that he has parted with possession without permission or used it for completely prohibited purposes such as residential or other commercial activity. Hence, the use of a portion of the premises ought not to entail the drastic consequence of determination of lease. The DDA ought to have kept in mind the principle indicated in Rajandheer's case while considering the issue of misuse, and seen the predominant use, as well as nature of use. It cannot be said that the use of part of an industrial plot as godown is completely prohibited; the extent of such use, in relation to the entire property had to be seen.

20. Coming to the other aspect, the manner in which the action was taken, cannot be sustained. Every action of the State or a public agency has to satisfy the test of non-arbitrariness. Hence any action that would adversely impact a citizen has to be preceded by a fair procedure. In the present case, the DDA did not follow that procedure. I am of the view that the DDA is under an obligation not only to issue a show-cause notice but also to grant hearing before passing an order of the kind impugned here namely, cancelling/determining leasehold right. Valuable rights of parties in relation to their property and source of livelihood are involved when such decisions are taken. The requirements of notice, hearing by an impartial person with an unbiased mind and reasons based on relevant factors are indispensable elements of the fair procedure. None of these were admittedly followed in this case. The impugned order is, therefore, unsustainable.

21. In view of the foregoing discussion this petition is entitled to succeed. It is made clear that this decision does not deal with the further relief sought in these proceedings namely, a direction to DDA to forthwith convert the property. All contentions and rights of parties in that regard are left open.

22. A direction is, therefore, issued to the DDA quashing its impugned letter. It is also directed not to take any steps towards dispossessing the petitioner. The writ petition is allowed to the extent indicated above.

23. No costs.

Writ Petition allowed.