Delhi Development Authority v. Polo Singh & Co
Factual and Procedural Background
The respondent/claimant was awarded contracts by the appellant-Authority for construction of 356 and 132 SFS houses at Madipur, with work commencement stipulated on 17th March 1989 and completion within 15 months. The tendered amount was Rs. 1,48,28,910/-. The respondent failed to commence work, citing non-handover of the site and defective piling work by another contractor, which incapacitated construction. Despite bringing defects to the appellant's notice and undertaking preparatory actions like constructing a godown and securing utilities, the respondent could not proceed. The appellant rescinded the contract on 21st August 1989, alleging the respondent never intended to execute the work and had been making excuses. Disputes arose, leading to arbitration. The arbitrator issued an award on 26th December 1992, partially allowing respondent's claims and disallowing appellant's counter-claims. Subsequent proceedings involved challenges to the award, particularly relating to loss of profit claims, culminating in a fresh award dated 4th March 1998. The appellant objected to this award, which was dismissed by the Learned Single Judge, leading to the present appeal.
Legal Issues Presented
- Whether the rescission of the contract by the appellant-Authority was illegal and unjustified.
- Whether the respondent/claimant was entitled to damages for loss of profit on account of illegal rescission of the contract.
- Whether the award granting loss of profit damages at 10% of the contract value was supported by evidence and legally sustainable under Sections 73 and 74 of the Indian Contract Act, 1872.
- Whether the objections raised by the appellant against the arbitration award, particularly on claim No. 5, were tenable.
Arguments of the Parties
Respondent/Claimant's Arguments
- The contract termination was illegal as the delay in work commencement was due to the appellant's failure to hand over the site and rectify defective piling work.
- The respondent took preparatory steps indicating intent and readiness to commence work, including site preparations and securing utilities.
- Claimed damages including refund of security deposit, interest, infructuous expenditure, cost of materials, loss of profit, and arbitration costs.
Appellant-Authority's Arguments
- The respondent had no intention to execute the work, evidenced by the timely handover of substantial portions of the site.
- The piling work defects were minor and rectifiable with minimal cement usage.
- The contract was rescinded after due notice due to respondent's failure to execute work, and the work was completed through another agency.
- Objected to the award on loss of profit (claim No. 5) on grounds that it was a remote claim not permissible under Indian Contract Act.
Table of Precedents Cited
| Precedent | Rule or Principle Cited For | Application by the Court |
|---|---|---|
| Superintending Engineers T.N.U.D.P Madras Circle & Another v. A.V Rangaraju & Another, 1994 Arbitration Law Reporter 173 | Justification of loss of profit claim at 10% of contract value. | Used to support the arbitrator's award of loss of profit damages. |
| State of Kerala v. Bhaskaran, AIR 1985 Kerala 49 | Recognition of loss of profit claims in breach of contract cases. | Supported the reasoning that loss of profit was a direct loss arising from illegal rescission. |
| M/s. A.T Brij Paul Singh & Brothers v. State of Gujarat, AIR 1984 SC 1703 | Interpretation of Section 73 of the Indian Contract Act regarding damages for breach of contract and loss of profit. | Relied upon to affirm that loss of profit damages are compensable where contract is improperly rescinded. |
| M/s. R.B Chy. Ruchi Ram Khattar & Sons v. Delhi Development Authority, 1997 (40) DRJ 607; 1997 (1) Arb.LR 372 | Distinction between direct and remote loss of profit claims under Section 73 of the Indian Contract Act. | Distinguished on facts; held loss of profit claim in present case was direct and permissible. |
| Kersandas H. Tacket v. The Saran Engineering Co. Limited, AIR 1965 SC 1981 | Principle that compensation under Section 73 Indian Contract Act is for direct loss and not remote or indirect loss. | Applied to reject appellant’s argument that loss of profit claim was remote. |
| Mohd. Salamatullah & Others v. Government of Andhra Pradesh, AIR 1977 SC 1481 | Judicial deference to trial court’s quantification of damages even if based on guesswork. | Supported the arbitrator’s 10% profit calculation as reasonable. |
| Dwarka Das v. State of Madhya Pradesh & Another, AIR 1999 SC 1031 | Entitlement to damages for expected profit where contract is illegally rescinded. | Affirmed claim for loss of profit as a direct consequence of breach. |
| Puri Construction Pvt. Ltd. v. Union Of India, (1989) 1 SCC 411 : AIR 1989 SC 777 | Scope of judicial review of arbitration awards; courts should not re-assess evidence. | Applied to uphold the arbitrator’s findings without re-evaluation of evidence. |
| Food Corporation of India v. Joginder Pal Mohinder Pal & Another, AIR 1989 SC 1263 | Grounds for setting aside arbitration awards under Sections 30 & 33 of Arbitration Act. | Reinforced that mere error of law or fact by arbitrator is not ground to set aside award. |
| Smt. Santa Sia Devi & Another v. Dhirendra Nath Sen & Others, AIR 1963 SC 1677 | Judicial approach to arbitration awards should favor supporting rather than destroying them. | Guided the court’s approach to uphold the award where reasonably possible. |
Court's Reasoning and Analysis
The Court analyzed the facts and prior findings, noting that the arbitrator had already held the rescission of the contract by the appellant-Authority as illegal and such finding had attained finality, unchallenged by appeal. The Court observed that awarding damages for loss of profit requires a prior finding of illegal rescission, which was present here. The arbitrator’s calculation of loss of profit at 10% of the prime cost was considered a reasonable and accepted norm supported by trade practice and judicial precedents.
The appellant’s objection that the loss of profit claim was remote and unsupported by evidence was rejected by distinguishing relevant precedent where claims were disallowed due to delays caused by the claimant. Here, the loss was direct, flowing from wrongful termination. The arbitrator’s award was made after careful consideration of evidence and prior judicial observations. The Court emphasized that it could not re-examine or re-assess evidence before the arbitrator, and no allegation of misconduct or error of law apparent on the face of the award was made. The Court relied on established Supreme Court principles that arbitration awards should be upheld unless there is clear legal infirmity.
Holding and Implications
The Court dismissed the appeal and upheld the award dated 4th March 1998 making it rule of the court, confirming the respondent/claimant’s entitlement to damages for loss of profit calculated at 10% of the contract value.
The direct effect is that the respondent/claimant’s claims under claim No. 5 are sustained and enforceable. No new precedent was set; the Court applied established principles affirming the finality of arbitration awards and the compensability of direct loss of profit where contract rescission is illegal.
B.N Chaturvedi, J.:— Aggrieved by an order and judgment dated 21.3.2001 of the Learned Single Judge dismissing appellant's objections and making the award dated 4.3.1998 rule of the Court, the appellant preferred instant appeal seeking reversal thereof.
2. First, a resume of facts—
The respondent/claimant was awarded construction work of 356 SFS houses, Category II at Madipur, Pocket III and 132 SFS houses, Category II, at Madipur, Pocket III, Grade II, by the appellant-Authority. The stipulated date for commencement of work was 17th of March, 1989. The estimated cost of the work was Rs. 1,23,06,150/- and the tendered amount was Rs. 1,48,28,910/-. The work was to be completed within 15 months, on or before 16th of June, 1990. The respondent/claimant, however, failed to commence the work. The contract was eventually rescinded by the appellant-Authority on 21st of August, 1989. The reason for non-commencement of work, as stated by the respondent/claimant is that the site was not handed over to it on 7th of March, 1989 when the work was awarded as the piling work, being executed by another contractor, was incomplete apart from being defective, thereby incapacitating the respondent/claimant from proceeding with construction thereon. In spite of such defects being brought to the notice of the appellant by way of sketches and photographs, the same were not got rectified. The respondent/claimant claimed to have been keen to start the work and for that purpose constructed a godown at the site for storage of cement, besides undertaking the boring of a tube well, drawing water sample therefrom and sending the same to Shriram Institute for Industrial Research for analysis. It also paid a sum of Rs. 1,810/- to DESU on 11th of April, 1989 to secure an electric connection, and collected building materials, including cement, bricks, iron bars, etc. However, due to non-availability of site and defective piling work, it could not proceed with the work. The respondent/claimant, in the circumstances, termed the termination of the contract by the appellant as illegal since the delay in the commencement of work, according to it, was attributable to the appellant only.
3. The plea of the appellant, on the other hand, was that the respondent/claimant had no intention from the very beginning to execute the work as is manifest from the fact that the site for 11.5 blocks was handed over to the respondent/claimant on the stipulated date for commencement of the work w.e.f 17.3.1989, which was followed by handing over of 2.5 blocks on the 11th of April, 1989 and the remaining 2.5 blocks on the 25th of April, 1989. It is, accordingly, claimed that substantial portion of the site was made available to the respondent/claimant to proceed with the work. According to the appellant, the piling foundation work did not suffer from any major defect and only minor rectifications were required to be carried out, for which only 16 bags of cement were consumed, the details of which are as under:—
4th of July, 1989 -10 bags
5th of July, 1989 -3 bags
6th of July, 1989 -3 bags
4. It is pleaded that as the respondent/claimant failed to execute the work and had simply been making excuses to cover up the lapse on its part, the contract was rescinded by the appellant on 21st of August, 1989 after serving a notice dated 12.7.1989 on the respondent/claimant, and got the work executed through another agency.
5. In view of the parties to the contract finding fault with each other for non-commencement of the construction work, disputes arose, which were referred to arbitration. The arbitrator made his award on 26th of December, 1992.
6. The following claims were made by the respondent/claimant:—
Claim No. 1 :— Rs. 50,920/- being refund of security deposit.
Claim No. 2 :— Interest on Rs. 50,920/- @ 18% per annum being amount illegally recovered by getting the fixed deposit receipts encashed with interest.
Claim No. 3 :— Rs. 26,290/- on account of infructuous expenditure and damages sustained by the claimant due to various breaches committed by the appellant-Authority.
Claim No. 4 :— Rs. 1,93,000/- as cost of material collected at site.
Claim No. 5 :— Rs. 14,39,972/- being loss of profit to the extent of 10% of the contract value.
Claim No. 6 :— Rs. 1 lakh on account of infructuous expenditure and damages on maintenance of site establishment and T & P for a period of five months.
Claim No. 7 :— Interest @ 18% per annum from 20.4.1991 to the date of first hearing from the date of first hearing to the date of making of award and from the date of award until payment,
Claim No. 8 :— Costs of the arbitration proceedings.”
7. The arbitrator awarded a sum of Rs. 24,368/- in favour of respondent/claimant on account of claim No. 1, simple interest @ 18% per annum from 28th of August, 1991, the date of entering upon reference, to 26th of December, 1992, the date of making and publishing the award under claim Nos. 2 & 7. Claim No. 3 was partly allowed to the extent of Rs. 5,000/- in lumpsum. A sum of Rs. 10,000/- was awarded against claim No. 4 on account of cost of material at site. Against claim No. 5, a sum of Rs. 13,48,083/- was awarded as compensation for loss of profit while claim No. 6 was disallowed. In relation to claim No. 8, the parties were directed to bear their own costs.
8. The appellant-Authority had also made counter-claims as under:—
Counter-ciaim No. 1 : Rs. 20 lacs (Approx.) on account of higher cost of balance work got done at the risk and cost of the claimant.
Counter-claim No. 2 : Rs. 4,35,000/- (Approx.) on account of interest paid by the appellant-Authority to the allottees of SFS houses.
Counter-claim No. 3 : Rs. 10 lacs (Approx.) on account of defamation.
9. All these counter-claims were, however, disallowed by the arbitrator.
10. An application under Sections 14, 17 & 29 of the Arbitration Act (hereinafter referred to as ‘the Act’) was filed on behalf of respondent/claimant for making the award dated 26.12.1992 rule of the court. In addition, interest @ 18% per annum on the decretal amount was claimed from the date of award till realisation of the amount.
11. The appellant-Authority does not appear to have had filed any objection to the award. However, in the course of oral submissions, it objected to the award being made rule of the court in relation to claim No. 5 on account of damages for loss of profit. By judgment dated 30.5.1997 barring claim No. 5, the award was made rule of the Court. The award in relation to claim No. 5, was set aside and the matter was remitted back to the arbitrator for fresh adjudication thereon in tha light of observations made in the judgment. The arbitrator, on reconsideration, made and published a fresh award dated 4.3.1998 in relation to claim No. 5, awarding a sum of Rs. 12,35,742/- in favour of respondent/claimant. On a notice of filing of the award being issued, the appellant-Authority filed its objections under Sections 30 & 33 of the Act (IA 7010/99) in respect of claim No. 5.
12. Referring to a part of the judgment dated 30.5.1997 rendered by the learned Single Judge earlier, in respect of claim No. 5, the validity of the award was questioned by the appellant-Authority on the grounds that the same is based on no evidence and it reiterated its stand which was taken while challenging the award dated 26.12.1992 earlier in relation to claim No. 5.
13. On perusal of impugned order dismissing the objections being (IA.7010/99), it is gathered that in the course of hearing before the learned Single Judge, challenge to the impugned award was based on the sole plea that the claim with respect to loss of profits was a claim of remote nature, which was not permissible under sections 73 & 74 of the indian contract act, 1872. It was contended that after undertaking the construction work respondent/claimant would not have necessarily earned profits. The learned Single Judge, however, did not find any merit in the objection to the aforesaid effect. Holding that the rescission of the contract by the appellant-Authority having already been adjudged as illegal and such finding having attained finality, the arbitrator was quite justified in awarding 10% of the prime cost work as reasonable measure of profit. It was noted that for allowing the claim on this count, the arbitrator has given valid reasons. Taking note of judgments in Superintending Engineers T.N.U.D.P Madras Circle & Another v. A.V Rangaraju & Another, 1994 Arbitration Law Reporter 173; State of Kerala v. Bhaskaran, AIR 1985 Kerala 49 and M/s. A.T Brij Paul Singh & Brothers v. State of Gujarat, AIR 1984 SC 1703, wherein claim on account of loss of profit @ 10% was held justified, the objections petition (IA.7010/99) was dismissed. In view of dismissal of objections, the award pertaining to claim No. 5 was made rule of court.
14. We have heard both the parties.
15. The arbitrator, taking note of the fact that the rescission of the contract by the appellant-Authority having already been held in his earlier award dated 26.12.1992 as legally unjustified, allowed the claim of the respondent/claimant on account of loss of profit to the extent of Rs. 12,35,742/- in view of his finding as stated hereunder:—
“Under the circumstances when the rescission of the contract effected by the respondents was in disregard of the merits/facts, the claimants have been deprived of their legitimate right to earn profit out of a legal binding contract between the parties. The fact that the department at the time of preparing the estimates itself takes into consideration the element of profit to be 10% remains unrebutted. Besides this the said element of profit is according to the norms/practice prevailing in the trade and is recognised accordingly. Accordingly I conclude that fair ends of justice would be met by granting damages under the head “Loss of Profit” worked out @ 10% of prime cost of work which is reasonable measure of profit. From my experience in the field I think that 10% profit in a work of this nature can be said to be a loss naturally arising out of termination of contract.:”
16. To justify award of damages on account of loss of profit, a finding adjudging rescission of the contract as illegal is essential. The quantum of damages to be awarded in a particular case is another point for consideration. A reference to the earlier award dated 26.12.1998 reveals that while allowing claim No. 1 and disallowing counter-claims of appellant-Authority on three counts, the arbitrator returned his finding holding the rescission of the contract as illegal and bad in law. Except on claim No. 5, the award dated 26.12.1992 was made rule of the court. The decision of the learned Single Judge on the aforesaid aspect was not appealed against by the appellant-Authority. As a result, the finding of the arbitrator that the rescission of contract by the appellant-Authority was legally unsustainable becomes final and the same is no longer open to challenge while seeking to assail the validity of the award dated 4.3.1998 on claim No. 5. No infirmity is, thus, noticeable in the finding of the learned Single Judge holding the finding adjudging the rescission of the contract by the appellant-Authority illegal as attaining finality.
17. On behalf of the appellant-Authority, in the course of hearing before the learned Single Judge, in support of their objections against the award, a reference was made to a decision of this Court in M/s. R.B Chy. Ruchi Ram Khattar & Sons v. Delhi Development Authority, 1997 (40) DRJ 607 : 1997 (1) Arb.LR 372, to contend that the claim on account of loss of profit could not have been awarded as the claimant could not be sure of earning profits in the event it would have been allowed to undertake the complete the work in question. Learned Single Judge, noticing the facts in M/s. R.B Chy. Ruchi's case (supra) held that the same was manifestly distinguishable and could in no way held promote the argument advanced on behalf of the appellant-authority. That was a case where the contract had unduly been prolonged on account of lapses attributable to the respondent. For delay in completion of work by the stipulated date, the contractor staked his claim for compensation on the ground that had the contract been completed by the stipulated date, it would have had earned profits by executing another contract/work. The claim was, however, negatived though the arbitrator had allowed the contractor's claim and awarded a sum of Rs. 1,54,081/28 on that count. Relying on a decision of the Supreme Court in Kersandas H. Tacket v. The Saran Engineering Co. Limited, AIR 1965 SC 1981, the award in this respect was set aside observing that under Section 73 of the Indian Contract Act, 1872, a party is liable to be compensated for breach of contract by the other party on account of direct loss of profits. Remote or indirect loss or damage sustained by reason of the breach will not entitle the party to receive any compensation on that score. In the given case, claim No. 5 being made on account of loss of profit owing to rescission of the contract is in the nature of direct loss and not a remote one.
18. The award dated 4.3.1998 clearly spells out the reason for awarding the aforesaid amount on account of damages for loss of profit. The arbitrator took note of the entire relevant facts and the materials placed before him by the parties, and made his award in the light of observations occurring in the earlier judgment dated 30.5.1997 which is evident on a bare perusal of the same. The plea to the effect that the award is based on no evidence is, therefore, totally unfounded.
19. Adverting to the point relating to award of compensation, reference may be made to a decision in M/s. A.T Brij Paul Singh & Brothers v. State of Gujarat, AIR 1984 SC 1703, wherein while interpreting the provisions of Section 73 of the Indian Contract Act, 1872, the Supreme Court held that where the party entrusting the work commits breach of contract by improperly rescinding the contract, the contractor is entitled to claim damages for loss of profit which he expected to earn by undertaking the works/contract. Speaking on measure to evaluate the amount of damages, it was observed:
“What, would be the measure of profit would depend upon facts and circumstances of each case. But that there shall be a reasonable expectation of profit is implicit in a works contract and its loss has to be compensated by way of damages if the other party to the contract is guilty of breach of contract cannot be gainsaid....”
20. In Mohd. Salamatullah & Others v. Government of Andhra Pradesh, AIR 1977 SC 1481, where the trial court awarded damages for breach of contract @ 15% and the High Court, in appeal, reduced the same from 15% to 10% of the contract price, the Supreme Court held that the appellate court was not justified to interfere with the finding of fact given by the trial Court regarding quantification of the damages even if it was based on guesswork.
21. In yet another decision in Dwarka Das v. State of Madhya Pradesh & Another, AIR 1999 SC 1031, where the appellant was in response to the tenders invited by the respondent/State, allotted the work for construction of a hostel within a specified period, in different phases, failed to complete the work within the time schedule and the contract executed between the parties was rescinded by the respondent/State on the ground of non-completion of work within the stipulated time, and the appellant made a claim of Rs. 20,000/- as damages contending that the termination of the contract was in breach thereof and the suit in this respect was decreed by the trial Court in favour of the appellant, which was, however, disallowed by the High Court, in appeal, as the appellant was found to have not placed the material on record to show that he had actually suffered any loss on account of the breach of contract, setting aside the judgment of the High Court, the Supreme Court held:
“The appellant had never claimed Rs. 20,000/- on account of alleged actual loss suffered by him. He had preferred his claim on the ground that had he carried out the contract, he would have earned profit of 10% on Rs. 2 lakhs which was the value of the contract....”
“....it follows, therefore, as and when the breach of contract is held to have been proved being contrary to law and terms of the agreement, the erring party is legally bound to compensate the other party to the agreement. The appellate Court was, therefore, not justified in disallowing the claim of the appellant for Rs. 20,000/- on account of damages as expected profit out of the contract which was found to have been illegally rescinded”.
22. It is not necessary for a Court to examine the merits of the award with reference to the materials produced before the arbitrator. The Court cannot sit in appeal over the view of the arbitrator by re-examining and re-assessing the materials. [see Puri Construction Pvt. Ltd. v. Union Of India , (1989) 1 SCC 411 : AIR 1989 SC 777, Food Corporation of India v. Joginder Pal Mohinder Pal & Another, AIR 1989 SC 1263]
23. In Smt. Santa Sia Devi & Another v. Dhirendra Nath Sen & Others, AIR 1963 SC 1677, the Supreme Court laid down:
“... a court should approach an award with a desire to support it, if that is reasonably possible, rather than to destroy it by calling it illegal.....”
24. In “Joginder Pal Mohinder Pal” (supra), the Supreme Court in the context of sections 30 & 33 of the arbitration act, 1940, while dealing with the grounds on which an award can be set aside held:
“It is necessary to find whether the arbitrator has misconducted himself or the proceedings legally in the sense whether the arbitrator has gone contrary to the terms of reference between the parties or whether the arbitrator has committed any error of law appearing on the fact of it.....It is not misconduct on the part of an arbitrator to come to an erroneous decision whether his error is one of fact or law, and whether or not his findings of fact are supported by evidence.”
25. In the present case, there is no allegation of arbitrator misconducting himself or the proceedings. Also there is no challenge to the award in question on the ground that the arbitrator has committed any error of law apparent on the face of the award. In the given situation, it is not open to re-evaluate the material placed before the arbitrator which constitute the basis of his finding leading to award under claim No. 5.
26. In the instant case, the arbitrator awarded damages to the respondent claimant to the tune of Rs. 12,35,742/- to compensate it on account of loss of profit. He arrived at this figure by calculating the same @ 10% of the contract value. This was a fair and reasonable basis to work out the amount of loss of profit. It is relevant to take into account if the respondent claimant would have actually been able to earn profit to the said extent had the contract not been rescinded and the respondent-claimant would have been allowed to complete the awarded work. The impugned order & judgment, thus, call for no interference as the learned Single Judge rightly dismissed the appellant's objections and made the award rule of the court.
27. Being devoid of merit, the appeal is dismissed. No costs.