Factual and Procedural Background
The Court took up multiple Petitions for final hearing with the consent of learned counsel for the parties and directed that all the Petitions be disposed of by a common order. The central procedural context is an application for impleadment of the Archaeological Survey of India (ASI) in proceedings concerning the Red Fort. According to a relevant Notification, the owner of the Red Fort is the Government of India through the Ministry of Defence, but the Respondent's counsel represented that ASI acts as the custodian of protected ancient monuments. The Court considered these representations, permitted steps to implead the ASI, and set aside the impugned order to the limited extent indicated. The Petitioners' counsel undertook to file an amended Memo of Parties in the First Appellate Court on the next date of hearing (14.8.2003). The ASI's counsel stated that the ASI would join the proceedings and make submissions. The Court allowed the Petitions to the extent indicated and requested that the First Appellate Court dispose of the Appeal by 12th September, 2003. The Order directs that a copy be provided "dusty" to counsel for the parties under the signatures of the Court Master.
Legal Issues Presented
- Whether the application for impleadment of the Archaeological Survey of India (ASI) should be accepted despite the Notification naming the Government of India through the Ministry of Defence as the owner of the Red Fort.
- Whether the impugned order that directed otherwise (i.e., refusing impleadment of the ASI) should be set aside to permit ASI's impleadment.
- Procedural: the appropriate timeline for expedited disposal in the First Appellate Court following the impleadment and amendment of parties.
Arguments of the Parties
Respondent's Arguments
- Mr. Sanjay Jain, learned counsel for the Respondent, stated that although the Notification lists the owner of the Red Fort as the Government of India through the Ministry of Defence, the ASI performs the role of custodian of ancient monuments placed in the category of protected monuments.
- On that basis, he argued that the application for impleadment of the ASI may be accepted and that the impugned order directing otherwise should be set aside to that extent.
Petitioners' Position
- Learned counsel for the Petitioners stated that an amended Memo of Parties would be filed in the First Appellate Court on the next date of hearing, namely 14.8.2003.
Archaeological Survey of India (ASI)
- Counsel for the ASI stated that the ASI would join the proceedings and make such submissions as it may be advised to make.
- The Court record notes an apprehension that the proceedings might be protracted under one guise or another.
Table of Precedents Cited
No precedents were cited in the provided opinion.
Court's Reasoning and Analysis
The Court proceeded on consent to take up the Petitions for final hearing and to dispose of them by a common order. The reasoning recorded in the opinion is concise and focused on the parties' representations:
- The Respondent's counsel represented that, notwithstanding the Notification naming the Government of India (Ministry of Defence) as owner of the Red Fort, the ASI functions as the custodian of ancient monuments categorized as protected.
- On this factual-legal representation about the ASI's custodial role, the Court accepted that the application for impleadment of the ASI "may be accepted" and that the impugned order refusing impleadment should be set aside to that limited extent.
- The Petitioners' counsel undertook to file an amended Memo of Parties in the First Appellate Court on the next date of hearing (14.8.2003), and counsel for the ASI indicated an intention to join and make submissions—facts relied upon in directing further procedural steps.
- Because of concerns about potential delay, the Court expressly requested the First Appellate Court to dispose of the Appeal expeditiously and by a specified deadline (12th September, 2003).
- Finally, the Court ordered administrative compliance: a copy of the Order was to be given "dusty" to counsel for the parties under the signatures of the Court Master.
Holding and Implications
The Petitions are allowed to the extent indicated: the application for impleadment of the Archaeological Survey of India (ASI) may be accepted and the impugned order directing otherwise is set aside to that extent.
Direct consequences and instructions recorded in the opinion:
- The Petitioners are to file an amended Memo of Parties in the First Appellate Court on the next date of hearing (14.8.2003).
- The ASI will join the proceedings and make such submissions as it deems fit.
- The First Appellate Court is requested to dispose of the Appeal with expedition and, in any event, by 12th September, 2003.
- A copy of the Order is to be given "dusty" to counsel for the parties under the signatures of the Court Master.
The opinion does not discuss broader legal precedents or set out a novel legal principle beyond accepting the counsel's representation about the ASI's custodial role; therefore, no new precedent is recorded in this Order.
1. Rule.
2. With the consent of the learned counsel for the parties, the Petitions are taken up for final hearing.
3. All these Petitions shall be disposed of by this common Order.
4. Mr. Sanjay Jain, learned counsel appearing for the Respondent states that although in the relevant Notification, the owner of the Red Fort is the Government of India through the Ministry of defense, since the ASI fulfillls the roll of a custodian of all ancient monuments which have been placed in the category of protected monuments, the application for the impleadment of the ASI may be accepted, and the impugned Order directing otherwise be set aside to this extent.
5. Learned counsel for the Petitioners states that an amended Memo of Parties shall be filed in the First Appellate Court on the next date of hearing itself i.e. 14.8.2003. Counsel for the ASI states that they will join the proceedings and make whatever submissions they are advised to make. The apprehension, however, is that the proceedings may be protracted under one guise or the other.
In these circumstances, the Petitions are allowed to the extent indicated above. However, the First Appellate Court is requested to dispose of the Appeal with expedition and latest by 12th September, 2003.
Copy of the Order be given dusty to counsel for the parties under the signatures of Court Master.